QUESTIONS

1. Which of the following is not an example of constraints that can limit flexibility in the
Acquire Project Team process?

A) Organizational structure
B) Resource availability
C) Location
D) Activity resource requirements




2. Question: You are managing a telecommunication project. Three project teams are working for you. Each team
contains four engineers and a team lead. The job requirements is such that there is no requirement for cross-team
communications; every person is only communicating within his team. Only team leads are reporting to you, and in
situations where information from one team is required to be passed on to another team, this information goes through
you. How many communications channels do you have in this scenario?

A. 36
B. 30
C. 33
D. 120




3. Which of the following tools & techniques are used to create a Communications Management Plan?

A) Communications Requirements Analysis & Communications Technology.
B) Communications Skills & Lessons Learned Process.
C) Stakeholder Analysis & Project Scope Statement.
D) Communication Channels & Work Performance Information.




4. Question: "Activity / Duration / Predecessor

A / 4 / START
B/3/A
C/1/B
D / 5 / START
E/4/D
F/6/E
G / 2 / C,F
H/4/D
I/2/H

What is the duration of the critical path?"

A. 10
B. 11
C. 17
D. 18




5. CPI is 1.03 and AC is 6000. How much is EV?
A) 200
B) 7000
C) 6180
D) 7200

.

6 Which of the following strategies are suggested to deal with threats or risks that have
negative impact on projects?

A) Avoid, transfer or enhance.
B) Exploit, share or enhance
C) Avoid, transfer or mitigate
D) Avoid, exploit or mitigate




7. Question: "You are managing a construction project. You are currently estimating the duration of a very critical
activity. You have gathered the following information from the experts:
Best case scenario: Activity can take 3 days to complete.
Worst case scenario: Activity may take up to 12 days to complete.
Expected scenario: On average it takes up to 6 days to complete such activities.

What duration you will put into your schedule for this activity if you want to put some weight on the expected
scenario?"

A. 7 days
B. 7.5 days
C. 6 days
D. 6.5 days

8. What is the work breakdown structure (WBS)?

A) It is a deliverable-oriented hierarchical decomposition of the work
to be executed by the project team, to accomplish the project
objectives and create the required deliverables.

B) It is a hierarchically organized depiction of the project organization
arranged so that the work packages can be related to the
performing organizational unit.

C) It is a hierarchically organized depiction of the resources by type
to be used on the project.

D) It is a hierarchical tabulation of the physical assemblies,
subassemblies and component needed to fabricate a
manufactured product.

9. Which of the following may be considered as the outputs of performing Quality Assurance?

A) Requested changes, recommended corrective actions, organizational process assets, project management plan.

B) Requested changes, requested preventive actions,Quality metrics

C) Quality management plan, Quality metrics, Quality baseline

D) Quality control measurements, recommended preventive actions
10.Corrective action is:

A. Fixing past anomalies

B. Anything done to bring the project's future performance in like with the project management plan.

C. The responsibility of the change control board

D. An output of project plan execution.
ANSWERS

1. The Answer is D.

Source: http://pmhub.net/forums/viewtopic.php?f=102&t=15574


2. Hint : To simplify the mesh, there are teams each having 5 members, then there is another management team
containing you and the three team leads.
Correct : C
Reference: PMBOK4 - pg:253

source: http://pmhub.net/forums/viewtopic.php?f=102&t=15579

PMBOK Section: Manage Stakeholder Expectations
Process Group: Executing Process Group
Question Type: Calculation
Knowledge Area: Communications Management
Difficulty Level: Hard

Explanation: Each team contains 4 engineers and a team lead. So the total number of internal team communications
channels are 5*4/2 = 10. Since there are three such teams, so the total of all internal team communications channels is
30. Since three team leads are also reporting to you and not with each other, that adds three more communication
channels. So the total number of project communication channels is 33. Choice C is the correct answer to this question.

3. Souce: http://pmhub.net/forums/viewtopic.php?f=102&t=15585

4. source: http://pmhub.net/forums/viewtopic.php?f=102&t=15613

Answer
PMBOK Section: Sequence Activities
Process Group: Planning Process Group
Question Type: Calculation
Knowledge Area: Time Management
Difficulty Level: Moderate

Hint : Use PDM to calculate.
Reference: PMBOK4 – pg:138

The answer is C.
Explanation: The duration of the critical path for the given data is 17. Hence choice C is correct while rest of the
choices are incorrect.

5. The Answer is C

6. http://pmhub.net/forums/viewtopic.php?f=102&t=15633

7. Answer: http://pmhub.net/forums/viewtopic.php?f=102&t=15639

Hint : Use PERT to calculate.
Reference: PMBOK4 – pg:150

Explanation:Since you want to put some weight on the expected scenario, you will use the PERT formula. Your
estimate will then be 6.5 days. Hence choice D is the correct answer.
8.http://pmhub.net/forums/viewtopic.php?f=102&t=15657

9. http://pmhub.net/forums/viewtopic.php?f=102&t=15661

10. Answer is B

http://pmhub.net/forums/viewtopic.php?f=50&t=15343

More Related Content

Similar to Questions

1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
jackiewalcutt
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
alfred4lewis58146
 
Pmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitionerPmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitioner
Isabella789
 
POM 3 JUNE 2022 PROJECT MANAGEMENT QUESTION.pdf
POM 3 JUNE 2022 PROJECT MANAGEMENT QUESTION.pdfPOM 3 JUNE 2022 PROJECT MANAGEMENT QUESTION.pdf
POM 3 JUNE 2022 PROJECT MANAGEMENT QUESTION.pdf
Alison Tutors
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
IRESH3
 
910 - Questions.pdf
910 - Questions.pdf910 - Questions.pdf
910 - Questions.pdf
Nguyen Hai
 
Pmp6
Pmp6Pmp6
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comPROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
RoelofMerwe131
 
PROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comPROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.com
agathachristie149
 
PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.com
venkat60045
 
Final project se
Final project seFinal project se
Final project se
nadeem shahzad
 
CAPM Study Session 2
CAPM Study Session 2CAPM Study Session 2
CAPM Study Session 2
Kinetic Potential
 
Department of Business & ComputingProgramme TitleBTEC HND.docx
Department of Business & ComputingProgramme TitleBTEC HND.docxDepartment of Business & ComputingProgramme TitleBTEC HND.docx
Department of Business & ComputingProgramme TitleBTEC HND.docx
theodorelove43763
 
PROJ 586 Entire Course NEW
PROJ 586 Entire Course NEWPROJ 586 Entire Course NEW
PROJ 586 Entire Course NEW
shyamuopuoptwelve
 
Pmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magicPmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magic
Ellina Beckman
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project Summary
Minhas Kamal
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
Hussain111321
 
Project management slides
Project management slidesProject management slides
Project management slides
President Career Development Academy
 
Project management
Project managementProject management

Similar to Questions (20)

1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
Pmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitionerPmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitioner
 
POM 3 JUNE 2022 PROJECT MANAGEMENT QUESTION.pdf
POM 3 JUNE 2022 PROJECT MANAGEMENT QUESTION.pdfPOM 3 JUNE 2022 PROJECT MANAGEMENT QUESTION.pdf
POM 3 JUNE 2022 PROJECT MANAGEMENT QUESTION.pdf
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
 
910 - Questions.pdf
910 - Questions.pdf910 - Questions.pdf
910 - Questions.pdf
 
Pmp6
Pmp6Pmp6
Pmp6
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comPROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
 
PROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comPROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.com
 
PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.com
 
Final project se
Final project seFinal project se
Final project se
 
CAPM Study Session 2
CAPM Study Session 2CAPM Study Session 2
CAPM Study Session 2
 
Department of Business & ComputingProgramme TitleBTEC HND.docx
Department of Business & ComputingProgramme TitleBTEC HND.docxDepartment of Business & ComputingProgramme TitleBTEC HND.docx
Department of Business & ComputingProgramme TitleBTEC HND.docx
 
PROJ 586 Entire Course NEW
PROJ 586 Entire Course NEWPROJ 586 Entire Course NEW
PROJ 586 Entire Course NEW
 
Pmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magicPmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magic
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project Summary
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
 
Project management slides
Project management slidesProject management slides
Project management slides
 
Project management
Project managementProject management
Project management
 

Recently uploaded

DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
katiejasper96
 
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
The Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac SignThe Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac Sign
my Pandit
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
➑➌➋➑➒➎➑➑➊➍
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
Cambridge Product Management Network
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
HajeJanKamps
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
irhcs
 
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
Ksquare Energy Pvt. Ltd.
 
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
IPLTech Electric
 
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip
 
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium PresentationKirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Niswey
 
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
BBPMedia1
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
ZevinAttisha
 
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdfRegistered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
dazzjoker
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
valvereliz227
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 

Recently uploaded (20)

DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
 
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
 
The Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac SignThe Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac Sign
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
 
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
 
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
 
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
 
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium PresentationKirill Klip GEM Royalty TNR Gold Lithium Presentation
Kirill Klip GEM Royalty TNR Gold Lithium Presentation
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
 
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
 
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdfRegistered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
IMG_20240615_091110.pdf dpboss guessing
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
 

Questions

  • 1. QUESTIONS 1. Which of the following is not an example of constraints that can limit flexibility in the Acquire Project Team process? A) Organizational structure B) Resource availability C) Location D) Activity resource requirements 2. Question: You are managing a telecommunication project. Three project teams are working for you. Each team contains four engineers and a team lead. The job requirements is such that there is no requirement for cross-team communications; every person is only communicating within his team. Only team leads are reporting to you, and in situations where information from one team is required to be passed on to another team, this information goes through you. How many communications channels do you have in this scenario? A. 36 B. 30 C. 33 D. 120 3. Which of the following tools & techniques are used to create a Communications Management Plan? A) Communications Requirements Analysis & Communications Technology. B) Communications Skills & Lessons Learned Process. C) Stakeholder Analysis & Project Scope Statement. D) Communication Channels & Work Performance Information. 4. Question: "Activity / Duration / Predecessor A / 4 / START B/3/A C/1/B D / 5 / START E/4/D F/6/E G / 2 / C,F H/4/D I/2/H What is the duration of the critical path?" A. 10 B. 11 C. 17 D. 18 5. CPI is 1.03 and AC is 6000. How much is EV?
  • 2. A) 200 B) 7000 C) 6180 D) 7200 . 6 Which of the following strategies are suggested to deal with threats or risks that have negative impact on projects? A) Avoid, transfer or enhance. B) Exploit, share or enhance C) Avoid, transfer or mitigate D) Avoid, exploit or mitigate 7. Question: "You are managing a construction project. You are currently estimating the duration of a very critical activity. You have gathered the following information from the experts: Best case scenario: Activity can take 3 days to complete. Worst case scenario: Activity may take up to 12 days to complete. Expected scenario: On average it takes up to 6 days to complete such activities. What duration you will put into your schedule for this activity if you want to put some weight on the expected scenario?" A. 7 days B. 7.5 days C. 6 days D. 6.5 days 8. What is the work breakdown structure (WBS)? A) It is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables. B) It is a hierarchically organized depiction of the project organization arranged so that the work packages can be related to the performing organizational unit. C) It is a hierarchically organized depiction of the resources by type to be used on the project. D) It is a hierarchical tabulation of the physical assemblies, subassemblies and component needed to fabricate a manufactured product. 9. Which of the following may be considered as the outputs of performing Quality Assurance? A) Requested changes, recommended corrective actions, organizational process assets, project management plan. B) Requested changes, requested preventive actions,Quality metrics C) Quality management plan, Quality metrics, Quality baseline D) Quality control measurements, recommended preventive actions
  • 3. 10.Corrective action is: A. Fixing past anomalies B. Anything done to bring the project's future performance in like with the project management plan. C. The responsibility of the change control board D. An output of project plan execution.
  • 4. ANSWERS 1. The Answer is D. Source: http://pmhub.net/forums/viewtopic.php?f=102&t=15574 2. Hint : To simplify the mesh, there are teams each having 5 members, then there is another management team containing you and the three team leads. Correct : C Reference: PMBOK4 - pg:253 source: http://pmhub.net/forums/viewtopic.php?f=102&t=15579 PMBOK Section: Manage Stakeholder Expectations Process Group: Executing Process Group Question Type: Calculation Knowledge Area: Communications Management Difficulty Level: Hard Explanation: Each team contains 4 engineers and a team lead. So the total number of internal team communications channels are 5*4/2 = 10. Since there are three such teams, so the total of all internal team communications channels is 30. Since three team leads are also reporting to you and not with each other, that adds three more communication channels. So the total number of project communication channels is 33. Choice C is the correct answer to this question. 3. Souce: http://pmhub.net/forums/viewtopic.php?f=102&t=15585 4. source: http://pmhub.net/forums/viewtopic.php?f=102&t=15613 Answer PMBOK Section: Sequence Activities Process Group: Planning Process Group Question Type: Calculation Knowledge Area: Time Management Difficulty Level: Moderate Hint : Use PDM to calculate. Reference: PMBOK4 – pg:138 The answer is C. Explanation: The duration of the critical path for the given data is 17. Hence choice C is correct while rest of the choices are incorrect. 5. The Answer is C 6. http://pmhub.net/forums/viewtopic.php?f=102&t=15633 7. Answer: http://pmhub.net/forums/viewtopic.php?f=102&t=15639 Hint : Use PERT to calculate. Reference: PMBOK4 – pg:150 Explanation:Since you want to put some weight on the expected scenario, you will use the PERT formula. Your estimate will then be 6.5 days. Hence choice D is the correct answer.