In-Flight WiFi
Presented to the RAA-FTC
The Program at a Glance
• This is a Delta Connection program only.
• Installation will occur only on the 2-Class
  configured airplanes:
   – This includes our CRJ700 and CRJ900 airplanes.
   – This does not include our CRJ200 or EMB145
     airplanes.
• The official service kicked off last week with a
  publicized event:
   – Free WiFi for all the people riding our airplane that
     day.
   – Completed 5 legs.
This Presentation
• Mainly from a Flight Operations point of view as I
  didn’t have much to do with Maintenance side of
  this project.
• An overview of the STC process.
• An overview of the production installation plans.
• The WiFi system and its operation.
• The flight tests.
• Operational impact.
STC Prototype - Overview
• Planning for this program has been happening
  for nearly a year.
• N722EV (CRJ700) was designated to be the
  prototype airplane.
• The installation was planned for this airplane at
  the Bombardier facility in Macon, GA.
• The installation occurred during the last 10 days
  or so of the scheduled C-Check.
STC Prototype - Overview
• August 6 (ish): Ship 722 came out of MCN after
  the completed C-Check.
  – It was planned to complete the ground and flight tests
    then, but there were some scheduling issues with the
    AirCell DER/DAR folks.
  – The system was deactivated and the airplane placed
    back into service.
• August 20: Ship 722 was taken out of service in
  Atlanta where the ground tests were completed.
• August 21: Ship 722 completed the two phase
  flight testing required
  – Discuss this in a moment.
STC Prototype - Overview
• August 22: Ship 722 was moved to GLH for new
  Delta paint.
• September 2: The STC was approved.
• September 5: Came out of GLH to ATL.
  – I flew this one and got pictures for the RAA 
• September 7: The Dog & Pony show.
• September 9: AirCell received PMA for the
  installation kits.
• September 11: 10 kits each were shipped to
  IAH and DFW.
Production Installations
• September 12: N708EV was routed to IAH for
  the first production install.
  – AirCell plans on 4 “ramp up” installations:
     • 3 days – 2 days – 2 days – 1 day
• After the first 4, they are planning these
  installations for a 12 to 14 hour overnight.
• All will be done in IAH.
• Comair airplanes are being done during the
  same time period in DFW.
• The other DCI carriers will follow.
The System
Power:  CB Location
CBP2 – E10 (AC Service Bus)
The System

CWAP (Cabin Wireless Access Point)
Location: Left – Forward Closet

                         No idea what this is 
                         for.




              ON/OFF switch
The System




CWAP Antenna
Location: Left – Forward Closet
The System




             CWAP 2
Location – Left/Aft Last Row
The System




         CWAP 2 
         Antenna
Location – Left/Aft Last Row
The System




  ABS (Airborne Broadband System) Rack
Location – Aft Cargo Bin
   (FWD Bulkhead)
The System




  ABS Antenna 1   ABS Antenna 2
Location: Bottom AFT & FWD
The System




      PCS Antenna
Location: Upper Aft (ish)
Flight Test
• ATL to PIE and back.
• 2 separate tests were performed on the same
  flight:
  – EMI testing
  – Cargo smoke testing
Operational Impacts
• Atlantic Southeast fleet is set for completion by
  November 8th, barring any problems.
   – We canceled one of six paint lines to help meet this
     goal.
• Slight shift aft of the empty CG – less than half a
  percent MAC.
• Aft cargo bin reduced maximum weight by 90
  pounds.
   – 3,740 to 3,650 pounds.
• A bunch of cool WiFi placards in the cabin.

Raa.ftc.ev.in flightwifi

  • 1.
  • 2.
    The Program ata Glance • This is a Delta Connection program only. • Installation will occur only on the 2-Class configured airplanes: – This includes our CRJ700 and CRJ900 airplanes. – This does not include our CRJ200 or EMB145 airplanes. • The official service kicked off last week with a publicized event: – Free WiFi for all the people riding our airplane that day. – Completed 5 legs.
  • 3.
    This Presentation • Mainlyfrom a Flight Operations point of view as I didn’t have much to do with Maintenance side of this project. • An overview of the STC process. • An overview of the production installation plans. • The WiFi system and its operation. • The flight tests. • Operational impact.
  • 4.
    STC Prototype -Overview • Planning for this program has been happening for nearly a year. • N722EV (CRJ700) was designated to be the prototype airplane. • The installation was planned for this airplane at the Bombardier facility in Macon, GA. • The installation occurred during the last 10 days or so of the scheduled C-Check.
  • 5.
    STC Prototype -Overview • August 6 (ish): Ship 722 came out of MCN after the completed C-Check. – It was planned to complete the ground and flight tests then, but there were some scheduling issues with the AirCell DER/DAR folks. – The system was deactivated and the airplane placed back into service. • August 20: Ship 722 was taken out of service in Atlanta where the ground tests were completed. • August 21: Ship 722 completed the two phase flight testing required – Discuss this in a moment.
  • 6.
    STC Prototype -Overview • August 22: Ship 722 was moved to GLH for new Delta paint. • September 2: The STC was approved. • September 5: Came out of GLH to ATL. – I flew this one and got pictures for the RAA  • September 7: The Dog & Pony show. • September 9: AirCell received PMA for the installation kits. • September 11: 10 kits each were shipped to IAH and DFW.
  • 7.
    Production Installations • September12: N708EV was routed to IAH for the first production install. – AirCell plans on 4 “ramp up” installations: • 3 days – 2 days – 2 days – 1 day • After the first 4, they are planning these installations for a 12 to 14 hour overnight. • All will be done in IAH. • Comair airplanes are being done during the same time period in DFW. • The other DCI carriers will follow.
  • 8.
  • 9.
    CBP2 – E10(AC Service Bus)
  • 10.
  • 11.
    Location: Left –Forward Closet No idea what this is  for. ON/OFF switch
  • 12.
  • 13.
    Location: Left –Forward Closet
  • 14.
    The System CWAP 2
  • 15.
  • 16.
    The System CWAP 2  Antenna
  • 17.
  • 18.
    The System ABS (Airborne Broadband System) Rack
  • 19.
    Location – AftCargo Bin (FWD Bulkhead)
  • 20.
    The System ABS Antenna 1 ABS Antenna 2
  • 21.
  • 22.
    The System PCS Antenna
  • 23.
  • 24.
    Flight Test • ATLto PIE and back. • 2 separate tests were performed on the same flight: – EMI testing – Cargo smoke testing
  • 25.
    Operational Impacts • AtlanticSoutheast fleet is set for completion by November 8th, barring any problems. – We canceled one of six paint lines to help meet this goal. • Slight shift aft of the empty CG – less than half a percent MAC. • Aft cargo bin reduced maximum weight by 90 pounds. – 3,740 to 3,650 pounds. • A bunch of cool WiFi placards in the cabin.