3. 3
Basic Elements to Calculate :-
Pressure
1. Required Air Pressure for Components
Flow Rate
1. Total Air Flow from Compressors
2. Total Air Consumption by machines
Temperature
1. Ambient Temperature
2. Medium Temperature
Air Quality
1. Air Efficency(Grade of Filtration)
4. 4
Pneumatic Calculations Include:-
Air Production Ratio.
Air Pressure Drop.
Air Purification Percentage.
Air Consumption.
Required Pressure at Different Stages.
Required Temperature.
Pneumatic Components Calculations
Components Function.
Solution to increase efficiency.
5. 5
Air Production Ratio:-
No of Compressor Installed = 11
Make=Comp Air
Total Air Flow Rate = 43.6 m³/min
4.0 m³/min3.75 m³/min
3.65 m³/min 3.65 m³/min 3.75 m³/min
4.0 m³/min 4.0 m³/min 3.75 m³/min 3.75 m³/min
5.5 m³/min 3.60m³/min
6. 6
Air Pressure Drop:-
The pressure drop in a piping system can be divided into two parts
1. Major Pressure Losses(Pipe Losses)
2. Minor Pressure Losses(Losses Through Fittings,Valve,etc)
Equation for Major Losses
p1-p2 = f l /D .1/2 ρv²...........(i)
Equation for Minor Losses
p1-p2 = r ∑hL. ………………..(ii)
Where:-
ρ =Density of Fluid (slugs/ft³)
v=Velocity of Fuuid(ft/sec)
f=Frictional Factor
l =Pipe Length
D =Diameter of Pipe(in or ft)
r =Specific Weight(lb/ft³)
hL =Head Loss(ft)
Total Pressure Loss =Major Losses + Minor Losses
Result:-
According to calculation the total Air pressure drop From Compressor to Machine is 11.2 psi
that is approximately equal to 1bar.
7. 7
Calculation of Pressure Drop:-
The Moody friction factor - λ (or f) - is used in the Darcy-Weisbach major
loss equation. The coefficient can be estimated with the diagram below:
If the flow is transient - 2300 < Re < 4000 - the flow varies between laminar
and turbulent flow and the friction coefiicient is not possible to determine.
The friction factor can usually be interpolated between the laminar value at
Re = 2300 and the turbulent value at Re = 4000.
9. 9
Air Purification Percentage:-
Number of Filters used from Compressor to PU Hall
1. 1st in Compressor For (Inlet Air)
2. After Air Storage Tank (Manual Drain)
3. Under Machine(Upto 40µ)
4. Dryer is installed before ISO Tank(100%)
Solution:-
The Air Quality is not good we must Install Dryer after
Compressor and also install Active carbon filter after air
filter mounted on dryer in material tanks.
10. 10
Air Consumption:-
AIR CONSUMPTION
The air consumption data for a cylinder is required to
estimate the compressor capacity. The calculations include
air consumption during forward as well as return stroke. The free air
consumption for forward stroke is calculated as
follows:
Free air consumption = piston area x (operating pressure +1.013) x
stroke
The free air consumption for return stroke is also calculated
similarly and added to arrive at total free air consumption of
cylinder during one complete cycle.
11. 11
Theoretical Air Consumption:-
Let
D=Dia of Piston in cm
d=Dia of Piston Rod
L=Stroke Length in cm
P=Pressure in Bar
Free Air Consumption in Liter for forward stroke
C={4/ת x D² x (P+1)x L}/1000
Free Air Consumption in Liter for Return Stroke
C={4/ת x (D²-d²) x (P+1)x L}/1000
12. 12
Pneumatic Components at
Injection Side x 2:-
Pneumatic Cylinders
Air Consumption /per cycle)
ADVU-63-280-APA-S1 11.60 l/cycle
ADVU-63-30-APA-S1 1.24 l/cycle
DNC-50-280-PPV-A 7.08 l/cycle
ADVU-63-50-PPV-A 2.07 l/cycle
Linear Drive(40-250) 6.47 l/cycle
Rotary Cylinder 0.63 l/cycle
Other Equipments
Air Spray Nozzle
Pneumatic Valve
Pressure Switch
Regulators
Distributors
Filters
Nozzle Opening Cylinders
Roller Lever Vlves
13. 13
Pneumatic Componts
Installed at Rotary Table:-
1.Station 1 x 30 Air Consumption per Cycle
ADVU-80-250-A-P-A-SA 16.7 l
DS-80-115-P-SA 7.70 l
DS-80-115-P-SA 7.70 l
Base Moving Cylinder(2 Position) D=200 S.L=4 17.35l
2.Main Components of Supply
Air Storage Tank
Air Filters
Ball Valve Drive Unit
Pressure Gauges
Solenoid Valves
Push Buttons
Pneumatic Fittings
Pneumatic Pipe
Pneumatic Valves
OR Gates
Reed Switched
14. 14
Why Calculating Components
Calculations:-
As in above slide it is mentioned that what parts are
installed in machine and how much air they consume in
one cycle.
As per machine design the total air consumed by one
DESMA Machine in one hour is 88m³ at11 second cycle.
According to these calculation of pneumatic components
we can check that how our machine is consuming air
according to operation) so that we can install better
solution to improve our machine efficiency.
15. 15
Required Pressure:-
Turn Table:-
Main or Compressor------- appro 15bar
Operating Pressure-------- 10bar
Controll Pressure----------- appro 6 bar
Break pressure-------------- app 2 bar
Clamping Unit
Operating Pressure--------- 10 bar
Controll Pressure ----------- 6 bar
Material Tank-----------------Dry Compressed Air app 2 bar
Reaction casting unit-------- operating pressure 10 bar
Controll pressure--------------6 bar
16. 16
Required Temperature:-
Ambient Temperature
The Ambient Temperature is the surrounding
temperature and ambient temperature required
for the installed components are maximum 60-
70°C.
Medium Temperature
Where as the medium temperature is the
temperature of compressed air and it may not be
more than 45°C.
17. 17
Solutions for Improvement:-
As per our Calculation our Flow Rate is Complete and
full fill our machines requirements,
The main problem which we are facing is air leakage that
will not maintain our pressure for that leaked pipe and
fitting should be replaced to save energy
For Better air quality we should use Air Dryer after
compressors
To Get 100 % pure air in material tanks we should use
Active Carbon Filter before Dryer.
For further study we must install flow meter in main air
supply pipe to study in much detail.
19. 19
Data Maintaining Solutions:-
Analysis
Compressed air supply analysis
Compressed air quality analysis
Compressed air consumption measurement
Leakage detection
Planning
Development of leakage management concept
Development of condition monitoring concept
Implementation
Performance of repairs
Implementation of condition monitoring concept
Maintenance
Regular leakage detection 3-2-1 and compressed air quality analysis
Performance of preventive and corrective maintenance 3-2-1
Training
20. 20
Energy analysis of compressed
air production:-
Measurement of compressor operating times as well as load and idling
times
Electricity consumption measurement
Flow measurement/measurement of compressed air consumption
Pressure level and band width measurement
Estimation of leakage volume
Comparison of energy consumption and supplied compressed air volume
Calculation of current energy costs and potential savings
The benefits to us:
Installation of the measuring devices during ongoing operation
Analysis and interpretation of measurement results.
21. 21
Compressed air quality
analysis:-
Clean compressed air – reliable processes and longer service life
for all pneumatic components
How we can Analyze:-
Inspection of the decentralized compressed air preparation at its
point of use
Measurement of residual oil content (up to ISO 8573 Class 2)
Measurement of pressure dew point (up to ISO 8573 Class 2)
Analysis of the results and recommendations for improvement
Documentation of the results
The benefits to us:
Increased life expectancy for pneumatic components
Identification of weak points
Increased process reliability
22. 22
Compressed air consumption
analysis:-
Optimal compressed air provision, reliable cost planning, reliable
processes
How it take parts:
Determining the static compressed air consumption of machines
when at standstill and when they are running
Installation and removal of a metering section with standard parts
(fittings, tubing etc.)
Graphic display of measurement results: either as PDF file or colour
printout
Analysis of the results and suggestions for improvement
Documentation of the results
The benefits to us:
Optimal compressed air supply
Reliable processes
Reliable cost planning
23. 23
Measure for Energy Savings:-
Leakage detection and elimination
1. The greatest potential for savings is in the elimination of leaks. That has been
demonstrated by the independent study “Compressed Air Systems in the European
Union” by the Fraunhofer Institute ISI.
How it take part:
1. Detection of compressed air leaks during operation
2. Inspection of the complete compressed air system, from the compressor to the
pneumatic application
3. Recording and documenting the leaks and the information relevant for repair or
improvement
The benefits:
1. Reduced compressed air requirements and costs
2. Immediate savings of energy and costs with every leak eliminated
3. Production downtime is usually not required
4. Detailed documentation of the leaks discovered including all data required for
eliminating them
24. 24
Benefits
Determine potential savings for compressed air
and save up to 60% of cost the benefits are
given below.
Reduced operating costs
Optimal use of compressor output
Extended service life of components
High system availability
Reliable processes
Energy-efficient and environmentally-friendly system
operation