SlideShare a Scribd company logo
1 | P a g e 
Mantra for Entrepreneurial Project Management 
Bhavesh Thakkar 
Dy Manager 
Gammon India Limited
Decision Analysis for successful Project Investment in midcourse of 
BOT Infrastructure Projects 
2 | P a g e 
Theme – Mantra for Entrepreneurial Project Management 
Abstract 
For any Projects selection, organization invariably undertakes Sensitivity Analysis, if project offers either 
decent IRR or positive NPV. Sensitivity analysis particularly pivots on understanding few key variables 
like revenue fluctuations in Toll etc and its consequences before finally agree to bid / sign the Concession 
Agreement. 
In midcourse, some process excellence or innovative methodologies may emerge to improve bottom line 
or top line which may require considerable investment. Iloiu and Csiminga have devised methodology of 
Sensitivity Analysis using the guided criteria of Switching Value and Sensitivity Indicator which proves to 
be very effective tool for better selection. 
Case Study to reduce Energy Costs of street lighting by using Power Savers, in Operation phase of PLC 
which in turn can improve bottom line and enhances company’s brand value, was taken up in a 4 lane 
divided road project between Rajahmundry and Tuni in Andhra Pradesh on NH 16 using this stated 
approach. 
The analysis provides the following major conclusions: 
On Switching Value: 
a) Up to Impact of 50% increase in Cost in Investment , IRR would be above the Cost of Capital 
thereby NPV will be positive in these range; 
b) But for any reason, Balance Concession Period as envisaged for this analysis gets reduced due 
to capacity augmentation by NHAI or Concessionaire delays in implementing this feasibility 
exercise by more than 28% of balance period, NPV would be less than zero 
On Sensitivity Indicator: 
a) Low sensitivity indicator ranging between 1.2% and 4.9% on cost of equipment and balance 
project duration indicates positive NPV.
3 | P a g e 
Table of Contents 
Sl. No Contents Page No 
1.0 Introduction 3 
2.0 Project Details 3 
3.0 Case genesis of Energy conservation 4 
4.0 Evaluating options 5 
5.0 Field Experimentation 7 
5.1 Fixture of Power Saver 7 
5.2 Fixture of LED Lights 8 
5.3 Comparison of Alternatives 8 
6.0 
Financial model of project investment including capital 
budgeting 
9 
6.1 Method Approach 9 
6.2 WACC analysis and project assumptions 9 
6.3 
Identifying locations of Investment and evaluation of 
alternatives 
10 
7.0 Sensitivity Analysis 12 
7.1 Identification of Variables 13 
7.2 Calculation of effects of changing Variables 13 
7.3 Sensitivity Analysis of risk factors: 14 
8.0 Result observations 14 
9.0 Conclusions 14 
10.0 Acknowledgements 15 
11.0 References 15
4 | P a g e 
1.0 Introduction: 
Survival in infrastructure industry in an environment of highly unorganized section, fragmented, intense 
rivalry, wafer thin margins amidst opportunities for executing Road projects but lacking in supply side 
issues such as non-availability of professional management skill and insufficient equipment had brought 
almost all the companies to an alarming situation because of cost overruns and declining profit margins 
across the board 
This is even particular especially when any investment proposal in O & M Phase of Project Life Cycle is 
not keenly given due importance and as a result, good opportunity is lost for improving bottom line 
especially when projects are being executed on Annuity basis. 
A Case study conducted in our 100 Km Road Project which had approximately 40% of yearly expenses 
towards Energy consumption bills. Feasibility studies states that investment of Rs. 19.7 Lakhs towards 
installing Power Saver Equipment will yield around 25% savings in Energy consumption 
These operational efficiencies if implemented, by infusing capital investment, will enhance brand image, 
improve bottom line, and bring sustainability. Unless the scenario of any future impact due to likely policy 
changes is evaluated it is likely that the decision taken in favorable condition may go haywire and 
therefore Sensitivity Analysis, desirable tool, has to be undertaken using IRR and NPV 
2.0 Project Details: 
it is a 100Km long Operation and Maintenance Road Project of two continuous packages namely 
Rajahmundry Expressway Limited (53 Kms) and Andhra Expressway Limited (47 Kms) being executed by 
Gammon Infrastructure Projects Limited, a subsidiary of Gammon India Limited is in 15 years O & M 
Phase slated to end in Nov 2019. 
In O & M period, Concessionaire has to carry out the routine maintenance works such as Corridor 
Cleaning, Reinstating the damaged / missing road furniture, median plantation, Street lighting, repairs to 
pavement such as pot holes and crack sealing, re-doing the faded road marking, providing emergent first 
aid treatment to accident victims, clearing the blocked vehicles on carriage way etc. besides executing 
periodic maintenance works in every fifth year. 
Among the above, Major component of routine maintenance activities constitute towards incurring the 
energy charges of street lighting which is 42% of total monthly expenses. 
There exists a scope of process improvement amidst customer dissatisfaction in the area of minimizing 
energy consumption
5 | P a g e 
3.0 Case Genesis on Energy Conservation: 
The Project site had provided Street lighting in all urban areas within corridor. Source of power for 
illumination is APGENCO supplied electricity. Barring Toll Plaza location, no other location has any 
standby power generation. 
Package No of locations No of Poles No of bulbs (250 W) 
AP – 15 ( REL) 14 504 880 
AP – 16 ( AEL) 13 774 1157 
Total 27 1278 2037 
Table 1 – Details of Electrical Installations 
The site are in receipt of customer complaints for the below par performance from operational 
deliverables as stipulated in Concession Agreement. 
The root causes of below par performance were evaluated using Fish bone method as drawn below: 
Key 
factor 
Fig 1 – Fish bone diagram of Illumination for below par performance
Out of the above causes, barring Electricity Transmission issues all other parameters are man managed 
with effective planning and execution. While experimenting, it is understood that electrical losses are to 
the extent of 25% in transmission due to fluctuation of voltage termed as Spikes. The sudden voltage 
fluctuations are not considered in inputs by any of the electrical appliances and thus these spikes go as a 
waste of electricity and an alternate solution needs to be adopted to minimize wastage which in turn can 
reduce costs and improve bottom line. 
6 | P a g e 
4.0 Evaluating options 
Life cycle project management is necessary because of turbulent environments (particularly shifting 
markets), the rapid rate at which technology changes, the increasing influence of the host communities 
and stakeholders, and the environmental, social, safety and legal implications of capital projects (Jaafari 
2000; Jaafari & Manivong 2000). 
Fig 2 – Pictorial representation of choosing projects 
To improve the performance, options are explored using Saaty’s analytical hierarchy process which 
advocates usage of weighted average criteria. 
Criteria and qualifying parameters for rating are tabulated below:
7 | P a g e 
Table 2 - Weightage criteria of qualitative parameters of illumination 
Table 4 – Ratings assigned for qualitative deliverables 
However, the evaluation of detailed investment analysis with respect to the balance time of the 
Concession period needs to be computed for preferred lighting (existing setup (SV) lights of Power saver 
vis-à-vis LED lights on conventional electricity 
Physical features of the all the alternatives are studied with the existing provisions before zeroing on 
choosing the options:
But considering the customer need from the above survey and feasibility, two alternatives are possible 
for enhancing the customer satisfaction and meeting road user needs; 
 Addition of spike utilization devices for smoother flow of electricity such as Power Savers 
to the existing setup and assess the power consumption to minimize cost and 
improvement in efficiency; 
 Introduction of new technology of LED lights by replacing the entire Sodium Vapor lamp 
setup which has high investment cost but low power consumption to be evaluated with 
reference to the balance time; 
8 | P a g e 
5.0 Field Experimentation 
Field experimentation at site was undertaken for two options 
5.1 Fixture of Power saver to the existing 250 W Sodium Vapor lamp being operated on 
conventional basis; 
Fig 3 – Power Saver Experimentation Fig 4 – Power Saver Experimentation 
Trial tests were conducted at our AEL Maintenance Yard using Servomax ‘Power Saver’ by fixing Power 
saver to the setup without operating power saver to know the utilization of spikes quantum of energy for 
conserving the electrical energy. 
The readings were taken at one and half hour intervals to also study the fluctuation in voltages and 
ampere readings 
The Summary of the test results are tabulated as under: 
Load Applied : 750 W 
Test duration / day : 12 hours
5.2 Fixture of LED lights functioning on the normal conventional supply from APEPDCL 
Since, the usage of LED lights is in developing stage of introduction at various places in the 
country including our present town, Rajahmundry. Usage of LED lights is a deviated item from 
the scope of works. As such, if at all, it needs to be initiated under NHAI approval for modification 
of scheme. However, if adopted, the following is comparative table 
9 | P a g e 
5.3 Comparison of alternatives 
Table 7 – preliminary comparison of initial costs
In light of obtaining the similar savings in the power, investment of Rs. 41.0 Lakhs is far viable than 
the investment of Rs. 10 Cr. 
10 | P a g e 
6.0 Financial Model for the Project Investment including Capital Budgeting 
“Time is the essence of the Contract” and similarly timely investment is the key driver for 
obtaining the first mover advantage to improve the profitability of the organization. Based on the 
technical findings, it is the time to capitalize the opportunity for investment for obtaining smart 
returns 
The question remains how to tap the savings in energy wattage can be translated into 
income by suitably investing in the system wherein the time and expenses have been 
frozen. 
6.1 Method Approach for analyzing the Project Investment 
The viability of project investment is done in the following sequence 
 Calculate the Savings from the present billing trend; 
 Freeze Project assumptions like tax rates, risk parameters and other components; 
 Do WACC analysis and arrive D/E ratio; 
 Identify the locations of investment ; 
 Evaluate the project feasibility in different conditions; 
 Compute Cash flow statement based on the project assumptions; 
 Determine Internal Rate of Return and Net Present Value on all the parameters; 
 Select the best option inclining towards 15% profitability; 
 Carry out sensitivity analysis; 
6.2 WACC Analysis and Project Assumptions 
WACC Analysis is tabulated below: 
Table 8 – WACC Analysis
11 | P a g e 
Table 9- Project Assumptions 
6.3 Identifying locations of Investment and evaluating various alternatives 
On evaluation of present energy consumption vis-à-vis theoretical gains, 21 locations are chosen 
from 26 locations to be provided with Power Saver Equipment 
Investment feasibility is evaluated for IRR, NPV and Cost Improvements in four conditions 
separately for these two packages: 
 Debt funding in first phase followed by internal accruals in second phase 
 Debt funding in two phases 
 Entire Debt funding at the beginning of project 
 Own Equity at the beginning of the Project 
Sample Result among the eight alternatives is depicted below:
12 | P a g e 
Table 10- IRR and NPV analysis for one of the alternative 
The summary results of all the options are tabulated below for taking appropriate decisions: 
Table 11 – Summary of Project Investment
13 | P a g e 
With the above analysis, it was financially concluded to opt with the below recommendations: 
REL Package: Debt financing in first phase and through internal accruals in second phase 
AEL Package: Entire Debt financing in one go. 
The likely net savings with this above proposal would fetch in improving bottom line by Rs. 7.1 mn in 
balance concession period. 
Table 12 – Final Proposal of Investment 
7.0 Sensitivity Analysis 
The purpose of sensitivity analysis is 
 To help identify the key variables which influence the project cost and benefit streams 
 To investigate the consequences of likely adverse changes in these key variables 
 To assess whether the project decisions are likely to be affected by such changes 
 To identify actions that could mitigate possible adverse effects on the project 
Sensitivity analysis needs to be conducted to understand its impact on both financial and 
economical internal rate of return. Model suggested in this risk evaluation method is based on 
the Technical Paper submitted at Annals of the University of Petrosani, Economics by Mirela 
Iloiu and Diana Csiminga 
Sequence of steps to be adopted:
14 | P a g e 
7.1 Identification of Variables 
Considering the project under study, the author identifies two variables to assess the impact on 
possible changes on the recommended proposal of IRR and NPV on the following risks: 
 Cost of the Assets due to delay in approval from Head Office; 
 Balance Concession period as the adjacent packages have already been awarded for six 
laning works. 
7.2 Calculation of effects of changing Variables: 
The values of the basic indicators of project viability (EIRR and ENPV) should be recalculated for 
different values of key variables. This is preferably done by calculating sensitivity indicators 
and switching values which is reproduced below: 
Table 13 – Explanation of SI and SV
15 | P a g e 
7.3 Sensitivity Analysis of risk factors: 
Financial Model for Price increase of 10% and duration reduction by every one year is prepared 
and analyzed using the above formula and obtain the following results: 
8.0 Result Observations: 
Price Variable: 
The values obtained in Sensitivity Indicator are far less than the discount factor of around 12%. 
As such the price is not critical for both the packages as indicated in Sensitivity Indicator 
On the price front as indicated in switching value, unless increase in prices vary minimum around 
50% to have NPV Value zero equivalent to Cost of Capital. 
Duration Variable 
The values obtained in Sensitivity Indicator are less by around 8 ½ percent as such price is not 
the critical issue 
However on the duration front, switching value indicates that no economic value will be added to 
investment proposal, if duration reduces by 20.40%. 
9.0 Conclusions: 
As a result, Rs. 71 Lakhs can be saved providing annual savings of around 12% in the balance 
concession period of 7 years with Positive NPV and IRR 35%. 
Up to Impact of 50% increase in Cost in Investment, IRR would be above the Cost of Capital 
thereby NPV will be positive in these range; 
But for any reason, either Balance Concession Period as envisaged for this analysis gets reduced 
due to capacity augmentation by NHAI or Concessionaire delays in implementing this feasibility 
exercise by more than 28% of balance period, NPV would be less than zero
Due to cost constraints amidst economic slowdown, Company could not envisage this proposal 
till now and thereby great opportunity is lost now due to balance concession period being only five 
years. However still, if management pursues, it can have process improvement to fulfill green 
objectives and at the time of handover, these power savers can be shifted to other project sites to 
have positive economic value added scenario 
Thus leveraging PM methodologies and leadership skills can launch new innovations at the 
earliest possible time and gain competitive advantage. 
16 | P a g e 
10.0 Acknowledgements 
The Author thanks PMI for giving the opportunity to present the paper. The Author also thanks 
entire team of Rajahmundry Site team comprising M/s. Bhagavan Raju, and other team members 
besides GIPL Management for facilitating this experimentation to give way for this new thought 
process. The Author thanks Mr. D. V Prasad, Power tech solutions for permitting his equipment at 
site for demonstration and evaluation. The Author also thanks Mr. M. U. Shah, member- BoM for 
his constant guidance and encouragement in submitting this paper. The Author also thanks 
various authors shown in the references for providing their various valuable insights in their 
respective fields to culminate this overall innovation into possible new thought process of 
sustainable project execution 
11.0 References: 
1) Concession Agreement signed between REL / AEL with NHAI, Asset Deliverable 
Criteria(2001) , Appendix A of Schedule I, 
2) European Renewable Energy council, Green Peace (2007), A report on Indian National 
Energy Scenario 
3) Giedrius Grondskis, Alfreda Sapkauskiene(2011) – Cost Accounting information use for 
product mix design (Eknomica IR Vadyaba,2011:16) 
4) Jack R. Meredith, Samuel J. Mantel (2010)- Text book of Project Management, a Managerial 
approach, seventh edition 
5) L. Dwayne Barney Jr., Morris G. Danielson(20034) – Ranking mutually exclusive projects – 
The role of duration, The Engineering Economist, 49 , 43 -61 
6) ManTech Associates(2012), Catalogue on Servomax Power Savers by, pp1-3 
7) Mirela Iloiu, Diana Csiminga(2009) – Project risk evaluation methods – Sensitivity Analysis , 
Annals of the University of Petrosani, Economics, 9(2), 2009, 33-38 
8) Project Management Institute(2013), “A Guide to the Project Management Body of 
Knowledge”, fifth edition

More Related Content

What's hot

Presentation by jv rao
Presentation by jv raoPresentation by jv rao
Presentation by jv raoPMI_IREP_TP
 
Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPMI_IREP_TP
 
Presentation by sameer murdeshwar
Presentation by sameer murdeshwarPresentation by sameer murdeshwar
Presentation by sameer murdeshwarPMI_IREP_TP
 
Presentation by shubham vyas
Presentation by shubham vyasPresentation by shubham vyas
Presentation by shubham vyasPMI_IREP_TP
 
Presentation by piyush jain
Presentation by piyush jainPresentation by piyush jain
Presentation by piyush jainPMI_IREP_TP
 
Presentation by dakshinamoorthi g
Presentation by dakshinamoorthi  gPresentation by dakshinamoorthi  g
Presentation by dakshinamoorthi gPMI_IREP_TP
 
Presentation by dhruva sen
Presentation by dhruva senPresentation by dhruva sen
Presentation by dhruva senPMI_IREP_TP
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadirPMI_IREP_TP
 
Presentation by pavan adipuram
Presentation by pavan adipuramPresentation by pavan adipuram
Presentation by pavan adipuramPMI_IREP_TP
 
Presentation by parag saha
Presentation by parag sahaPresentation by parag saha
Presentation by parag sahaPMI_IREP_TP
 
Presentation by vikas dubey
Presentation by vikas dubeyPresentation by vikas dubey
Presentation by vikas dubeyPMI_IREP_TP
 
Presentation by vignesh swamidurai
Presentation by vignesh swamiduraiPresentation by vignesh swamidurai
Presentation by vignesh swamiduraiPMI_IREP_TP
 
Presentation by dhruba jyoti chaudhuri
Presentation by dhruba jyoti chaudhuriPresentation by dhruba jyoti chaudhuri
Presentation by dhruba jyoti chaudhuriPMI_IREP_TP
 
Presentation by lakshmi varagan d
Presentation by lakshmi varagan dPresentation by lakshmi varagan d
Presentation by lakshmi varagan dPMI_IREP_TP
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjeePMI_IREP_TP
 
Presentation by dattatraya pathak
Presentation by dattatraya pathakPresentation by dattatraya pathak
Presentation by dattatraya pathakPMI_IREP_TP
 
Updated - Enterprise architecture as a capability
Updated - Enterprise architecture as a capability Updated - Enterprise architecture as a capability
Updated - Enterprise architecture as a capability
Million Innovators Group
 

What's hot (20)

Presentation by jv rao
Presentation by jv raoPresentation by jv rao
Presentation by jv rao
 
Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajan
 
Presentation by sameer murdeshwar
Presentation by sameer murdeshwarPresentation by sameer murdeshwar
Presentation by sameer murdeshwar
 
Presentation by shubham vyas
Presentation by shubham vyasPresentation by shubham vyas
Presentation by shubham vyas
 
Presentation by piyush jain
Presentation by piyush jainPresentation by piyush jain
Presentation by piyush jain
 
Presentation by dakshinamoorthi g
Presentation by dakshinamoorthi  gPresentation by dakshinamoorthi  g
Presentation by dakshinamoorthi g
 
Presentation by dhruva sen
Presentation by dhruva senPresentation by dhruva sen
Presentation by dhruva sen
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadir
 
Presentation by pavan adipuram
Presentation by pavan adipuramPresentation by pavan adipuram
Presentation by pavan adipuram
 
Presentation by parag saha
Presentation by parag sahaPresentation by parag saha
Presentation by parag saha
 
Presentation by vikas dubey
Presentation by vikas dubeyPresentation by vikas dubey
Presentation by vikas dubey
 
Presentation by vignesh swamidurai
Presentation by vignesh swamiduraiPresentation by vignesh swamidurai
Presentation by vignesh swamidurai
 
Presentation by dhruba jyoti chaudhuri
Presentation by dhruba jyoti chaudhuriPresentation by dhruba jyoti chaudhuri
Presentation by dhruba jyoti chaudhuri
 
Presentation by lakshmi varagan d
Presentation by lakshmi varagan dPresentation by lakshmi varagan d
Presentation by lakshmi varagan d
 
ETPM5
ETPM5ETPM5
ETPM5
 
DPPM2
DPPM2DPPM2
DPPM2
 
DPPM6
DPPM6DPPM6
DPPM6
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjee
 
Presentation by dattatraya pathak
Presentation by dattatraya pathakPresentation by dattatraya pathak
Presentation by dattatraya pathak
 
Updated - Enterprise architecture as a capability
Updated - Enterprise architecture as a capability Updated - Enterprise architecture as a capability
Updated - Enterprise architecture as a capability
 

Similar to Presentation by bhavesh thakkar

Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
Craig Abednego Malone
 
Energy Manager_MRV article pdf
Energy Manager_MRV article pdfEnergy Manager_MRV article pdf
Energy Manager_MRV article pdfAvijit Choudhury
 
Engineering Services Department (ME217)
Engineering Services Department (ME217)Engineering Services Department (ME217)
Engineering Services Department (ME217)
Jo Balucanag - Bitonio
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
smsksolar
 
IRJET- Comparison of Energy Audit Methods for Buildings
IRJET- Comparison of Energy Audit Methods for BuildingsIRJET- Comparison of Energy Audit Methods for Buildings
IRJET- Comparison of Energy Audit Methods for Buildings
IRJET Journal
 
[Oil & Gas White Paper] Optimizing Pipeline Energy Consumption
[Oil & Gas White Paper] Optimizing Pipeline Energy Consumption[Oil & Gas White Paper] Optimizing Pipeline Energy Consumption
[Oil & Gas White Paper] Optimizing Pipeline Energy Consumption
Schneider Electric
 
05_GMR Hyderabad International Airport.pdf
05_GMR Hyderabad International Airport.pdf05_GMR Hyderabad International Airport.pdf
05_GMR Hyderabad International Airport.pdf
shiv53296
 
IRJET - Energy Audit and Electrical Power Consumption of ADIT College
IRJET - Energy Audit and Electrical Power Consumption of ADIT CollegeIRJET - Energy Audit and Electrical Power Consumption of ADIT College
IRJET - Energy Audit and Electrical Power Consumption of ADIT College
IRJET Journal
 
2015 TAPR Forum Presentation
2015 TAPR Forum Presentation2015 TAPR Forum Presentation
2015 TAPR Forum Presentation
TransGrid AU
 
Demand Side Management (DSM) and Energy Efficiency – Elements for Optimizing ...
Demand Side Management (DSM) and Energy Efficiency – Elements for Optimizing ...Demand Side Management (DSM) and Energy Efficiency – Elements for Optimizing ...
Demand Side Management (DSM) and Energy Efficiency – Elements for Optimizing ...
IEA DSM Implementing Agreement (IA)
 
Time to step up performance-based energy efficiency measurement and verificat...
Time to step up performance-based energy efficiency measurement and verificat...Time to step up performance-based energy efficiency measurement and verificat...
Time to step up performance-based energy efficiency measurement and verificat...
Leonardo ENERGY
 
Solwatt Energy Performance Contract
Solwatt Energy Performance ContractSolwatt Energy Performance Contract
Solwatt Energy Performance Contract
Solvay Energy Services Iberica
 
Solwatt Energy Performance Contract
Solwatt Energy Performance ContractSolwatt Energy Performance Contract
Solwatt Energy Performance Contract
Solvay Energy Services Iberica
 
B046060611
B046060611B046060611
B046060611
IJERA Editor
 
CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption
WRI Ross Center for Sustainable Cities
 
IRJET- Industrial Energy Audit
IRJET-  	  Industrial Energy AuditIRJET-  	  Industrial Energy Audit
IRJET- Industrial Energy Audit
IRJET Journal
 
Energy efficiency implementation program for state level in Malaysia
Energy efficiency implementation program for state level in MalaysiaEnergy efficiency implementation program for state level in Malaysia
Energy efficiency implementation program for state level in Malaysia
ZAINI ABDUL WAHAB
 
ENVOGUE - Energy Trending!
ENVOGUE - Energy Trending!ENVOGUE - Energy Trending!
ENVOGUE - Energy Trending!
Umesh Bhutoria
 
Industrial energy auditing and reporting
Industrial energy auditing and reportingIndustrial energy auditing and reporting
Industrial energy auditing and reporting
Vignesh Sekar
 

Similar to Presentation by bhavesh thakkar (20)

Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
Energy Manager_MRV article pdf
Energy Manager_MRV article pdfEnergy Manager_MRV article pdf
Energy Manager_MRV article pdf
 
Engineering Services Department (ME217)
Engineering Services Department (ME217)Engineering Services Department (ME217)
Engineering Services Department (ME217)
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
IRJET- Comparison of Energy Audit Methods for Buildings
IRJET- Comparison of Energy Audit Methods for BuildingsIRJET- Comparison of Energy Audit Methods for Buildings
IRJET- Comparison of Energy Audit Methods for Buildings
 
[Oil & Gas White Paper] Optimizing Pipeline Energy Consumption
[Oil & Gas White Paper] Optimizing Pipeline Energy Consumption[Oil & Gas White Paper] Optimizing Pipeline Energy Consumption
[Oil & Gas White Paper] Optimizing Pipeline Energy Consumption
 
05_GMR Hyderabad International Airport.pdf
05_GMR Hyderabad International Airport.pdf05_GMR Hyderabad International Airport.pdf
05_GMR Hyderabad International Airport.pdf
 
IRJET - Energy Audit and Electrical Power Consumption of ADIT College
IRJET - Energy Audit and Electrical Power Consumption of ADIT CollegeIRJET - Energy Audit and Electrical Power Consumption of ADIT College
IRJET - Energy Audit and Electrical Power Consumption of ADIT College
 
2015 TAPR Forum Presentation
2015 TAPR Forum Presentation2015 TAPR Forum Presentation
2015 TAPR Forum Presentation
 
Demand Side Management (DSM) and Energy Efficiency – Elements for Optimizing ...
Demand Side Management (DSM) and Energy Efficiency – Elements for Optimizing ...Demand Side Management (DSM) and Energy Efficiency – Elements for Optimizing ...
Demand Side Management (DSM) and Energy Efficiency – Elements for Optimizing ...
 
Time to step up performance-based energy efficiency measurement and verificat...
Time to step up performance-based energy efficiency measurement and verificat...Time to step up performance-based energy efficiency measurement and verificat...
Time to step up performance-based energy efficiency measurement and verificat...
 
Solwatt Energy Performance Contract
Solwatt Energy Performance ContractSolwatt Energy Performance Contract
Solwatt Energy Performance Contract
 
Solwatt Energy Performance Contract
Solwatt Energy Performance ContractSolwatt Energy Performance Contract
Solwatt Energy Performance Contract
 
B046060611
B046060611B046060611
B046060611
 
CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption
 
GS Economy
GS EconomyGS Economy
GS Economy
 
IRJET- Industrial Energy Audit
IRJET-  	  Industrial Energy AuditIRJET-  	  Industrial Energy Audit
IRJET- Industrial Energy Audit
 
Energy efficiency implementation program for state level in Malaysia
Energy efficiency implementation program for state level in MalaysiaEnergy efficiency implementation program for state level in Malaysia
Energy efficiency implementation program for state level in Malaysia
 
ENVOGUE - Energy Trending!
ENVOGUE - Energy Trending!ENVOGUE - Energy Trending!
ENVOGUE - Energy Trending!
 
Industrial energy auditing and reporting
Industrial energy auditing and reportingIndustrial energy auditing and reporting
Industrial energy auditing and reporting
 

More from PMI_IREP_TP

Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakathPMI_IREP_TP
 
Presentation by pranal dongare
Presentation by pranal dongarePresentation by pranal dongare
Presentation by pranal dongarePMI_IREP_TP
 
Presentation by shreyas bhargave
Presentation by shreyas bhargavePresentation by shreyas bhargave
Presentation by shreyas bhargavePMI_IREP_TP
 
Presentation by anipriya p
Presentation by anipriya pPresentation by anipriya p
Presentation by anipriya pPMI_IREP_TP
 
Presentation by mangesh sardesai
Presentation by mangesh sardesaiPresentation by mangesh sardesai
Presentation by mangesh sardesaiPMI_IREP_TP
 
Presentation by rahul ghodke
Presentation by rahul ghodkePresentation by rahul ghodke
Presentation by rahul ghodkePMI_IREP_TP
 
Presentation by Ruchika Wadhwa
Presentation by Ruchika WadhwaPresentation by Ruchika Wadhwa
Presentation by Ruchika WadhwaPMI_IREP_TP
 
Presentation by prameela kumar
Presentation by prameela kumarPresentation by prameela kumar
Presentation by prameela kumarPMI_IREP_TP
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjeePMI_IREP_TP
 
Presentation by jayanta debnath
Presentation by jayanta debnathPresentation by jayanta debnath
Presentation by jayanta debnathPMI_IREP_TP
 

More from PMI_IREP_TP (10)

Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakath
 
Presentation by pranal dongare
Presentation by pranal dongarePresentation by pranal dongare
Presentation by pranal dongare
 
Presentation by shreyas bhargave
Presentation by shreyas bhargavePresentation by shreyas bhargave
Presentation by shreyas bhargave
 
Presentation by anipriya p
Presentation by anipriya pPresentation by anipriya p
Presentation by anipriya p
 
Presentation by mangesh sardesai
Presentation by mangesh sardesaiPresentation by mangesh sardesai
Presentation by mangesh sardesai
 
Presentation by rahul ghodke
Presentation by rahul ghodkePresentation by rahul ghodke
Presentation by rahul ghodke
 
Presentation by Ruchika Wadhwa
Presentation by Ruchika WadhwaPresentation by Ruchika Wadhwa
Presentation by Ruchika Wadhwa
 
Presentation by prameela kumar
Presentation by prameela kumarPresentation by prameela kumar
Presentation by prameela kumar
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjee
 
Presentation by jayanta debnath
Presentation by jayanta debnathPresentation by jayanta debnath
Presentation by jayanta debnath
 

Presentation by bhavesh thakkar

  • 1. 1 | P a g e Mantra for Entrepreneurial Project Management Bhavesh Thakkar Dy Manager Gammon India Limited
  • 2. Decision Analysis for successful Project Investment in midcourse of BOT Infrastructure Projects 2 | P a g e Theme – Mantra for Entrepreneurial Project Management Abstract For any Projects selection, organization invariably undertakes Sensitivity Analysis, if project offers either decent IRR or positive NPV. Sensitivity analysis particularly pivots on understanding few key variables like revenue fluctuations in Toll etc and its consequences before finally agree to bid / sign the Concession Agreement. In midcourse, some process excellence or innovative methodologies may emerge to improve bottom line or top line which may require considerable investment. Iloiu and Csiminga have devised methodology of Sensitivity Analysis using the guided criteria of Switching Value and Sensitivity Indicator which proves to be very effective tool for better selection. Case Study to reduce Energy Costs of street lighting by using Power Savers, in Operation phase of PLC which in turn can improve bottom line and enhances company’s brand value, was taken up in a 4 lane divided road project between Rajahmundry and Tuni in Andhra Pradesh on NH 16 using this stated approach. The analysis provides the following major conclusions: On Switching Value: a) Up to Impact of 50% increase in Cost in Investment , IRR would be above the Cost of Capital thereby NPV will be positive in these range; b) But for any reason, Balance Concession Period as envisaged for this analysis gets reduced due to capacity augmentation by NHAI or Concessionaire delays in implementing this feasibility exercise by more than 28% of balance period, NPV would be less than zero On Sensitivity Indicator: a) Low sensitivity indicator ranging between 1.2% and 4.9% on cost of equipment and balance project duration indicates positive NPV.
  • 3. 3 | P a g e Table of Contents Sl. No Contents Page No 1.0 Introduction 3 2.0 Project Details 3 3.0 Case genesis of Energy conservation 4 4.0 Evaluating options 5 5.0 Field Experimentation 7 5.1 Fixture of Power Saver 7 5.2 Fixture of LED Lights 8 5.3 Comparison of Alternatives 8 6.0 Financial model of project investment including capital budgeting 9 6.1 Method Approach 9 6.2 WACC analysis and project assumptions 9 6.3 Identifying locations of Investment and evaluation of alternatives 10 7.0 Sensitivity Analysis 12 7.1 Identification of Variables 13 7.2 Calculation of effects of changing Variables 13 7.3 Sensitivity Analysis of risk factors: 14 8.0 Result observations 14 9.0 Conclusions 14 10.0 Acknowledgements 15 11.0 References 15
  • 4. 4 | P a g e 1.0 Introduction: Survival in infrastructure industry in an environment of highly unorganized section, fragmented, intense rivalry, wafer thin margins amidst opportunities for executing Road projects but lacking in supply side issues such as non-availability of professional management skill and insufficient equipment had brought almost all the companies to an alarming situation because of cost overruns and declining profit margins across the board This is even particular especially when any investment proposal in O & M Phase of Project Life Cycle is not keenly given due importance and as a result, good opportunity is lost for improving bottom line especially when projects are being executed on Annuity basis. A Case study conducted in our 100 Km Road Project which had approximately 40% of yearly expenses towards Energy consumption bills. Feasibility studies states that investment of Rs. 19.7 Lakhs towards installing Power Saver Equipment will yield around 25% savings in Energy consumption These operational efficiencies if implemented, by infusing capital investment, will enhance brand image, improve bottom line, and bring sustainability. Unless the scenario of any future impact due to likely policy changes is evaluated it is likely that the decision taken in favorable condition may go haywire and therefore Sensitivity Analysis, desirable tool, has to be undertaken using IRR and NPV 2.0 Project Details: it is a 100Km long Operation and Maintenance Road Project of two continuous packages namely Rajahmundry Expressway Limited (53 Kms) and Andhra Expressway Limited (47 Kms) being executed by Gammon Infrastructure Projects Limited, a subsidiary of Gammon India Limited is in 15 years O & M Phase slated to end in Nov 2019. In O & M period, Concessionaire has to carry out the routine maintenance works such as Corridor Cleaning, Reinstating the damaged / missing road furniture, median plantation, Street lighting, repairs to pavement such as pot holes and crack sealing, re-doing the faded road marking, providing emergent first aid treatment to accident victims, clearing the blocked vehicles on carriage way etc. besides executing periodic maintenance works in every fifth year. Among the above, Major component of routine maintenance activities constitute towards incurring the energy charges of street lighting which is 42% of total monthly expenses. There exists a scope of process improvement amidst customer dissatisfaction in the area of minimizing energy consumption
  • 5. 5 | P a g e 3.0 Case Genesis on Energy Conservation: The Project site had provided Street lighting in all urban areas within corridor. Source of power for illumination is APGENCO supplied electricity. Barring Toll Plaza location, no other location has any standby power generation. Package No of locations No of Poles No of bulbs (250 W) AP – 15 ( REL) 14 504 880 AP – 16 ( AEL) 13 774 1157 Total 27 1278 2037 Table 1 – Details of Electrical Installations The site are in receipt of customer complaints for the below par performance from operational deliverables as stipulated in Concession Agreement. The root causes of below par performance were evaluated using Fish bone method as drawn below: Key factor Fig 1 – Fish bone diagram of Illumination for below par performance
  • 6. Out of the above causes, barring Electricity Transmission issues all other parameters are man managed with effective planning and execution. While experimenting, it is understood that electrical losses are to the extent of 25% in transmission due to fluctuation of voltage termed as Spikes. The sudden voltage fluctuations are not considered in inputs by any of the electrical appliances and thus these spikes go as a waste of electricity and an alternate solution needs to be adopted to minimize wastage which in turn can reduce costs and improve bottom line. 6 | P a g e 4.0 Evaluating options Life cycle project management is necessary because of turbulent environments (particularly shifting markets), the rapid rate at which technology changes, the increasing influence of the host communities and stakeholders, and the environmental, social, safety and legal implications of capital projects (Jaafari 2000; Jaafari & Manivong 2000). Fig 2 – Pictorial representation of choosing projects To improve the performance, options are explored using Saaty’s analytical hierarchy process which advocates usage of weighted average criteria. Criteria and qualifying parameters for rating are tabulated below:
  • 7. 7 | P a g e Table 2 - Weightage criteria of qualitative parameters of illumination Table 4 – Ratings assigned for qualitative deliverables However, the evaluation of detailed investment analysis with respect to the balance time of the Concession period needs to be computed for preferred lighting (existing setup (SV) lights of Power saver vis-à-vis LED lights on conventional electricity Physical features of the all the alternatives are studied with the existing provisions before zeroing on choosing the options:
  • 8. But considering the customer need from the above survey and feasibility, two alternatives are possible for enhancing the customer satisfaction and meeting road user needs;  Addition of spike utilization devices for smoother flow of electricity such as Power Savers to the existing setup and assess the power consumption to minimize cost and improvement in efficiency;  Introduction of new technology of LED lights by replacing the entire Sodium Vapor lamp setup which has high investment cost but low power consumption to be evaluated with reference to the balance time; 8 | P a g e 5.0 Field Experimentation Field experimentation at site was undertaken for two options 5.1 Fixture of Power saver to the existing 250 W Sodium Vapor lamp being operated on conventional basis; Fig 3 – Power Saver Experimentation Fig 4 – Power Saver Experimentation Trial tests were conducted at our AEL Maintenance Yard using Servomax ‘Power Saver’ by fixing Power saver to the setup without operating power saver to know the utilization of spikes quantum of energy for conserving the electrical energy. The readings were taken at one and half hour intervals to also study the fluctuation in voltages and ampere readings The Summary of the test results are tabulated as under: Load Applied : 750 W Test duration / day : 12 hours
  • 9. 5.2 Fixture of LED lights functioning on the normal conventional supply from APEPDCL Since, the usage of LED lights is in developing stage of introduction at various places in the country including our present town, Rajahmundry. Usage of LED lights is a deviated item from the scope of works. As such, if at all, it needs to be initiated under NHAI approval for modification of scheme. However, if adopted, the following is comparative table 9 | P a g e 5.3 Comparison of alternatives Table 7 – preliminary comparison of initial costs
  • 10. In light of obtaining the similar savings in the power, investment of Rs. 41.0 Lakhs is far viable than the investment of Rs. 10 Cr. 10 | P a g e 6.0 Financial Model for the Project Investment including Capital Budgeting “Time is the essence of the Contract” and similarly timely investment is the key driver for obtaining the first mover advantage to improve the profitability of the organization. Based on the technical findings, it is the time to capitalize the opportunity for investment for obtaining smart returns The question remains how to tap the savings in energy wattage can be translated into income by suitably investing in the system wherein the time and expenses have been frozen. 6.1 Method Approach for analyzing the Project Investment The viability of project investment is done in the following sequence  Calculate the Savings from the present billing trend;  Freeze Project assumptions like tax rates, risk parameters and other components;  Do WACC analysis and arrive D/E ratio;  Identify the locations of investment ;  Evaluate the project feasibility in different conditions;  Compute Cash flow statement based on the project assumptions;  Determine Internal Rate of Return and Net Present Value on all the parameters;  Select the best option inclining towards 15% profitability;  Carry out sensitivity analysis; 6.2 WACC Analysis and Project Assumptions WACC Analysis is tabulated below: Table 8 – WACC Analysis
  • 11. 11 | P a g e Table 9- Project Assumptions 6.3 Identifying locations of Investment and evaluating various alternatives On evaluation of present energy consumption vis-à-vis theoretical gains, 21 locations are chosen from 26 locations to be provided with Power Saver Equipment Investment feasibility is evaluated for IRR, NPV and Cost Improvements in four conditions separately for these two packages:  Debt funding in first phase followed by internal accruals in second phase  Debt funding in two phases  Entire Debt funding at the beginning of project  Own Equity at the beginning of the Project Sample Result among the eight alternatives is depicted below:
  • 12. 12 | P a g e Table 10- IRR and NPV analysis for one of the alternative The summary results of all the options are tabulated below for taking appropriate decisions: Table 11 – Summary of Project Investment
  • 13. 13 | P a g e With the above analysis, it was financially concluded to opt with the below recommendations: REL Package: Debt financing in first phase and through internal accruals in second phase AEL Package: Entire Debt financing in one go. The likely net savings with this above proposal would fetch in improving bottom line by Rs. 7.1 mn in balance concession period. Table 12 – Final Proposal of Investment 7.0 Sensitivity Analysis The purpose of sensitivity analysis is  To help identify the key variables which influence the project cost and benefit streams  To investigate the consequences of likely adverse changes in these key variables  To assess whether the project decisions are likely to be affected by such changes  To identify actions that could mitigate possible adverse effects on the project Sensitivity analysis needs to be conducted to understand its impact on both financial and economical internal rate of return. Model suggested in this risk evaluation method is based on the Technical Paper submitted at Annals of the University of Petrosani, Economics by Mirela Iloiu and Diana Csiminga Sequence of steps to be adopted:
  • 14. 14 | P a g e 7.1 Identification of Variables Considering the project under study, the author identifies two variables to assess the impact on possible changes on the recommended proposal of IRR and NPV on the following risks:  Cost of the Assets due to delay in approval from Head Office;  Balance Concession period as the adjacent packages have already been awarded for six laning works. 7.2 Calculation of effects of changing Variables: The values of the basic indicators of project viability (EIRR and ENPV) should be recalculated for different values of key variables. This is preferably done by calculating sensitivity indicators and switching values which is reproduced below: Table 13 – Explanation of SI and SV
  • 15. 15 | P a g e 7.3 Sensitivity Analysis of risk factors: Financial Model for Price increase of 10% and duration reduction by every one year is prepared and analyzed using the above formula and obtain the following results: 8.0 Result Observations: Price Variable: The values obtained in Sensitivity Indicator are far less than the discount factor of around 12%. As such the price is not critical for both the packages as indicated in Sensitivity Indicator On the price front as indicated in switching value, unless increase in prices vary minimum around 50% to have NPV Value zero equivalent to Cost of Capital. Duration Variable The values obtained in Sensitivity Indicator are less by around 8 ½ percent as such price is not the critical issue However on the duration front, switching value indicates that no economic value will be added to investment proposal, if duration reduces by 20.40%. 9.0 Conclusions: As a result, Rs. 71 Lakhs can be saved providing annual savings of around 12% in the balance concession period of 7 years with Positive NPV and IRR 35%. Up to Impact of 50% increase in Cost in Investment, IRR would be above the Cost of Capital thereby NPV will be positive in these range; But for any reason, either Balance Concession Period as envisaged for this analysis gets reduced due to capacity augmentation by NHAI or Concessionaire delays in implementing this feasibility exercise by more than 28% of balance period, NPV would be less than zero
  • 16. Due to cost constraints amidst economic slowdown, Company could not envisage this proposal till now and thereby great opportunity is lost now due to balance concession period being only five years. However still, if management pursues, it can have process improvement to fulfill green objectives and at the time of handover, these power savers can be shifted to other project sites to have positive economic value added scenario Thus leveraging PM methodologies and leadership skills can launch new innovations at the earliest possible time and gain competitive advantage. 16 | P a g e 10.0 Acknowledgements The Author thanks PMI for giving the opportunity to present the paper. The Author also thanks entire team of Rajahmundry Site team comprising M/s. Bhagavan Raju, and other team members besides GIPL Management for facilitating this experimentation to give way for this new thought process. The Author thanks Mr. D. V Prasad, Power tech solutions for permitting his equipment at site for demonstration and evaluation. The Author also thanks Mr. M. U. Shah, member- BoM for his constant guidance and encouragement in submitting this paper. The Author also thanks various authors shown in the references for providing their various valuable insights in their respective fields to culminate this overall innovation into possible new thought process of sustainable project execution 11.0 References: 1) Concession Agreement signed between REL / AEL with NHAI, Asset Deliverable Criteria(2001) , Appendix A of Schedule I, 2) European Renewable Energy council, Green Peace (2007), A report on Indian National Energy Scenario 3) Giedrius Grondskis, Alfreda Sapkauskiene(2011) – Cost Accounting information use for product mix design (Eknomica IR Vadyaba,2011:16) 4) Jack R. Meredith, Samuel J. Mantel (2010)- Text book of Project Management, a Managerial approach, seventh edition 5) L. Dwayne Barney Jr., Morris G. Danielson(20034) – Ranking mutually exclusive projects – The role of duration, The Engineering Economist, 49 , 43 -61 6) ManTech Associates(2012), Catalogue on Servomax Power Savers by, pp1-3 7) Mirela Iloiu, Diana Csiminga(2009) – Project risk evaluation methods – Sensitivity Analysis , Annals of the University of Petrosani, Economics, 9(2), 2009, 33-38 8) Project Management Institute(2013), “A Guide to the Project Management Body of Knowledge”, fifth edition