Presentation on
Delay and Cost Performance in Construction using Primavera P6 and MSP
Guided by: Mr. D.S.Desale
INTRODUCTION
• Resort constructioninvolves multiple activities (blocks, pool, landscaping) making
time and cost control challenging.
• Delays often arise due to labor, material shortages, or site conditions, leading to
cost overruns.
• Project management tools like MSP and Primavera P6 help in scheduling,
monitoring, and analyzing performance.
• This study applies these tools to a Resort Project to identify lagging activities and
evaluate time–cost performance using Earned Value Management (EVM)
4.
Aim & Objectives
•AIM: To study the role of Primavera and MSP in identifying, managing, and
reducing construction project costs by analyzing scheduling, resource allocation,
and lagging activities.
• OBJECTIVES:
To efficiently plan and schedule construction activities using Primavera.
To identify and eliminate time and cost overruns through tracking tools.
To analyze delays and implement corrective actions.
To optimize resource allocation and reduce idle time.
To enhance overall project performance and cost effectiveness.
5.
Methodology
Collect projectdata (activities, durations, resources).
Develop WBS and input in MSP & Primavera.
Create baseline schedule.
Record actual progress from site visits.
Conduct lagging analysis (planned vs actual).
Apply Critical Path Method and Earned Value Analysis.
Generate dashboards & reports for visualization.
Literature Review
Sr.
No.
Author NameTitle Conclusion
1 K. Suresh Kannan,
M. G. Ranjith
Kumar
Planning and Scheduling
Residential Building
Using Primavera
Software
The project aimed to prepare proper planning and
scheduling for the timely completion of a two-storey
residential building in Dindugal. All activities were
identified, their sequence, duration, and required
resources were planned and scheduled using Primavera
P6 software. The process included defining work tasks,
estimating resources, calculating durations, and
identifying task interactions. The study concludes that
with effective planning and scheduling, the project can
be completed ahead of the contract period, thereby
reducing both time and cost while ensuring efficient
use of resources. This demonstrates the effectiveness
of Primavera in managing residential construction
projects.
8.
Literature Review
Sr.
No.
Author NameTitle Conclusion
2 Rohan S. Deshanur,
Prof. Shashank U.
Vanakudari
Manpower Planning
Estimation and Forecasting
for a Construction Project
Using MSP Software
MSP enables effective manpower planning,
scheduling, and resource allocation, helping control
costs, reduce delays, and ensure timely project
delivery despite challenges like cost fluctuations or
unforeseen conditions.
3 Madhura
Durgaprasad Akant
Risk Management and
Cost Overruns due to
Delays in Construction
Project using Primavera
Primavera P6 enables effective planning, scheduling,
and resource management, helping to minimize
delays, control costs, and mitigate risks, ensuring
efficient and timely project delivery.
4 Himanshu Maurya,
Dr. Gaurav Shukla
Cost Overrun and Delays
in Construction
Management by Using
Primavera
Primavera P6 helps reduce delays and cost overruns
through better planning and resource management.
In the study, it shortened completion by 79 days and
saved ₹31.4 lakhs, proving its effectiveness in
ensuring timely and cost-efficient project delivery.
9.
Literature Review
Sr.
No.
Author NameTitle Conclusion
5 K. Suresh Kannan,
M. G. Ranjith Kumar
Planning and Scheduling
Residential Building Using
Primavera Software
Primavera P6 enabled efficient planning
and scheduling of a two-storey residential
building, ensuring early completion,
reduced cost, and optimal resource use,
proving its effectiveness in residential
construction projects.
6 Harshal V.
Gayakwad, Prof.
Pankaj Attarde
Project Scheduling and Cost
Estimation Using Advanced
Software Tools (MS Project &
Primavera P6)
MS Project is simple and effective for small
to medium projects, while Primavera P6 is
better suited for large-scale construction
due to its advanced features in scheduling,
cost control, and risk management.