SlideShare a Scribd company logo
1 of 18
Download to read offline
MSU, MANKATO – MET 489
4/30/15
Process Analysis & Improvement: Painting at JMP
STUDENT: Christopher Boote
FACULTY ADVISORS: Dr. Agarwal
PROJECT SPONSORS: Jones Metal Products
David Olson
ABSTRACT
The purpose of this report is to outline and discuss our
analysis of the painting process at Jones Metal
Products. Our team was assigned to study the process
as a whole, and implement lean manufacturing
principles. Our method of execution involved several
time studies, observations of the processes as they
unfolded, and placing all of the data into a current state
value stream map. After analyzing the data and coming
up with new ways to improve upon the process used by
JMP, we followed with a future state value stream map.
INTRODUCTION
Originally, our project had been centered on how to
apply the usage of PLM software to simulate factory
operations. However, with the guidance of Dr. Kuldeep
Agarwal, we drifted more towards the idea of how to
apply Lean Manufacturing principles in a certain area of
the factory. In our new project, we would take days to
observe the workers in the painting area. We’d talk with
them, ask vital questions about how they would work in
their stations (approach to certain pieces, steps to
perform, etc.), the tools they would use and how they
worked, and other questions about how and what they
did. We would perform other quantitative studies
(discussed later) to measure each stage of the process.
After analyzing the process, we would then apply lean
methods to suggest improvement for the future.
MAIN SECTION
PROJECT DESCRIPTION
Background
Jones Metal Products (or JMP) was founded in 1942 by
Mildred M. Jones. The company was started originally as
Jones Sheet Metal and Roofing Company to support
KATO engineering, and also provide roofing services to
the community. Down the road, more emphasis was
placed on metal fabrication, which led to the multitude of
industries they cater to today. Our team worked
specifically on analyzing the painting process at JMP.
Problem Definition
Currently, the paint process at JMP is pretty efficient.
However, they are looking to continuously improve the
process, in order to stay competitive in the industry.
There are certain areas that create a bottleneck, or slow
the process down. Overall, they are looking to cut down
on waste, both product and time. Our team was to
explore the paint process, and find these areas that
could use improvement. Once found, we could apply
lean methods and suggest ways to cut down on waste,
and reduce time spent in the paint area.
Objectives
The main objective was to analyze the painting process
at Jones Metal Products. Afterwards, we would use that
analysis and understanding to suggest areas of
improvement in that area using lean principles. In order
to do so, we needed to have specific objectives:
• Define product of study
• Observe the process in entirety, exploring all
steps toward finished product
• Take time studies of the product through each
step of the process
• Construct a Value Stream Map (VSM) of the
painting process
• Construct a future Value Stream Map
• Suggest improvement based on future VSM
Constraints
The production would be constrained by size of the
product or products. It would also be constrained by the
type of paint used, how the product needed to be
treated, according to specifications of the customer. For
us, our constraints in the project were centered around
time. Specifically, it was whether or not we could talk to
certain people, our own availability and theirs.
Design Function
The function of value stream map was to take time data
analyzed by us, put it into the VSM, and after careful
analysis by us, determine where time was being wasted
and what could be done to eliminate the muda.
Design Alternatives
After creation and analysis of the VSM, we would create
a future state value stream map. In this future VSM, we
would group certain processes together, and make
changes to streamline the process. More information on
this is provided later in the report.
PROJECT EXECUTION
Define Product
Before we could analyze the paint process at JMP, we
needed to define the product of study. We chose to work
with custom enclosures, one of Jones’ main products.
These enclosures are made for a variety of different
purposes, depending on the customer. However, the
enclosures that we looked at were “outlet boxes” that
housed internal components for generators. These
boxes are meant to offer protection from electrical
connections or other moving parts of a generator. The
main customer in our case was KATO engineering.
Since these enclosures are made according to the
customer’s specification, they can range from small
scale, to very large (as shown below).
	
  
Figure 1: Large Heat Exchanger (finished)
Below is another style of enclosure (outlet box), and its
corresponding drawing:
Figure 2: Outlet Box (before paint)
Figure 3: Outlet Box Drawing
Process Analysis - Painting
Once we had defined the product of study, the next step
was to analyze the painting process from start to finish.
This would set up the next part of the project, which was
taking time studies at each step. With the guidance of a
few employees in the paint area, as well as a detailed
map of the shop floor (Appendix D), we were able to fully
understand the painting process. The paint process has
3 main steps: Wash, Paint, and Dry. More detail on each
of these steps is provided below.
Wash	
  
The first step that any part requiring paint will go through
is the wash process. The purpose of washing is to
remove any contaminants on the part that may inhibit the
paint from adhering correctly. Paint doesn’t usually like
to stick well to bare metal, so washing will “etch” the
part, also promoting adhesion. There are two different
wash areas: one is a spray wash for large parts, the
other is a system of 5 dip tanks.
Spray Wash Area
Figure 4: Spray Wash Station
The spray wash area is used for large parts that wouldn’t
normally fit in the roughly 4’ x 7’ x 4’ dip tanks. Here they
use a mixture of water and a metal wash/prep (named
GF Seal Prep) through a pressurized wash. The amount
of time spent washing a part here depends on the size of
the part and the operator. We were told that the operator
would know when the part was fully clean by the bluish
tint on the metal (pictured below).
Figure 5: Finished Sprayed Part
Tank Wash Area
Figure 6: Tank Wash Station
Figure 7: Tank Wash Showing Crane
Right next to the Spray Wash station is the more
commonly used Dip Tank station. All of the smaller parts
produced by JMP come through this station, usually in
large batches. Multiple parts are placed on a rack that is
about the length and width of the tanks and moved
between each one using an overhead crane. This area
produces the most consistent parts, since each tank is
temperature regulated, as well as time. Tanks 1 through
5 are as follows:
1. Ultrax 92D – Cleaner (5 to 15 minutes)
2. Rinse Water
3. Zircobond 4200D – Metal Etch (2 minutes)
4. Rinse Water
5. Hot Rinse Water (used to speed up drying time
by ~10 minutes)
After tank 5, the parts are set out to dry before they go in
for paint. If the operator has time, they will spray the
parts thoroughly with compressed air, to speed up the
drying even further.
Figure 8: Visual Aid and Thermometer for Tank 3
The images above are examples of the process control
of each tank. The poster gives information such as the
chemical in the tank, target temperatures (thermometer
in figure 8), and how much time the part(s) can spend in
that particular tank. All five wash tanks have both of
these objects, ensuring a perfect wash every time, as
long as the operator follows guidelines.
Paint
After all of the parts in the batch are dried off, we move
to the next step: painting. There are two different
methods of painting at JMP: hot pot and p-mix.
Hot Pot
	
  
Figure 9: Hot Pot Paint Booth
The Hot Pot system of painting requires the operator to
manually mix a batch per order size or parts to be
painted. The Hot Pot system is primarily used for short
production runs or small orders that require a special
color. The products that we observed for our time studies
used this paint method, because there was only an order
for 40, so only 40 were painted at that time. For our
example, the mix was 1 gallon of primer to 1 gallon of
catalyst (or hardener). As with the p-mix system, parts
generally travel along a system of conveyors, controlled
by the painter. These conveyors are equipped with
hooks, so the painter can reach every angle of the part.
Once done painting, the painter can move the painted
parts to the drying/shipping area with the touch of a
button.
Figure10: Drying / Shipping Area (Hot Pot side)
If parts are in a hurry to get out of the door, the two heat
lamps (shown above) are used to speed up the curing of
the paint.
P-Mix
Figure 11: P-Mix Paint Booth
The other method of painting at JMP is the P-Mix
system. The P-Mix paint is generally used for long
production runs with one color, as opposed to the Hot
Pot system. In this system, each color is already mixed
in huge barrels in a back room and then fed to the spray
gun. Colors are changed with the touch of a button
outside the paint booth (pictured below):
Figure 12: P-Mix Control Panel
This one touch of a button gives the operator ease of
use, and full control over the paint system. This system
is optimal for JMP’s big customers that request the
majority of their parts in one color. A couple of customers
that fit the criteria are KATO Engineering and Caterpillar.
Similar to the Hot Pot system, most parts that get the P-
Mix travel along a conveyor. In our case, the size of
enclosure would determine whether it traveled along
conveyor, or painted on a stand.
Figure 13: Enclosure After Paint
Drying
After paint comes drying, and you would think that would
be pretty straightforward. However, Jones Metal uses a
few methods to dry the finished product.
	
  
Figure 14: Drying Area	
  
The first option is air drying. If the product is on or ahead
of schedule, regular drying would suffice. This method is
simple, letting the parts dry by hanging on the hooks.
Figure 15: Heat Lamps
The second option, touched on a little bit previously, is
using heat lamps. These lamps use high intensity
infrared light to speed up the paint’s curing process.
These lamps are located on the Hot Pot side, where they
are mainly used.
Figure 16: Drying Oven
On the other side, the conveyors from the p-mix side
travel into the big metal box pictured above. This is a
giant oven used for rapid curing of painted products.
Parts will generally travel through this oven if they are in
a hurry to get out the door. This is a very efficient
process in terms of drying, but as far as energy costs go-
probably not.
Time Studies
After analyzing the entire painting process from start to
finish, it was time for the actual data part. In order to
construct a proper value stream map, we had to find out
the amount of time the product spent in each stage.
	
  
Methodology	
  
For our time studies, we would be observing a certain
product from the moment it arrived to be washed, all the
way to the finished product to be shipped. Ideally, we
would’ve liked to observe enclosures being painted, but
our schedules never lined up right to the enclosures in
paint. Instead, we observed another product (Appendix I)
through the entire paint line, and took our time studies
that way. We chose to split the times up by stage:
Washing, Painting, and Drying. We used a simple phone
stopwatch, and had somebody record times on a
notepad. Afterwards, we were able to calculate the time
per square inch, and compare that time to the rough
surface areas of the enclosures. The surface area of the
observed part was 1734.13 sq. in.
Results	
  
Our studies started at the wash tanks. We measured
time starting from the moment the operator placed the
parts onto the rack. For this study, 18 parts were washed
at a time (for space purposes). The complete list of
times is attached in the appendix, but this section will
give a brief overview. We were able to conclude that the
full wash process, arrival to dried part, took a total of 36
minutes. We observed that the parts in Tank #1 were in
for much longer than spec. (13 minutes, when the spec
is 5 minutes max) shown below:
Figure 17: Tank #1 Specification
The extra time in the wash seemed to have no adverse
effects on the product, but adhering strictly to the
specification could cut wash time down significantly.
The next step to observe was the actual paint process.
We were told that the down time between washing and
paint depends on the order size and color to be painted.
For our studies, the order size was 40 parts, so the paint
process did not start until the full order was through the
wash process and ready for paint. Once the parts were
in the paint area, the painter would then do a final scuff
and wipe down of the piece, further ensuring good
quality. For the 40 parts we observed, 79 minutes were
spent on prepping the parts alone. Once the paint got
rolling, parts traveled quickly along, with an average of
35 seconds per part. The total time spent in the paint
area was 49 minutes, including the time moving the
conveyor, and random down times. The conveyor was
advanced every 4 parts, and added 30 seconds each
time it was moved. There were 3 instances of down time:
one was a problem in the back paint room, one part had
to be cleaned again, and the paint ran out at the 37th
part. These down times totaled 15 minutes. Upon
completion of the time studies, we found the time per sq.
inch to be 0.111 seconds. This number includes both
prepping and paint. We then used that number to
calculate the amount of time per enclosure. The small
outlet boxes (768.125 sq. in.) came out to be roughly 1.5
minutes per box. The medium enclosures (10,158.33 sq.
in.) calculated out to be about 18 minutes per part.
Remember these times include both prep and paint of
each enclosure.
As for the drying process, once again our schedules
could not accommodate observing such a long process.
Because of the schedule conflicts, we were not able to
take time studies of the drying process. However, the
paint has a curing time of 15-30min touch dry, or 72
hours fully cured	
  (at 77°F (21°C)). The addition of the
oven or the infrared lamps speed the drying process
considerably, but since most parts are air-dried, our
focus was mainly there.
Value Stream Mapping
In our value stream map, we decided to label the
shipping part of Jones Metal Products as the customer
and the previous processes (welding, metal bending,
and cutting) as the supplier. Times will vary given the
quantity of parts, or size, but for our purposes, and the
sake of similar data, we decided to create our current
map on a single product. Our value stream map, in its
current state, starts of in washing.
Figure 18: Wash Process VSM
After receiving the product from the previous stations,
we either spray wash the product (large generator
covers usually receive this kind of treatment), or they are
sent into a chemical bath treatment (Wash).
Figure 19: Drying Process #1 VSM
After the treatment, they are then sent to the first drying
station (Drying 1).
Figure 20: Painting Process VSM
After the parts are dried and residual chemicals are
removed from the surfaces, the products are hooked
onto a conveyer belt and sent into the painting area
(painting). This process involves pull over push since it’s
the painter who will call for the products from drying and
start the process.
Figure 21: Drying Process #2 VSM
The next step varied depending on time constraints, and
the drying properties of the paint. If there is time, and/or
the customer allows for it, the preferred method of drying
the paint is to let it be air dried. They will also put the
finished products under infrared light to help speed up
the process (Drying 2 process 1). If there is a lack of
time, and/or the customer demands it, they will go with
the alternative method, which involves sending the
pieces through the oven. This method does dry the
product faster, but is very costly. Also, some paints don't
behave the same way as others and may not dry in the
desired way for the product.
After the final drying process, the products need to be
held in inventory for a minimum of 72 hours for the
painted product to be completely cured.
In this current state value stream map, all recorded times
are in minutes. The full VSM can be found in Appendix
F.
Figure 22: Takt Times
Shown above is calculated Takt time for all of the steps
in the painting process. This showed us that the
processes we needed to focus on were the washing,
painting, and second drying processes.
Future Value Stream Mapping
The improvements to the painting process include
integrating the drying 1 and painting process into a
manufacturing cell. What we will do here is the moment
the parts come out of the final wash, instead of letting
them sit and be blown for drying; we will use the
conveyor belt to pull parts out of the washing as needed.
We will need to add fans and Infrared lights (which are
already purchased and used) to dry the parts as they are
hung. This will allow the parts to be ready for pulling into
the next station. We could possibly extend the conveyor
system to come closer to the wash station. This would
allow the operator to put parts directly onto the paint line
from washing with minimal movement and effort. There
will also be a supermarket before the washing process
which uses a Kanban system of pulling parts.
Another change that we will make in order to reduce the
down time on the washing station is to add covers to the
final wash station. This is necessary because we have
seen instances where the whole process, which
depends on the baths being at a certain temperature,
could not be started because the last bath was too cold
to start the process. We don’t know the exact time
improvement adding these covers will make, but we
expect it to make an impact.
BUDGET
Aside from labor hours, this project of analysis and
improvement had no budget.
RESULTS
Based on our observations of the paint process, and
analysis of the future state VSM, we were able to come
up with a few ideas to improve the process. These
improvements start with the lean principles described in
the previous section. Aside from the lean principles,
there are a few physical upgrades that could be made,
one being an extension of the conveyor system.
Extending the conveyor over to the wash area would
allow an easy transition of parts from washing to drying
to painting. With this system, there would be no
inventory sitting between the washing and painting
processes. This would also allow the wash operator to
wash more parts in the time it would’ve taken them to
blow dry the washed parts. Some parts with small
crevices would likely still need to be blow dried a bit, but
the time would still be reduced. Another improvement we
thought of was having the conveyor constantly moving at
a slow pace. This would eliminate the 30 seconds or so
that the painter has to stop painting in order to advance
the parts on the conveyor. However, we would need to
keep the speed low enough (~0.15 ft/s) so that it does
not interfere with the painter. We could see a significant
reduction in time using the moving conveyor. Last, as
stated before, covering the wash tanks when not in use
would improve the process by keeping the wash in its
effective temperature. In order to provide constant
results, the wash tanks need to stay in spec.
temperature.
CONCLUSIONS
From our study and analysis of the painting process at
JMP, we were able to grasp a great understanding of the
methods used. This understanding helped us to
construct a Value Stream Map, and also to come up with
potential improvements. The Value Stream Map was a
very helpful tool in showing us areas in need of
improvement. The current process used by Jones Metal
Products is a good one, however it could stand to use a
few upgrades. For starters, we decided to extend the
conveyor belt so it would eliminate the need for a second
inventory before going to the paint station. We also
decided on adding fans and infrared lights along the
conveyer belt to speed up the drying process after the
products leave the washing station. In the paint station,
we decided to make the conveyer belt slow moving so
the painter would only need to focus on painting instead
of having to stop and move the line after finishing every
4 or more products. Overall, we learned a lot about how
even a well-working process can be improved upon
using lean techniques. In the future, we can see even
our suggestions being superceded by others, since lean
manufacturing is an ever changing process.
ACKNOWLEDGEMENTS
We would like to thank Dr. Agarwal and Dr. Jones for
steering us in the right direction, and coming up with a
feasible project to complete on such short notice. Also,
we would like to thank Dave Olson for setting aside his
time to work with us and help us through this project, as
well as the employees at JMP for their cooperation. Also,
we would like thank Jesus Contreras Villegas for all of
his help in gathering information about the paint process.
APPENDIX
INDEX
A: Small Outlet Box CAD Drawing
B: Medium Outlet Box CAD Drawing
C: Large Heat Exchanger CAD Drawing
D: Paint Area Shop Floor Drawing
E: Time Study Data
F: Value Stream Map
G: Primer Sealer Spec.
H: Future-State Value Stream Map
I: Observed Product (Rhino Hybrid 44”)
APPENDIX A: SMALL OUTLET BOX CAD DRAWING
APPENDIX B: MEDIUM OUTLET BOX CAD DRAWING
APPENDIX C: LARGE HEAT EXCHANGER CAD DRAWING
APPENDIX D: PAINT AREA SHOP FLOOR DRAWING
APPENDIX E: TIME STUDY DATA
Time	
  Studies	
  -­‐	
  Painting	
  Process	
  
WASH	
   (18	
  parts)	
   	
  
Step	
   Time	
   Total	
  
Parts	
  arrive	
   9:50	
  AM	
   10	
  min	
  
Wash	
  start/Tank	
  #1	
   10-­‐10:13	
  	
   3	
  min	
  
Tank	
  #2	
   10:14	
   38	
  sec	
  
Tank	
  #3	
  
10:16-­‐
10:18	
   2	
  min	
  
Tank	
  #4	
  
10:19-­‐
10:20	
   1	
  min	
  
Tank	
  #5	
   10:20	
   39	
  sec	
  
Drying	
  
10:20-­‐
10:26	
   6	
  min	
  
Total	
   9:50-­‐10:26	
   36	
  min	
  
	
   	
   	
  
PAINT	
   (40	
  parts)	
   	
  
Step	
   Time	
   Total	
  
Set-­‐up/Prep	
   10:35	
  AM	
   	
  
Finish	
  Prep	
   11:54	
   79	
  min	
  
LUNCH	
  BREAK	
  
12-­‐
12:30pm	
   30	
  min	
  
Start	
  Paint	
   12:39	
   	
  
Finish	
  Paint	
   1:28	
   49	
  min	
  
Total	
   	
  	
  
128	
  
min	
  
	
   	
   	
  
PAINT	
  DOWN	
  TIME	
   	
   	
  
Issue	
   Time	
   	
  
Problem	
  back	
  room	
   7	
  min	
   	
  
Re-­‐clean	
  part	
   1	
  min	
   	
  
Mix	
  paint	
  -­‐	
  ran	
  out	
  @37	
  parts	
   7	
  min	
   	
  
Total	
   15	
  min	
   	
  
APPENDIX F: VALUE STREAM MAP
APPENDIX G: PRIMER SEALER SPEC
http://www.diamondvogel.com/prod_data/PG 1http://www.diamondvogel.com/prod_data/PG-1236HDPCPI.pdf
APPENDIX H: FUTURE STATE VALUE STREAM MAP
APPENDIX I: OBSERVED PRODUCT (TIME STUDIES)
Painting process analysis and improvement

More Related Content

Similar to Painting process analysis and improvement

Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...eSAT Journals
 
Difference between DFM, DFA, DFMA with good explanation
Difference between DFM, DFA, DFMA with good explanationDifference between DFM, DFA, DFMA with good explanation
Difference between DFM, DFA, DFMA with good explanationManiKandan214178
 
What is new_cast_designer_v73_r0
What is new_cast_designer_v73_r0What is new_cast_designer_v73_r0
What is new_cast_designer_v73_r0Victor Mitov
 
Drilling experiment.docx
Drilling experiment.docxDrilling experiment.docx
Drilling experiment.docxkanepbyrne80830
 
Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3Julien Lecadou,MSc.
 
Dye House Projectonly
Dye House ProjectonlyDye House Projectonly
Dye House ProjectonlySanjaya Khs
 
Design and analysis of sla printer
Design and analysis of sla printerDesign and analysis of sla printer
Design and analysis of sla printerSatyajeet Udavant
 
Report on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al WheelsReport on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al WheelsLAVA KUMAR ADDEPALLI
 
Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternIRJET Journal
 
CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
 CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docxarnit1
 
Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout Javier Siles
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.Raheem Arif
 
Senior Design II Final Report Group 3 Paper Stock Bubbles
Senior Design II Final Report Group 3 Paper Stock BubblesSenior Design II Final Report Group 3 Paper Stock Bubbles
Senior Design II Final Report Group 3 Paper Stock BubblesAustin Sims
 
Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant MustafaElAkkad
 
Design and Development of Hybrid Storage Shelf
Design and Development of Hybrid Storage ShelfDesign and Development of Hybrid Storage Shelf
Design and Development of Hybrid Storage ShelfIRJET Journal
 

Similar to Painting process analysis and improvement (20)

6 MONTH INTERNSHIP AT
6 MONTH INTERNSHIP AT6 MONTH INTERNSHIP AT
6 MONTH INTERNSHIP AT
 
Internship Report
Internship ReportInternship Report
Internship Report
 
Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...Process optimization of pressure die casting to eliminate defect using cae so...
Process optimization of pressure die casting to eliminate defect using cae so...
 
Difference between DFM, DFA, DFMA with good explanation
Difference between DFM, DFA, DFMA with good explanationDifference between DFM, DFA, DFMA with good explanation
Difference between DFM, DFA, DFMA with good explanation
 
What is new_cast_designer_v73_r0
What is new_cast_designer_v73_r0What is new_cast_designer_v73_r0
What is new_cast_designer_v73_r0
 
Drilling experiment.docx
Drilling experiment.docxDrilling experiment.docx
Drilling experiment.docx
 
Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3
 
Dye House Projectonly
Dye House ProjectonlyDye House Projectonly
Dye House Projectonly
 
Design and analysis of sla printer
Design and analysis of sla printerDesign and analysis of sla printer
Design and analysis of sla printer
 
Report on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al WheelsReport on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al Wheels
 
Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and Pattern
 
Automatic bottle filling Machine
Automatic bottle filling Machine  Automatic bottle filling Machine
Automatic bottle filling Machine
 
CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
 CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
 
Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout
 
Rp
RpRp
Rp
 
ME8793 PPCE QB-1.pdf
ME8793 PPCE QB-1.pdfME8793 PPCE QB-1.pdf
ME8793 PPCE QB-1.pdf
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
 
Senior Design II Final Report Group 3 Paper Stock Bubbles
Senior Design II Final Report Group 3 Paper Stock BubblesSenior Design II Final Report Group 3 Paper Stock Bubbles
Senior Design II Final Report Group 3 Paper Stock Bubbles
 
Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant
 
Design and Development of Hybrid Storage Shelf
Design and Development of Hybrid Storage ShelfDesign and Development of Hybrid Storage Shelf
Design and Development of Hybrid Storage Shelf
 

Painting process analysis and improvement

  • 1. MSU, MANKATO – MET 489 4/30/15 Process Analysis & Improvement: Painting at JMP STUDENT: Christopher Boote FACULTY ADVISORS: Dr. Agarwal PROJECT SPONSORS: Jones Metal Products David Olson ABSTRACT The purpose of this report is to outline and discuss our analysis of the painting process at Jones Metal Products. Our team was assigned to study the process as a whole, and implement lean manufacturing principles. Our method of execution involved several time studies, observations of the processes as they unfolded, and placing all of the data into a current state value stream map. After analyzing the data and coming up with new ways to improve upon the process used by JMP, we followed with a future state value stream map. INTRODUCTION Originally, our project had been centered on how to apply the usage of PLM software to simulate factory operations. However, with the guidance of Dr. Kuldeep Agarwal, we drifted more towards the idea of how to apply Lean Manufacturing principles in a certain area of the factory. In our new project, we would take days to observe the workers in the painting area. We’d talk with them, ask vital questions about how they would work in their stations (approach to certain pieces, steps to perform, etc.), the tools they would use and how they worked, and other questions about how and what they did. We would perform other quantitative studies (discussed later) to measure each stage of the process. After analyzing the process, we would then apply lean methods to suggest improvement for the future. MAIN SECTION PROJECT DESCRIPTION Background Jones Metal Products (or JMP) was founded in 1942 by Mildred M. Jones. The company was started originally as Jones Sheet Metal and Roofing Company to support KATO engineering, and also provide roofing services to the community. Down the road, more emphasis was placed on metal fabrication, which led to the multitude of industries they cater to today. Our team worked specifically on analyzing the painting process at JMP. Problem Definition Currently, the paint process at JMP is pretty efficient. However, they are looking to continuously improve the process, in order to stay competitive in the industry. There are certain areas that create a bottleneck, or slow the process down. Overall, they are looking to cut down on waste, both product and time. Our team was to explore the paint process, and find these areas that could use improvement. Once found, we could apply lean methods and suggest ways to cut down on waste, and reduce time spent in the paint area. Objectives The main objective was to analyze the painting process at Jones Metal Products. Afterwards, we would use that analysis and understanding to suggest areas of improvement in that area using lean principles. In order to do so, we needed to have specific objectives: • Define product of study • Observe the process in entirety, exploring all steps toward finished product • Take time studies of the product through each step of the process • Construct a Value Stream Map (VSM) of the painting process • Construct a future Value Stream Map • Suggest improvement based on future VSM Constraints The production would be constrained by size of the product or products. It would also be constrained by the type of paint used, how the product needed to be treated, according to specifications of the customer. For us, our constraints in the project were centered around time. Specifically, it was whether or not we could talk to certain people, our own availability and theirs. Design Function
  • 2. The function of value stream map was to take time data analyzed by us, put it into the VSM, and after careful analysis by us, determine where time was being wasted and what could be done to eliminate the muda. Design Alternatives After creation and analysis of the VSM, we would create a future state value stream map. In this future VSM, we would group certain processes together, and make changes to streamline the process. More information on this is provided later in the report. PROJECT EXECUTION Define Product Before we could analyze the paint process at JMP, we needed to define the product of study. We chose to work with custom enclosures, one of Jones’ main products. These enclosures are made for a variety of different purposes, depending on the customer. However, the enclosures that we looked at were “outlet boxes” that housed internal components for generators. These boxes are meant to offer protection from electrical connections or other moving parts of a generator. The main customer in our case was KATO engineering. Since these enclosures are made according to the customer’s specification, they can range from small scale, to very large (as shown below).   Figure 1: Large Heat Exchanger (finished) Below is another style of enclosure (outlet box), and its corresponding drawing: Figure 2: Outlet Box (before paint) Figure 3: Outlet Box Drawing Process Analysis - Painting Once we had defined the product of study, the next step was to analyze the painting process from start to finish. This would set up the next part of the project, which was taking time studies at each step. With the guidance of a few employees in the paint area, as well as a detailed map of the shop floor (Appendix D), we were able to fully understand the painting process. The paint process has 3 main steps: Wash, Paint, and Dry. More detail on each of these steps is provided below. Wash   The first step that any part requiring paint will go through is the wash process. The purpose of washing is to remove any contaminants on the part that may inhibit the paint from adhering correctly. Paint doesn’t usually like to stick well to bare metal, so washing will “etch” the part, also promoting adhesion. There are two different wash areas: one is a spray wash for large parts, the other is a system of 5 dip tanks.
  • 3. Spray Wash Area Figure 4: Spray Wash Station The spray wash area is used for large parts that wouldn’t normally fit in the roughly 4’ x 7’ x 4’ dip tanks. Here they use a mixture of water and a metal wash/prep (named GF Seal Prep) through a pressurized wash. The amount of time spent washing a part here depends on the size of the part and the operator. We were told that the operator would know when the part was fully clean by the bluish tint on the metal (pictured below). Figure 5: Finished Sprayed Part Tank Wash Area Figure 6: Tank Wash Station Figure 7: Tank Wash Showing Crane Right next to the Spray Wash station is the more commonly used Dip Tank station. All of the smaller parts produced by JMP come through this station, usually in large batches. Multiple parts are placed on a rack that is about the length and width of the tanks and moved between each one using an overhead crane. This area produces the most consistent parts, since each tank is temperature regulated, as well as time. Tanks 1 through 5 are as follows: 1. Ultrax 92D – Cleaner (5 to 15 minutes) 2. Rinse Water 3. Zircobond 4200D – Metal Etch (2 minutes) 4. Rinse Water 5. Hot Rinse Water (used to speed up drying time by ~10 minutes) After tank 5, the parts are set out to dry before they go in for paint. If the operator has time, they will spray the parts thoroughly with compressed air, to speed up the drying even further.
  • 4. Figure 8: Visual Aid and Thermometer for Tank 3 The images above are examples of the process control of each tank. The poster gives information such as the chemical in the tank, target temperatures (thermometer in figure 8), and how much time the part(s) can spend in that particular tank. All five wash tanks have both of these objects, ensuring a perfect wash every time, as long as the operator follows guidelines. Paint After all of the parts in the batch are dried off, we move to the next step: painting. There are two different methods of painting at JMP: hot pot and p-mix. Hot Pot   Figure 9: Hot Pot Paint Booth The Hot Pot system of painting requires the operator to manually mix a batch per order size or parts to be painted. The Hot Pot system is primarily used for short production runs or small orders that require a special color. The products that we observed for our time studies used this paint method, because there was only an order for 40, so only 40 were painted at that time. For our example, the mix was 1 gallon of primer to 1 gallon of catalyst (or hardener). As with the p-mix system, parts generally travel along a system of conveyors, controlled by the painter. These conveyors are equipped with hooks, so the painter can reach every angle of the part. Once done painting, the painter can move the painted parts to the drying/shipping area with the touch of a button. Figure10: Drying / Shipping Area (Hot Pot side) If parts are in a hurry to get out of the door, the two heat lamps (shown above) are used to speed up the curing of the paint. P-Mix Figure 11: P-Mix Paint Booth The other method of painting at JMP is the P-Mix system. The P-Mix paint is generally used for long production runs with one color, as opposed to the Hot Pot system. In this system, each color is already mixed in huge barrels in a back room and then fed to the spray gun. Colors are changed with the touch of a button outside the paint booth (pictured below):
  • 5. Figure 12: P-Mix Control Panel This one touch of a button gives the operator ease of use, and full control over the paint system. This system is optimal for JMP’s big customers that request the majority of their parts in one color. A couple of customers that fit the criteria are KATO Engineering and Caterpillar. Similar to the Hot Pot system, most parts that get the P- Mix travel along a conveyor. In our case, the size of enclosure would determine whether it traveled along conveyor, or painted on a stand. Figure 13: Enclosure After Paint Drying After paint comes drying, and you would think that would be pretty straightforward. However, Jones Metal uses a few methods to dry the finished product.   Figure 14: Drying Area   The first option is air drying. If the product is on or ahead of schedule, regular drying would suffice. This method is simple, letting the parts dry by hanging on the hooks. Figure 15: Heat Lamps The second option, touched on a little bit previously, is using heat lamps. These lamps use high intensity infrared light to speed up the paint’s curing process. These lamps are located on the Hot Pot side, where they are mainly used.
  • 6. Figure 16: Drying Oven On the other side, the conveyors from the p-mix side travel into the big metal box pictured above. This is a giant oven used for rapid curing of painted products. Parts will generally travel through this oven if they are in a hurry to get out the door. This is a very efficient process in terms of drying, but as far as energy costs go- probably not. Time Studies After analyzing the entire painting process from start to finish, it was time for the actual data part. In order to construct a proper value stream map, we had to find out the amount of time the product spent in each stage.   Methodology   For our time studies, we would be observing a certain product from the moment it arrived to be washed, all the way to the finished product to be shipped. Ideally, we would’ve liked to observe enclosures being painted, but our schedules never lined up right to the enclosures in paint. Instead, we observed another product (Appendix I) through the entire paint line, and took our time studies that way. We chose to split the times up by stage: Washing, Painting, and Drying. We used a simple phone stopwatch, and had somebody record times on a notepad. Afterwards, we were able to calculate the time per square inch, and compare that time to the rough surface areas of the enclosures. The surface area of the observed part was 1734.13 sq. in. Results   Our studies started at the wash tanks. We measured time starting from the moment the operator placed the parts onto the rack. For this study, 18 parts were washed at a time (for space purposes). The complete list of times is attached in the appendix, but this section will give a brief overview. We were able to conclude that the full wash process, arrival to dried part, took a total of 36 minutes. We observed that the parts in Tank #1 were in for much longer than spec. (13 minutes, when the spec is 5 minutes max) shown below: Figure 17: Tank #1 Specification The extra time in the wash seemed to have no adverse effects on the product, but adhering strictly to the specification could cut wash time down significantly. The next step to observe was the actual paint process. We were told that the down time between washing and paint depends on the order size and color to be painted. For our studies, the order size was 40 parts, so the paint process did not start until the full order was through the wash process and ready for paint. Once the parts were in the paint area, the painter would then do a final scuff and wipe down of the piece, further ensuring good quality. For the 40 parts we observed, 79 minutes were spent on prepping the parts alone. Once the paint got rolling, parts traveled quickly along, with an average of 35 seconds per part. The total time spent in the paint area was 49 minutes, including the time moving the conveyor, and random down times. The conveyor was advanced every 4 parts, and added 30 seconds each time it was moved. There were 3 instances of down time: one was a problem in the back paint room, one part had to be cleaned again, and the paint ran out at the 37th part. These down times totaled 15 minutes. Upon completion of the time studies, we found the time per sq. inch to be 0.111 seconds. This number includes both prepping and paint. We then used that number to calculate the amount of time per enclosure. The small outlet boxes (768.125 sq. in.) came out to be roughly 1.5 minutes per box. The medium enclosures (10,158.33 sq. in.) calculated out to be about 18 minutes per part. Remember these times include both prep and paint of each enclosure. As for the drying process, once again our schedules could not accommodate observing such a long process. Because of the schedule conflicts, we were not able to take time studies of the drying process. However, the paint has a curing time of 15-30min touch dry, or 72 hours fully cured  (at 77°F (21°C)). The addition of the oven or the infrared lamps speed the drying process considerably, but since most parts are air-dried, our focus was mainly there.
  • 7. Value Stream Mapping In our value stream map, we decided to label the shipping part of Jones Metal Products as the customer and the previous processes (welding, metal bending, and cutting) as the supplier. Times will vary given the quantity of parts, or size, but for our purposes, and the sake of similar data, we decided to create our current map on a single product. Our value stream map, in its current state, starts of in washing. Figure 18: Wash Process VSM After receiving the product from the previous stations, we either spray wash the product (large generator covers usually receive this kind of treatment), or they are sent into a chemical bath treatment (Wash). Figure 19: Drying Process #1 VSM After the treatment, they are then sent to the first drying station (Drying 1). Figure 20: Painting Process VSM After the parts are dried and residual chemicals are removed from the surfaces, the products are hooked onto a conveyer belt and sent into the painting area (painting). This process involves pull over push since it’s the painter who will call for the products from drying and start the process. Figure 21: Drying Process #2 VSM The next step varied depending on time constraints, and the drying properties of the paint. If there is time, and/or the customer allows for it, the preferred method of drying the paint is to let it be air dried. They will also put the finished products under infrared light to help speed up the process (Drying 2 process 1). If there is a lack of time, and/or the customer demands it, they will go with the alternative method, which involves sending the pieces through the oven. This method does dry the product faster, but is very costly. Also, some paints don't behave the same way as others and may not dry in the desired way for the product. After the final drying process, the products need to be held in inventory for a minimum of 72 hours for the painted product to be completely cured. In this current state value stream map, all recorded times are in minutes. The full VSM can be found in Appendix F. Figure 22: Takt Times Shown above is calculated Takt time for all of the steps in the painting process. This showed us that the processes we needed to focus on were the washing,
  • 8. painting, and second drying processes. Future Value Stream Mapping The improvements to the painting process include integrating the drying 1 and painting process into a manufacturing cell. What we will do here is the moment the parts come out of the final wash, instead of letting them sit and be blown for drying; we will use the conveyor belt to pull parts out of the washing as needed. We will need to add fans and Infrared lights (which are already purchased and used) to dry the parts as they are hung. This will allow the parts to be ready for pulling into the next station. We could possibly extend the conveyor system to come closer to the wash station. This would allow the operator to put parts directly onto the paint line from washing with minimal movement and effort. There will also be a supermarket before the washing process which uses a Kanban system of pulling parts. Another change that we will make in order to reduce the down time on the washing station is to add covers to the final wash station. This is necessary because we have seen instances where the whole process, which depends on the baths being at a certain temperature, could not be started because the last bath was too cold to start the process. We don’t know the exact time improvement adding these covers will make, but we expect it to make an impact. BUDGET Aside from labor hours, this project of analysis and improvement had no budget. RESULTS Based on our observations of the paint process, and analysis of the future state VSM, we were able to come up with a few ideas to improve the process. These improvements start with the lean principles described in the previous section. Aside from the lean principles, there are a few physical upgrades that could be made, one being an extension of the conveyor system. Extending the conveyor over to the wash area would allow an easy transition of parts from washing to drying to painting. With this system, there would be no inventory sitting between the washing and painting processes. This would also allow the wash operator to wash more parts in the time it would’ve taken them to blow dry the washed parts. Some parts with small crevices would likely still need to be blow dried a bit, but the time would still be reduced. Another improvement we thought of was having the conveyor constantly moving at a slow pace. This would eliminate the 30 seconds or so that the painter has to stop painting in order to advance the parts on the conveyor. However, we would need to keep the speed low enough (~0.15 ft/s) so that it does not interfere with the painter. We could see a significant reduction in time using the moving conveyor. Last, as stated before, covering the wash tanks when not in use would improve the process by keeping the wash in its effective temperature. In order to provide constant results, the wash tanks need to stay in spec. temperature. CONCLUSIONS From our study and analysis of the painting process at JMP, we were able to grasp a great understanding of the methods used. This understanding helped us to construct a Value Stream Map, and also to come up with potential improvements. The Value Stream Map was a very helpful tool in showing us areas in need of improvement. The current process used by Jones Metal Products is a good one, however it could stand to use a few upgrades. For starters, we decided to extend the conveyor belt so it would eliminate the need for a second inventory before going to the paint station. We also decided on adding fans and infrared lights along the conveyer belt to speed up the drying process after the products leave the washing station. In the paint station, we decided to make the conveyer belt slow moving so the painter would only need to focus on painting instead of having to stop and move the line after finishing every 4 or more products. Overall, we learned a lot about how even a well-working process can be improved upon using lean techniques. In the future, we can see even our suggestions being superceded by others, since lean manufacturing is an ever changing process. ACKNOWLEDGEMENTS We would like to thank Dr. Agarwal and Dr. Jones for steering us in the right direction, and coming up with a feasible project to complete on such short notice. Also, we would like to thank Dave Olson for setting aside his time to work with us and help us through this project, as well as the employees at JMP for their cooperation. Also, we would like thank Jesus Contreras Villegas for all of his help in gathering information about the paint process. APPENDIX INDEX A: Small Outlet Box CAD Drawing B: Medium Outlet Box CAD Drawing C: Large Heat Exchanger CAD Drawing D: Paint Area Shop Floor Drawing E: Time Study Data F: Value Stream Map G: Primer Sealer Spec.
  • 9. H: Future-State Value Stream Map I: Observed Product (Rhino Hybrid 44”) APPENDIX A: SMALL OUTLET BOX CAD DRAWING
  • 10.
  • 11. APPENDIX B: MEDIUM OUTLET BOX CAD DRAWING
  • 12. APPENDIX C: LARGE HEAT EXCHANGER CAD DRAWING
  • 13. APPENDIX D: PAINT AREA SHOP FLOOR DRAWING
  • 14. APPENDIX E: TIME STUDY DATA Time  Studies  -­‐  Painting  Process   WASH   (18  parts)     Step   Time   Total   Parts  arrive   9:50  AM   10  min   Wash  start/Tank  #1   10-­‐10:13     3  min   Tank  #2   10:14   38  sec   Tank  #3   10:16-­‐ 10:18   2  min   Tank  #4   10:19-­‐ 10:20   1  min   Tank  #5   10:20   39  sec   Drying   10:20-­‐ 10:26   6  min   Total   9:50-­‐10:26   36  min         PAINT   (40  parts)     Step   Time   Total   Set-­‐up/Prep   10:35  AM     Finish  Prep   11:54   79  min   LUNCH  BREAK   12-­‐ 12:30pm   30  min   Start  Paint   12:39     Finish  Paint   1:28   49  min   Total       128   min         PAINT  DOWN  TIME       Issue   Time     Problem  back  room   7  min     Re-­‐clean  part   1  min     Mix  paint  -­‐  ran  out  @37  parts   7  min     Total   15  min    
  • 15. APPENDIX F: VALUE STREAM MAP
  • 16. APPENDIX G: PRIMER SEALER SPEC http://www.diamondvogel.com/prod_data/PG 1http://www.diamondvogel.com/prod_data/PG-1236HDPCPI.pdf
  • 17. APPENDIX H: FUTURE STATE VALUE STREAM MAP APPENDIX I: OBSERVED PRODUCT (TIME STUDIES)