This document provides a summary of a project manager role at Canadian Pacific Railway from February 2013 to January 2015. The project successfully migrated the entire mainframe environment, including various technologies, to a vBlock server environment running Dell Unikix in 22 months and within budget. Key accomplishments included managing over 200 resources across multiple countries, converting over 76 applications, 2,100 jobs, and 6,000 files to the new platform, and completing a successful 10-hour production cutover with minimal post-cutover issues.