SlideShare a Scribd company logo
1 of 2
RECOMMENDED PROCEDURES
FOR
LAYING UP BOILERS
A. Pre-operation Period. When the boiler is ready for the hydrostatic test, proceed as follows:
1. Fill the superheater with condensate or demineralized water containing 10 ppm (10
cm3/m3) of ammonia and 20 ppm (200 cmi/mi) of hydrazine. The pH value of the
solution should be approximately 10.0. The condensate is added at the superheater
outlet to overflow into the boiler drum.
2. When the condensate overflows from the superheater into the boiler drum, the
addition of condensate at the superheater can be stopped and the unit filled as
described in step3.
3. Fill the boiler through the normal. filling connections with hydrazine treated water.
Close boiler drains and open boiler vents as during normal filling procedures.
4. At the conclusion of the hydrostatic test, with the boiler and superheater filled to
overflowing, pressurize the unit to 3-5 psi (21-35 kPa) gage with nitrogen.
a. Where freezing is a problem, the water in the drainable circuits can be displaced
with nitrogen and then the unit is laid up under nitrogen pressure. Auxiliary
heat is then applied to keep the non:drainable superheater elements above
freezing.
b. With drainable superheaters allsurfaces can belaid up under nitrogen pressure.
5. Boilers without stop valves in the main steam line should have the outlet isolated by
meansof a blank flange, or equivalent, so that a small positive pressure can be applied.
8. Post Boil-Out Period. Ifthe operation of the boiler isdelayed after boiling out or acid cleaning
it should be filled as follows:
Introduce condensate containing about 10 ppm (10 cm3/m3) of ammonia and 200 ppm (200
cm3/m3) of hydrazine to the boiler and superheater and pressurize the unit with nitrogen.
C. Short Outage Period. No draining. If the boiler isshut down for a period of three to four days,
and the boiler pressure will drop to atmospheric pressure:
Introduce nitrogen through the boiler drum vent or at a superheater drain valve when the
steam pressure drops below5 psi (35 kPa). Maintain a total pressure of 5 psi (35 kPa) due to
nitrogen.
D. Long Outage. Boiler not opened for repair work. Where the boiler is removed from service
for a prolonged shutdown, asa seasonal outage of a month or longer:
1. Fillthe superheater, adding the condensate to the outlet of the non-drainable sections
until overflowing into the boiler. Then proceed with filling the boiler with a
condensate containing 10 ppm(10 cm3/m3) of ammonia and 200 ppm (200 cm3/m3) of
hydrazine.
The treated condensate can be displaced with nitrogen or
the entire unit can be laid up wet under nitrogen pressure
depending upon the temperature of the surrounding
area. Maintain a nitrogen pressure of 3-5 psi (21-35 kPa)
gage. If the main steam line is not equipped with a stop
valve, steps should be taken to blank off the line so that
the boiler can be pressurized.
2. If freezing weather conditions arise during the outage
means must be provided to keep the elements above
freezing temperature.
NOTES: The use of hydrazine (N2H4) has been found acceptable as a reducing
agent.
Nitrogen purging is important in the complete
elimination of oxygen.
When the unit is to be put. in service, it will be
necessary to bring the water levelto normal
and open the drum and superheater vents
before lighting off. To conserve nitrogen supply
used in pressurizing the unit, shut off the supply
before opening the vents.

More Related Content

What's hot

Ammonia Plant - Secondary Reforming
Ammonia Plant - Secondary ReformingAmmonia Plant - Secondary Reforming
Ammonia Plant - Secondary ReformingGerard B. Hawkins
 
Water and fire tube boilers. (EME)
Water and fire tube boilers. (EME)Water and fire tube boilers. (EME)
Water and fire tube boilers. (EME)dishant pagdar
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common ProblemsGerard B. Hawkins
 
BOILER MOUNTINGS & ACCESSORIES
BOILER MOUNTINGS & ACCESSORIESBOILER MOUNTINGS & ACCESSORIES
BOILER MOUNTINGS & ACCESSORIESSmit Shah
 
Babcock and Wilcox Boiler
Babcock and Wilcox BoilerBabcock and Wilcox Boiler
Babcock and Wilcox Boilerrishironak
 
Reduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystReduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystGerard B. Hawkins
 
Aiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumAiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumSatria Sakata
 
Powerplant(waterwalls)
Powerplant(waterwalls)Powerplant(waterwalls)
Powerplant(waterwalls)skulboy12
 
Mounting and Accessories of Boiler
Mounting and Accessories of BoilerMounting and Accessories of Boiler
Mounting and Accessories of BoilerRavi Suman
 

What's hot (20)

Turbine
TurbineTurbine
Turbine
 
Thermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boilerThermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boiler
 
Cochran Boiler
Cochran BoilerCochran Boiler
Cochran Boiler
 
Ammonia Plant - Secondary Reforming
Ammonia Plant - Secondary ReformingAmmonia Plant - Secondary Reforming
Ammonia Plant - Secondary Reforming
 
Water and fire tube boilers. (EME)
Water and fire tube boilers. (EME)Water and fire tube boilers. (EME)
Water and fire tube boilers. (EME)
 
Machinery safety inspection
Machinery safety inspectionMachinery safety inspection
Machinery safety inspection
 
Cochran Boiler
Cochran Boiler Cochran Boiler
Cochran Boiler
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common Problems
 
Boiler Maintenance & Safety
Boiler Maintenance & SafetyBoiler Maintenance & Safety
Boiler Maintenance & Safety
 
BOILER MOUNTINGS & ACCESSORIES
BOILER MOUNTINGS & ACCESSORIESBOILER MOUNTINGS & ACCESSORIES
BOILER MOUNTINGS & ACCESSORIES
 
Cv presentation of boiler
Cv presentation of boilerCv presentation of boiler
Cv presentation of boiler
 
Babcock and Wilcox Boiler
Babcock and Wilcox BoilerBabcock and Wilcox Boiler
Babcock and Wilcox Boiler
 
Boiler safety
Boiler safetyBoiler safety
Boiler safety
 
Reduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystReduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming Catalyst
 
Aiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumAiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agrium
 
Powerplant(waterwalls)
Powerplant(waterwalls)Powerplant(waterwalls)
Powerplant(waterwalls)
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
 
Cochran Boiler
Cochran BoilerCochran Boiler
Cochran Boiler
 
boiler
boilerboiler
boiler
 
Mounting and Accessories of Boiler
Mounting and Accessories of BoilerMounting and Accessories of Boiler
Mounting and Accessories of Boiler
 

Viewers also liked

Antique Marine Steam Engine Solidoworks Project
Antique Marine Steam Engine Solidoworks ProjectAntique Marine Steam Engine Solidoworks Project
Antique Marine Steam Engine Solidoworks ProjectMichael Lagalle
 
Unit 2 lubrication, cooling and fuels
Unit 2  lubrication, cooling and fuelsUnit 2  lubrication, cooling and fuels
Unit 2 lubrication, cooling and fuelsSairammurty Peddada
 
Design of an Engine Crankshaft
Design of an Engine CrankshaftDesign of an Engine Crankshaft
Design of an Engine Crankshaftsarkersakib
 
Engine materials for camshaft and crankshaft
Engine materials for camshaft and crankshaftEngine materials for camshaft and crankshaft
Engine materials for camshaft and crankshaftAntonio Manicone
 
cooling and lubrication of engine report
cooling and lubrication of engine reportcooling and lubrication of engine report
cooling and lubrication of engine reportjyotigangar
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler okBunk Bonk
 
Lubrication system for an automobile
Lubrication system for an automobile Lubrication system for an automobile
Lubrication system for an automobile sgrsoni45
 

Viewers also liked (15)

Antique Marine Steam Engine Solidoworks Project
Antique Marine Steam Engine Solidoworks ProjectAntique Marine Steam Engine Solidoworks Project
Antique Marine Steam Engine Solidoworks Project
 
Steam Engine 3751
Steam Engine 3751Steam Engine 3751
Steam Engine 3751
 
Steam engine
Steam engineSteam engine
Steam engine
 
Unit 2 lubrication, cooling and fuels
Unit 2  lubrication, cooling and fuelsUnit 2  lubrication, cooling and fuels
Unit 2 lubrication, cooling and fuels
 
Crankshaft
CrankshaftCrankshaft
Crankshaft
 
Design of an Engine Crankshaft
Design of an Engine CrankshaftDesign of an Engine Crankshaft
Design of an Engine Crankshaft
 
Engine materials for camshaft and crankshaft
Engine materials for camshaft and crankshaftEngine materials for camshaft and crankshaft
Engine materials for camshaft and crankshaft
 
Boilers (1) (1)
Boilers (1) (1)Boilers (1) (1)
Boilers (1) (1)
 
cooling and lubrication of engine report
cooling and lubrication of engine reportcooling and lubrication of engine report
cooling and lubrication of engine report
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler ok
 
Boilers
BoilersBoilers
Boilers
 
Lubrication system for an automobile
Lubrication system for an automobile Lubrication system for an automobile
Lubrication system for an automobile
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Steam power plants
Steam power plantsSteam power plants
Steam power plants
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 

Similar to RECOMMENDED PROCEDURES FOR LAYING UP BOILERS

Methanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownMethanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownGerard B. Hawkins
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedureABVSAI
 
Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Dinesh Panchal
 
Study of Boilers for Mechanical Engineering
Study of Boilers for Mechanical EngineeringStudy of Boilers for Mechanical Engineering
Study of Boilers for Mechanical EngineeringAbdullahKafi18
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)sneh patel
 
Anaesthesia Vaporizers by Dr shailendra
Anaesthesia Vaporizers by Dr shailendraAnaesthesia Vaporizers by Dr shailendra
Anaesthesia Vaporizers by Dr shailendraShailendra Satpute
 
Unit-II- Steam Generators.pptx
Unit-II- Steam Generators.pptxUnit-II- Steam Generators.pptx
Unit-II- Steam Generators.pptxssuser8147f6
 
firedheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptx
firedheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptxfiredheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptx
firedheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptxFahadReda2
 
STEAM Boiler for Thermal Engineering Mech
STEAM Boiler for Thermal Engineering MechSTEAM Boiler for Thermal Engineering Mech
STEAM Boiler for Thermal Engineering MechBalaji Ganesh
 
Multi pressure system in VCRS
Multi pressure system in VCRSMulti pressure system in VCRS
Multi pressure system in VCRSSuyog_Kadam
 
Armfield Gas Absorption Column Experiment
Armfield Gas Absorption Column ExperimentArmfield Gas Absorption Column Experiment
Armfield Gas Absorption Column ExperimentHadeer Khalid
 
mech 2nd yr lab report.pdf
mech 2nd yr lab report.pdfmech 2nd yr lab report.pdf
mech 2nd yr lab report.pdfMOHDAHMED52
 

Similar to RECOMMENDED PROCEDURES FOR LAYING UP BOILERS (20)

Methanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownMethanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut Down
 
Ch.2
Ch.2Ch.2
Ch.2
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedure
 
Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Boilers ppt (energy conversion)
Boilers ppt (energy conversion)
 
Study of Boilers for Mechanical Engineering
Study of Boilers for Mechanical EngineeringStudy of Boilers for Mechanical Engineering
Study of Boilers for Mechanical Engineering
 
boilers
boilersboilers
boilers
 
sugar mill ss.pptx
sugar mill ss.pptxsugar mill ss.pptx
sugar mill ss.pptx
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)
 
Anaesthesia Vaporizers by Dr shailendra
Anaesthesia Vaporizers by Dr shailendraAnaesthesia Vaporizers by Dr shailendra
Anaesthesia Vaporizers by Dr shailendra
 
Unit-II- Steam Generators.pptx
Unit-II- Steam Generators.pptxUnit-II- Steam Generators.pptx
Unit-II- Steam Generators.pptx
 
Steam and Steam Boiler
Steam and Steam BoilerSteam and Steam Boiler
Steam and Steam Boiler
 
firedheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptx
firedheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptxfiredheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptx
firedheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptx
 
STEAM Boiler for Thermal Engineering Mech
STEAM Boiler for Thermal Engineering MechSTEAM Boiler for Thermal Engineering Mech
STEAM Boiler for Thermal Engineering Mech
 
Multi pressure system in VCRS
Multi pressure system in VCRSMulti pressure system in VCRS
Multi pressure system in VCRS
 
Cochran boiler presentation
Cochran boiler presentationCochran boiler presentation
Cochran boiler presentation
 
Armfield Gas Absorption Column Experiment
Armfield Gas Absorption Column ExperimentArmfield Gas Absorption Column Experiment
Armfield Gas Absorption Column Experiment
 
mech 2nd yr lab report.pdf
mech 2nd yr lab report.pdfmech 2nd yr lab report.pdf
mech 2nd yr lab report.pdf
 
steam pow rplant
steam pow  rplantsteam pow  rplant
steam pow rplant
 
Water treatment of steam boilers
Water treatment of steam boilersWater treatment of steam boilers
Water treatment of steam boilers
 
Different Boiler's
Different Boiler'sDifferent Boiler's
Different Boiler's
 

RECOMMENDED PROCEDURES FOR LAYING UP BOILERS

  • 1. RECOMMENDED PROCEDURES FOR LAYING UP BOILERS A. Pre-operation Period. When the boiler is ready for the hydrostatic test, proceed as follows: 1. Fill the superheater with condensate or demineralized water containing 10 ppm (10 cm3/m3) of ammonia and 20 ppm (200 cmi/mi) of hydrazine. The pH value of the solution should be approximately 10.0. The condensate is added at the superheater outlet to overflow into the boiler drum. 2. When the condensate overflows from the superheater into the boiler drum, the addition of condensate at the superheater can be stopped and the unit filled as described in step3. 3. Fill the boiler through the normal. filling connections with hydrazine treated water. Close boiler drains and open boiler vents as during normal filling procedures. 4. At the conclusion of the hydrostatic test, with the boiler and superheater filled to overflowing, pressurize the unit to 3-5 psi (21-35 kPa) gage with nitrogen. a. Where freezing is a problem, the water in the drainable circuits can be displaced with nitrogen and then the unit is laid up under nitrogen pressure. Auxiliary heat is then applied to keep the non:drainable superheater elements above freezing. b. With drainable superheaters allsurfaces can belaid up under nitrogen pressure. 5. Boilers without stop valves in the main steam line should have the outlet isolated by meansof a blank flange, or equivalent, so that a small positive pressure can be applied. 8. Post Boil-Out Period. Ifthe operation of the boiler isdelayed after boiling out or acid cleaning it should be filled as follows: Introduce condensate containing about 10 ppm (10 cm3/m3) of ammonia and 200 ppm (200 cm3/m3) of hydrazine to the boiler and superheater and pressurize the unit with nitrogen. C. Short Outage Period. No draining. If the boiler isshut down for a period of three to four days, and the boiler pressure will drop to atmospheric pressure: Introduce nitrogen through the boiler drum vent or at a superheater drain valve when the steam pressure drops below5 psi (35 kPa). Maintain a total pressure of 5 psi (35 kPa) due to nitrogen. D. Long Outage. Boiler not opened for repair work. Where the boiler is removed from service for a prolonged shutdown, asa seasonal outage of a month or longer: 1. Fillthe superheater, adding the condensate to the outlet of the non-drainable sections until overflowing into the boiler. Then proceed with filling the boiler with a condensate containing 10 ppm(10 cm3/m3) of ammonia and 200 ppm (200 cm3/m3) of hydrazine.
  • 2. The treated condensate can be displaced with nitrogen or the entire unit can be laid up wet under nitrogen pressure depending upon the temperature of the surrounding area. Maintain a nitrogen pressure of 3-5 psi (21-35 kPa) gage. If the main steam line is not equipped with a stop valve, steps should be taken to blank off the line so that the boiler can be pressurized. 2. If freezing weather conditions arise during the outage means must be provided to keep the elements above freezing temperature. NOTES: The use of hydrazine (N2H4) has been found acceptable as a reducing agent. Nitrogen purging is important in the complete elimination of oxygen. When the unit is to be put. in service, it will be necessary to bring the water levelto normal and open the drum and superheater vents before lighting off. To conserve nitrogen supply used in pressurizing the unit, shut off the supply before opening the vents.