Project Brief
Introduction To Construction Industry (QSB30105)
Name of project: Budget Hotel
Tutor: Miss Jaqurliyn Ann See Peng
Group members:
Hazel Razon Crisostomo
(0320152)
2
CONTEXT
Jacquelyn Vanessa Tee
(0320021)
3
CONTEXT PAGES
1. INTRODUCTIONTOPROJECT
1.1 Project Description
1.2 Site Analysis
1.3 Project Concept
1.4 Project Background
1.5 Project Summary
1.6 Visuals
 1.6.1 Sketches of Proposed Site
1.7 Project Objectives
1.8 Project Benefits
1.9 Success Criteria
2. RATIONALE& CLIENTEVALUATION
2.1 Issues of the area
2.2 Benefits of the area
2.3 Goals of the construction project
3. PROJECT ORGANIZATION
3.1 Overview
3.2 Team Objective
3.3 Project Management Team
4. DOCUMENTS
4.1 Letter to authorities
4
1.Introductiontoproject
1.1ProjectDescription
For our final project for the subject Introduction to Construction Industry,
we were asked to make a project proposal. Hence, the title – The Project
Proposal. The objective behind this project is to enable us students to
develop an understanding of the building team, its organization, duties
and inter-relations within which they will seek employment, career
progression or further study. Not only that, it is also to develop an
awareness of their professional responsibilities and to appreciate their
professionin the constructionindustry.
Basically, our
project’s name is
called
“Maharajalela
Road Hotel”. It
involves the
construction of a
budget hotel
LOCATION PLAN
The 30M X 30M SITE
N
5
right besidea staircase thatleads to theMaharajalela Monorail Station. The
project is on top of a 30m x 30m vacant ground, located at Jalan
Maharajalela, Kuala Lumpur, Malaysia, with the coordinates of 3°8′20″N
101°41′56″E.
The estimated date for the agreement of the project brief to be signed is on
November 18th
2014. The whole construction process will be up to
approximately6months.
(Si
te
Co
nte
xt)
1. Kuan Yin Temple
6
2. WismaPahlawan
3. Stadium Merdeka
4. Selangor Chinese AssemblyHall
5. M
ahar
ajale
la
Mon
orail
Stati
on
6. MalayanPublic LibraryAssociation
1.2 SiteAnalysis
These arethephotosof thesite.
7
Our site is actually a recent large vacant space. Before this, it was a land
filled with trees. But now that the trees have been timbered down, we came
up with a siteanalysis and it showed that thesiteis ideal for a construction
plan. These are thereasons why:
1. Next to a monorailstation.
 Tourists or locals, who uses the monorail and gets down at
Maharajalela Monorail Station, can stay at our hotel proposed at
this sitebecause ofthe convenience it brings.
2. Approximately10 minutes walk awayfromStadium Merdeka.
 If there’s a sport events held in Stadium Merdeka, thehotel at our
site is the perfect place to spend the night in after a tiring and
fun day/nightthere.
3. Ventilationatthis siteis goodbecause ithas a bigopen space.
 This benefits our hotel at our sitebecause it is cooling and breezy.
Because from a rational perspective, no one wants to stay in a
place where it’s hot and humid. People would usually aim for
places witha comfortabletemperature, and a nice environment.
1.3 PROJECTCONCEPT
We have teamed up to brainstormed and discuss ideas as well as concepts
that fit in this construction project after conducting a site analysis. In
8
conclusion, wecameup with theidea for our finished project to function as
a
placefor peopleto stay in that comes with an affordableprice. Thepricefor
a night in this hotel will be fairly reasonable, which is why it will be a
budget hotel. Our targeted customers are tourists who are finding a fine
placeto livein, and atthe sametimetrying to savemoney.
A green budget hotelbuilding
9
Due to Malaysia’s tropical weather, the exterior of the budget hotel will be
filled with greenery to emit more breezy air to the surroundings. Not only
that, this concept will attract people’s attention. Besides, this concept will
definitely attract theattention of other’s because it is uniqueand it helps in
minimizing the carbon footprints we humans are causing. Basically, it’s a
win-win situation.
1.4 PROJECTBACKGROUND
(Buildingdesign inspirations)
10
Actually, it’s only recently that this site has become a vacant space. Before
this, it is actually filled with trees and tall grass. Now that the trees are
chopped down and some grass got trimmed, this area requires something
for it to be a sight for sore eyes. We think this site is very strategic for a
budget to be located due to the site contexts. For example: Maharajalela
Monorail Station, Kuan Yin Temple, as well as Stadium Merdeka. These site
contexts revolve around thetourism industry, so why not make it easier for
tourist to roam around by building a budget hotel that is so nearby and
convenient? Therefore, weproposed this project.
1.5PROJECTSUMMARY
11
1. A budget hotel will be built to utilize the vacant space in the site we
havechosen.
2. The name of the hotel will be“Maharaja Road Hotel”, in conjunction
ofthe nameofthe roadofwhere it is located.
3. Comfortable hotel rooms’ will built inside and have a simple yet
artisticinterior design.
4. If there is a major sports event held in
Stadium Merdeka, there will be promotions
on theprices ofthe rooms.
5. The exterior of the building will be filled with greenery, for the
surroundings ofthe sitetobebreezy and airy.
6. An underground car park will be built and provided for guests with
cars to park their cars.
7. A muslim praying room will be provided too in the hotel for the
muslim-raced customers.
8. A rooftop garden will bebuilt too that will function as a recreational
area for guests to relax. Garden lamps,
tables, benches and a hammock will be
provided forthe uses ofthe guests.
9. A small gym will also be provided in the
hotel toencourage guests to keep themselves fit and healthy.
12
1.6 VISUALS
1.6.1 Sketches ofProposedSite
(Sketch of proposed budget hotel)
(Sketch of rooftop
garden design, on top
of thehotel)
13
1.7 PROJECTBENEFITS
1. Provideconvenience fortourist and locals
2. To promotegoodbusiness ethics and standards
3. To provide more greenery to the city that is known as a “concrete
jungle”.
1.8 PROJECTSNUMBERING
1. Convenient for sports-goers to stay at the budget hotel we
proposed asStadium Merdeka islocated nearby.
2. Thesiteis strategic to buildabudget hotel.
3. People who just came down from the Maharajalela Monorail
Station could just drop by thebudget hotel to use the restrooms if
needed.
4. The increase of softscape helps in decreasing the negative effects
thatis caused byurban development.
1.9 SUCCESSCRITERIA
1. Thehotel willbebuiltcompletely withintheestimated time.
2. The rooftop garden will be designed with the furniture as well as
floraswithintheestimated timeand alsoestimated budget.
3. Therooms willbefullyfurnished withintheestimated time.
14
4. Furniture in the hotel for all rooms will be within the targeted
budget.
5. Therooftop will havea shadethat can help to protect guests from
UV rays.
6. The gym equipment will be well maintained and always in a
usablemanner.
7. All rooms will have a television provided that comes with a few
selected channels thatare family-friendly.
8. Wi-Fi availabilityforguests.
9. Hotel toprovidegood customer service.
10. Abletoget enough staffforthehotel withinthe estimated time.
15
2.RATIONALEANDCLIENTEVALUATION
Our site that we chose is a 900
square meter (30m x 30m) vacant area
next to the Maharajalela Monorail Station.
After looking at the area features the
advantage and disadvantages we could
design around the site, we settled on the purpose of our site to be: “Budget
Hotel”. For this construction project, we decide to look upon the weakness
of the area currently the facility of study by
doing so, we are able to issues and problems
and propose a plan that can make up for its
shortcomings, particular at the Budget Hotel
area. Through analysis, we have pinpointed the following issues of the area,
which we hope to use this information to create a Budget Hotel area fit for
the clients ofour project.
16
2.1ISSUESOFTHEAREA
1. Few budget hotel and some old hotel is already existing near the
area ofthe site. The competitionforthe walk-in guest is high.
2. The location is exactly opposite of the stadium, that is why when
there is an occasion, event, or concert the area will be noisy and
crowded. Thiswillaffect the peace in the area.
3. The area is a bit dark especially at night. There is inefficient light in
the main roadespecially at night.
2.2BENEFITSOFTHEAREA
1. Location-wise it is great because it is situated in the center of Kuala
Lumpur.
2. Very accessible, because it is near to the Maharajalela Monorail
Station.
3. Walking distance to China Town, Times Square, as well as Bukit
Bintang.These 3 are one ofKuala Lumpur’sfavouritetouristspots.
4. About 15 minutes drive to Petronas Twin Tower that used to hold the
record forWorld’sTallestBuilding Structure.
5. 45 minute drive from the airport.
17
2.3GOALSOFTHECONSTRUCTIONPROJECT
1. Site should besimplisticand idealistic.
2. Utilize the locationand space effectively.
3. Compensate the failuresofthe areato enhance study.
2.4CONCEPT
1. The concept of our project must be able to provide a comfortable
space for the traveler.
2. We also implement a green landscape approach that will help the
guest to feel more connected to the nature & enable to make the
Budget Hotel progress with harmonywiththe nature.
3. It should address the issues of the area particular the issue of sound
effect from stadium specially when there is an occasion going on to
the area as a result we should provide isolation with feeling
claustrophobicthroughwellspace isolationroom.
4. Grassy field and implementation of green approaches provides
customer a relaxing and cozy space as well as encourage green space
into a human lifestyle Isolation rooms provide personal space and
privacyto relax and enjoy the stay in the budget hotel.
5. Open space gives the impression of freedom - more open air
especially in the lobbyarea.
18
3.PROJECTORGANIZATION
3.1Overview
Project Requestor: Dewan BandarayaKuala Lumpur
Project Sponsor: Dewan BandarayaKualaLumpur
Project Owner: Dewan BandarayaKualaLumpur
Project Manager: Ar. Hazel Razon Crisostomo
Team Members: Architect – Ar. Hazel Razon Crisostomo
LandscapeArchitect – Ar. Jacquelyn Vanessa Tee
QuantitySurveyor – Sir. Satesh Raj
Civil&Structural Engineer – Ir. SitiMd. Ezamudin
Mechanical & Electrical Engineer – Pn. Atiqah Syasya
Contractor– Mr. CharelFernando
Supplier – Sir. AbdulQayyumShahmie
3.2TEAMOBJECTIVE
Basically, it is to understand everything such as the need to plan and
design thebuildingfromscratch, toproduce “MaharajalelaRoadHotel”.
19
3.3PROJECTMANAGEMENTTEAM
Key Members Person In-Charge Company
Architect Ar. Hazel Crisostomo H.R.CArchitect Firm
Landscape Architect Ar. JacquelynVanessa JV Landschitecture Firm
QuantitySurveyor Sir. Satesh Raj SR ConstructionBHD.
Civil &Structural Engineer Ir. Siti Md.Ezamudin Siti’s Engineering Firm
Mechanical &Electrical Engineer Pn. Atiqah Syasya Syasya’sElectrical Works

More Related Content

Similar to Proposal for ici 2

Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Reportashleyyeap
 
Theeyefoodcourt 141218142103-conversion-gate02
Theeyefoodcourt 141218142103-conversion-gate02Theeyefoodcourt 141218142103-conversion-gate02
Theeyefoodcourt 141218142103-conversion-gate02danielsong15
 
The eye foodcourt
The eye foodcourtThe eye foodcourt
The eye foodcourtchoo zizhao
 
Ici final project
Ici final projectIci final project
Ici final projectDaniel Tan
 
ICI Final Project Proposal
ICI Final Project ProposalICI Final Project Proposal
ICI Final Project ProposalJunXiang97
 
Landscape architecture design portfolio
Landscape architecture design portfolioLandscape architecture design portfolio
Landscape architecture design portfolioJoan Marie Tachado
 
Building economic
Building economicBuilding economic
Building economictfkc1212
 
Ici- final project
Ici- final projectIci- final project
Ici- final projectdinnahanny
 
Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiKai Yun Pang
 
Ici final report
Ici final reportIci final report
Ici final reportDevin Wong
 
Project management(roro)
Project management(roro)Project management(roro)
Project management(roro)AwZhiXuan
 
Ici - final project
Ici - final projectIci - final project
Ici - final projectleejanett3
 
Ici final project
Ici final project Ici final project
Ici final project Sarah Esa
 

Similar to Proposal for ici 2 (20)

Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Report
 
Theeyefoodcourt 141218142103-conversion-gate02
Theeyefoodcourt 141218142103-conversion-gate02Theeyefoodcourt 141218142103-conversion-gate02
Theeyefoodcourt 141218142103-conversion-gate02
 
The eye foodcourt
The eye foodcourtThe eye foodcourt
The eye foodcourt
 
Ici final project
Ici final projectIci final project
Ici final project
 
ICI Final Project Proposal
ICI Final Project ProposalICI Final Project Proposal
ICI Final Project Proposal
 
Assignment 2
Assignment 2Assignment 2
Assignment 2
 
Pm final
Pm finalPm final
Pm final
 
Landscape architecture design portfolio
Landscape architecture design portfolioLandscape architecture design portfolio
Landscape architecture design portfolio
 
pa 4.pptx
pa 4.pptxpa 4.pptx
pa 4.pptx
 
Building economic
Building economicBuilding economic
Building economic
 
Ici- final project
Ici- final projectIci- final project
Ici- final project
 
Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
 
Mbfc project
Mbfc project Mbfc project
Mbfc project
 
LGMCL TPD Profile 2017
LGMCL TPD Profile 2017LGMCL TPD Profile 2017
LGMCL TPD Profile 2017
 
Group bel assingment
Group bel assingmentGroup bel assingment
Group bel assingment
 
Ici final report
Ici final reportIci final report
Ici final report
 
Project management(roro)
Project management(roro)Project management(roro)
Project management(roro)
 
Ici - final project
Ici - final projectIci - final project
Ici - final project
 
Ici final project
Ici final project Ici final project
Ici final project
 
Icip3 project brief
Icip3 project briefIcip3 project brief
Icip3 project brief
 

More from Jacquelyn Vanessa (20)

Facility management
Facility managementFacility management
Facility management
 
Management science
Management scienceManagement science
Management science
 
Bs2individualassignment
Bs2individualassignmentBs2individualassignment
Bs2individualassignment
 
Ct3 presentation slides
Ct3 presentation slidesCt3 presentation slides
Ct3 presentation slides
 
Ct3
Ct3Ct3
Ct3
 
Bs2 presentation
Bs2 presentation Bs2 presentation
Bs2 presentation
 
Buildingservicesi igroup
Buildingservicesi igroupBuildingservicesi igroup
Buildingservicesi igroup
 
Water treatment for domestic water supply 2
Water treatment for domestic water supply 2Water treatment for domestic water supply 2
Water treatment for domestic water supply 2
 
Water treatment for domestic water supply
Water treatment for domestic water supplyWater treatment for domestic water supply
Water treatment for domestic water supply
 
Bs1
Bs1Bs1
Bs1
 
M2 project assignment aug 2016
M2 project assignment aug 2016M2 project assignment aug 2016
M2 project assignment aug 2016
 
Case Study Report
Case Study ReportCase Study Report
Case Study Report
 
Design project one brief
Design project one   briefDesign project one   brief
Design project one brief
 
Dpj 02 brief
Dpj 02 briefDpj 02 brief
Dpj 02 brief
 
Design e portfolio brief
Design e portfolio briefDesign e portfolio brief
Design e portfolio brief
 
Design project two brief-2
Design project two   brief-2 Design project two   brief-2
Design project two brief-2
 
Design design process journal brief 5
Design design process journal brief 5Design design process journal brief 5
Design design process journal brief 5
 
The design process journal 01 2
The design process journal 01 2The design process journal 01 2
The design process journal 01 2
 
Psychologyreport
PsychologyreportPsychologyreport
Psychologyreport
 
Psychology film slides
Psychology film slidesPsychology film slides
Psychology film slides
 

Recently uploaded

BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 

Recently uploaded (20)

BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 

Proposal for ici 2

  • 1. 1 Project Brief Introduction To Construction Industry (QSB30105) Name of project: Budget Hotel Tutor: Miss Jaqurliyn Ann See Peng Group members: Hazel Razon Crisostomo (0320152)
  • 3. 3 CONTEXT PAGES 1. INTRODUCTIONTOPROJECT 1.1 Project Description 1.2 Site Analysis 1.3 Project Concept 1.4 Project Background 1.5 Project Summary 1.6 Visuals  1.6.1 Sketches of Proposed Site 1.7 Project Objectives 1.8 Project Benefits 1.9 Success Criteria 2. RATIONALE& CLIENTEVALUATION 2.1 Issues of the area 2.2 Benefits of the area 2.3 Goals of the construction project 3. PROJECT ORGANIZATION 3.1 Overview 3.2 Team Objective 3.3 Project Management Team 4. DOCUMENTS 4.1 Letter to authorities
  • 4. 4 1.Introductiontoproject 1.1ProjectDescription For our final project for the subject Introduction to Construction Industry, we were asked to make a project proposal. Hence, the title – The Project Proposal. The objective behind this project is to enable us students to develop an understanding of the building team, its organization, duties and inter-relations within which they will seek employment, career progression or further study. Not only that, it is also to develop an awareness of their professional responsibilities and to appreciate their professionin the constructionindustry. Basically, our project’s name is called “Maharajalela Road Hotel”. It involves the construction of a budget hotel LOCATION PLAN The 30M X 30M SITE N
  • 5. 5 right besidea staircase thatleads to theMaharajalela Monorail Station. The project is on top of a 30m x 30m vacant ground, located at Jalan Maharajalela, Kuala Lumpur, Malaysia, with the coordinates of 3°8′20″N 101°41′56″E. The estimated date for the agreement of the project brief to be signed is on November 18th 2014. The whole construction process will be up to approximately6months. (Si te Co nte xt) 1. Kuan Yin Temple
  • 6. 6 2. WismaPahlawan 3. Stadium Merdeka 4. Selangor Chinese AssemblyHall 5. M ahar ajale la Mon orail Stati on 6. MalayanPublic LibraryAssociation 1.2 SiteAnalysis These arethephotosof thesite.
  • 7. 7 Our site is actually a recent large vacant space. Before this, it was a land filled with trees. But now that the trees have been timbered down, we came up with a siteanalysis and it showed that thesiteis ideal for a construction plan. These are thereasons why: 1. Next to a monorailstation.  Tourists or locals, who uses the monorail and gets down at Maharajalela Monorail Station, can stay at our hotel proposed at this sitebecause ofthe convenience it brings. 2. Approximately10 minutes walk awayfromStadium Merdeka.  If there’s a sport events held in Stadium Merdeka, thehotel at our site is the perfect place to spend the night in after a tiring and fun day/nightthere. 3. Ventilationatthis siteis goodbecause ithas a bigopen space.  This benefits our hotel at our sitebecause it is cooling and breezy. Because from a rational perspective, no one wants to stay in a place where it’s hot and humid. People would usually aim for places witha comfortabletemperature, and a nice environment. 1.3 PROJECTCONCEPT We have teamed up to brainstormed and discuss ideas as well as concepts that fit in this construction project after conducting a site analysis. In
  • 8. 8 conclusion, wecameup with theidea for our finished project to function as a placefor peopleto stay in that comes with an affordableprice. Thepricefor a night in this hotel will be fairly reasonable, which is why it will be a budget hotel. Our targeted customers are tourists who are finding a fine placeto livein, and atthe sametimetrying to savemoney. A green budget hotelbuilding
  • 9. 9 Due to Malaysia’s tropical weather, the exterior of the budget hotel will be filled with greenery to emit more breezy air to the surroundings. Not only that, this concept will attract people’s attention. Besides, this concept will definitely attract theattention of other’s because it is uniqueand it helps in minimizing the carbon footprints we humans are causing. Basically, it’s a win-win situation. 1.4 PROJECTBACKGROUND (Buildingdesign inspirations)
  • 10. 10 Actually, it’s only recently that this site has become a vacant space. Before this, it is actually filled with trees and tall grass. Now that the trees are chopped down and some grass got trimmed, this area requires something for it to be a sight for sore eyes. We think this site is very strategic for a budget to be located due to the site contexts. For example: Maharajalela Monorail Station, Kuan Yin Temple, as well as Stadium Merdeka. These site contexts revolve around thetourism industry, so why not make it easier for tourist to roam around by building a budget hotel that is so nearby and convenient? Therefore, weproposed this project. 1.5PROJECTSUMMARY
  • 11. 11 1. A budget hotel will be built to utilize the vacant space in the site we havechosen. 2. The name of the hotel will be“Maharaja Road Hotel”, in conjunction ofthe nameofthe roadofwhere it is located. 3. Comfortable hotel rooms’ will built inside and have a simple yet artisticinterior design. 4. If there is a major sports event held in Stadium Merdeka, there will be promotions on theprices ofthe rooms. 5. The exterior of the building will be filled with greenery, for the surroundings ofthe sitetobebreezy and airy. 6. An underground car park will be built and provided for guests with cars to park their cars. 7. A muslim praying room will be provided too in the hotel for the muslim-raced customers. 8. A rooftop garden will bebuilt too that will function as a recreational area for guests to relax. Garden lamps, tables, benches and a hammock will be provided forthe uses ofthe guests. 9. A small gym will also be provided in the hotel toencourage guests to keep themselves fit and healthy.
  • 12. 12 1.6 VISUALS 1.6.1 Sketches ofProposedSite (Sketch of proposed budget hotel) (Sketch of rooftop garden design, on top of thehotel)
  • 13. 13 1.7 PROJECTBENEFITS 1. Provideconvenience fortourist and locals 2. To promotegoodbusiness ethics and standards 3. To provide more greenery to the city that is known as a “concrete jungle”. 1.8 PROJECTSNUMBERING 1. Convenient for sports-goers to stay at the budget hotel we proposed asStadium Merdeka islocated nearby. 2. Thesiteis strategic to buildabudget hotel. 3. People who just came down from the Maharajalela Monorail Station could just drop by thebudget hotel to use the restrooms if needed. 4. The increase of softscape helps in decreasing the negative effects thatis caused byurban development. 1.9 SUCCESSCRITERIA 1. Thehotel willbebuiltcompletely withintheestimated time. 2. The rooftop garden will be designed with the furniture as well as floraswithintheestimated timeand alsoestimated budget. 3. Therooms willbefullyfurnished withintheestimated time.
  • 14. 14 4. Furniture in the hotel for all rooms will be within the targeted budget. 5. Therooftop will havea shadethat can help to protect guests from UV rays. 6. The gym equipment will be well maintained and always in a usablemanner. 7. All rooms will have a television provided that comes with a few selected channels thatare family-friendly. 8. Wi-Fi availabilityforguests. 9. Hotel toprovidegood customer service. 10. Abletoget enough staffforthehotel withinthe estimated time.
  • 15. 15 2.RATIONALEANDCLIENTEVALUATION Our site that we chose is a 900 square meter (30m x 30m) vacant area next to the Maharajalela Monorail Station. After looking at the area features the advantage and disadvantages we could design around the site, we settled on the purpose of our site to be: “Budget Hotel”. For this construction project, we decide to look upon the weakness of the area currently the facility of study by doing so, we are able to issues and problems and propose a plan that can make up for its shortcomings, particular at the Budget Hotel area. Through analysis, we have pinpointed the following issues of the area, which we hope to use this information to create a Budget Hotel area fit for the clients ofour project.
  • 16. 16 2.1ISSUESOFTHEAREA 1. Few budget hotel and some old hotel is already existing near the area ofthe site. The competitionforthe walk-in guest is high. 2. The location is exactly opposite of the stadium, that is why when there is an occasion, event, or concert the area will be noisy and crowded. Thiswillaffect the peace in the area. 3. The area is a bit dark especially at night. There is inefficient light in the main roadespecially at night. 2.2BENEFITSOFTHEAREA 1. Location-wise it is great because it is situated in the center of Kuala Lumpur. 2. Very accessible, because it is near to the Maharajalela Monorail Station. 3. Walking distance to China Town, Times Square, as well as Bukit Bintang.These 3 are one ofKuala Lumpur’sfavouritetouristspots. 4. About 15 minutes drive to Petronas Twin Tower that used to hold the record forWorld’sTallestBuilding Structure. 5. 45 minute drive from the airport.
  • 17. 17 2.3GOALSOFTHECONSTRUCTIONPROJECT 1. Site should besimplisticand idealistic. 2. Utilize the locationand space effectively. 3. Compensate the failuresofthe areato enhance study. 2.4CONCEPT 1. The concept of our project must be able to provide a comfortable space for the traveler. 2. We also implement a green landscape approach that will help the guest to feel more connected to the nature & enable to make the Budget Hotel progress with harmonywiththe nature. 3. It should address the issues of the area particular the issue of sound effect from stadium specially when there is an occasion going on to the area as a result we should provide isolation with feeling claustrophobicthroughwellspace isolationroom. 4. Grassy field and implementation of green approaches provides customer a relaxing and cozy space as well as encourage green space into a human lifestyle Isolation rooms provide personal space and privacyto relax and enjoy the stay in the budget hotel. 5. Open space gives the impression of freedom - more open air especially in the lobbyarea.
  • 18. 18 3.PROJECTORGANIZATION 3.1Overview Project Requestor: Dewan BandarayaKuala Lumpur Project Sponsor: Dewan BandarayaKualaLumpur Project Owner: Dewan BandarayaKualaLumpur Project Manager: Ar. Hazel Razon Crisostomo Team Members: Architect – Ar. Hazel Razon Crisostomo LandscapeArchitect – Ar. Jacquelyn Vanessa Tee QuantitySurveyor – Sir. Satesh Raj Civil&Structural Engineer – Ir. SitiMd. Ezamudin Mechanical & Electrical Engineer – Pn. Atiqah Syasya Contractor– Mr. CharelFernando Supplier – Sir. AbdulQayyumShahmie 3.2TEAMOBJECTIVE Basically, it is to understand everything such as the need to plan and design thebuildingfromscratch, toproduce “MaharajalelaRoadHotel”.
  • 19. 19 3.3PROJECTMANAGEMENTTEAM Key Members Person In-Charge Company Architect Ar. Hazel Crisostomo H.R.CArchitect Firm Landscape Architect Ar. JacquelynVanessa JV Landschitecture Firm QuantitySurveyor Sir. Satesh Raj SR ConstructionBHD. Civil &Structural Engineer Ir. Siti Md.Ezamudin Siti’s Engineering Firm Mechanical &Electrical Engineer Pn. Atiqah Syasya Syasya’sElectrical Works