SlideShare a Scribd company logo
1 of 5
RECENT TRENDS IN RENEWABLEENERGY ON SOLAR .
POINTING THE SUPPLY AND DEMAND FOR TAMILNADU.
The wind energy sector in the state suffers from a number of policy-based challenges,
say those in the industry.
For Tamil Nadu’s wind energy sector, the future may not be a breeze. The top producer
of wind energy in the country and home to India’s biggest wind farm with an installed
capacity of 1,500 MW at Kanyakumari, Tamil Nadu’s generation, however, is slowing.
According to data from the Ministry of New and Renewable Energy (MNRE), Tamil
Nadu produced 10,147.1 million units of power from wind energy in 2014-15. It
however, saw a dip the subsequent year, falling to 7,273.23 million units of power in
2015-16.
However, in 2016-17, the state witnessed an increase with 11,935 million units of wind energy
generated.
Growth in wind power generation has since slowed.
In 2017-18, Tami Nadu saw a marginal rise in wind power generation by 423 million units,
while the next year it grew by 242 million units.
While Tamil Nadu remains the top producer in wind power generation, those in the
industry point to the fact that it’s nowhere close to achieving its full capacity.
K Kasturirangan, the President of the Indian Wind Power Association (IWPA) says, “The generation
is increasing, no doubt. But the quantity by which it is increasing is falling, which means that in due
course the generation will show a decline.”
For Wind Energy Generators (WEGs), the issues within the sector are manifold, most crucially the
delayed payment scheduled from the Tamil Nadu Generation and Distribution Corporation
(TANGEDCO).
“So in the last two to three years, many Wind Energy Generators (WEGs) in Tamil Nadu chose not
to produce wind power so that they don’t have to put up with these issues,” says Kasturirangan.
The state’s wind energy sector is plagued by adversaries of two kinds -- inherent disadvantages like
seasonal availability, unpredictability and challenges that are policy-based, like lack of sufficient
facilities for power-banking, payment issues etc. While state-of-the-art technology can indeed help
the sector resolve inherent disadvantages, policy challenges also need to be addressed, say those
in the field.
One of the biggest challenges that wind energy generators face today is the banking period. Power -
banking is the process by which the electricity generated by wind energy is stored in the grid for
future use. In this case, the electricity generated by the Wind Energy Generators (WEG) over and
above what has already been consumed is generally integrated into the grid. The WEG can then use
the remaining units at their convenience any time within the next twelve months by taking it from the
grid. This process of storing the electricity for future use is called power banking.
Power banking is costly
Tamil Nadu Electricity Board’s (TNEB) reservations against providing banking facilities to the WEGs
stem from the fact that it is expensive and that most of the generators use the power generated from
wind for their own captive purposes.
A lot of WEGs in Tamil Nadu generate electricity from wind energy to be used in their own factories
or mills. This is called captive consumption. WEGs that produce electricity usually make use of the
power banking facility, by which the power generated by the WEGs is made available to them as and
when required.
A senior official from TNEB tells TNM that the demand to do away with banking facility is a long-
standing one. The Board has made multiple appeals in the past to the Tamil Nadu Energy
Regulatory Commission (TNERC), the state regulatory body which sets policies, tariffs etc., for
electricity generation and distribution.
“Historically, a lot of wind generators have been enjoying power banking facility from us. Especially
those who are involved in captive power generation where they produce power for their own
consumption and store the unutilised units during the non-season period. During the off-wind season
period, we are forced to purchase power from the open market to supply to the WEGs, which turns
out to be expensive for us,” the official says, who points out that Wind Energy Generators enjoy
subsidies from the Board.
Following multiple meetings, the TNERC in 2018 reduced the banking period to one month from the
existing 12-month period, albeit for new WEGs. In a tariff directive, the TNERC revised the banking
period to a month for new WEGs established in the state on or after April 1, 2018. This is a drastic
reduction from the earlier one year period, enjoyed by the WEGs set up before April 1, 2018.
Speaking to TNM about the change in banking period brought in by the TNERC, Deepak Krishnan
from the World Resources Institute (WRI) says that one-year-banking period resulted in an increase
in costs for TANGEDCO, the discom which is a fully owned subsidiary of TNEB.
“Initially banking of energy was allowed over a period of one year, which meant that electricity can
be accumulated over the monsoon season, when the wind flow is high, and plan its own production
schedule accordingly. But what really was happening was that in summer, the companies that used
wind power needed extra units to cope up with the power demand. They all turned to TANGEDCO at
that juncture asking it to cater to their demands, since their units were exhausted when it was
pushed into the grid for banking purposes. TANGEDCO had to oblige at that point, resulting in
higher costs for TANGEDCO since this demand was unexpected as far as TANGEDCO was
concerned,” explains Deepak.
While the regulator reduced banking period for new WEG installations, it also increased banking
charges (in terms of units) for the existing WEGs, also known as legacy WEGs, from 12% to 14%.
This move created significant impact on the WEGs, who are now allowed to withdraw only 86 units
of power from the grid for every 100 units they have generated and added to the grid. WEGs were
earlier allowed to withdraw 88 units of power.
Sector experts point out that this has made wind power generation more expensive for WEGs.
Erratic payments from discom
While TNERC tightened the noose on one side, several wind energy generators say that they are left
with no guarantee of payments from TANGEDCO for the power units added to the grid.
Many WEGs in Tamil Nadu have payments outstanding for the last 20 months, says K Kasturirangan
of IWPA, . He adds that along with the lack of regular payment, clauses in the Power Purchase
Agreements (PPA) entered between the WEGs and the discom restrict generators from seeking
other means to sell power and get paid. This discourages many from entering the sector.
The senior TNEB official admits that delayed payments are due to TANGEDCO reporting huge
losses, over Rs 7500 crore for 2017-18. He argues, however, that giving options for WEGs to review
or cancel the PPAs will lead to the opening of a Pandora’s box. “It can really affect our energy
security because we calculate our own availability and forecast based on these kind of PPAs. So if
the PPAs start getting cancelled or reviewed, then it totally upsets our planning,” he explains.
Pointing out that payment issues are not unique to Tamil Nadu alone, Deepak Krishnan says,
“Breaking a contract with TANGEDCO right now and selling power to someone is a challenge as of
now, because the main question then is 'Where do you sell?'.” He also adds that if the plan is to sell
to some customers in north India, then the next issue would be to figure out how to go about it.
“If gradually all generators are moved to a competitive market, then it can become much more
interesting, because when you operate in a market, all buyers (utilities and other big factories) will
have to put some earnest deposit money before the contract starts etc. This will at least ensure
payments to generators, easing up the situation a little,” he adds.
Solar eating into wind’s share
Deepak also flags another major problem that is reportedly facing Tamil Nadu’s wind energy sector
and by extension the renewable energy sector. Solar energy, he says, is slowly eating into the
market share of wind energy.
“When a state is planning its energy bills across its next five to ten years, it would have factored in
some mix of thermal with renewable energy. In the renewable energy, for example, 25% would have
been for wind and 15% for solar. Theoretical assumption is that as solar cost starts falling lower and
lower, they would effectively start eating into the thermal share. But what has happened is because
of the cost decrease, and the notion of the discom that without thermal the system won’t function
well, the obvious victim has been wind energy,” he explains.
Moreover, the Union government’s move to cut the tax benefit for WEGs from 2017-18 has also
disincentivised the generation of wind energy.
Need for reliable power source
Since wind and solar energy are intermittent energy sources, the state’s electricity board is
dependent on thermal power plants for ensuring that the grid is steady. Given that the demand for
electricity peaks after sunset, relying on wind or solar power to be the source for base load supply is
out of the question. This non-reliability also puts the state a few steps back from being a 100%
green-energy state.
“The problem with thermal generation is that you cannot switch it on and off instantly. It takes several
hours for any plant to light up the boiler after shut down. It also increases the wear and tear of these
plants, adding to the cost since these plants are designed only for a stable load. So it is always
advisable to have these plants running at some technical minimum. Our experience is that it is not
technically feasible to keep running them at very low capacity utilisation,” says the TNEB official.
The officer, however, adds that in spite of sophisticated forecasting models, the discom isn’t able to
predict the unexpected increase or fall in wind energy generation. “That really creates a problem for
us in terms of grid management. We are expected by law to operate within a very narrow band of
frequency and if we violate, we will be liable to pay a penalty to the national regulator,” he says,
further explaining that having a dependable, solid source for supplying base load is crucial.
DONE BY: V.SREENIVAS REDDY
19BME0602

More Related Content

What's hot

Hydroelectric power plant
Hydroelectric power plant Hydroelectric power plant
Hydroelectric power plant Ravindra Kolhe
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plantpranavn007
 
FINAL PROJECT PPT
FINAL PROJECT PPTFINAL PROJECT PPT
FINAL PROJECT PPTShivarajaDM
 
WAVE ENERGY CONVERTER
WAVE ENERGY CONVERTERWAVE ENERGY CONVERTER
WAVE ENERGY CONVERTERHamid Raza
 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Pritesh Priyadarshi
 
Chapter one-Introduction to Hydroelectric power plant
Chapter one-Introduction to Hydroelectric power plantChapter one-Introduction to Hydroelectric power plant
Chapter one-Introduction to Hydroelectric power plantYimam Alemu
 
Permanent magnet synchronousgenerator
Permanent magnet synchronousgeneratorPermanent magnet synchronousgenerator
Permanent magnet synchronousgeneratorSonuKumarBairwa
 
Power electronics in Wind Turbine Systems
Power electronics in Wind Turbine SystemsPower electronics in Wind Turbine Systems
Power electronics in Wind Turbine SystemsManasa K
 
POWER QUALITY IMPROVEMENT
POWER QUALITY IMPROVEMENTPOWER QUALITY IMPROVEMENT
POWER QUALITY IMPROVEMENTUday Wankar
 
Pelamis wave energy converter seminar report
Pelamis wave energy converter seminar reportPelamis wave energy converter seminar report
Pelamis wave energy converter seminar reportSukh Raj
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plantSuresh Rathore
 
Role of phasor measuring unit in power system
Role of phasor measuring unit in power systemRole of phasor measuring unit in power system
Role of phasor measuring unit in power systemHASEENA. M
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plantCraZzy Shubh
 

What's hot (20)

Matlab/Simulink Projects
Matlab/Simulink Projects Matlab/Simulink Projects
Matlab/Simulink Projects
 
Hydroelectric power plant
Hydroelectric power plant Hydroelectric power plant
Hydroelectric power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
 
WIND ENERGY
WIND   ENERGYWIND   ENERGY
WIND ENERGY
 
FINAL PROJECT PPT
FINAL PROJECT PPTFINAL PROJECT PPT
FINAL PROJECT PPT
 
WAVE ENERGY CONVERTER
WAVE ENERGY CONVERTERWAVE ENERGY CONVERTER
WAVE ENERGY CONVERTER
 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment
 
EXCITATION SYSTEMS
EXCITATION SYSTEMSEXCITATION SYSTEMS
EXCITATION SYSTEMS
 
Chapter one-Introduction to Hydroelectric power plant
Chapter one-Introduction to Hydroelectric power plantChapter one-Introduction to Hydroelectric power plant
Chapter one-Introduction to Hydroelectric power plant
 
Permanent magnet synchronousgenerator
Permanent magnet synchronousgeneratorPermanent magnet synchronousgenerator
Permanent magnet synchronousgenerator
 
Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
 
Wave Energy
Wave EnergyWave Energy
Wave Energy
 
Power electronics in Wind Turbine Systems
Power electronics in Wind Turbine SystemsPower electronics in Wind Turbine Systems
Power electronics in Wind Turbine Systems
 
POWER QUALITY IMPROVEMENT
POWER QUALITY IMPROVEMENTPOWER QUALITY IMPROVEMENT
POWER QUALITY IMPROVEMENT
 
Pelamis wave energy converter seminar report
Pelamis wave energy converter seminar reportPelamis wave energy converter seminar report
Pelamis wave energy converter seminar report
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plant
 
Role of phasor measuring unit in power system
Role of phasor measuring unit in power systemRole of phasor measuring unit in power system
Role of phasor measuring unit in power system
 
Wind energy
Wind energyWind energy
Wind energy
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plant
 

Similar to Recent trends in renewable energy on solar

Nepal Energy Scenario
Nepal Energy ScenarioNepal Energy Scenario
Nepal Energy ScenarioAvdesh Mandal
 
Natural group presentation tamil nadu solar energy policy devising cost effec...
Natural group presentation tamil nadu solar energy policy devising cost effec...Natural group presentation tamil nadu solar energy policy devising cost effec...
Natural group presentation tamil nadu solar energy policy devising cost effec...Ritesh Pothan
 
Wind Force Newsletter Dec, Edition, 2011
Wind Force Newsletter   Dec, Edition, 2011Wind Force Newsletter   Dec, Edition, 2011
Wind Force Newsletter Dec, Edition, 2011rupeshsingh_1
 
Internship report of NTPC kawas ,summer internship report of ntpc
Internship report of  NTPC kawas ,summer internship report of ntpcInternship report of  NTPC kawas ,summer internship report of ntpc
Internship report of NTPC kawas ,summer internship report of ntpcLalitGoyal27
 
Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)Nieza Noordin
 
Opportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in IndiaOpportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in India Devesh Gautam
 
IRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in IndiaIRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in IndiaIRJET Journal
 
Global Investor Meet 2019 Curtain Raiser
Global Investor Meet 2019 Curtain RaiserGlobal Investor Meet 2019 Curtain Raiser
Global Investor Meet 2019 Curtain Raiserindecom50
 
Sir wind
Sir windSir wind
Sir windgvee
 
Response to msedcl demands
Response to msedcl demandsResponse to msedcl demands
Response to msedcl demandsJay Ranvir
 
OVERVIEW OF NET ENERGY METERING IN MALAYSIA
OVERVIEW OF  NET ENERGY METERING  IN MALAYSIAOVERVIEW OF  NET ENERGY METERING  IN MALAYSIA
OVERVIEW OF NET ENERGY METERING IN MALAYSIAZAINI ABDUL WAHAB
 
Assessing the Impact of Tamil Nadu’s Electricity Tariff Policy on TANGEDCO’S ...
Assessing the Impact of Tamil Nadu’s Electricity Tariff Policy on TANGEDCO’S ...Assessing the Impact of Tamil Nadu’s Electricity Tariff Policy on TANGEDCO’S ...
Assessing the Impact of Tamil Nadu’s Electricity Tariff Policy on TANGEDCO’S ...AurovilleConsulting
 
KREDL- Energy Efficiency Workshop - Bangalore
KREDL- Energy Efficiency Workshop -  BangaloreKREDL- Energy Efficiency Workshop -  Bangalore
KREDL- Energy Efficiency Workshop - BangaloreAdvit Foundaion
 
Renewable energy for bts (2)
Renewable energy for bts (2)Renewable energy for bts (2)
Renewable energy for bts (2)nasir12345678900
 
Hosting Capacity Analysis for Photovoltaic Rooftop in Indonesia
Hosting Capacity Analysis for Photovoltaic Rooftop in IndonesiaHosting Capacity Analysis for Photovoltaic Rooftop in Indonesia
Hosting Capacity Analysis for Photovoltaic Rooftop in IndonesiaSyamsirAbduh2
 
wind energy
wind energywind energy
wind energyShayan29
 

Similar to Recent trends in renewable energy on solar (20)

9-Energy
9-Energy9-Energy
9-Energy
 
Solar power - A developer prespective
Solar power - A developer prespectiveSolar power - A developer prespective
Solar power - A developer prespective
 
Nepal Energy Scenario
Nepal Energy ScenarioNepal Energy Scenario
Nepal Energy Scenario
 
Natural group presentation tamil nadu solar energy policy devising cost effec...
Natural group presentation tamil nadu solar energy policy devising cost effec...Natural group presentation tamil nadu solar energy policy devising cost effec...
Natural group presentation tamil nadu solar energy policy devising cost effec...
 
Wind Force Newsletter Dec, Edition, 2011
Wind Force Newsletter   Dec, Edition, 2011Wind Force Newsletter   Dec, Edition, 2011
Wind Force Newsletter Dec, Edition, 2011
 
Internship report of NTPC kawas ,summer internship report of ntpc
Internship report of  NTPC kawas ,summer internship report of ntpcInternship report of  NTPC kawas ,summer internship report of ntpc
Internship report of NTPC kawas ,summer internship report of ntpc
 
Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)Energy Malaysia Volume 6 (1)
Energy Malaysia Volume 6 (1)
 
Opportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in IndiaOpportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in India
 
Energy audit tata power solar
Energy audit   tata power solarEnergy audit   tata power solar
Energy audit tata power solar
 
IRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in IndiaIRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in India
 
Global Investor Meet 2019 Curtain Raiser
Global Investor Meet 2019 Curtain RaiserGlobal Investor Meet 2019 Curtain Raiser
Global Investor Meet 2019 Curtain Raiser
 
Sir wind
Sir windSir wind
Sir wind
 
Making sense of kusum
Making sense of kusumMaking sense of kusum
Making sense of kusum
 
Response to msedcl demands
Response to msedcl demandsResponse to msedcl demands
Response to msedcl demands
 
OVERVIEW OF NET ENERGY METERING IN MALAYSIA
OVERVIEW OF  NET ENERGY METERING  IN MALAYSIAOVERVIEW OF  NET ENERGY METERING  IN MALAYSIA
OVERVIEW OF NET ENERGY METERING IN MALAYSIA
 
Assessing the Impact of Tamil Nadu’s Electricity Tariff Policy on TANGEDCO’S ...
Assessing the Impact of Tamil Nadu’s Electricity Tariff Policy on TANGEDCO’S ...Assessing the Impact of Tamil Nadu’s Electricity Tariff Policy on TANGEDCO’S ...
Assessing the Impact of Tamil Nadu’s Electricity Tariff Policy on TANGEDCO’S ...
 
KREDL- Energy Efficiency Workshop - Bangalore
KREDL- Energy Efficiency Workshop -  BangaloreKREDL- Energy Efficiency Workshop -  Bangalore
KREDL- Energy Efficiency Workshop - Bangalore
 
Renewable energy for bts (2)
Renewable energy for bts (2)Renewable energy for bts (2)
Renewable energy for bts (2)
 
Hosting Capacity Analysis for Photovoltaic Rooftop in Indonesia
Hosting Capacity Analysis for Photovoltaic Rooftop in IndonesiaHosting Capacity Analysis for Photovoltaic Rooftop in Indonesia
Hosting Capacity Analysis for Photovoltaic Rooftop in Indonesia
 
wind energy
wind energywind energy
wind energy
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

Recent trends in renewable energy on solar

  • 1. RECENT TRENDS IN RENEWABLEENERGY ON SOLAR . POINTING THE SUPPLY AND DEMAND FOR TAMILNADU. The wind energy sector in the state suffers from a number of policy-based challenges, say those in the industry. For Tamil Nadu’s wind energy sector, the future may not be a breeze. The top producer of wind energy in the country and home to India’s biggest wind farm with an installed capacity of 1,500 MW at Kanyakumari, Tamil Nadu’s generation, however, is slowing. According to data from the Ministry of New and Renewable Energy (MNRE), Tamil Nadu produced 10,147.1 million units of power from wind energy in 2014-15. It however, saw a dip the subsequent year, falling to 7,273.23 million units of power in 2015-16. However, in 2016-17, the state witnessed an increase with 11,935 million units of wind energy generated. Growth in wind power generation has since slowed. In 2017-18, Tami Nadu saw a marginal rise in wind power generation by 423 million units, while the next year it grew by 242 million units. While Tamil Nadu remains the top producer in wind power generation, those in the industry point to the fact that it’s nowhere close to achieving its full capacity. K Kasturirangan, the President of the Indian Wind Power Association (IWPA) says, “The generation is increasing, no doubt. But the quantity by which it is increasing is falling, which means that in due course the generation will show a decline.” For Wind Energy Generators (WEGs), the issues within the sector are manifold, most crucially the delayed payment scheduled from the Tamil Nadu Generation and Distribution Corporation (TANGEDCO). “So in the last two to three years, many Wind Energy Generators (WEGs) in Tamil Nadu chose not to produce wind power so that they don’t have to put up with these issues,” says Kasturirangan. The state’s wind energy sector is plagued by adversaries of two kinds -- inherent disadvantages like seasonal availability, unpredictability and challenges that are policy-based, like lack of sufficient facilities for power-banking, payment issues etc. While state-of-the-art technology can indeed help the sector resolve inherent disadvantages, policy challenges also need to be addressed, say those in the field. One of the biggest challenges that wind energy generators face today is the banking period. Power - banking is the process by which the electricity generated by wind energy is stored in the grid for future use. In this case, the electricity generated by the Wind Energy Generators (WEG) over and
  • 2. above what has already been consumed is generally integrated into the grid. The WEG can then use the remaining units at their convenience any time within the next twelve months by taking it from the grid. This process of storing the electricity for future use is called power banking. Power banking is costly Tamil Nadu Electricity Board’s (TNEB) reservations against providing banking facilities to the WEGs stem from the fact that it is expensive and that most of the generators use the power generated from wind for their own captive purposes. A lot of WEGs in Tamil Nadu generate electricity from wind energy to be used in their own factories or mills. This is called captive consumption. WEGs that produce electricity usually make use of the power banking facility, by which the power generated by the WEGs is made available to them as and when required. A senior official from TNEB tells TNM that the demand to do away with banking facility is a long- standing one. The Board has made multiple appeals in the past to the Tamil Nadu Energy Regulatory Commission (TNERC), the state regulatory body which sets policies, tariffs etc., for electricity generation and distribution. “Historically, a lot of wind generators have been enjoying power banking facility from us. Especially those who are involved in captive power generation where they produce power for their own consumption and store the unutilised units during the non-season period. During the off-wind season period, we are forced to purchase power from the open market to supply to the WEGs, which turns out to be expensive for us,” the official says, who points out that Wind Energy Generators enjoy subsidies from the Board. Following multiple meetings, the TNERC in 2018 reduced the banking period to one month from the existing 12-month period, albeit for new WEGs. In a tariff directive, the TNERC revised the banking period to a month for new WEGs established in the state on or after April 1, 2018. This is a drastic reduction from the earlier one year period, enjoyed by the WEGs set up before April 1, 2018. Speaking to TNM about the change in banking period brought in by the TNERC, Deepak Krishnan from the World Resources Institute (WRI) says that one-year-banking period resulted in an increase in costs for TANGEDCO, the discom which is a fully owned subsidiary of TNEB. “Initially banking of energy was allowed over a period of one year, which meant that electricity can be accumulated over the monsoon season, when the wind flow is high, and plan its own production schedule accordingly. But what really was happening was that in summer, the companies that used wind power needed extra units to cope up with the power demand. They all turned to TANGEDCO at that juncture asking it to cater to their demands, since their units were exhausted when it was pushed into the grid for banking purposes. TANGEDCO had to oblige at that point, resulting in higher costs for TANGEDCO since this demand was unexpected as far as TANGEDCO was concerned,” explains Deepak. While the regulator reduced banking period for new WEG installations, it also increased banking charges (in terms of units) for the existing WEGs, also known as legacy WEGs, from 12% to 14%. This move created significant impact on the WEGs, who are now allowed to withdraw only 86 units of power from the grid for every 100 units they have generated and added to the grid. WEGs were earlier allowed to withdraw 88 units of power.
  • 3. Sector experts point out that this has made wind power generation more expensive for WEGs. Erratic payments from discom While TNERC tightened the noose on one side, several wind energy generators say that they are left with no guarantee of payments from TANGEDCO for the power units added to the grid. Many WEGs in Tamil Nadu have payments outstanding for the last 20 months, says K Kasturirangan of IWPA, . He adds that along with the lack of regular payment, clauses in the Power Purchase Agreements (PPA) entered between the WEGs and the discom restrict generators from seeking other means to sell power and get paid. This discourages many from entering the sector. The senior TNEB official admits that delayed payments are due to TANGEDCO reporting huge losses, over Rs 7500 crore for 2017-18. He argues, however, that giving options for WEGs to review or cancel the PPAs will lead to the opening of a Pandora’s box. “It can really affect our energy security because we calculate our own availability and forecast based on these kind of PPAs. So if the PPAs start getting cancelled or reviewed, then it totally upsets our planning,” he explains. Pointing out that payment issues are not unique to Tamil Nadu alone, Deepak Krishnan says, “Breaking a contract with TANGEDCO right now and selling power to someone is a challenge as of now, because the main question then is 'Where do you sell?'.” He also adds that if the plan is to sell to some customers in north India, then the next issue would be to figure out how to go about it. “If gradually all generators are moved to a competitive market, then it can become much more interesting, because when you operate in a market, all buyers (utilities and other big factories) will have to put some earnest deposit money before the contract starts etc. This will at least ensure payments to generators, easing up the situation a little,” he adds. Solar eating into wind’s share Deepak also flags another major problem that is reportedly facing Tamil Nadu’s wind energy sector and by extension the renewable energy sector. Solar energy, he says, is slowly eating into the market share of wind energy. “When a state is planning its energy bills across its next five to ten years, it would have factored in some mix of thermal with renewable energy. In the renewable energy, for example, 25% would have been for wind and 15% for solar. Theoretical assumption is that as solar cost starts falling lower and lower, they would effectively start eating into the thermal share. But what has happened is because of the cost decrease, and the notion of the discom that without thermal the system won’t function well, the obvious victim has been wind energy,” he explains. Moreover, the Union government’s move to cut the tax benefit for WEGs from 2017-18 has also disincentivised the generation of wind energy. Need for reliable power source Since wind and solar energy are intermittent energy sources, the state’s electricity board is dependent on thermal power plants for ensuring that the grid is steady. Given that the demand for
  • 4. electricity peaks after sunset, relying on wind or solar power to be the source for base load supply is out of the question. This non-reliability also puts the state a few steps back from being a 100% green-energy state. “The problem with thermal generation is that you cannot switch it on and off instantly. It takes several hours for any plant to light up the boiler after shut down. It also increases the wear and tear of these plants, adding to the cost since these plants are designed only for a stable load. So it is always advisable to have these plants running at some technical minimum. Our experience is that it is not technically feasible to keep running them at very low capacity utilisation,” says the TNEB official. The officer, however, adds that in spite of sophisticated forecasting models, the discom isn’t able to predict the unexpected increase or fall in wind energy generation. “That really creates a problem for us in terms of grid management. We are expected by law to operate within a very narrow band of frequency and if we violate, we will be liable to pay a penalty to the national regulator,” he says, further explaining that having a dependable, solid source for supplying base load is crucial.
  • 5. DONE BY: V.SREENIVAS REDDY 19BME0602