Nazim Eqbal has over 13 years of experience as an Electrical Supervisor in oil, gas, and petrochemical industries. He is seeking a position as an Electrical Supervisor where he can utilize his skills in electrical engineering, construction supervision, and health and safety training. He has experience managing electrical installation and construction projects in various industries. His background includes supervising substations, switchgear, cable laying, and other electrical systems for projects in Qatar, the UAE, Kazakhstan, and India.
Since last 13.7 years, I have been working electrical fields of industrial experience with GASCO UAE, Shell Pearl GTL Qatar. Aramco KSA, SEWA Sharjah, such 11KV to 400 KV substations, (GIS 33 KV to 220 KV) 5 KVA Upto120 MVA Transformer Erection installation, switch gears & Circuit breaker, as, LV, MV, HV, VCB, ACB, OCB, SF6, to 11 KV, 33 KV, 132 KV, 220 KV, installation Erection. Power & Control Cables termination, Grounding system, pre-commissioning & commissioning testing done other project
Since last 13.7 years, I have been working electrical fields of industrial experience with GASCO UAE, Shell Pearl GTL Qatar. Aramco KSA, SEWA Sharjah, such 11KV to 400 KV substations, (GIS 33 KV to 220 KV) 5 KVA Upto120 MVA Transformer Erection installation, switch gears & Circuit breaker, as, LV, MV, HV, VCB, ACB, OCB, SF6, to 11 KV, 33 KV, 132 KV, 220 KV, installation Erection. Power & Control Cables termination, Grounding system, pre-commissioning & commissioning testing done other project
With an experience in the field of Testing and Commissioning of power system products, I look forward for an opportunity to display my skills in the field of Testing & commissioning ,Operation & Maintenance and Execution of projects related to power systems.
Experience in the field of Testing and Commissioning & QA/QC of power system products, look forward for an opportunity to display my skills in the field of Testing, commissioning Operation & Maintenance and Execution of projects related to power systems
With an experience in the field of Testing and Commissioning of power system products, I look forward for an opportunity to display my skills in the field of Testing & commissioning ,Operation & Maintenance and Execution of projects related to power systems.
Experience in the field of Testing and Commissioning & QA/QC of power system products, look forward for an opportunity to display my skills in the field of Testing, commissioning Operation & Maintenance and Execution of projects related to power systems
Senario Masyarakat Islam di Akhir Era Khulafa’ al-RashidinEzad Azraai Jamsari
PPPJ1153 Sejarah Islam 11-656H, 2016
Jabatan Pengajian Arab dan Tamadun Islam, FPI, UKM
"Perkuliahan 02: Senario Masyarakat Islam di Akhir Era Khulafa’ al-Rashidin"
Testing & Commissioning Engineer | Power Supply Tech. | Traction Rail Power |...Sanil Balakrishnan
8+ yrs of GCC exp. as electrical engineer with proficiency in testing & commissioning, operation & maintenance @ traction rail industry, oil & gas and in power plants.
Testing & Commissioning Engineer | Power Supply Tech. | Traction Rail Power |...
MY CV
1. CURRICULUM VITAE
ELECTRICAL SUPERVISOR
NAZIM EQUBAL
Mob, +918083309424/+919973249460
E-mail:nazimeqbal@gmail.com.com/nazimeqbal@yahoo.com
OBJECTIVE:
Around13 yearsof experience inOil &GasIndustries, Petro-chemical Industries Seeking a position as an
Electrical Supervisorina stable organizationengagedinconstructionwhere I can perform my skills what I
have achieved from my past and be the part of that organization.
ACHIEVEMENT:
,
BOSIET (Basic offshore induction and emergency training)
PTW FSI & TSTI Trainingl Agip Kco Kazakhstan
Practical leadership, Training Agip Kco Kazakhstan
Lock-out and Tag-out Training Agip Kco Kazakhstan
SUMMARY OF QUALIFICATION:
Electrical Engineering, Diploma
Total work experience More than 13 years/ Function & Responsibilities
Experience in EPC & Construction Green field and Brownfield pipeline projects in Oil & Gas
Coordinates with contractors/Sub contractors and vendors, expedite document review cycle
components, and systems for commercial and industrial purposes
Manage & Monitor and inspect the electrical erection/installation activities of the contractor.
Handle all aspects of Electrical Construction activities including site investigations,
Good knowledge in reading and understanding Equipment Layout drawings.
Computer literate MS Office (Excel, Word and Access).
Co-ordinate and supervise construction work teams and plan future work programs
Knowledge of how to assess and minimize risks associated with working on Hazardous area
Review and Approval of Materials and Method Statements
WORK EXPERIENCES:
Company CEGELEC QATAR
Project RLESC
Position Electrical Construction Supervisor
Period From27/09/2014 to 26/01/2015
Job Responsibilities:
Installation of two new power Gas turbines generators, construction of new sub-station and other
associated facilities including electro-mech. work modification to the existing facilities and tie ins.
providingcontrol of the electrical constructionworks asdirected.Providingdirectionandleadershiptothe
Contractor works scope in all electrical related works. Co-ordinate and interface with other Technical
Departments, Business Units, Operations, and contractors/consultants to resolve technical issues and
ensure quality Electrical/Instrument Engineering execution and integrity.
Trainings and Seminars:
Company N.P.C.C ABU DHABI
Project Fujairah Refinery plant
Position Electrical Supervisor
Client ZADCO
Period From23/03/2014 to 01/08/2014
2. Job Responsibilities:
Responsible for Construction 35 KV Substation LER comprising of two 35/10KV, 6MVA, four 6.6/415KV,
2MVA and Transformers6.6KV and 10kv switchgear& softstarterpanelsLV panelsIRP UPS control Panels
and Desksinstallationof aviationLight&installation of Battery with Electrolyte Field Work in CPF & Inlet
Facilitiesinstallationof lightingDB,JB& MOV panelsHeattracingAndcathodicprotectionandInstallation
of HV, MV &LV Switchboard & motors fin fan Cable Termination & Hi-pot test cable laying And Monitor
Workforce ProgressProvide Technical input to Facilitate and assist Subcontractor to safely Work Prepare
the three Week forecast for submission to The Planning department for review & to Draw up the final
ExecutionPlanforthe Electrical DepartInitial projectmeetingwiththe Management&Superintendent to
Ensure the Entire Requirement Preparation of materials as per site Requirement Serve as day-to-day
interface withContractorCraftlaborprovidingafocuson safety and Quality• Ensure that procedures and
processesare Understoodandfollowed by the Construction Personnel• Monitor and ensure compliance
with Specification procedures and plans provide on-site Knowledge of project specific electrical
installation Requirement.
Nature of Work:
Job Responsibility.
This project was involved on pipeline around 150 km Brownfield construction of 135 Megawatt CCGT
Cogeneration power projects with Laying of 115 KV high voltage cable from GIS substation to power
Transformer installation & erection of GIS switchgear power and control panels UPS System fire & gas
sys16.5/115kv 250 Mva powertransformer5000 ampere isolatedbus duct from CGTG to transformer low
Voltage & medium Voltage cable laying cable tray for power lighting welding Outlet field Lighting
GlandingTermination in switchgear motor & solo run test low & medium voltage Initial project meeting
with the management & superintendent to ensure the entire requirement Utilize and control the
manpowerinaccordance to giventhe workscheduledtosubcontractor.Periodic monitoring time to time
to subcontractors Preparation of materials as per site requirement Project specification given by Saudi
Aramco Provide work scheduled as per priority of requirement of Project according to management
Alwaysconsciousaboutthe qualitycontrol of workforce asper WorkScheduledandpriority.Monitoring
and preservation all of the olefins project for requirement Such of Power transformer LV & MV motor,
distributiontransformer13.8kV & lowvoltage switchgearEffective Manage interfaces between new and
existing facilities ensure adherence to company golden HSE Policies and Aramco specification, without
Effective the subcontractor’s schedule
Job responsibilities:
ThisProjectisinvolvedonfull constructionof 34.5/4.16 kV SubstationandFAR buildingwiththe 4no’s,
10 mva & 14nos 2.5mva transformerinstallationof switchgearmediumandLow voltage marshaling
Company AGIP KCO (ENI) Kazakhstan
Project Kshaghan project
Position Construction Electrical Supervisor
Client AGIP KCO
PeriodAug. From11/06/2011 to 22/06/2013
Company CEGELEC CBI (QATAR)
Project QAFCO
Position Construction Electrical Supervisor
Period From April 2010.to April 2011
3. CabinetAlsoinstallationof cable trayInstallationof complete subStationbuildingworkincludingMCC
Relaypanel &patch panel fire alarmSystemAnnunciatorpanelsetc.
Job responsibilities:
Responsible for Construction installation, of Sub-station comprising of two 33/6.6KV, 6MVA, four
6.6/.415KV,2MVA And Two 6.6/415 Transformers,6.6KV panels, LV panels, lighting Panels, IRP, RTU UPS,
BC panels and Field work in CPF and Inlet Facilities, power & control cable Laying and glanding
Termination & installation of lighting DB cable tray, GI, RGS & EMT Conduit & Street light structural
Lighting etc.
Job Responsibility:
Supervision of electrical Construction installation work. This project involved installation of HV MV LV
switchgear MCC panel & IRP UPS, lighting & Distribution Board, 750 KVA transformer 5 HP to 50HP LT
motors,HT/ LT cable layingterminationAndinstallation of lighting fixture Ladder cable tray conduit etc.
Job Responsibility:
Work outline:Electrical activities inthe sub-station and compressor Installation of panels, cable ladders,
cable trays,conduits,cable laying,Glandingterminationof Power&control Cables, installation of lighting
systems and grounding systems, loop checking
Personal Details:
• Name : Nazim Eqbal
• Fathers ‘Name : Asim Eqbal
• Birth Date : June 30, 1982
• Height/Weight : 5’7”/70 kg
• Old Passport No : F-4139881
• New passport no : L-3005636(ECNR)
• Date of Expiry : Aug, 26, 2023
• Dist. west Champaran
• State: Bihar-845438
• India
• Contact: +918083309424/+919973
• 249460
Company C.C.C Abu Dhabi (Supply By Kentech)
Project GASCO
Position Construction Electrical Supervisor
Period from Oct 2006 to Nov 2009
Company TECNIMONT ICB INDIA
Project water& distillation plant
Position Electrical Foreman
Period from OCT. 2004 to NOV.2006.
Company ARTSON ENGG. INDIA
Project HPCL POWER PLANT
Position Electrical Foreman
Period from DEC 2001 to JULY 2004.