SlideShare a Scribd company logo
1 of 62
Download to read offline
................................................DOCUMENTS.
FOR
CONSTRUCTION
OF
AT K.M. OF
CONSTRUCTION OF RCC OVER HEAD TANK AT WORK
SHOPCOMPOUND KALPIPARA
SARYU NAHAR KHAND-4, BAHRAICH
TENDER
(CONTENTS)
SL.NO. PARTICULARS PAGE NO.
1. Invitation of Tender
2. I.D. Form No. 112 and schedule of bids
3. I.D. Form No. 111
4. Schedule 'B'
5. Schedule 'C'
6. Schedule 'D'
7. SPECIAL CONDITIONS OF CONTRACT
CHAPTER-1
1.1 Definition
1.2 Death, Bankruptcy of contractor
1.3 Acccess to the contractor's Bank
1.4 Contract documents and matters to be treated as confidential.
1.5 Use of construction facilities to other contractors and Government
employees.
1.6 Finds of the work.
1.7 Errors, omission and discrepancies
1.8 The site.
1.9 Drawings
1.10 Roads in work area.
1.11 Contractor not to dispose off soil etc.
1.12 Land
1.13 Employment of labour brought by other contractors.
1.14 Rate for increase in quantities.
1.15 Juri-diction.
CHAPTER-2 PLANT, EQUIPMENT & CONSTRUCTION POWER.
2.1 General
2.2 Conditions for the hire of Government machinery.
2.3 Construction Power.
CHAPTER-3 MATERIALS
3.1 General
3.2 Cement
3.3 Issue Rates
3.4 Consumption of cement
3.5 Excess consumption of materials
3.6 Contractor's Godown
3.7 Materials to be supplied by the contractor
3.8 Deviations, Alterations etc. in the materials
3.9 Reference specifications.
CHAPTER-4 EXECUTION OF WORKS AND
CONSTRUCTION PROGRAMME
4.1 Date and drawing to be furnished
4.2 Stacking out of works
4.3 Lines and Grades
4.4 Bench Marks and survey stakes
4.5 Works subject of Inspection of Technical Audit Cell.
4.6 contractor to be responsible for the
sufficiency of means employed
4.7 Materials, Workmanship etc.
4.8 Period and Hours of work
4.9 Spead of work
4.10 Contractor responsible for maintenance
of works during construction
4.11 Construction Programme
4.12 Clearing up
SPECIFICATIONS
8. CHAPTER-1 EARTHE WORK
1.0 TO 1.12 EARTH WORK in excavation of foundation
1.13 Measurement of Earth Work and Payment
CHAPTER-2 DEWATERING.
SL.NO. PARTICULARS PAGE NO.
CHAPTER-3 CEMENT CONCRETE WORK.
3.01 General
3.02 Composition
3.03 Quality
3.04 Cement
3.05 Air entraining Admixture
3.06 Fine Aggregate
3.07 Coarse Aggregate
3.08 Water
3.09 Proportioning of concrete
3.10 Batching and mixing concrete by volume
3.11 Mixing
3.12 Conveying
3.13 Placing
3.14 Time interval between mixing and placing
3.15 Concrete on earth foundation
3.16 Vibration of concrete
3.17 Replacement of rejected concrete
3.18 Curing and protections
3.19 Repair of concrete
3.20 Finishing of concrete surface
3.21 Vibaration in cement content of concrete
3.22 Strength of concrete
3.23 Measurement of concrete
3.24 Rate
CHAPTER-4 CENTERING & SHUTTERING
4.01 General
4.02 Inspection of forms
4.03 Form sheating and lining
4.04 to 4.05 Form Ties
4.06 Removal of forms
4.07 Scaffolding for centering and shuttering
4.08 Measurement and payment
to 4.10
4.11 Slurry
CHAPTER-5 JOINT FILLER BOARD
5.01 Joint filler board.
CHAPTER-6 STEEL REINFORCEMENT
6.01 General
6.02 Quality of reinforcement
6.03 Placing of reinforcement
6.04 Joints in reinforcement bars
6.05 Overlap Joints
6.06 Welded Joins
6.07 Measurement and payments
CHAPTER-7 Ist Class brick-work in 1:3 or 1:4
cement mortar.
CHAPTER-8 Cement pointing (Struck)
CHAPTER-9 Expansion Joint Drainage, spout, Bearing
& Wheel Guards.
9.01 Expansion Joint
9.02 Drainage Spout
9.03 Bearing
9.04 Wheel guard
9. R.C.C. Railing
10. Contractor's Warranty
11. Certificate of relation ship
12. Drawing.
Each tenderer is advised to carefully examine the conditions of contract, drawings and
specifications, visit the site of works and fully satisfy and acquaint himself with the nature and
locations of the work configuration of ground spring levels, sub-surface conditions, nature of
the river and its character and hydrology, quality and quantity of materials required, character
and quality of materials to be encountered, character of equipment and facilities needed for the
prelimineries and during the execution of the work, leads and lifts involved, the diversions, and
pumping problem etc. and the general and local conditions which may in any way affect the
work or the cost thereof.
3.00 Tenders will be submitted in the I.D. Form No. 112 in sealed cover (envelope)
marked on the upper left hand corner "Tender for construction of
in District_________________________________
4.00 Unless delivered personally, tenders should be submitted by Registered post.
Tenders may be addressed as follows :-
EXECUTIVE ENGINEER
U.P. India
Forwarded by post, the sealed envelope containing the tender and marked as directed
above, shall be enclosed in another envelope properly addressed. Tenders received late or
after the specified time as mentioned above shall not be entertained. Telephonic or
Telegraphic bids shall not be accepted.
5.00 Tendered rates shall be legibly written in English or in Hindi in ink, in Indian
currency in words and figures. The rates in words will Govern. In case of any
discrepency between unit prices and amounts, unit prices will Govern. Erasures and
over witings are strictly prohibited and all corrections must be intialled and dated by the
tenderer.
6.00 Each tender shall contain the name, residence and place of business of the
person or persons tendering for the work and shall be singned by the tenderer with his
usual signature. It shall be signed with the partnership name by one of the members of
the partnership or by and authorised representative followed by the name and
designation (in capital letters) of the person signing the tender.
Tenders by corporations shall be signed with the legal name of corporation followed by
the name of states and by the signature and designation of the president, other person
authorised to bid it in the matter. Attested copy of consititution of the firm with the name
of partners shall be furnished. Letters of attorney authorising the person to sign the
tender shall also the furnished.
7.00 Each tender shall be accompanied with an amount of Rs. __________________
ad earnest money in the form of a Bank call Deposit, F.D.R., or N.S.C. securities
post office Saving Bank Pass Book dly pledged in favour of Executive
Engineer, _______________________________________. Earnest money in cash or
cheque shall not be accepted.
8.00 The tender shall be sbmitted with th following information.
8.01 A declaration that the contractor is an Engineering construction firm who has
successfully carried out large works of this nature and has adequate organisation
including experienced personnel to handle job of the type and magnitude and that he
undertakes to get himself registered in India whithin three months of the date of the
notice of acceptance of the tender, in case he is not already so registred.
8.02 A brief description of major works previously executed by him after the tender
has been opened, tenderer may be required to submit detailed particulars of such works
alongwith the manner of their execution and any other information that may satisfy the
Superintending Engineer, that the contractor has adequate organization including
experienced personnel for efficient execution of the work.
9.00 The Superintending Engineer _______________________________________,
U.P., India may revise or amed the specifications and drawing prior to the date notified
for opening of the tenders, such revision, amendments, if any will be communicated to
all prospective tenderers as addendum or addenda to this invitation of tender. All
tenderers should incorporate the addenda which are fully part of this tender as if herein
set out or if not attached as if hereto attached.
10.00 In consideration of the Government having treated the tenderer be an eligible
person whose tender may be considered, the tenderer shall agree to the condition that
the proposal in responses to this invitation shall not be with drawn by the tenderer with
in One hundred & twenty days from the date of opening of the tender, and also to the
condition that if thereafter the tenderer does withdraw his proposal within the said period
the earnest money deposited by him may be fortified to the Governor of Uttar Pradesh
in the discretion of the later.
NOTE-1- If subsequent to the subimission of the tender, any tenderer amends, alters or
modifies the contents of this tender which are not acceptable to the department, then for
the purposes of these conditions the tnderer shall be deemed to have with drawn his
proposals.
2- If a tenderer, who is exempted from furnishing earnest money, withdraws his
proposal within the said period, he mayin discretion of the Government of Utter Pradesh
be debarred for tendering for a period if one year reckoned from the date of opening of
the tender.
And the tenderer hereby alsoagrees that if subsequent to the submission of his tender,
the tenderer amends, alters, or modifies the contents of his tender which are not
acceptable to the department then the tenderer shall for the prpose of the aforesaid
conditions, be deemed to have withdrawn his poposal.
11.00 Any explanation desired by bidders regarding the meaning or interpretations of
the drawing and specification must be requested in writing and with sufficient time
allowed for a replay to reach them before submisasion of bids.
12.00 The earnest money received with a tender shall be refundable when tender has
been finally rejected.
13.00 Tenderers should always clearly specify in the tenders whether or not any of their
relatives are employed in the State Irrigation Department and if so their names,
disignations and places of posting should be given. Failure in the part of the tenderer to
correctly disclose the names disignation and places of postings would render the
earnest money-security deposit of the tenderer liable to be fortified and the contract, if
executed, liable to be rescinded.
14.00 The tenderers are hereby informed that they have to tender rates for each and
every item contained in the schedule of quantities and bids, as per conditions and
provisions of this tender, otherwise their tender will not be considered.
15.00 While deciding the tender, due consideration shall be given to tenderer's previous
experience in having handled works of similar nature and magnitude, his organisational
and technical knowledge the equipment and machinery available with the tenderer his
financial capacity as well as the existing commitments of tender.
16.00 The tender shall remain open for acceptance for a period commencing from the
date of submission of the tender and ending with the expiry of one hundred and twenty
calender days from the date fixed from opening of the tenders.
17.00 The person or persons who tender is accepted (here in called the contractor)
shall with in one week after the acceptance of his or their tender, deposit in the form
of securities such sum as well, with the tender, amount to 10% of the total cost of
tender.
Superintending Engineer
U.P. India.
iiiiiiiizzzzzzzzssssssss’’’’’’’’kkkkkkkkdddddddd]]]]]]]]
vvvvvvvvffffffff////////kkkkkkkk””””””””kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk
lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM &&&&&&&& pppppppprrrrrrrrqqqqqqqqFFFFFFFFkkkkkkkkZZZZZZZZ
ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbppppppppAAAAAAAA
iiiiiiiizzzzzzzzssssssssffffffff’’’’’’’’kkkkkkkkrrrrrrrr
llllllllwwwwwwwwppppppppuuuuuuuukkkkkkkk ffffffffuuuuuuuunnnnnnnnssssssss””””””””kkkkkkkkdddddddd
llllllllwwwwwwwwppppppppuuuuuuuukkkkkkkk ,,,,,,,,aaaaaaaaoooooooo ttttttttuuuuuuuullllllllEEEEEEEEiiiiiiiiddddddddZZZZZZZZ ffffffffooooooooHHHHHHHHkkkkkkkkkkkkkkkkxxxxxxxx]]]]]]]]
mmmmmmmm00000000 iiiiiiiizzzzzzzz00000000 yyyyyyyy[[[[[[[[kkkkkkkkuuuuuuuuÅÅÅÅÅÅÅÅAAAAAAAA
ii==kkaadd && 22227711@@ll00uu00[[kk00&&44@@VVhh&&88@@ ffnnuukkaadd 1155@@1111@@22000088
ffoo’’kk;; &&%% vvvvvvvvYYYYYYYYiiiiiiiiddddddddkkkkkkkkyyyyyyyyhhhhhhhhuuuuuuuu ffffffffuuuuuuuuffffffffoooooooonnnnnnnnkkkkkkkk ddddddddssssssss llllllllEEEEEEEEccccccccUUUUUUUU////////kkkkkkkk eeeeeeeessssssssaaaaaaaaAAAAAAAA
eeeeeeeeggggggggkkkkkkkkssssssssnnnnnnnn;;;;;;;;]]]]]]]]
ffuuffoonnkk llwwppuukk llaa[[;;kk 0022@@vv00vv00@@ll00uu00[[kk00&&44@@0088&&0099 ddhh 66 iizzffrr;;kkWWaa ee;; llhh00MMhh00 ddss iizzssff’’kkrr ggSS ffdd vvkkii
bbUUggssaa mmRRrrjj iizznnss””kk eessaa iizzppffyyrr ffddUUgghhaa nnkkssaa nnSSffuudd lleekkppkkjj ii==kkssaa eessaa nnkkss&&nnkkss ffnnuu ddss vvUUrrjjkkyy iijj nnkkss cckkjj iizzddkkff””kkrr ddjjuuss
ddkk dd’’VV ddjjssaaAA bbllddss vvffrrffjjDDrr bbllss mm00iizz00 jjkkTT;; ddhh oossccllkkbbVV iijj HHkkhh iizzddkkff””kkrr ddjjuuss ddkk dd’’VV ddjjssaaAA rrFFkkkk iizzddkkff””kkrr
ffuuffoonnkk lleekkppkkjj ii==kkss++ ddhh ,,dd&&,,dd iizzffrr bbll ddkk;;kkZZyy;; ddkkss llaannHHkkZZ ggssrrqq HHkkssttuuss ddhh dd``iikk ddjjssaaAA
ddzzee llaa[[;;kk lleekkppkkjj ii== ddkk uukkee LLFFkkkkuu NNiiuuss ddhh llaa[[;;kk ffrrffFFkk rrdd
11 nnSSffuudd ttkkxxjj..kk yy[[kkuuÅÅ nnkkss cckkjj 3300--1111--22000088
22 ffggUUnnqqLLrrkkuu yy[[kkuuÅÅ nnkkss cckkjj 3300--1111--22000088
33 vvnncc VVkkbbEEll xxkkss..MMkk nnkkss cckkjj 3300--1111--22000088
llaayyXXuudd && mmiijjkkssDDrrkkuuqqllkkjjAA
vvvvvvvvffffffff////////kkkkkkkk””””””””kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk
lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM&&&&&&&&pppppppprrrrrrrrqqqqqqqqFFFFFFFFkkkkkkkkZZZZZZZZ
ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbpppppppp
iiiiiiii========kkkkkkkkaaaaaaaadddddddd &&&&&&&& 22222222222222227777777711111111@@@@@@@@llllllll00000000uuuuuuuu00000000[[[[[[[[kkkkkkkk00000000 &&&&&&&& 44444444@@@@@@@@VVVVVVVVhhhhhhhh&&&&&&&&88888888 @@@@@@@@rrrrrrrrffffffffnnnnnnnnuuuuuuuukkkkkkkkaaaaaaaadddddddd
iizzffrrffyyffii ffuuEEuuffyyff[[kkrr ddkkss llwwppuukkFFkkZZ ,,aaoo vvkkoo'';;dd ddkk;;ZZookkgghh ggssrrqq iizzssff""kkrr ggSS %%&&
11-- eeqq[[;; vvffHHkk;;UUrrkk ¼¼ll00ii00 && 11@@22½½ ffll00ffoo00 mm00iizz00]] QQSSttkkcckknn@@xxkkss..MMkk AA
22-- vv//kkhh{{kk..kk vvffHHkk;;UUrrkk]] uuooee ee..MMyy]] ffllaappkkbbZZ ddkk;;ZZ ccggjjkkbbppAA
33-- vv//kkhh{{kk..kk vvffHHkk;;UUrrkk]] ffaallppkkbbZZ ffuueekkZZ..kk ee..MMyy ccggjjkkbbppAA
44-- vv//kkhh{{kk..kk vvffHHkk;;UUrrkk ;;kkaaff==dd ee..MMyy && ccggjjkkbbppAA
55-- vv//kkhh{{kk..kk vvffHHkk;;UUrrkk]] ddEEII;;wwVVjj ddssUUnnzz]] ddkk;;kkZZyy;; iizzeeqq[[kk vvffHHkk;;UUrrkk]] ffllaappkkbbZZ ffooHHkkkkxx]] mm00iizz00]] yy[[kkuuÅÅ ddkkss llhh00MMhh00
ddss llkkFFkk ffllaappkkbbZZ ffooHHkkkkxx ddhh oossccllkkbbVV iijj iizzddkkff””kkrr ddjjkkuuss ggssrrqqAA
66-- vvff//kk''kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww uuggjj [[kk..MM && 11]]33]]55]]66]]77 ,,aaoo 88 ccggjjkkbbppAA
77-- vvff//kk””kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww MMªªssuusstt [[kk..MM && iizzFFkkee]] ccggjjkkbbppAA
88-- vvff//kk””kkkkllhh vvffHHkk;;UUrrkk]] iizzkkUUrrhh;; [[kk..MM]] ffuueekkZZ..kk [[kk..MM]] yykkssdd ffuueekkZZ..kk ffooHHkkkkxx]] ccggjjkkbbppAA
99-- vvff//kk””kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww uuggjj [[kk..MM @@iizzFFkkee]] uukkuuiikkjjkk]] ccggjjkkbbppAA
1100-- vvff//kk''kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww uuggjj [[kk..MM&&22]] ccyyjjkkeeiiqqjj]] lljj;;ww uuggjj [[kk..MM && iizzFFkkee]] xxkkss..MMkk ddkkss ffuuffoonnkk iizzii==
llaayyXXuu ddjj bbll vvkk''kk;; llss iizzssff""kkrr ggSS ffdd ffnnuukkaadd 1166--1122--22000088 rrdd ddhh ffccØØhh ddhh xxbbZZ lleeLLrr ffuuffoonnkkvvkkssaa ddkkss
ffnnuukkaadd 1188--1122--22000088 ddhh llkk;;aa 55--0000 ccttss rrdd bbll ddkk;;kkZZyy;; ddkkss iizzssff""kkrr ddjjuussaa ddkk dd""VV ddjjssAA
1111-- vv//;;{{kk]] BBssddssnnkkjj llaa??kk]] ddYYiihhiikkjjkk]] ccggjjkkbbppAA
1122-- llggkk;;dd vvffHHkk;;UUrrkk && 11]]22]]33]]44]]55 ,,aaoo [[kk..MMhh;; yyss[[kkkkff//kkddkkjjhh]] lljj;;ww uuggjj [[kk..MM && 44]] ccggjjkkbbppAA
1133 ffttyykkff//kkddkkjjhh@@iiqqffyyll vv//kkhh{{kkdd]] ccggjjkkbbppAA
1144-- uukkssffVVll cckkssMMZZAA
vvvvvvvvffffffff////////kkkkkkkk””””””””kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk
lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM&&&&&&&&pppppppprrrrrrrrqqqqqqqqFFFFFFFFkkkkkkkkZZZZZZZZ
ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbpppppppp
ddddddddkkkkkkkk;;;;;;;;kkkkkkkkZZZZZZZZyyyyyyyy;;;;;;;; vvvvvvvvffffffff////////kkkkkkkk''''''''kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk
lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM &&&&&&&& 44444444
ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbppppppppAAAAAAAA
vvvvvvvvYYYYYYYYiiiiiiii ddddddddkkkkkkkkyyyyyyyyhhhhhhhhuuuuuuuu ffffffffuuuuuuuuffffffffoooooooonnnnnnnnkkkkkkkk llllllllwwwwwwwwppppppppuuuuuuuukkkkkkkk llllllllaaaaaaaa[[[[[[[[;;;;;;;;kkkkkkkk &&&&&&&& 0000000022222222@@@@@@@@vvvvvvvv00000000vvvvvvvv00000000@@@@@@@@llllllll00000000uuuuuuuu00000000[[[[[[[[kkkkkkkk00000000&&&&&&&&44444444@@@@@@@@22222222000000000000000088888888&&&&&&&&0000000099999999
eeggkkeeffggee jjkkTT;;iikkyy mmRRrrjj iizznnss””kk ddhh vvkkssjj llss ffuuEEuuffyyff[[kkrr ddkk;;kkssZZaa ggssrrqq eeqqggjjccUUnn ffuuffoonnkk;;ssaa ooxxhhZZdd``rr
JJss..kkhh eessaa iiaatthhdd``rr BBssddssnnkkjjkkssaa llss ffnnuukkaadd&& 1177--1122--22000088 ddkkss vviijjkkUUgg 33--0000 ccttss rrdd vvkkeeaaff==rr ddhh ttkkrrhh ggSS ttkkss
ffnnuukkaadd&&1199--1122--22000088 ddkkss vviijjkkUUgg 33--0000 ccttss vv//kkkkssggLLrrkk{{kkjjhh ddss dd{{kk eessaa vv//kkkkssggLLrrkk{{kkjjhh vvFFkkookk vvff//kkdd``rr iizzffrrffuuff//kk
}}kkjjkk [[kkkkssyyhh ttkk;;ssxxhhAA ffuuffoonnkk iizzii== ffnnuukkaadd&& 1155--1122--22000088 llss 1166--1122--22000088 rrdd ffddllhh HHkkhh ddkk;;ZZ ffnnooll eessaa
¼¼vvooddkk””kk ffnnooll NNkkssMM++ddjj½½ vv//kkkkssggLLrrkk{{kkjjhh ddss ddkk;;kkZZyy;; ddss vvffrrffjjDDrr lljj;;ww uuggjj [[kk..MM&&iizzFFkkee]] xxkkss..MMkk rrFFkkkk
lljj;;ww uuggjj [[kk..MM&&ff}}rrhh;;]] ccyyjjkkeeiiqqjj ddss ddkk;;kkZZyy;; llss iiaatthhddjj..kk ,,ooaa ffttyykkff//kkddkkjjhh }}kkjjkk ffuuxxZZrr ppffjj==
iizzeekk..kk&&ii== ¼¼II DDTT--11½½]] ggSSffll;;rr iizzeekk..kk&&ii== ¼¼II DDTT--22½½ ddhh eewwyy iizzffrr;;kkWW iizzLLrrqqrr ddjj rrFFkkkk mmuuddhh NNkk;;kk iizzffrr;;kkWW
HHkkhh BBssddssnnkkjj vvFFkkookk mmllddss vvff//kkdd``rr iizzffrrffuuff//kk }}kkjjkk tteekk ddjj ffuuffoonnkk iizzii== ddkk ffuu//kkkkZZffjjrr eewwYY;; tteekk ddjjuuss ddss
ii””ppkkrr iizzkkIIrr ffdd;;ss ttkk llddrrss ggSSAA ddkk;;ZZ llEEccUU//kkhh ffoooojj..kk ,,ooaa ““kkrrssZZ ffuuffoonnkk [[kkqqyyuuss llss ,,dd llIIrrkkgg iiwwooZZ ffddllhh HHkkhh
ddkk;;ZZ ffnnooll eessaa 1111--0000 ccttss llss vviijjkkUUgg 44--0000 ccttss rrdd nnss[[kkss ttkk llddrrss ggSSAA BBssddssnnkkjj }}kkjjkk iizznnRRrr vvff//kkddkkjj ii==
eessaa iizzffrrffuuff//kk ddkk ggLLrrkk{{kkjj iizzeekkff..kkrr ggkkssuukk vvkkoo””;;dd ggSSAA ffuuffoonnkk,, ffnnuukkaadd&&1177--1122--22000088 ddkkss ffooØØssrrkk [[kk..MM eessaa gghh
MMkkyyhh ttkk;;ssxxhhAA ffttUUggss vvUU;; [[kk..MM iizzkkIIrr ffuuffoonnkkvvkkssaa ddkkss ,,dd llhhYYMM ffyyQQkkQQss eeaass jj[[kkddjj ffoo””kkss’’kk nnwwrr ddss eekk//;;ee llss
vv//kkkkssggLLrrkk{{kkjjhh ddss ddkk;;kkZZyy;; eessaa ffnnuukkaadd&& 1188--1122--22000088 nnkkssiiggjj 44%%0000 ccttss rrdd mmiiyyCC//kk ddjjkk;;ssxxssAA
//kkjjkkssggjj //kkuujjkkff””kk ,,uu00,,ll00llhh00 vvFFkkookk ,,QQ00MMhh00vvkkjj00 vvFFkkookk ffuu;;eekkuuqqllkkjj vvUU;; iizzffrrHHkkwwffrr ddss ::ii eessaa ttkkss
vvff//kk””kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww uuggjj [[kk..MM&&pprrqqFFkkZZ]] ccggjjkkbbpp ddss uukkee ccUU//kkdd ggkkssxxhh]] tteekk ddjjuukk vvffuuookk;;ZZ ggkkssxxkk
vvUU;;FFkkkk ffuuffoonnkk LLoohhddkkjj uugghhaa ddhh ttkk;;ssxxhhaaAA ,,dd ;;kk mmllllss vvff//kkdd ffuuffoonnkkvvkkssaa ddkkss ffccuukk ddkkjj..kk ccrrkk;;ssaa ffuujjLLrr
ddjjuuss ddkk iiww..kkZZ vvff//kkddkkjj vv//kkkkssggLLrrkk{{kkjjhh ddkkss ggkkssxxkkAA ll””kkrrZZ ffuuffoonnkk eekkUU;; uugghhaa ggkkssxxhhAA iizzRR;;ssdd ffuuffoonnkk nnkkrrkk ddkkss
::ii;;ss 110000--0000 ddss uukkuu ttqqMMhhff””kk;;yy LLVVSSEEii iissiijj iijj ,,dd ::ii;;ss ddkk jjllhhnnhh ffVVddVV yyxxkkddjj vvuuqqccUU//kk ffyy[[kkuukk
ggkkssxxkk ffdd nnjjssaa 9900 ffnnooll rrdd eekkUU;; ggkkssxxhhAA bbllllss iiggyyss ffuuffoonnkk@@vvkkQQjj ookkiill yyssuuss iijj //kkjjkkssggjj //kkuujjkkff””kk ttCCrr
ddjj yyhh ttkk;;ssxxhhAA ffuu;;eekkuuqqllkkjj nnss;; ffcczzddhhddjj]] vvkk;;ddjj]] LLVVSSEEii MM~~;;wwVVhh rrFFkkkk jjkk;;YYVVhh nnssuukk ggkkssxxkkAA vvuuqqccUU//kk ddss
llee;; LLVVSSEEii MM~~;;wwVVhh rrFFkkkk 1100%% tteekkuurr ddhh vvoo””kkss’’kk ffllDD;;kkssffjjVVhh HHkkhh tteekk ddjjuukk vvffuuookk;;ZZ ggkkssxxkkAA
ØØeekkaadd ddkk;;ZZ ddkk uukkee vvuuqqeekkffuurr
eekk==kk
//kkjjkkssggjj
//kkuujjkkff””kk
vvooff//kk ffuuffoonnkk
iizzii== ddkk
eewwYY;;
iiaatthhdd``rr
JJss..kkhh
11-- ddYYiihhiikkjjkk ddkkyykkssuuhh ooddZZ””kkkkii
ddEEiikkmmUUMM eessaa vvkkjj00llhh00llhh00
vvkkssoojj ggssMM VVSSaadd ccuukkuuss ddkk
ddkk;;ZZ
11 vvnnnn 1144000000--0000 66 eekkgg 222255--0000 llhh vvFFkkookk
mmPPpp
uukkssVV%%&& ffuuffoonnkknnkkrrkk ddkkss LLoo;;aa }}kkjjkk llRR;;kkffiirr vviiuukk QQkkssVVkkss ffuuffoonnkk iizzii== ddss llkkFFkk yyxxkkuukk ggkkssxxkkAA
vvvvvvvvffffffff////////kkkkkkkk””””””””kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk
lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM&&&&&&&&pppppppprrrrrrrrqqqqqqqqFFFFFFFFkkkkkkkkZZZZZZZZ
ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbppppppppAAAAAAAA
AGREEMENT
(To be submitted on General stamp paper)
of Rs. 100.00 only with a Revenue stamp of
Tender invited by :- E.E. S.N.K.-4, BAHRAICH
Tender for :- CONSTRUCTION OF RCC OVER HEAD TANK AT WORK SHOPCOMPOUND KALPIPARA
Tender Notice No. 02/E.E./SNK-4/2008-09 & date 15.11.2008
Name of Tenderer
In Consideration of the Government of Uttar Pradesh having treated the tenderer to be
an eligible person whose tender may be considered, the tenderer here by agrees to the
conditions that the proposal in response to the above invitation shall not be withdrawn within
120/90 days from the date of opening of the tender and also to the condition that if after the
tenderer does withdraw his proposal within the said period, the earnest money deposited by
him may be forfeited to the Governor of Uttar Pradesh in the discretion of the letter.
The tenderer hereby also agrees that if subsequent to submission of his tender, the
tenderer amends, or modifies the contents of his tender which are not acceptable to the
department, then the tenderer shall for the purpose of the aforesaid condition be deemed to
have withdrawn his proposal.
Signed this day of
Witness TENDERER
I.D. FORM NO. 112
I.D. FORM NO. 112
PUBLIC WORKS DEPARTMENT UTTAR PRADESH
S.N.K-4, BAHRAICH Division BAHRAICH Sub Division
ITEM OF PERCENTAGE RATE-TENDER OF CONTRACTORS
Name of work - CONSTRUCTION OF RCC OVER HEAD TANK AT WORK
SHOPCOMPOUND KALPIPARA
Name of contractor....................................................................
GENERAL RULES AND DIRECTIONS FOR THE GUIDANCE OF
CONTRACTORS
1. All works proposed for execution by contract will be notified in a from of invitation to
tender pasted on a board hung up in the office of and signed by the Sub-Divisional Officer
kgkg -------------------------------------------------------------------------------------------Executive Engineer
This from will state the work to be carried out, as well as the date for submitting and
opening tenders, And the time allowed for carrying out the work also the amount of carnets
money to be deposited with the tender and the amount of the security deposit to be deposited
by the successful tenderer and the percentages, if any to be deducted from bills, this set of
contract documents consisting of copies of drawing and details of the proposed work
specifications schedule of quantities of various items of the works and a form of the printed
conditions of contract together with the form of tender to be used signed for the purposes of
identification by the Sub-Divisional Officer and approved by the authority competent to make
-----------------------------Executive Engineer
the contract shall be available for public inspection at the Office of the Sub-Divisional Officer
kgkg -------------------------------------------------------------------------------------------Executive Engineer
during the office hours.
2. In the even of the tender being submitted by a firm, it must be signed separately by
each member there of in the event of the absence of any partner it must be
signed on behalf by a person holding a power-of attorney authorizing him to do so.
3. Receipt for payments made on account of work when executed by a firm must also be
signed by the several partners, except where the contractors are described in their tender as a
firm in which case the receipt must be signed in the name of the firm by one of the partners or
by some-other persons having authority to give receipts for the firm.
4. Any contractor who submits a tender shall fill up the prescribed form of tender striking
out alternative office on page 3 of the form not applicable to the case. Tenderers which
propose any alteration in the work specified in the form of notice inviting tender or in the time
allowed for carrying out the work or which contain any other conditions of any sort, or are not
filled up in English or not accompanied by the deposit of earnest money notified, will be liable
to rejection. Tenders shall have the name of the work to which they refer written outside the
envelope.
5. (1) The Executive Engineer; or his duly authorized assistant will open tender in the
presence of any intending contractors who may be present at the time and will enter the
amounts of several tenders in a comparative statements in a suitable form. In the event of a
tender being accepted, a receipt for the earnest money forwarded here with shall thereupon be
given to the contractor, who shall thereupon for the purpose of identification, sign copies of the
specification and other documents mentioned in rule I. In the event of a tender being rejected
the earnest money forwarded with such unaccepted tender shall thereupon be returned to the
contractor making the same.
(2) When tenders are received by the Sub-Divisional Office he will open and deal with
them in the manner specified above, and will submit then to the Executive Engineer for orders.
The earnest money if in currency notes shall be credited in the cash-book and paid into the
Treasury, a receipt in Account Form No. 3 being given to the party tendering. If earnest money
in preferred in any of the securities specified in Rule 9, it shall be entered in the register of
securities. Account form 85 and 86, Earnest money received in currency notes shall be
returned to unsuccessful tenderers as soon as their tender are rejected the usual stamp
receipt being taken.
6. The accepting authority shall have the right of rejecting all or any of the tenders.
7. The receipt of an accountant or a clerk for the earnest money paid by the contractor will
not be considered as any acknowledgement if Payment to the Sub-Divisional Officer and -
------------------------------------------------------------------------------------- Executive Engineer
Contractor shall be responsible for seeing that he procures a receipt signed by the Sub-
Divisional Officer- gkkgkkgkgkgkg--------------------------------------------------------------------------
kExecutive Engineer
8. The memorandum of work tendered for shall be filled in and completed in the office of
the Sub Divisional Officer offer the tender form is issued kgkgkgkgkglkglkgkfkgfkgkgfgkfkgflkg
k Executive Engineer
9. The amount of earnest money should ordinarily be...........................................................
(a) When the amount of the tender does not
exceed Rs. 2000 50
(b) When exceeding Rs. 2,000 and not exceeding Rs. 5000 100
(c) When exceeding Rs. 5,000 and not exceeding Rs. 10000 200
(d) For each additional Rs. 5,000 or portion of Rs. 5000
a further sum of 100
Such earnest money shall be deposited by the contractor in Government treasury or
sub treasury as laid down in paragraphs 340 (b) (1) 344 and 345 (b) of the Financial
Handbook. Volume V, part I, Account Rules and the receipted treasury challan attached to the
tender
Note- The Officer calling for tender may, in special cases where it would nbe
inconvenient for tenderers the deposit money into Government treasury, relax the rule an
permit contractors to deposit earnest money with in cash or currency notes up to a limit of Rs.
100 instead of it a treasury, such deposits should be treated as "Public Works Department
Depostit"
CONSTRUCTION OF RCC OVER HEAD TANK AT WORK SHOPCOMPOUND KALPIPARA
Bill of Quantity
Sl.
No.
Item of work No L (m) B (m) H/D (m) Content
1- Supply of all material, labor T&P etc.
complete for conatruction of a R.C.C.
over head thank of 50kl capacity at
15.00m. Staging above ground level
and 1.00m. Wide P.C.C apron around
with 15cm semi circlure PCC drain,
1.00m. Wide RCC stair case from
G.L. up to balcony M.S.I. ladder with
hand rails on both side from balcony
to top dome and inside the tank body
1.00m wide RCC bolcony around the
thank at the junction point of vertical
and conical wall with proper railing of
20mm dia medium grade G.I. pipe in
3 row on both side of staircase case ,
balcony, at the dome and at each
landing on RCC posts space at not
more than 1.50 interval proper
ventilattor at top dome water level
indicator lightening conductor as
latest ISI on electrcity rule 0.60m. dia
main hol cover hinged with locking
arrangement, fixing and jointion
vertical pipes for inlet, outlet over flow
and washout withall jointing materials
for proper completion and other
supplementry works including
excavation in all type of soils painting
of all expose surface and steel pipe
work with three coats of approvad
cement paint or anticorrosive paints
and assumad safe vearing capacity
of soil has been taken as
8.00mt./sqm.
1 - - - 1 job
2- Supplying laying jointing of 80 mm
dia medium grade G.I. pipe I.S. 1239
part (i) 1979 complete with fitting and
refilling etc. complete
1x20 6.00 - - 120.00RM
3- Supply of 80 dia copper alloy gate
valve class (i) I.S. 778-1980 with iron
wheel head etc. complete.
1x4 - - - 04 No.
4- Supplying and fixing of 80mm dia G.I.
elbow ISI make including cost of all
material labour T&P etc. complete.
1x12 - - - 12 No.
5- Supplying and fixing of 80 mm dia
G.I. socket ISI make including cost of
all material labour T&P etc. complete.
1x20 - - - 20 No.
"I or "We"
TENDER FOR WORKS
Hereby tender for the execution for the Governor of Uttar Pradesh
of the work specified in the underwritten memorandum within the time
specified in each memorandum at the rate specified there in and in
accordance, in all respects, with the specifications, designs drawings and
instructions, in writing referred to in rule I herein and in clause 2 of the
conditions of contract and with such materials as are provided for by and
in all other respects in accordance with such conditions so for as
applicable
(a) if several sub work
are included, they
should-be detailed
in a separate list
(b) Vide rule 9 on page 2
(c)Strike out the
alternative and
attach signature to it
MEMORANDUM
(a) General description
(b) Estimate cost Rs.
(c) Earnest money Rs.
(d) Time allowed for the work from date of written order to commence
Months.
(c) TENDERED
Rate......................
...
(c) ANCTIONDED
Item
No
Item of work approximate
number of
quantity
unit per
(f) in
figure
(f) in
Word
s
N.B.-When tenders are
to be submitted at
a percentage above
or below the rate in
the sanctioned
estimate the
information in all
the columns should
be filled by the Sub
Divisional Officer/
Executive Engineer.
2.2--In the case of
works when
contractors are
required to quote
their own rates for
the different item
of works the
column (f) should
be left blank for
tendereres to fill in
Rs. P.
BILL OF QUANTITY
ATTACHED
uksV%&vko”;d Mªkbax vf/k”kklh vfHk;Urk ds dk;kZy; ls
i`Fkd ls izkIr dh tk ldsxhA
"I or "We"
Strike out the
alternative and attach
signature to it
_______________tender at______________percent above the rates
entered above
or
_________________________tender at the above rates,
should this tender be accepted___________ hereby agreed to
abide by and fulfil all the terms and provisions of the conditions of
contract annexed to the approved set of contract documents' or in
default thereof to forfeit and pay to Governor of Utter Pradesh or his
successors-in-office the dums of money mentioned in the said
conditions.
Give particulars
and number.
The sum Rs.___________is here with forwarded in currency
notes as earnest money the full value of which shall be retained by
government on account of the security deposit specified in clause I of
to the conditions of contract.
Signature of Witness
to contractor's
Signature
Dated the _____________________day of _________________200
__________________________ ___________________
Signature of
contractor before
submission tender
Witness_________________________
Address_________________________
Occupation_______________________
Here enter
Recommended or
Non Recommended
Signature
Date_____________Sub Divisional Officer___________Sub-Division
______________________
______________________
Signature
Date_______________Executive Officer________________Division
______________________
______________________
Signature & official
designation of the
accepting authority
Date___________Superintending Engineer______________Division
Irrigation Works
The above tender is hereby accepted by me on behalf on the
Governor Uttar Pradesh.
_______________________
Date the__________________day of _____________________200
I.D. FORM NO. 111
I.D. From No. 111
CONDITIONS OF CONTRACT
Clause 1: The person or persons whose tender is accepted (hereinafter
called the contractor) shall within one week after his or their tender has been
accepted, deposit with Government of Uttar Pradesh (hereinafter called the
"Government") either in cash or in securities as provided in paragraphs 614
and 615 of the Financial Handbook, volume VI such as will with the earnest
money deposited with the tender amount to rupees.......................................of
the cost of contract where any security so deposited is not payable to bearer,
the contractor shall endorse to transfer into the said Government in such a
manner that the sum represented by it can be realized without the consent or
assistance of the contractor, the contractor shall permit Government at the
time of making any payment to him for work done under the contract t deduct
10% (ten percent) of all money so payable on account of security deposit until
such dedicators along with the sum already deposited as earnest money to be
adjusted in the last deduction will amount to 10% of the cost of contract.
Security Deposit
The amount of the security money shall, if not withheld on account on
breach of contract be refunded after six month of the date of completion of the
work or after payment of the final bill whichever is later, subject to the
conditions that in case of building work of the first rainy season comprising of
June, July, August, September is fully covered with in the period of six months
mentioned above the amount of security money if not withheld on account of
breach of contract, be refunded after the expire of the first rainy season
comprising of the months mentioned above or after the payment of the final bill
which ever is later.
Provided that in case the payment of the final bill is not made within six
month of the completions of the works 75% of the amount of the security
money can be refunded with the prior approval of the authority next higher to
the person accepting the contract on behalf of the government.
All compensation or other sum of money payable by the contractor to
Govt. under the terms of his contract may be deducted from or realized by the
sale of the sufficient part of his security deposit, or from the interest arising
there from or from any sum which may be due or may become due to the
contractor by Govt. or on any account whatsoever and in the event of his
security deposit being reduced by the reason of any such deduction or sale as
aforesaid, the contractor shall within ten days there after made good in case
or Govt. securities endorsed aforesaid any sums which may have been
deducted from, or raised by sale of his security deposit or any part thereof.
EXPLANATION- For the purposes of this clause if the work under this
contract includes construction, reconstruction or repair of any structure having
proof over it, the whole work will be classed as building work.
CLAUSE-2(A) Time is the essence of the contract. The contractor shall
commence &-shall complete the work covered by the tender on the dates fixed
by the...................................Engineer for the commencement and completion
of such work & shall in the interval between those dates keep the work upto
the schedule of quantities and dates and dates shown in the progress
Statement be signed by the contractor and attached to the tender. If the work
fails in arrears of the progress Statement either in Quantity or in time, then for
every day that the work is so in arrears the contractor shall be liable to pay as
compensation an amount equal to one percent or such similar amount as
the...............................................Engineer (Whose decision in writing shall be
final) may decide on the estimated cost of the whole work provided always that
the entire amount of compensation to be paid under the provisions of the
clause shall not exceed 10% of the estimated cost of the work as shown in the
tender.
[CLAUSE-2.B To be used instead of 2 (A) when the latter is from the
nature of the work impracticable]
CLAUSE-2.B Time is the essence of the contract. The contractor shall
commence & shall complete the work within the period specific in the tender.
Such period shall be reckoned from the date on which the order to commence
work is given to the contractor. The contractor shall at all times during such
period proceed with the work with due diligence and he shall pay as
compensation an amount equal to one percent or such smaller amount as
the.........................................................................Engineer (whose decision in
Compensation
for delay
writing shall be final) may decide on the amount of the amount of the
estimated cost of the whole work as shown in the tender for every day that the
work remains uncommented or unfinished after the proper dates and further in
order to ensure good progress during the execution of the work the contractor
shall be bound in all cases in which the time allowed of any work exceeds one
months to complete on-fourth of the value or quantity (as the
.............................................Engineer may determine) of the whole of the work
before on-forth of the whole time allowed under the contract has elapsed, one
half of the value or quantity (as the........................................... Engineer may
determine) of the work before one-half of such time has elapsed and three-
fourths of the value or quantity (as the................................ Engineer may
determine) of this work before three-fourths of such time has elapsed if the
contractor fails to comply with his condition he shall be liable to pay as
compensation an amount equal to one present of such smaller amount
as.........................................Engineer (whose decision in writing shall be final)
may decide on the estimated cost of the whole work for every day that the
quantity of work for every day that quantity of work remains incomplete,
Provided always that the entire amount of compensation to be paid under the
provisions of the clause shall not exceed 10% on the estimated cost of the
work as shown in the tender
CLAUSE-3(i) In any in which under any clause or clauses of this
contract amounting to the whole of his security deposit (whether paid in one
sum or deducted by installment) the .........................................Engineer shall
have power to adopt such of the following courses as he may deem best.
Action by which
whole of security
deposit is
forfeited
(a) He may rescind the contract by giving the contractor ................days
notice of rescission signed by the...................................Engineer and may
then take the whole of the contractor's security deposit for the use of Govt. as
compensation for the loss caused by the contractor's default.
(b) He may, after giving the contractor..........................................days
notice in writing of his intension to do so, measure up the work done by the
contractor and then employ and pay labourers and supply or produce
materials and carry out all or any part of the work himself on behalf of Govt.
debiting the contractor with the actual cost and crediting him at the contract
rates with the value of the work so done, and may postpone till completion of
the work, so taken over assessment of the compensation to be paid by the
contractor, if any work is so taken over by the.....................................Engineer
the certificate in writing of the Executive Engineer or the Sub-divisional Office
as to its cost and value shall be final and conclusive against the contractor.
(c) He may, after giving the contractor..........................................days
notice in writing of his intension to do so, measure up the work done by the
contractor take the work out of his hand and give a contractor for its
completion to another contractor and may postpone till the completion of the
work. The assessment of the compensation to be paid by the original
contractor. If the.............................Engineer elects to give the completion of
the work to another contractor the original contractor shall pay any expenses
which may be incurred in excess of the sum which would have been paid to
him if the whole work had been carried out by him, and a certificate in writing
of the...................................Engineer or of the ..................................... shall be
final and conclusive as against the original contractor as to the amount of any
such expenses.
(i) If the...................................................Engineer does not desire to do
so the work, the contractor shall not be entitled to compensation for any loss
sustained by him by reason of his having purchased or procured any
materials, or entered into any engagements, or made any advances on
account of or with a view to the execution of the performance of the contract,
and shall not be entitled to recover or be paid or be given credit for any sum
for any work there of actually performed by him under this contract, unless
and until the Executive Engineer or the Sub-Divisional Officer acting under
this order shall have certified in writing the performance of such work and the
value thereof the contractor shall only be entitled to be paid the value as so
certified.
(ii) If upon any occasion the..........................................Engineer
abstains from exercising the powers given to him by this clause such
abstention shall not prevent him from exercising such powers upon a
subsequent occasion if the contractor again makes default, not shall such
abstention absolve the contractor from liability to pay compensation for any
default which he may have made.
CLAUSE 4.If the...............................................Engineer exercise any
of the powers given to him by clause 3 he may, if he so desires take,
possession of all or an tools, plants, materials and stores in or upon the
work, or the side thereof and belonging to the contractor or procured by
him and intended to be used for he execution of the work or any part
thereof, and pay or allow the contractor for the same at the contract rates,
or in the case of these not being applicable, at current market rates to be
certified by the Executive Engineer, whose certificate thereof shall be final,
and if the...........................Engineer does not desire to do so the Executive
Engineer may be notice in writing to the contractor or his clerk if the works
foreman of other authorized agent required him to remove such tools,
plants, materials or stores from the premises (with in a time to be specified
in such notice), and if the contractor fails to comply with any such
requisition, the Executive Engineer as to expenses of any such removal
and the amount of the proceeds and expenses of any such shall be final
and conclusive against the contractor.
Contractor
remains liable
to pay
compensation
if action not
taken under
clause 3
Power to take
possession of
or require
removal of or
sell
contractor's
plant
CLAUSE 5. If the contractor desires an extension of the time for
completion of the work on the ground of any unavoidable hindrance to its
execution having arisen, he shall apply in writing to
the................................ Engineer within 30 days the existence of such
hindrance first becomes known to him, and the........................................
Engineer shall if in his opinion (which shall be final) reasonable ground be
shown thereof, authorize such extension of time as may, in his opinion be
necessary or proper.
Extension of
time
CLAUSE 6. On completion of the work the contractor shall send a
registered notice to the Sub-Divisional Officer (hereinafter called Engineer-
in- charge) given the date of completion and shall also send a copy of such
notice to the Executive Engineer, and shall request the Engineer –in-
charge to give him a certificate of completion No Such certificate will be
given not shall the work be considered to be complete until the contractor
has removed from the premises on which the work has been executed all
scaffolding, surplus materials and rubbish, and cleaned all wood-work,
doors, windows, walls, floors or other parts of any building in, upon or
about which the work has been executed or of which he may have had
possession for the purpose of the execution thereof and, if the contractor
fails to do so or before the date fixed or completion of the work the
Engineer-in-charge may do so, and may sell such scaffoldings and
materials as have not been removed by the contractor and the contractor
shall forthwith pay all expenses so incurred and shall have no claim in
respect of any such scaffolding, surplus materials as aforesaid except for
any sum actually realized by the sale thereof. On completion the work shall
be measured by the Engineer-in-charge, whose measurements shall be
binding and conclusive against the contractor.
Final
Certificates
CLAUSE 7. In the case of work estimated to cost more than rupees
one thousand, the contractor shall, on submitting the bill thereof be
entitled to receive a monthly payment proportionate to the part thereof
then approved for such purpose by the Engineer-in-charge, whose
certificate of approval and passing of the sum to payable shall be final
and conclusive against the contractor, But any such payments will only be
mane as advances to be credited to Government in the final settlement of
accounts, with the contractor and not as payment for work completed and
passed, and the making of any such payment shall not either preclude the
Executive Engineer or Sub-Divisional Officer from requiring the contractor to
remove or reconstruct any work on the ground that such work is bad,
unsound, imperfect or unskilled or prevent Government form enforcing any
claim against the contractor on account of any default by him or conclude,
determine or affect in any way the powers of the Engineer-in-charge under
payment on
intermediate
certificate to
be regarded
as advance
these conditions or any of them as to final settlement and adjustment of the
accounts or otherwise in any other way very or effect the contractor. The
Engineer-in-charge's certificate of the measurement and of the total amount
payable for the work shall be final and biding on all parties.
CLAUSE 8. If the contractor abandons, or is unable to complete the
work the................................Engineer may certificate in writing the value of
the work done by the contractor towards the completion of the contract. Such
a certificate shall be final and conclusive against the contractor and he will not
be paid more than the value of such work as so certified is respective of the
contract rates.
liability to
complete the
work.
CLAUSE 9- When the estimate on which a tender is made includes
lump sum in respect of parts of the work, the contractor shall be entitled to
payment in respect of the items of work involved, or the part of the work in
question at the same rates as are payable under this contract for other such
items of work, unless the part of the work in question is not in the opinion of
the Engineer-in-charge, capable of measurements in which case the
Engineer-in-charge may pay such lump sum as he may determine to be the
value thereof, and the certificate in writing of the Engineer-in-charge shall be
final and conclusive against contractor as to the basis upon which payment is
to be made is such case and as the amount to be paid.
Lump sum
estimates
CLAUSE 10. Evers month on or before a date to be fixed by the
Engineer-in-charge the contractor shall if so required, submit a bill for all
works executed by him during the previous month and the Engineer-in-charge
shall take or cause to be taken all measurements necessary for checking the
contractor's bill and adjusting his claim as speedily as possible. If the
contractor does not submit his bill within the time so fixed the Engineer-in-
charge may after giving the contractor..........................................day's notice
in writing measure or depute some one to measure such work in the presence
of the contractor whose signature on the list of measurements shall be
sufficient authority to the Engineer-in-charge to draw up, a bill based on such
measurements and any bills so drawn up shall be binding on the contractor. If
the contractor fails to attend when such measurements are taken, such
measurements shall be binding on him, and if he attends but refuses to sign
the list of measurements the matter shall be referred to the immediate
superior of the Engineer-in-charge whose decision shall be binding on the
contractor.
Bills to be
submitted
monthly
CLAUSE 11. The contractor shall submit all bill on the printed for which
will be supplied to him at the office of the Engineer-in-charge and all items in
such bills shall be charged at the rates specified in the tender or in the case of
any extra work ordered in pursuance of these conditions, and not mentioned
or provided for in the tender, at the rates hereinafter provided in such work.
Bills to be
printed form
CLAUSE 12. If the specification or estimate of the work provides for the
use of any special description of materials to be supplied form the Engineer-in
–charge's store, or if it is required that the contractor shall use certain stored
to be provided by the Engineer-in-charge mentioned being so for as
practicable and for the convenience of the contractor specified in the schedule
hereto annexed but not so as in any way to control the meaning or effect of
this contract) the contractor shall be supplied with which materials and stores
may from time to time be required by him for the purposes of the contract but
only for such purposes and he shall pay for the same at the rates specified in
the said schedule or if no rates are so specified at cost price at defined in
clause 13 thereof
Stores supply
by
Government
All materials so supplied to the contractor will become the property of
the contractor, but shall not on any account be removed from the site of the
work until the whole work is certified to be completed by the Executive
Engineer except with the written permission of the Executive Engineer, and
shall at all times be open to inspection by the Engineer-in-charge shall
however have the opinion to take over any such materials, if unused at time of
the completion or termination of the contractor at the specified issue rate or
the current market rat, whichever is less.
CLAUSE 13. All articles requires by the contractor for the contraction of
the work and which the contractor is to supply himself, shall be obtained by
the contractor from the firms with which the Director of Industries has made
arrangements and if for the supply of any articles no such arrangements have
been made, any such articles supplied by the contractor shall conform to such
specification and/or tests, if any, as may be prescribed by the Director of
Industries in consolation with the consuming department .
CLAUSE 14. The contractor shall obtain from the stores of the
Engineer-in-charge all such imported stores or materials as may be
requires in any part thereof for making up articles required thereof for in
connection therewith. The value of such stores and articles as may be
supplied to the contractor by the Engineer-in-charge will be debited to the
contractor in his account at the rates shown in the Schedule attached to
the contract and if they are not entered in the Schedule they will be debited
at the cost price, which for the purposes of this contract shall include the
cost of carriage and all other expenses whatever which shall has been
incurred in obtaining delivery of the same at the store aforesaid. The
Executive Engineer may issue materials to the contractor from existing
stock if he asked for any excess of those entered in the Schedule. In such
cases the price charged will be the stock rate or the market rate which ever
is greater.
Stores
imported from
Europe to be
obtained from
Government
CLAUSE 15. The contractor shall execute the whole and every part
of the work in the most substantial and workman like manner and in every
respect in strict accordance with the specification both as regards materials
and otherwise. The contractor shall also conform exactly, fully and faithfully
to the designs, drawings and instructions in writing relating to the work
signed by the Engineer-in-charge and lodged in his office, and the
contractor shall be entitled to inspect the same during office hours and may
at his own expense have copies of the specifications and of all such
designs, drawings and instructions as aforesaid made for own use.
Work to be
executed in
accordance
within
Specifications
drawings
orders, etc.
CLAUSE 16. The Engineer-in-charge shall have power to make such
alteration in additions to, the original specifications, drawings, designs and
instructions as may appear to him to be necessary or advisable during the
progress of the work, and the contractor shall be bound to carry out the
work in accordance with any instructions which may be given to him in
writing signed by the Engineer-in-charge and such alteration shall not
invalidate the contract, and any additional work which the contractor may
be so directed to do shall be carried by the contractor on the same
conditions in all respects on which be agreed to do the main work, and at
the same rates as are specified in the tender for the main work. The time
for the completion of the work shall be extended in the proportion that the
additional work bears to the original contract work, and the certificate of the
Engineer-in-charge shall be conclusive as to such proportion. If the
additional work includes any item for which on rates is specified hereunder
then the contractor shall carry out the work at the rate entered in the
schedule of rates of the direct but if the schedule does not contain any rate
for such work, then the contractor shall not begin such work until a rate in
respect of such work has been settled by mutual agreement between him
and the Engineer-in-charge with the approval of the officer accepting the
contractor any if they are unable to agree upon a rate within two weeks
from the date when the contractor received the order, the Engineer-in-
charge may be a notice in writing cancel the order for such work and carry
it out in such work carry it out in such manner as he may think best in the
event of a dispute, the decision of the Superintending Engineer shall be
final and binding on the contractor.
Alteration in
specification
and designs.
Do not
invalidate
contract
Extension of
time in
consequence
of all contract
Rate for
additional
work not in
estimate or
schedule of
rate of district.
CLAUSE 17. The Executive Engineer acting on the writing order of
his immediate superior, may at any time by notice in writing to the
contractor either stop the work altogether or reduce or cut it down. If the
work is stopped altogether, the contractor will only be paid for work done
and expenses legitimately incurred by him on, or preparation for the
execution for the work up to the date on which such notice is received by
him such expenses shall be assessed by the Executive Engineer, whose
decision shall be final and binding on the contractor. If work is cut down the
No
compensation
or alteration in
a restriction of
work to be
carried out
contractor will be paid for the work as so cut down but in neither case
will be paid any compensation whatever for the loss of profit which he
might have made if he had been allowed to complete all the work
included in the tender.
CLAUSE 18. If the Engineer-in-charge is satisfied that the
construction of any part of the work is faulty all that materials used in the
same are inferior to those for which the specification provides or that any
materials or articles provided by the contractor are not in accordance with
the contract, he may notwithstanding that such work, materials or articles
may have been passed, certified or paid for, serve the contractor with
notice in writing specifying the work, materials or articles of which he
complaints and requiring the contractor to remedy such defects or to
replace such materials within a specified period of time.
Action and
compensation
payable in
case of hand
work
If the contractor fails to comply, in all respects with the
requirements of any such notice within ten days after the expiration of the
period specified in that notice, the Engineer-in-charge may himself
remedy such defects, or as the case may be replace such materials or
articles, and contractor shall pay all expenses incurred by the Engineer –
in-charge in so doing and the certificate in writing of the Engineer-in-
charge as to the amount of any such expense shall be final and binding
upon the contractor.
CLAUSE 19. All works ;under or in the course of extension or
executed in pursuance of the contract shall at all times be open for
inspection and supervision by the Engineer-in-charge and his
subordinates and the contractor shall at all times during the usual working
hours, and on any other occasion of which he shall have all responsible
notice either himself be present to receive orders and instructions, or
have responsible agent duly accredited in writing present for that
purpose, Orders given to any such agent have the same affect as order
given to the contractor himself.
Work to open
to inspection.
CLAUSE 19.(A) No labourer below the age of 14 years shall be
employed on the work
CLAUSE 19. (B) The contractor shall pay to his labourers a fair wage.
CLAUSE 19. (C) The contractor before he commences the work shall
(s)post in a conspicuous place on the work a notice giving the rates of wages
which have been certified as fair by the Executive Engineer, and (b) send a
copy of the notice to the Executive Engineer.
CLAUSE 19. (D) The contractor shall be responsible to comply with
the provisions of the labour laws in force in state of Uttar Pradesh including
the Minimum wages Act or any enactment in supersession, extension or
modification thereof which may be passed at any time or from time to time
by a competent legislative body any may have effect in the state of Uttar
Pradesh and the Rules and Regulations made there under or any
amendments or modifications thereof for the time being in force. All
expenses in connection. with the compliance of such laws and rules shall
be borne by the contractor, and the contractor, shall neither demand nor
claim nor shall be entitled to any additional payment for the reason that he
failed to take into account any such expense in his tender or that any
subsequent amendments in such laws or rules have changed the basis on
which he worked out such expenses while submitting his tender.
In every case in which by virtue of the provisions of the labour
laws in force in the State of Uttar Pradesh and the rules and regulations
made there under, the Government is obliged to pay any sum in the
execution of the work Government will recover from the contractor the
amount so paid, and without prejudice to the other rights of the
Government, the Government shall be at liberty to recover such amount
or any part thereof deducting it either from the security money deposited
by the contractor or to his credit under clause I of these conditions or
from any other sum due by the Government to the contractor whether
under this contract or otherwise.
Vide G.O. No. 1331 IBD-50/XXIII-IB-89—B.W. dated 26 may 1950
CLAUSE 20, In order that the work may be measured and the correct
dimensions thereon taken, the contractor shall not cover up any part of the
same or otherwise place it beyond reach of measurement until he has either
obtained the consent in writing of Engineer-in-charge or of his subordinate in
charge of the work or until he has given to the Engineer –in-charge or to such
subordinate five days notice in writing that the work is ready for measurement.
If the contractor, covers up any work or places it beyond of the measurement
without such consent and before the expiration of the period of such notice,
the contractor shall either, as he may elects tip such work at his own expense
order that it may be measured or shall forfeit the price of such work and of the
materials used in its contractions.
Contractor or
responsible
agent to be
present.
CLAUSE 21. All works to be executed under the contract shall be
executed under the direction and subject to the approval in all respect of the
Engineer-in-charge for the time being, who shall be entitled to direct at what
points or points and in what manner they are to be commences, and from time
to time carried on.
Notice to be
given before
work is
covered up.
CLAUSE 22. Except where otherwise specified in the contract the
decision of the.............................................................................Engineer for
the time being shall be final conclusive and binding on all parties to the
contract upon all questions relating to the meeting of the specifications,
designs, drawings and instructions herein before mentioned. The decisions of
such Engineer as to the quality of workmanship or materials used on the
work, or as to any other question, claim, right, matter or thing whatsoever in
any way arising out of or relating to the contract, designs or drawings,
specifications, estimates, instructions, over of these conditions or otherwise
concerning the work or the execution of failure to execute the same whether
arising during the progress of the work or after the completion or
abandonment of the contract by the contractor, shall also be final, conclusive
and binding on the contractor.
Direction of
work.
CLAUSE 23. If the contractor or his work people or servants shall
break, deface, injure or destroy any part of a building in which they may be
working or any building, road fence enclosure are grass land or cultivated
ground contiguous to the premises on which the work or any part of it is being
executed or if any damage shall happen to the work while in progress from
any cause due to the negligence of responsibility (the decision of the
Executive Engineer shall be final), the contractor shall at his own expense
make good such damage, or in default, the Engineer-in-charge may cause the
same to be made good and the contractor shall, pay any expense so incurred
and certificate of the Engineer-in-charge as to the amount of such expenses
shall be final and binding on the contractor.
Decision of
Engineer to be
final.
Contractor
liable for
damage done
and for
imperfections
for three
months after
certificate.
CLAUSE 24. The contractor shall supply at his own cost all materials
(except such special materials, if any as may in accordance with the contractor
be supplied from the Engineer-in- charge's stores), plant, tools, appliances,
implements, ladders, cordage tackle, scaffolding and temporary works requisite
for the proper execution of the work whether original, altered or substituted and
whether included in the specifications or other documents forming part of the
contract or referred to in these conditions or not or which may ne necessary for
the purpose of satisfying or complying with the requirements of the Engineer-in-
charge as to any matter as to which under these conditions he is entitled to be
satisfied or which he is entitled to require, and shall pay for the carriage of all
such things to and from the work. The contractor shall also supply without
charge workmen with the means and materials necessary for the purpose of
setting out works. and for counting, weighing and assisting in the measurement
or examination of the work, or materials at any time. If the contractor fails to do
so the same may be provided by the Engineer-in-charge and the contractor
shall pay the cost of the same as certified by the Engineer-in-charge whose
certificate shall be final. The contractor shall also provide all necessary fencing
and lights required to protect the public from accident and shall bear the
expenses of defense of every suit, action or other proceeding at law that may
be brought by any person for injury sustained owing to neglect of the above
precautions, and shall also pay any damages and costs which may be awarded
in any such suit action or proceeding to any such persons or, which nay with
the consent of the contractor be paid to compromise any claim by any such
Contractor to
supply plant,
ladders
scaffolding,
etc.
And liable for
damages
arising from
non provision
of light
fencing, etc.
Female labour
not to be
person. employed
CLAUSE 25. The contractor shall not employ female labour in the
execution of the work of any part thereof within the limits of a cantonment
Work not to
sub-let
CLAUSE 26. The contractor shall not assign or sub-let the contract
without the written approval of the...........................................................Engineer
and if the contractor does or attempts so to do or becomes insolvent or
commences any insolvency proceedings or makes attempts to make an
composition with his creditors, or if he or any of his servants or agents either
directly or indirectly, or gives, offers or promises any bride, gratuity gift loan,
perquisite, reward or advantage pecuniary or otherwise to any public officer or
person in the employ of Government in any way relating to his office or
employments, or if any such officer or person shall become in any way directly
or indirectly interested in the contract without having first obtained the
permission in writing of the Government, the.........................................Engineer
may thereupon by notice in writing resend the contract, and the security deposit
of the contractor shall thereupon stand forfeited and be absolutely at the
disposal of Government and the same consequences shall ensure as if the
contract had been rescinded under clause 3 hereof and in addition the
contractor shall not be entitled to recover or be paid for any work there for
actually performed under the contract.
CLAUSE 27. Any sum payable by the contractor as compensation under
any of these conditions shall be deemed to be reasonable compensation for the
act or default in respect of which the same becomes payable without proof of
the actual amount of damages or loss sustained.
CLAUSE 28. In the case of a tender by partners, the contractor shall the
name of the members of the firm and shall notify to the Engineer-in-charge any
change in the constitution of the firm as soon a such change occurs.
CLAUSE 29. In the case of any class of work for which there in no such
specification as is mentioned in rule, such work shall be carried out in
accordance with the district specification, and if there is no district specification,
the work shall be carried out in all respects in accordance with instructions and
requirements of the Engineer-in-charge.
Contract may
rescinded and
security
deposit
forfeited for
subletting
bribing or if
contractor
becomes
insolvent
Sum payable
way of
compensation
be considered
reasonable
compensation
without
reference to
actual loss
Changes in
constitution
firm
Action where
specification
Definition
work
CLAUSE 30. In these conditions unless there is something in the
subject or context repugnant to such an interpretation, the expressions
"work" mean the work to be done or executed under the contract whether
such work is permanent or temporary and where it is original altered
substituted or additional
CLAUSE 31. The additions and deductions on account of the
percentage referred to at page 3 of the accepted tender will be calculated
on the gross, and not the net amounts of the bills for the work done.
Contractor
percentage
whether
applied to net
or amount of
bills
CLAUSE 32 (1). In every case in which by virtue of the provisions of
section 12 sub-section (1) of the Workmen's Compensation Act, 1932
Government is obliged to pay compensation to a workman employed by the
contractor or by any sub-contractor from him in the execution of the work
Government will recover from the contractor the amount of the
compensation so paid, and without prejudice to the rights of the Government
under section 12 sub-section (2) of the said Act, Government shall be at
liberty to recover such amount or any part thereof by deduction it either from
the security money deposited by the contractor or the his credit under clause
1 of these condition pr from any other sum due by Government to the
contractor whether under this contract or otherwise.
(Strike out the
clause in
cases of an
item rate
contract)
CLAUSE 32 (2). Government shall not be bound to contest any claim
made against it under section 12 sub-section (1) of the said Act, excepts on the
Compensation
to workmen.
written request of the contractor and upon his giving to Government full security
for all costs for which Government might become liable in consequence of
contesting the claim
CLAUSE 33. Not withstanding anything stipulated in the aforesaid
clauses. Government shall have power to retain any sum due to the contractor.
(s) and set off all claims against him (there) whether arising out of the
particulars contract or out of any other transaction or in partnership with
others.
CLAUSE 34. All disputes in respect or contract arising between
contractor and the department will be put up to the Superintending Engineer
............................................circle irrigation work ........................... and his
decision shall be final and legally binding on both parties.
CLAUSE 34.(A) (i) If the contractor considers any record or any
ruling of the Engineer-in-charge or of his representatives in respect of any
of the provision of this contract to be unfair of considers any work
demanded by his to be outside the requirements of the contract he shall
immediately ask upon such record or ruling being made or such work being
damaged ask in writing for written instructions or decisions, no receipt
whereof he shall proceed without and delay to confirm to the record or
ruling or to perform the work demanded and within 15 days after date of
receipt of the written instructions or decisions he may file written protest up
objection is are made on record in the manner herein specified and within
the time limit stated ruling, instruction or decision of the Engineer-in-charge
shall be conclusive and binding on the contractor, instruction and/or
decisions of the Engineer-in-charge contained in letter transmitting drawing
to the contractor shall be considered as written instructions, subject to
protest objections as herein provided.
CLAUSE 34.(A) (ii) If the contractor is dissatisfied with the final
decision of the Engineer-in-charge on the protest or objection made by the
contractor in accordance with the procedure prescribed in clause 34(i) the
contractor may within twenty-eight (28) days after receiving notice on such
decision give notice in writing to the Engineer-in-charge requiring that the
matter be submitted to arbitration and furnishing detailed particulars of the
dispute of difference specified clearly that point at issue it the contractor
fails to give such notice within the period of 28 days as stipulated above
the decision of the Engineer-in-charge shall be conclusive and binding on
the contractor.
CLAUSE 34-A(iii) Every dispute, difference or question which may at
any time arise between the parties here to any person claiming them
couching or arising out in respect of this deed or the subject matter thereof
shall be referred to the arbitration of....................................... or any
person nominated by him. It will be no objection to any such appointment
that the arbitrator so appointed is a Government servant that he had to
deal with the matters to which the contract relates and that in the course of
his duties as Government servant he had expressed views on all or any of
the matters in dispute or difference. In the event of the arbitrator to nom the
matter is originally referred being transferred of vacating his office or being
unable to act for any person............................ . a hall either upon the
reference himself or appoint another person to act as arbitrator such
person shall be entitled to proceed with the reference from the stage it was
left by his predecessor, it is also a term of this contract that no person
other than a person appointed as aforesaid should act as arbitrator and if
form any reason that is not possible, the matter is not to referred to
arbitration at all. in all cases where the amount of the claim in dispute is
Rs. 50,000/- (Rupees Fifty thousand) and above the arbitrator shall give
reason for the award it is a term of the contract that the party invoking the
arbitration shall specify the dispute or dispute to be referred to arbitration
together with the amount or amounts claimed in respect of each dispute.
Subject as aforesaid the provision of the arbitration Act 1940 or any
statutory modification or re-enactment thereof and the rules made there
under and for the time being in force shall apply to the arbitration
proceedings.
The arbitrator may form time to time with the consent of the parities
enlarges the time for making and publishing the award.
CLAUSE-34 (A) (iv) The cost of such arbitration shall be borne by
the parties or party as decided by the arbitrator.
CLAUSE-34 (B) (i) If under the contract has not been completed
when a dispute is referred to arbitration the work shall continue the
arbitration proceeding and no payment due to the contractor within the
provision of the contract shall be withheld on account of arbitration
proceeding unless authoresses or required by the arbitrator.
CLAUSE-34 (B) (ii) Every dispute difference or question which may
at any time arise between the parties here to any person claiming under
them couching or arising out in respect of this deed or the subject matter,
thereof shall be referred to the arbitration of............................................ or
any person nominated by him. It will be not objection to any such
appointment that the arbitrator so appointed is a Government servant that
he had to deal with the matter to which the contract relate and that in the
course of his duties Government servant he had expressed views on all or
any of the matters in disputes or differences in the event of the arbitrator to
whom the matter is originally referred or being transferred or vacating his
office or being unable to act for any reason......................................shall
either enter upon the reference himself or appoint another person to act as
arbitrator. Such person shall be entitled to proceed with the reference from
the stage it was left by his Predecessor it is also a term of this contract that
no person other than a person appointed as aforesaid should act as
arbitrator and if for any reason that is not possible the matter is not to be
referred to arbitration at all. In all cases where the amount of the claim in
dispute is Rs. 50,000/- (Rupees fifty thousand) and above the arbitrator
shall give reason for the award.
CLAUSE-34 (B) (iii) It is a term of the contract that the party
invoking the arbitrator shall specify the dispute or disputes to be referred
to arbitration together with the amount or amounts claimed in respect of
each dispute.
Subject as aforesaid the provisions of the Arbitration Act. 1940 or
any statutory modification or re-enactment thereof and the rules made
there under and for the time being in force shall apply to the arbitration
proceedings.
The arbitrator may form time to time with the consent of the parities
enlarges the time for making and publishing the award.
CLAUSE-35 Quantities are liable to variation on either sides without
entitling the contractor to compensation on his account
CLAUSE-36 Contractor shall himself make proper living accommodation
water and sanitary arrangements etc. for labour which ordinarily should be
arrangement through Employment Exchange, will give preference to Ex-
serviceman, He will have to remove any undesirable labour if ordered by the
department.
CLAUSE-37 Claims not preferred within 48 hours of occurrence are
liable to be rejected.
CLAUSE-38 No extra payments shall be made to the contractor for
making profiles and naming as in connection with the execution with the
execution of work as per G.O. No. 355-3B/66XXXIII-IB-IT dated 22-06-1966
CLAUSE-39 During the course of construction if any emergency is
forwarded arisen due to any clause or claims of works the contractor shall
send a registered cover notice to the...................................... Engineer-in-
charge within a fortnight of the origin of the claims. If he fails to do so or if
he post pones submission of such claims till the work he will be entitled to
on compensation.
CLAUSE-40 The Contractor shall not influence or direct labour borne
on the muster Roll or by any other contractor by paying higher wages or
providing extra facilities with –out the permission of the Executive Engineer
and if he does so contrary to the above, will be responsible for the loss of
or damage caused or claimed by other parties and the decision of the
Executive Engineer as to the amount of such damage shall be final and
binding on both parties.
CLAUSE-41 This agreement is subject to the standard specifications
The clearance of site shall be done by the contractor at his own expenses.
CLAUSE-42 Income Tax at the rate of 2% shall be deducted from
the bill in terms of sub-section (I) of section 194 (c) of Income Tax Act XVI
of 1972
CLAUSE-43 FOR FAMILY PLANNING PURPOSEN IS CONTRACT.
The contractor agrees to persuade all his labour and other
employees, including casual labour employed by him, to adopt family
planning techniques (including vasectomy and Tubectony) in lines with the
policies and programme announced by the State Government from time to
time in relation to the State Government is so for as may be applicable and
to furnish to Engineer-in-charge monthly report in this behalf.
G.O. No. 5032/76-23/C-3/1975/76 Date 8 Sept. 1976
Schedule showing (approximate) material to be supplied from the Public work
Stores for works contracted to be executed and the rates at which they are to be
charged for. vide clause 12 of Conditions.
Particulars Rates at which the materials will be
charged to the contractor
Place of
delivery
Unit Rs. P.
Signature of Contractor Signature of sub-Divisional Officer
Executive Engineer
Schecule Of Consumption Of Material To Be
Used For Different Item Of Works
Sl.No. Item of Work Unit Cement of Bags
1. Cement concrete mix 1:4:8 Cum 3.25 (Natural Aggregates.)
3.40 (Crushed Aggregates.)
2. Cement concrete 1:3:6 Cum 4.15 (Natural Aggregates.)
4.30 (Crushed Aggregates.)
3. Cement concrete 1:2:4 Cum 5.76 (Natural Aggregates.)
6.10 (Crushed Aggregates.)
4. (A) Ist Class brick work in 1:4
Cement mortar.
Cum 2.00
(B) Ist Class brick work in 1:3
Cement mortar.
Cum 2.60
5. Cement Pointing (Struck) 1:2
Cement mortar
Sqm 0.055
6. (A) Cement plastering 12.5 mm. thick
in 1:4 Cement sand mortar.
Sqm 0.110
(B) -----------do-----------in 1:5 Sqm 0.095
(C) -----------do-----------in 1:6 Sqm 0.079
7. Reinforcement steel M.Tonne As per Quantity placed
according to Drawing as
intered in M.B.
_____________________________________________________________________________
SCHEDULE-B
Sl.No. Item of Work Unit Places of Issue Rate
1. Cement in bags of 50 Kg as
received from Factory
Bags Govt. Store at
Kalpipara
Rs. per bag
215/-
2. Steel for reinforcement M.T. ..............do.............. 31500/-
3. Structural steel (M.S. plate, angle
iron gierders, Flats & channels etc.)
M.T. ..............do.............. -
4. Max phalt M.T. ..............do.............. -
5. Rubber seal R.M. ..............do.............. -
6. Copper seal R.M. ..............do.............. -
7. Joint filler Board/Themocol S.M. ..............do.............. -
8. Pressure observation pipes. R.M. ..............do.............. -
9. Sheet piles M.T. ..............do.............. -
_____________________________________________________________________________
SCHEDULE-C
Sl.No. Name of equipment which can be given
on rent to the Contractor if available
with department
Hire charges per
month or part there of
[Calender months]
Unit Places of Issue
1. Electric/Diesel concrete mixer Each Govt. Store
at.........................
2. Electric/Petrol vibrater Each ...........do...........
3. Electric welding set 75/- Each ...........do...........
4. Diesel welding set 125/- Each ...........do...........
5. Shuttering plate 2/- S.M. ...........do...........
6. Steel shoulding for shuttering 20/- M.T. ...........do...........
7. Electric/Diesel pumps
(5 H.P. to 10 H.P.)
125/- Each ...........do...........
8. Bore Hole pump. 175/- Each ...........do...........
_____________________________________________________________________________
SCHEDULE-D
CHAPTER - 1
SPECIAL CONDITION OF CONTRACT
1.1 DEFINITIONS :
For the purpose of these specifications comprising conditions of contract
amendments, the following words will have the meanings herein assigned to them:
1.1-1 The "GOVERNMENT" shall mean the Government of Uttar Pradesh.
1.1-2 The "GOVERNOR" nominated by President of India from time to time, shall
mean the adminstrative head of the State of Uttar Pradesh.
1.1-3 The "CHIEF ENGINEER" shall mean the Chief Engineer, Irrigation Department,
Uttar Pradesh.
1.1-4 The "SUPERINTENDING ENGINEER" shall mean the Superintending
Engineer-in-charge of the work.
1.1-5 The "EXECUTIVE ENGINEER" shall mean the officer so designated
authorised by the Govt. of Uttar Pradesh who shall work under the general
administrative control of the Superintending Engineer and will be the in charge of the
entire operation pertaining to the contract.
1.1-6 The "ASSISTANT ENGINEER" or "Sub-Divisional Officer" shall mean the
officer so designated and authorised by the Govt. of Uttar Pradesh who shall be in
actual in charge of field operations.
1.1-7 The "ENGINEER IN CHARGE" shall mean the Executive Engineer in Charge
of the work. The Engineer may delegate any of his powers to his authorised
representatives. Wherever the word "Engineer-in-charge" occurs in the text of the
contract, it would be taken to imply the Engineer-in-charge as aforesaid or his
authorised representative, or representatives as the case may be.
1.1-8 The "CONTRACTOR" shall mean the tenderes whether a firm, registered
company, partnership or an individual whose tender shall be accepted and shall
include its legal representative, successors and assigness.
1.1-9 The word "WORK" or "WORKS" wherever used in this contract shall be hold to
comprise not only works of construction but also all accessories there to and all
matters and things pertaining to the work executed or to be carried out unet the
contract, whether such works permanent or temporary and whether it is original,
altered, substituted or additional including clearance of site on the completion of
construction. Wherever the context so require the words "WORK" or "WORKS" shall
also include all temporary establishments such as hutting, quarters, offices, store
sheds, workshop, roads, foundations or plant and machinery required for the work.
1.1-10 The word "SPECIFICATION" shall mean collectively all the terms and
stipulations contained in the conditions of contract, technical provisions and
annexires, and corrections and amendments to the specifications.
1.1-11 The word "DRAWINGS" shall mean collectively all accompanying general
drawings as well as all detailed drawing which may be issued by the Engineer-in-
charge from time to time during the period of construction.
1.1-12 The word "TONES" wherever used in this contract shall mean metric tonnes of
1000 Kg. unless otherwise specified.
1.1-13 Wherever fogures are shown after the word "ELEVATIONS, REDUCED
LEVEL" or any abbriviation thereof or when figures representing "ELEVATION" or
"REDUCED LEVEL" are given the shall mean the height in metres above the mean
sea level unless otherwise specified.
1.1-14 The words used in contract in the singular number shall be interpreted to
lincude the plural number and the plural, the singular number.
1.1-15 The words "Plant" "MACHINERY" and "EQUIPMENT" shall mean and include
plant machinery, tools and other equipment necessary for the work as per
specifications and plans in a workman I like manner.
1.1-16 "RATES" or "TENDERED RATES" shall mean the rates as entered in the
"Schedule of Quantities and Bids" by the contractor and is accepted by the
government or its authorised representative. The rate shall include all taxes such
as sales tax toll tax etc. all duties an royalties etc. and all incudental charges required
for the completion of particular item or work.
1.1-17 The "WORK SITE" shall mean the site of propsed work as detailed in
specification or any other place where works are to be executed under the contract
and such land in the vicinity of of works as may be notified by the Engineer-in-charge
as the work site.
1.1-18 The word "MONTH" shall mean the calender month.
1.1-19 The word "WRITING" include any manucript, type witten, cyclostyled or printed
statement under and over signature or seal as the case may be.
1.1-20 The word "SUB CONTRACTOR" shall mean the person named in the contract
for any part of the work or any person to whom any part of contract has been sublet
by the contractor with the consent in writing the Engineer-in-charge and the heirs,
legal representative, successors and assigness of such persons.
1.1-21 "CONTRACT & CONTRACT DOCUMENT" shall mean the agreement in I.D.
Form No. 112 and its component parts.
1.1-22 Matric system shall be followed in all interpretations and execution of the work
in this contract. Any conversion found necessary shall be in accordance with figures
given in Indian standard conversion Factor and Conversion Table (I.S. 786-1956) and
its subsequent revisions.
1.1-23 The "PARAGRAPH" shall mean clause also.
1.1-24 The word "SUBSTRUCTURE" shall mean the portion of the structure below
the level of rich wearing coat level of the floor, and the word "SUPERSTRUCTURE"
shall mean the portion of the structure from and above the level of the rich wearing
coat level at the floor.
DEATH ; BANKRUPTCY OF CONTRACTOR
1.2 If the contractor dies or commits any act of bankruptcy or being a corporation,
commences to be wound up, except for reconstitution purpose or carries on its
business under a receiver, the executors, successor or the representatives in law of
the estate of the contractor or any such receiver, liquidator or any person in whom the
contract may become vested shall forth with give notice there of in writing to the
Engineer-in-charge and shall for one month during which he shall take all reasonble
steps to prevent stoppage of work have the option to carry out the contract subject to
his or their providing such guarantee as may be required by the Engineer-in-charge
but not exceeding the value of the work at the time remaining unexecuted. In the
event of stopage of the work the period of the option under this clause shall be
fourteen days only, provided that should the above option not be exercised the
contract may be terminated by the Government by giving notice in writing to the
contractor and the Engineer-in-charge by exercise the same power which he could
exercise and will have same right which the would have under clause 3 of I.D. from
111 if the work had been taken out of the contractor's hand.
ACCESS TO THE CONTRACTOR'S BOOKS
1.3 Whenever it is considered necessary by the Engineer-in-charge to ascertain
the actual cost of the extra items or claims be shall direct the contractor to produce
the personnel, invoices of materials and any other data relevant to the item or
neccessary to determine its cost act and the contractor shall when so required furnish
information pertaining to the aforesaid items in the mode and manner that may be
specified.
CONTRACT DOCUMENTS AND MATTERS TO BE TREATED AS CONFIDENTIAL
1.4 All documents, correspondence, decision and other matters concerning the
contract shall be considered as of confidential and restricted nature by the contractor
and he shall not divulge or allow access there to any unauthorised persons of any
kind.
USE OF CONSTRUCTION FACILITIES TO OTHER CONTRACTORS AND GOVERNMENT
EMPLOYEES
1.5 The government may undertake or award other contract for additional work
at or in the vicinity of the works under this tender and the contractor shall fully
co-operate with such other contractor and Government employees and carefully fit in
his work of such additional works as may be directed by the Engineer-in-charge. The
contractor shall not commit or permit any act which will interfere with the performance
of the work being done by government to use the roads, bridges, lighting installation
and any other facilities constructed or acquired by the available without entailling any
increases in the cost to the contractor for maintenance or operation for such facilities.
FINDS OF THE WORKS
1.6 Any finds in the area of work such as relies of fossils or articles of other value
or any minerals etc shall be the absolute property of the Government of Uttar
Pradesh and shall be handed over intact by the contractor to the Engineer-in-charge.
The contractor shall take reasonable precautions to prevent articles or things and
shall immediatly, on discovery therof and before removal, acquaint the Engineer-in-
charge of such Discovery.
1.7 ERRORS OMISSIONS AND DISCREPANCIES
1.7-1 If the contractor discovers any error, omission and discrepancies on the
contract drawings or specifications or in the work undertaken and performed by him,
he shall immediately notify the Engineer-in-charge and the latter shall promptly verify
and set right the same. The contractor shall not take advantage or errors or
omissions as full instruction shall be available to the contractor. Should any error or
omission and prior to the correction thereof if the contractor proceeds with any work
affected thereby, he shall do so at own risk and the work so done shall not be
considered as work done under the contract and in performance thereof. However
payment for extra works done as a result of error of omissions in designs, drawings
or specifications issued by the Engineer-in-charge shall be made to the contractor to
the extent of quantities of work done before the errors or omissions were discovered
or were brought to the notice in writing.
1.7-2 The drawing and specifications are to be considered as explanatory of each
other and should anythins appear in the former but is not described in the latter no
advantage shall be taken by the contractor of any such omission. In case of
disagreement between specifications and drawing, the conditions of the
specifications shall govern the contract should any discrepancies, however appearor
should any misunderstanding as to the dimensions or the quantity of the materials for
the proper executions of the work or as to the measurements or quantity and
valuation of the works executed arise under this contract or as extra item, the same
shall be explaines by the Engineer-in-charge.
1.7-3 In case of errors, omissions and/or disagreement between the drawing and
specification, the following order of preference shall apply.
(i) Between the written or shown description one in the specifications the letter
shall apply.
(ii) Between the quantities shown in the schedule of quqntities and those arrived at
from drawings, the letter shall apply.
(iii) Between the written description of the item in the schedule of quantities an the
detailed description in the specification of the same item, the latter shall be
adopted.
(iv) Figured dimensions shall supercede sealed dimensions, drawing to a larger
scale shall take precedence over those on smaller scale.
1.7-4 Special directions incorporated in the drawing shall be complied with strictly.
1.7-5 Drawing issued as construction drawing from time to time will supercede the
once previously issued.
1.8 THE SITE
1.8-1 The is understood and agreed that contractor has satisfied himself as to the
nature and location of the works general and local conditions or and particularly
those being on transport, handling or storage of materials, disposal of spoils,
availability of labour, weather conditions or similar physical conditions at the work
site, sub soil water, hydrology and configuration of ground, the character, quality
and quantity of the surface materials to be encountered, the character or equipment
and facilities needs preominiary to and during the execution of the work and all other
matters which may in any default or failure by the work or the cost thereof under this
contract. Any default or failure by the contractor to acquaint himself with all the
information conerning these conditions will not relieve from responsibility for the
execution of the contract unless the contract provides that the the responsibility
thereof is assumed by the Government.
1.8-2 The information and date states herein and incorporated in the contract
elsewhere is for information only and the Engineer-in-charge does not guarantee that
the available records shown completely the existing condition and does not
guarantee any interpertations of these data or correctness of information. The
contractor shall assume full responsibility for any deductions or conclusions drawn
there from by him.
1.9 DRAWING
Index map and drawing showing plan and cross-sections areenclosed.
1.10 ROADS IN WORK AREA
The kachcha or pucca roads constucted by Government in work area and in
coloney will be available for use by the contractor subject to the conditions implsed by
Engineer-in-charge. The addition to the roads constructed at his own cost all the
roads requited in addition to the roads constructed by the Government.
1.11 CONTRACTOR NOT TO DISPOSE OFF SOIL ETC.
The contractor shall not dispose off or remove except for the purpose of
fulfilment of this contract, sand, stone, clay, ballast, earth, trees and shurbh or site of
the work and all such materials and produce shall remain property of the
Government, Government may upon request from the contractor or if so stipulated in
the conditions of the contract, allow the contractor to use any of the above materials
for the works free of cost.
1.12 LAND
The contractor will be permitted to use the land if available with the Irrigation
Department and remarked for the construction camp, free of cost during the period of
the contract. Such use of land shall not interfere with any part or work of the
contractor or of the Government in the vicinity. If no such land is in possession of the
Irrigation Department the same will be acquired by the contractor at his own cost by
private negotiations and no claim shall be admissibe to him on this on account.
1.13 EMPLOYMENT OF LABOUR BROUGHT BY OTHER CONTRACTOR
If the contractor takes away any labour brought and employed by other
contractors of the Government working in the project, he shall be liable to pay
compensation equal to the project the original contractor would have continued with
him and he will also have made if the return the labour this employed. The decision of
the Engineer-in-charge shall be final and binding on the contractor.
1.14 RATES FOR INCREASE IN QUANTITIES
If there is any increase in the quantities due to any reason, whatsoever the
access quantity more than that provided in the schedule of bids shall be paid either at
the tendered rates or at the departmental schedule of lates of operating at the time of
entering in to the agreement whichever is the minimum.
1.15 JURIDICTION
The contract shall be governed by the laws of Govt. of U.P./Govt. of India, for
the time being inforce & shall subject to the juridiction of this district Court at
Bahraich.
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender
Oht tender

More Related Content

What's hot

Tender Document for Solar Project in Himachal Pradesh
Tender Document for Solar Project in Himachal PradeshTender Document for Solar Project in Himachal Pradesh
Tender Document for Solar Project in Himachal PradeshHeadway Solar
 
1324 2013 04-09-13-28-52-1365494332
1324 2013 04-09-13-28-52-13654943321324 2013 04-09-13-28-52-1365494332
1324 2013 04-09-13-28-52-1365494332Dayanand Sonawane
 
KD Production and Technology Assistance Agreement (Purchase this doc, Text: 0...
KD Production and Technology Assistance Agreement (Purchase this doc, Text: 0...KD Production and Technology Assistance Agreement (Purchase this doc, Text: 0...
KD Production and Technology Assistance Agreement (Purchase this doc, Text: 0...GLC
 
Tender Notice Sample
Tender Notice SampleTender Notice Sample
Tender Notice SampleSATISH
 
5. international standard contract for construction
5. international standard contract for construction5. international standard contract for construction
5. international standard contract for constructionHyoyoung Kim
 
Bid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal PradeshBid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal PradeshHeadway Solar
 
Request For Proposals (RFP) For Recruitment Of Market Development Representat...
Request For Proposals (RFP) For Recruitment Of Market Development Representat...Request For Proposals (RFP) For Recruitment Of Market Development Representat...
Request For Proposals (RFP) For Recruitment Of Market Development Representat...Blogatize.net
 
Request For Proposal Rfp For Recruitment Of Mdr Russia
Request For Proposal   Rfp   For Recruitment Of Mdr RussiaRequest For Proposal   Rfp   For Recruitment Of Mdr Russia
Request For Proposal Rfp For Recruitment Of Mdr RussiaBlogatize.net
 
Time Related Professional Practice
Time Related Professional PracticeTime Related Professional Practice
Time Related Professional PracticeAzizan Supardi
 
Quality Related Professional Practice
Quality Related Professional PracticeQuality Related Professional Practice
Quality Related Professional PracticeAzizan Supardi
 
Engineering and Supervising Service Contract (Purchase this doc, Text: 081188...
Engineering and Supervising Service Contract (Purchase this doc, Text: 081188...Engineering and Supervising Service Contract (Purchase this doc, Text: 081188...
Engineering and Supervising Service Contract (Purchase this doc, Text: 081188...GLC
 
Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1Adnan Alam
 
New application form 08-6-2012 - klj greens
New application form   08-6-2012 - klj greensNew application form   08-6-2012 - klj greens
New application form 08-6-2012 - klj greenslandandhomesncr
 
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdfKrishnaKG4
 
Gls Sector 81 Gurgaon | 9650789998
Gls Sector 81 Gurgaon | 9650789998Gls Sector 81 Gurgaon | 9650789998
Gls Sector 81 Gurgaon | 9650789998Deepanshu Upadhyay
 

What's hot (20)

Tender Document for Solar Project in Himachal Pradesh
Tender Document for Solar Project in Himachal PradeshTender Document for Solar Project in Himachal Pradesh
Tender Document for Solar Project in Himachal Pradesh
 
1324 2013 04-09-13-28-52-1365494332
1324 2013 04-09-13-28-52-13654943321324 2013 04-09-13-28-52-1365494332
1324 2013 04-09-13-28-52-1365494332
 
ARTIST AGENT AGREEMENT
ARTIST AGENT AGREEMENT ARTIST AGENT AGREEMENT
ARTIST AGENT AGREEMENT
 
KD Production and Technology Assistance Agreement (Purchase this doc, Text: 0...
KD Production and Technology Assistance Agreement (Purchase this doc, Text: 0...KD Production and Technology Assistance Agreement (Purchase this doc, Text: 0...
KD Production and Technology Assistance Agreement (Purchase this doc, Text: 0...
 
Tender Notice Sample
Tender Notice SampleTender Notice Sample
Tender Notice Sample
 
5. international standard contract for construction
5. international standard contract for construction5. international standard contract for construction
5. international standard contract for construction
 
Bid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal PradeshBid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal Pradesh
 
Request For Proposals (RFP) For Recruitment Of Market Development Representat...
Request For Proposals (RFP) For Recruitment Of Market Development Representat...Request For Proposals (RFP) For Recruitment Of Market Development Representat...
Request For Proposals (RFP) For Recruitment Of Market Development Representat...
 
Adb zone-i
Adb zone-iAdb zone-i
Adb zone-i
 
Request For Proposal Rfp For Recruitment Of Mdr Russia
Request For Proposal   Rfp   For Recruitment Of Mdr RussiaRequest For Proposal   Rfp   For Recruitment Of Mdr Russia
Request For Proposal Rfp For Recruitment Of Mdr Russia
 
Time Related Professional Practice
Time Related Professional PracticeTime Related Professional Practice
Time Related Professional Practice
 
Ms.jkr.20800.2005
Ms.jkr.20800.2005Ms.jkr.20800.2005
Ms.jkr.20800.2005
 
Determination of enginer sbd2
Determination of enginer sbd2Determination of enginer sbd2
Determination of enginer sbd2
 
Quality Related Professional Practice
Quality Related Professional PracticeQuality Related Professional Practice
Quality Related Professional Practice
 
Engineering and Supervising Service Contract (Purchase this doc, Text: 081188...
Engineering and Supervising Service Contract (Purchase this doc, Text: 081188...Engineering and Supervising Service Contract (Purchase this doc, Text: 081188...
Engineering and Supervising Service Contract (Purchase this doc, Text: 081188...
 
Dtl nit-1496-140709 (1)
Dtl nit-1496-140709 (1)Dtl nit-1496-140709 (1)
Dtl nit-1496-140709 (1)
 
Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1Memorandum of Adjudicator-final1
Memorandum of Adjudicator-final1
 
New application form 08-6-2012 - klj greens
New application form   08-6-2012 - klj greensNew application form   08-6-2012 - klj greens
New application form 08-6-2012 - klj greens
 
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
 
Gls Sector 81 Gurgaon | 9650789998
Gls Sector 81 Gurgaon | 9650789998Gls Sector 81 Gurgaon | 9650789998
Gls Sector 81 Gurgaon | 9650789998
 

Viewers also liked

Pruebadeciencias8vo 110526223249-phpapp02
Pruebadeciencias8vo 110526223249-phpapp02Pruebadeciencias8vo 110526223249-phpapp02
Pruebadeciencias8vo 110526223249-phpapp02Claudia cea bahamonde
 
152273456 el-caso-del-futbolista-enmascarado
152273456 el-caso-del-futbolista-enmascarado152273456 el-caso-del-futbolista-enmascarado
152273456 el-caso-del-futbolista-enmascaradoClaudia cea bahamonde
 
Unit Cargo Presentation English
Unit Cargo Presentation   EnglishUnit Cargo Presentation   English
Unit Cargo Presentation EnglishDavor Sertic
 
Rfp document for preparation of comprehensive detailed project report for rej...
Rfp document for preparation of comprehensive detailed project report for rej...Rfp document for preparation of comprehensive detailed project report for rej...
Rfp document for preparation of comprehensive detailed project report for rej...Harish Mahavar
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank designHarish Mahavar
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
Internet
InternetInternet
Internetjohuca
 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateHarish Mahavar
 

Viewers also liked (16)

Pruebadeciencias8vo 110526223249-phpapp02
Pruebadeciencias8vo 110526223249-phpapp02Pruebadeciencias8vo 110526223249-phpapp02
Pruebadeciencias8vo 110526223249-phpapp02
 
152273456 el-caso-del-futbolista-enmascarado
152273456 el-caso-del-futbolista-enmascarado152273456 el-caso-del-futbolista-enmascarado
152273456 el-caso-del-futbolista-enmascarado
 
Frewen Megahacks
Frewen MegahacksFrewen Megahacks
Frewen Megahacks
 
15
1515
15
 
20
2020
20
 
11
1111
11
 
Los mapuches
Los mapuchesLos mapuches
Los mapuches
 
Unit Cargo Presentation English
Unit Cargo Presentation   EnglishUnit Cargo Presentation   English
Unit Cargo Presentation English
 
Rfp document for preparation of comprehensive detailed project report for rej...
Rfp document for preparation of comprehensive detailed project report for rej...Rfp document for preparation of comprehensive detailed project report for rej...
Rfp document for preparation of comprehensive detailed project report for rej...
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
 
Day-of winners 2016
Day-of winners 2016Day-of winners 2016
Day-of winners 2016
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Intze tank design
Intze tank designIntze tank design
Intze tank design
 
Internet
InternetInternet
Internet
 
24
2424
24
 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimate
 

Similar to Oht tender

1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdf1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdfEphremZeleke3
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -artijagadish108
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document xingxin_GOh
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practiceAditya Sanyal
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tenderneharajpl
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxFairFASST
 
World bank price adjustment documents.PDF
World bank price adjustment documents.PDFWorld bank price adjustment documents.PDF
World bank price adjustment documents.PDFGovinda Gaire
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.Abhishek kumar maurya
 
NOTICE INVITING TENDER
NOTICE INVITING TENDERNOTICE INVITING TENDER
NOTICE INVITING TENDERLaxman Chaldas
 
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdfSTANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdfMehediHasan615606
 
Standard specifications for_building_wor
Standard specifications for_building_worStandard specifications for_building_wor
Standard specifications for_building_worGAJENDRAN MUTHUKRISHNAN
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95MaximaSheffield592
 
Mo rth model rfp v for epc works_jan 2017
Mo rth model rfp v for epc works_jan 2017Mo rth model rfp v for epc works_jan 2017
Mo rth model rfp v for epc works_jan 2017Dheeraj Sehgal
 
!Rfq 9119 13-7035 final draft for approval (jan 30)
!Rfq 9119 13-7035 final draft for approval (jan 30)!Rfq 9119 13-7035 final draft for approval (jan 30)
!Rfq 9119 13-7035 final draft for approval (jan 30)Bob Gaspirc
 

Similar to Oht tender (20)

tendering
 tendering tendering
tendering
 
Notes unit 2A.ppt
Notes unit 2A.pptNotes unit 2A.ppt
Notes unit 2A.ppt
 
1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdf1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdf
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tender
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docx
 
Tender
TenderTender
Tender
 
World bank price adjustment documents.PDF
World bank price adjustment documents.PDFWorld bank price adjustment documents.PDF
World bank price adjustment documents.PDF
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
NOTICE INVITING TENDER
NOTICE INVITING TENDERNOTICE INVITING TENDER
NOTICE INVITING TENDER
 
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdfSTANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
 
Standard specifications for_building_wor
Standard specifications for_building_worStandard specifications for_building_wor
Standard specifications for_building_wor
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
 
Mo rth model rfp v for epc works_jan 2017
Mo rth model rfp v for epc works_jan 2017Mo rth model rfp v for epc works_jan 2017
Mo rth model rfp v for epc works_jan 2017
 
!Rfq 9119 13-7035 final draft for approval (jan 30)
!Rfq 9119 13-7035 final draft for approval (jan 30)!Rfq 9119 13-7035 final draft for approval (jan 30)
!Rfq 9119 13-7035 final draft for approval (jan 30)
 

Recently uploaded

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 

Recently uploaded (20)

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 

Oht tender

  • 1. ................................................DOCUMENTS. FOR CONSTRUCTION OF AT K.M. OF CONSTRUCTION OF RCC OVER HEAD TANK AT WORK SHOPCOMPOUND KALPIPARA SARYU NAHAR KHAND-4, BAHRAICH TENDER
  • 2. (CONTENTS) SL.NO. PARTICULARS PAGE NO. 1. Invitation of Tender 2. I.D. Form No. 112 and schedule of bids 3. I.D. Form No. 111 4. Schedule 'B' 5. Schedule 'C' 6. Schedule 'D' 7. SPECIAL CONDITIONS OF CONTRACT CHAPTER-1 1.1 Definition 1.2 Death, Bankruptcy of contractor 1.3 Acccess to the contractor's Bank 1.4 Contract documents and matters to be treated as confidential. 1.5 Use of construction facilities to other contractors and Government employees. 1.6 Finds of the work. 1.7 Errors, omission and discrepancies 1.8 The site. 1.9 Drawings 1.10 Roads in work area. 1.11 Contractor not to dispose off soil etc. 1.12 Land 1.13 Employment of labour brought by other contractors. 1.14 Rate for increase in quantities. 1.15 Juri-diction. CHAPTER-2 PLANT, EQUIPMENT & CONSTRUCTION POWER. 2.1 General 2.2 Conditions for the hire of Government machinery. 2.3 Construction Power. CHAPTER-3 MATERIALS 3.1 General 3.2 Cement 3.3 Issue Rates 3.4 Consumption of cement 3.5 Excess consumption of materials 3.6 Contractor's Godown 3.7 Materials to be supplied by the contractor 3.8 Deviations, Alterations etc. in the materials 3.9 Reference specifications. CHAPTER-4 EXECUTION OF WORKS AND CONSTRUCTION PROGRAMME 4.1 Date and drawing to be furnished 4.2 Stacking out of works 4.3 Lines and Grades 4.4 Bench Marks and survey stakes 4.5 Works subject of Inspection of Technical Audit Cell. 4.6 contractor to be responsible for the sufficiency of means employed 4.7 Materials, Workmanship etc. 4.8 Period and Hours of work 4.9 Spead of work 4.10 Contractor responsible for maintenance of works during construction 4.11 Construction Programme 4.12 Clearing up SPECIFICATIONS 8. CHAPTER-1 EARTHE WORK 1.0 TO 1.12 EARTH WORK in excavation of foundation 1.13 Measurement of Earth Work and Payment CHAPTER-2 DEWATERING.
  • 3. SL.NO. PARTICULARS PAGE NO. CHAPTER-3 CEMENT CONCRETE WORK. 3.01 General 3.02 Composition 3.03 Quality 3.04 Cement 3.05 Air entraining Admixture 3.06 Fine Aggregate 3.07 Coarse Aggregate 3.08 Water 3.09 Proportioning of concrete 3.10 Batching and mixing concrete by volume 3.11 Mixing 3.12 Conveying 3.13 Placing 3.14 Time interval between mixing and placing 3.15 Concrete on earth foundation 3.16 Vibration of concrete 3.17 Replacement of rejected concrete 3.18 Curing and protections 3.19 Repair of concrete 3.20 Finishing of concrete surface 3.21 Vibaration in cement content of concrete 3.22 Strength of concrete 3.23 Measurement of concrete 3.24 Rate CHAPTER-4 CENTERING & SHUTTERING 4.01 General 4.02 Inspection of forms 4.03 Form sheating and lining 4.04 to 4.05 Form Ties 4.06 Removal of forms 4.07 Scaffolding for centering and shuttering 4.08 Measurement and payment to 4.10 4.11 Slurry CHAPTER-5 JOINT FILLER BOARD 5.01 Joint filler board. CHAPTER-6 STEEL REINFORCEMENT 6.01 General 6.02 Quality of reinforcement 6.03 Placing of reinforcement 6.04 Joints in reinforcement bars 6.05 Overlap Joints 6.06 Welded Joins 6.07 Measurement and payments CHAPTER-7 Ist Class brick-work in 1:3 or 1:4 cement mortar. CHAPTER-8 Cement pointing (Struck) CHAPTER-9 Expansion Joint Drainage, spout, Bearing & Wheel Guards. 9.01 Expansion Joint 9.02 Drainage Spout 9.03 Bearing 9.04 Wheel guard 9. R.C.C. Railing 10. Contractor's Warranty 11. Certificate of relation ship 12. Drawing.
  • 4. Each tenderer is advised to carefully examine the conditions of contract, drawings and specifications, visit the site of works and fully satisfy and acquaint himself with the nature and locations of the work configuration of ground spring levels, sub-surface conditions, nature of the river and its character and hydrology, quality and quantity of materials required, character and quality of materials to be encountered, character of equipment and facilities needed for the prelimineries and during the execution of the work, leads and lifts involved, the diversions, and pumping problem etc. and the general and local conditions which may in any way affect the work or the cost thereof. 3.00 Tenders will be submitted in the I.D. Form No. 112 in sealed cover (envelope) marked on the upper left hand corner "Tender for construction of in District_________________________________ 4.00 Unless delivered personally, tenders should be submitted by Registered post. Tenders may be addressed as follows :- EXECUTIVE ENGINEER U.P. India Forwarded by post, the sealed envelope containing the tender and marked as directed above, shall be enclosed in another envelope properly addressed. Tenders received late or after the specified time as mentioned above shall not be entertained. Telephonic or Telegraphic bids shall not be accepted. 5.00 Tendered rates shall be legibly written in English or in Hindi in ink, in Indian currency in words and figures. The rates in words will Govern. In case of any discrepency between unit prices and amounts, unit prices will Govern. Erasures and over witings are strictly prohibited and all corrections must be intialled and dated by the tenderer. 6.00 Each tender shall contain the name, residence and place of business of the person or persons tendering for the work and shall be singned by the tenderer with his usual signature. It shall be signed with the partnership name by one of the members of the partnership or by and authorised representative followed by the name and designation (in capital letters) of the person signing the tender. Tenders by corporations shall be signed with the legal name of corporation followed by the name of states and by the signature and designation of the president, other person authorised to bid it in the matter. Attested copy of consititution of the firm with the name of partners shall be furnished. Letters of attorney authorising the person to sign the tender shall also the furnished. 7.00 Each tender shall be accompanied with an amount of Rs. __________________ ad earnest money in the form of a Bank call Deposit, F.D.R., or N.S.C. securities post office Saving Bank Pass Book dly pledged in favour of Executive Engineer, _______________________________________. Earnest money in cash or cheque shall not be accepted. 8.00 The tender shall be sbmitted with th following information. 8.01 A declaration that the contractor is an Engineering construction firm who has successfully carried out large works of this nature and has adequate organisation including experienced personnel to handle job of the type and magnitude and that he undertakes to get himself registered in India whithin three months of the date of the notice of acceptance of the tender, in case he is not already so registred. 8.02 A brief description of major works previously executed by him after the tender has been opened, tenderer may be required to submit detailed particulars of such works alongwith the manner of their execution and any other information that may satisfy the Superintending Engineer, that the contractor has adequate organization including experienced personnel for efficient execution of the work. 9.00 The Superintending Engineer _______________________________________, U.P., India may revise or amed the specifications and drawing prior to the date notified for opening of the tenders, such revision, amendments, if any will be communicated to all prospective tenderers as addendum or addenda to this invitation of tender. All tenderers should incorporate the addenda which are fully part of this tender as if herein set out or if not attached as if hereto attached.
  • 5. 10.00 In consideration of the Government having treated the tenderer be an eligible person whose tender may be considered, the tenderer shall agree to the condition that the proposal in responses to this invitation shall not be with drawn by the tenderer with in One hundred & twenty days from the date of opening of the tender, and also to the condition that if thereafter the tenderer does withdraw his proposal within the said period the earnest money deposited by him may be fortified to the Governor of Uttar Pradesh in the discretion of the later. NOTE-1- If subsequent to the subimission of the tender, any tenderer amends, alters or modifies the contents of this tender which are not acceptable to the department, then for the purposes of these conditions the tnderer shall be deemed to have with drawn his proposals. 2- If a tenderer, who is exempted from furnishing earnest money, withdraws his proposal within the said period, he mayin discretion of the Government of Utter Pradesh be debarred for tendering for a period if one year reckoned from the date of opening of the tender. And the tenderer hereby alsoagrees that if subsequent to the submission of his tender, the tenderer amends, alters, or modifies the contents of his tender which are not acceptable to the department then the tenderer shall for the prpose of the aforesaid conditions, be deemed to have withdrawn his poposal. 11.00 Any explanation desired by bidders regarding the meaning or interpretations of the drawing and specification must be requested in writing and with sufficient time allowed for a replay to reach them before submisasion of bids. 12.00 The earnest money received with a tender shall be refundable when tender has been finally rejected. 13.00 Tenderers should always clearly specify in the tenders whether or not any of their relatives are employed in the State Irrigation Department and if so their names, disignations and places of posting should be given. Failure in the part of the tenderer to correctly disclose the names disignation and places of postings would render the earnest money-security deposit of the tenderer liable to be fortified and the contract, if executed, liable to be rescinded. 14.00 The tenderers are hereby informed that they have to tender rates for each and every item contained in the schedule of quantities and bids, as per conditions and provisions of this tender, otherwise their tender will not be considered. 15.00 While deciding the tender, due consideration shall be given to tenderer's previous experience in having handled works of similar nature and magnitude, his organisational and technical knowledge the equipment and machinery available with the tenderer his financial capacity as well as the existing commitments of tender. 16.00 The tender shall remain open for acceptance for a period commencing from the date of submission of the tender and ending with the expiry of one hundred and twenty calender days from the date fixed from opening of the tenders. 17.00 The person or persons who tender is accepted (here in called the contractor) shall with in one week after the acceptance of his or their tender, deposit in the form of securities such sum as well, with the tender, amount to 10% of the total cost of tender. Superintending Engineer U.P. India.
  • 6. iiiiiiiizzzzzzzzssssssss’’’’’’’’kkkkkkkkdddddddd]]]]]]]] vvvvvvvvffffffff////////kkkkkkkk””””””””kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM &&&&&&&& pppppppprrrrrrrrqqqqqqqqFFFFFFFFkkkkkkkkZZZZZZZZ ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbppppppppAAAAAAAA iiiiiiiizzzzzzzzssssssssffffffff’’’’’’’’kkkkkkkkrrrrrrrr llllllllwwwwwwwwppppppppuuuuuuuukkkkkkkk ffffffffuuuuuuuunnnnnnnnssssssss””””””””kkkkkkkkdddddddd llllllllwwwwwwwwppppppppuuuuuuuukkkkkkkk ,,,,,,,,aaaaaaaaoooooooo ttttttttuuuuuuuullllllllEEEEEEEEiiiiiiiiddddddddZZZZZZZZ ffffffffooooooooHHHHHHHHkkkkkkkkkkkkkkkkxxxxxxxx]]]]]]]] mmmmmmmm00000000 iiiiiiiizzzzzzzz00000000 yyyyyyyy[[[[[[[[kkkkkkkkuuuuuuuuÅÅÅÅÅÅÅÅAAAAAAAA ii==kkaadd && 22227711@@ll00uu00[[kk00&&44@@VVhh&&88@@ ffnnuukkaadd 1155@@1111@@22000088 ffoo’’kk;; &&%% vvvvvvvvYYYYYYYYiiiiiiiiddddddddkkkkkkkkyyyyyyyyhhhhhhhhuuuuuuuu ffffffffuuuuuuuuffffffffoooooooonnnnnnnnkkkkkkkk ddddddddssssssss llllllllEEEEEEEEccccccccUUUUUUUU////////kkkkkkkk eeeeeeeessssssssaaaaaaaaAAAAAAAA eeeeeeeeggggggggkkkkkkkkssssssssnnnnnnnn;;;;;;;;]]]]]]]] ffuuffoonnkk llwwppuukk llaa[[;;kk 0022@@vv00vv00@@ll00uu00[[kk00&&44@@0088&&0099 ddhh 66 iizzffrr;;kkWWaa ee;; llhh00MMhh00 ddss iizzssff’’kkrr ggSS ffdd vvkkii bbUUggssaa mmRRrrjj iizznnss””kk eessaa iizzppffyyrr ffddUUgghhaa nnkkssaa nnSSffuudd lleekkppkkjj ii==kkssaa eessaa nnkkss&&nnkkss ffnnuu ddss vvUUrrjjkkyy iijj nnkkss cckkjj iizzddkkff””kkrr ddjjuuss ddkk dd’’VV ddjjssaaAA bbllddss vvffrrffjjDDrr bbllss mm00iizz00 jjkkTT;; ddhh oossccllkkbbVV iijj HHkkhh iizzddkkff””kkrr ddjjuuss ddkk dd’’VV ddjjssaaAA rrFFkkkk iizzddkkff””kkrr ffuuffoonnkk lleekkppkkjj ii==kkss++ ddhh ,,dd&&,,dd iizzffrr bbll ddkk;;kkZZyy;; ddkkss llaannHHkkZZ ggssrrqq HHkkssttuuss ddhh dd``iikk ddjjssaaAA ddzzee llaa[[;;kk lleekkppkkjj ii== ddkk uukkee LLFFkkkkuu NNiiuuss ddhh llaa[[;;kk ffrrffFFkk rrdd 11 nnSSffuudd ttkkxxjj..kk yy[[kkuuÅÅ nnkkss cckkjj 3300--1111--22000088 22 ffggUUnnqqLLrrkkuu yy[[kkuuÅÅ nnkkss cckkjj 3300--1111--22000088 33 vvnncc VVkkbbEEll xxkkss..MMkk nnkkss cckkjj 3300--1111--22000088 llaayyXXuudd && mmiijjkkssDDrrkkuuqqllkkjjAA vvvvvvvvffffffff////////kkkkkkkk””””””””kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM&&&&&&&&pppppppprrrrrrrrqqqqqqqqFFFFFFFFkkkkkkkkZZZZZZZZ ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbpppppppp iiiiiiii========kkkkkkkkaaaaaaaadddddddd &&&&&&&& 22222222222222227777777711111111@@@@@@@@llllllll00000000uuuuuuuu00000000[[[[[[[[kkkkkkkk00000000 &&&&&&&& 44444444@@@@@@@@VVVVVVVVhhhhhhhh&&&&&&&&88888888 @@@@@@@@rrrrrrrrffffffffnnnnnnnnuuuuuuuukkkkkkkkaaaaaaaadddddddd iizzffrrffyyffii ffuuEEuuffyyff[[kkrr ddkkss llwwppuukkFFkkZZ ,,aaoo vvkkoo'';;dd ddkk;;ZZookkgghh ggssrrqq iizzssff""kkrr ggSS %%&& 11-- eeqq[[;; vvffHHkk;;UUrrkk ¼¼ll00ii00 && 11@@22½½ ffll00ffoo00 mm00iizz00]] QQSSttkkcckknn@@xxkkss..MMkk AA 22-- vv//kkhh{{kk..kk vvffHHkk;;UUrrkk]] uuooee ee..MMyy]] ffllaappkkbbZZ ddkk;;ZZ ccggjjkkbbppAA 33-- vv//kkhh{{kk..kk vvffHHkk;;UUrrkk]] ffaallppkkbbZZ ffuueekkZZ..kk ee..MMyy ccggjjkkbbppAA 44-- vv//kkhh{{kk..kk vvffHHkk;;UUrrkk ;;kkaaff==dd ee..MMyy && ccggjjkkbbppAA 55-- vv//kkhh{{kk..kk vvffHHkk;;UUrrkk]] ddEEII;;wwVVjj ddssUUnnzz]] ddkk;;kkZZyy;; iizzeeqq[[kk vvffHHkk;;UUrrkk]] ffllaappkkbbZZ ffooHHkkkkxx]] mm00iizz00]] yy[[kkuuÅÅ ddkkss llhh00MMhh00 ddss llkkFFkk ffllaappkkbbZZ ffooHHkkkkxx ddhh oossccllkkbbVV iijj iizzddkkff””kkrr ddjjkkuuss ggssrrqqAA 66-- vvff//kk''kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww uuggjj [[kk..MM && 11]]33]]55]]66]]77 ,,aaoo 88 ccggjjkkbbppAA 77-- vvff//kk””kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww MMªªssuusstt [[kk..MM && iizzFFkkee]] ccggjjkkbbppAA 88-- vvff//kk””kkkkllhh vvffHHkk;;UUrrkk]] iizzkkUUrrhh;; [[kk..MM]] ffuueekkZZ..kk [[kk..MM]] yykkssdd ffuueekkZZ..kk ffooHHkkkkxx]] ccggjjkkbbppAA 99-- vvff//kk””kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww uuggjj [[kk..MM @@iizzFFkkee]] uukkuuiikkjjkk]] ccggjjkkbbppAA 1100-- vvff//kk''kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww uuggjj [[kk..MM&&22]] ccyyjjkkeeiiqqjj]] lljj;;ww uuggjj [[kk..MM && iizzFFkkee]] xxkkss..MMkk ddkkss ffuuffoonnkk iizzii== llaayyXXuu ddjj bbll vvkk''kk;; llss iizzssff""kkrr ggSS ffdd ffnnuukkaadd 1166--1122--22000088 rrdd ddhh ffccØØhh ddhh xxbbZZ lleeLLrr ffuuffoonnkkvvkkssaa ddkkss ffnnuukkaadd 1188--1122--22000088 ddhh llkk;;aa 55--0000 ccttss rrdd bbll ddkk;;kkZZyy;; ddkkss iizzssff""kkrr ddjjuussaa ddkk dd""VV ddjjssAA 1111-- vv//;;{{kk]] BBssddssnnkkjj llaa??kk]] ddYYiihhiikkjjkk]] ccggjjkkbbppAA 1122-- llggkk;;dd vvffHHkk;;UUrrkk && 11]]22]]33]]44]]55 ,,aaoo [[kk..MMhh;; yyss[[kkkkff//kkddkkjjhh]] lljj;;ww uuggjj [[kk..MM && 44]] ccggjjkkbbppAA 1133 ffttyykkff//kkddkkjjhh@@iiqqffyyll vv//kkhh{{kkdd]] ccggjjkkbbppAA 1144-- uukkssffVVll cckkssMMZZAA vvvvvvvvffffffff////////kkkkkkkk””””””””kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM&&&&&&&&pppppppprrrrrrrrqqqqqqqqFFFFFFFFkkkkkkkkZZZZZZZZ ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbpppppppp
  • 7. ddddddddkkkkkkkk;;;;;;;;kkkkkkkkZZZZZZZZyyyyyyyy;;;;;;;; vvvvvvvvffffffff////////kkkkkkkk''''''''kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM &&&&&&&& 44444444 ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbppppppppAAAAAAAA vvvvvvvvYYYYYYYYiiiiiiii ddddddddkkkkkkkkyyyyyyyyhhhhhhhhuuuuuuuu ffffffffuuuuuuuuffffffffoooooooonnnnnnnnkkkkkkkk llllllllwwwwwwwwppppppppuuuuuuuukkkkkkkk llllllllaaaaaaaa[[[[[[[[;;;;;;;;kkkkkkkk &&&&&&&& 0000000022222222@@@@@@@@vvvvvvvv00000000vvvvvvvv00000000@@@@@@@@llllllll00000000uuuuuuuu00000000[[[[[[[[kkkkkkkk00000000&&&&&&&&44444444@@@@@@@@22222222000000000000000088888888&&&&&&&&0000000099999999 eeggkkeeffggee jjkkTT;;iikkyy mmRRrrjj iizznnss””kk ddhh vvkkssjj llss ffuuEEuuffyyff[[kkrr ddkk;;kkssZZaa ggssrrqq eeqqggjjccUUnn ffuuffoonnkk;;ssaa ooxxhhZZdd``rr JJss..kkhh eessaa iiaatthhdd``rr BBssddssnnkkjjkkssaa llss ffnnuukkaadd&& 1177--1122--22000088 ddkkss vviijjkkUUgg 33--0000 ccttss rrdd vvkkeeaaff==rr ddhh ttkkrrhh ggSS ttkkss ffnnuukkaadd&&1199--1122--22000088 ddkkss vviijjkkUUgg 33--0000 ccttss vv//kkkkssggLLrrkk{{kkjjhh ddss dd{{kk eessaa vv//kkkkssggLLrrkk{{kkjjhh vvFFkkookk vvff//kkdd``rr iizzffrrffuuff//kk }}kkjjkk [[kkkkssyyhh ttkk;;ssxxhhAA ffuuffoonnkk iizzii== ffnnuukkaadd&& 1155--1122--22000088 llss 1166--1122--22000088 rrdd ffddllhh HHkkhh ddkk;;ZZ ffnnooll eessaa ¼¼vvooddkk””kk ffnnooll NNkkssMM++ddjj½½ vv//kkkkssggLLrrkk{{kkjjhh ddss ddkk;;kkZZyy;; ddss vvffrrffjjDDrr lljj;;ww uuggjj [[kk..MM&&iizzFFkkee]] xxkkss..MMkk rrFFkkkk lljj;;ww uuggjj [[kk..MM&&ff}}rrhh;;]] ccyyjjkkeeiiqqjj ddss ddkk;;kkZZyy;; llss iiaatthhddjj..kk ,,ooaa ffttyykkff//kkddkkjjhh }}kkjjkk ffuuxxZZrr ppffjj== iizzeekk..kk&&ii== ¼¼II DDTT--11½½]] ggSSffll;;rr iizzeekk..kk&&ii== ¼¼II DDTT--22½½ ddhh eewwyy iizzffrr;;kkWW iizzLLrrqqrr ddjj rrFFkkkk mmuuddhh NNkk;;kk iizzffrr;;kkWW HHkkhh BBssddssnnkkjj vvFFkkookk mmllddss vvff//kkdd``rr iizzffrrffuuff//kk }}kkjjkk tteekk ddjj ffuuffoonnkk iizzii== ddkk ffuu//kkkkZZffjjrr eewwYY;; tteekk ddjjuuss ddss ii””ppkkrr iizzkkIIrr ffdd;;ss ttkk llddrrss ggSSAA ddkk;;ZZ llEEccUU//kkhh ffoooojj..kk ,,ooaa ““kkrrssZZ ffuuffoonnkk [[kkqqyyuuss llss ,,dd llIIrrkkgg iiwwooZZ ffddllhh HHkkhh ddkk;;ZZ ffnnooll eessaa 1111--0000 ccttss llss vviijjkkUUgg 44--0000 ccttss rrdd nnss[[kkss ttkk llddrrss ggSSAA BBssddssnnkkjj }}kkjjkk iizznnRRrr vvff//kkddkkjj ii== eessaa iizzffrrffuuff//kk ddkk ggLLrrkk{{kkjj iizzeekkff..kkrr ggkkssuukk vvkkoo””;;dd ggSSAA ffuuffoonnkk,, ffnnuukkaadd&&1177--1122--22000088 ddkkss ffooØØssrrkk [[kk..MM eessaa gghh MMkkyyhh ttkk;;ssxxhhAA ffttUUggss vvUU;; [[kk..MM iizzkkIIrr ffuuffoonnkkvvkkssaa ddkkss ,,dd llhhYYMM ffyyQQkkQQss eeaass jj[[kkddjj ffoo””kkss’’kk nnwwrr ddss eekk//;;ee llss vv//kkkkssggLLrrkk{{kkjjhh ddss ddkk;;kkZZyy;; eessaa ffnnuukkaadd&& 1188--1122--22000088 nnkkssiiggjj 44%%0000 ccttss rrdd mmiiyyCC//kk ddjjkk;;ssxxssAA //kkjjkkssggjj //kkuujjkkff””kk ,,uu00,,ll00llhh00 vvFFkkookk ,,QQ00MMhh00vvkkjj00 vvFFkkookk ffuu;;eekkuuqqllkkjj vvUU;; iizzffrrHHkkwwffrr ddss ::ii eessaa ttkkss vvff//kk””kkkkllhh vvffHHkk;;UUrrkk]] lljj;;ww uuggjj [[kk..MM&&pprrqqFFkkZZ]] ccggjjkkbbpp ddss uukkee ccUU//kkdd ggkkssxxhh]] tteekk ddjjuukk vvffuuookk;;ZZ ggkkssxxkk vvUU;;FFkkkk ffuuffoonnkk LLoohhddkkjj uugghhaa ddhh ttkk;;ssxxhhaaAA ,,dd ;;kk mmllllss vvff//kkdd ffuuffoonnkkvvkkssaa ddkkss ffccuukk ddkkjj..kk ccrrkk;;ssaa ffuujjLLrr ddjjuuss ddkk iiww..kkZZ vvff//kkddkkjj vv//kkkkssggLLrrkk{{kkjjhh ddkkss ggkkssxxkkAA ll””kkrrZZ ffuuffoonnkk eekkUU;; uugghhaa ggkkssxxhhAA iizzRR;;ssdd ffuuffoonnkk nnkkrrkk ddkkss ::ii;;ss 110000--0000 ddss uukkuu ttqqMMhhff””kk;;yy LLVVSSEEii iissiijj iijj ,,dd ::ii;;ss ddkk jjllhhnnhh ffVVddVV yyxxkkddjj vvuuqqccUU//kk ffyy[[kkuukk ggkkssxxkk ffdd nnjjssaa 9900 ffnnooll rrdd eekkUU;; ggkkssxxhhAA bbllllss iiggyyss ffuuffoonnkk@@vvkkQQjj ookkiill yyssuuss iijj //kkjjkkssggjj //kkuujjkkff””kk ttCCrr ddjj yyhh ttkk;;ssxxhhAA ffuu;;eekkuuqqllkkjj nnss;; ffcczzddhhddjj]] vvkk;;ddjj]] LLVVSSEEii MM~~;;wwVVhh rrFFkkkk jjkk;;YYVVhh nnssuukk ggkkssxxkkAA vvuuqqccUU//kk ddss llee;; LLVVSSEEii MM~~;;wwVVhh rrFFkkkk 1100%% tteekkuurr ddhh vvoo””kkss’’kk ffllDD;;kkssffjjVVhh HHkkhh tteekk ddjjuukk vvffuuookk;;ZZ ggkkssxxkkAA ØØeekkaadd ddkk;;ZZ ddkk uukkee vvuuqqeekkffuurr eekk==kk //kkjjkkssggjj //kkuujjkkff””kk vvooff//kk ffuuffoonnkk iizzii== ddkk eewwYY;; iiaatthhdd``rr JJss..kkhh 11-- ddYYiihhiikkjjkk ddkkyykkssuuhh ooddZZ””kkkkii ddEEiikkmmUUMM eessaa vvkkjj00llhh00llhh00 vvkkssoojj ggssMM VVSSaadd ccuukkuuss ddkk ddkk;;ZZ 11 vvnnnn 1144000000--0000 66 eekkgg 222255--0000 llhh vvFFkkookk mmPPpp uukkssVV%%&& ffuuffoonnkknnkkrrkk ddkkss LLoo;;aa }}kkjjkk llRR;;kkffiirr vviiuukk QQkkssVVkkss ffuuffoonnkk iizzii== ddss llkkFFkk yyxxkkuukk ggkkssxxkkAA vvvvvvvvffffffff////////kkkkkkkk””””””””kkkkkkkkkkkkkkkkllllllllhhhhhhhh vvvvvvvvffffffffHHHHHHHHkkkkkkkk;;;;;;;;UUUUUUUUrrrrrrrrkkkkkkkk lllllllljjjjjjjj;;;;;;;;wwwwwwww uuuuuuuuggggggggjjjjjjjj [[[[[[[[kkkkkkkk........MMMMMMMM&&&&&&&&pppppppprrrrrrrrqqqqqqqqFFFFFFFFkkkkkkkkZZZZZZZZ ccccccccggggggggjjjjjjjjkkkkkkkkbbbbbbbbppppppppAAAAAAAA
  • 8. AGREEMENT (To be submitted on General stamp paper) of Rs. 100.00 only with a Revenue stamp of Tender invited by :- E.E. S.N.K.-4, BAHRAICH Tender for :- CONSTRUCTION OF RCC OVER HEAD TANK AT WORK SHOPCOMPOUND KALPIPARA Tender Notice No. 02/E.E./SNK-4/2008-09 & date 15.11.2008 Name of Tenderer In Consideration of the Government of Uttar Pradesh having treated the tenderer to be an eligible person whose tender may be considered, the tenderer here by agrees to the conditions that the proposal in response to the above invitation shall not be withdrawn within 120/90 days from the date of opening of the tender and also to the condition that if after the tenderer does withdraw his proposal within the said period, the earnest money deposited by him may be forfeited to the Governor of Uttar Pradesh in the discretion of the letter. The tenderer hereby also agrees that if subsequent to submission of his tender, the tenderer amends, or modifies the contents of his tender which are not acceptable to the department, then the tenderer shall for the purpose of the aforesaid condition be deemed to have withdrawn his proposal. Signed this day of Witness TENDERER
  • 10. I.D. FORM NO. 112 PUBLIC WORKS DEPARTMENT UTTAR PRADESH S.N.K-4, BAHRAICH Division BAHRAICH Sub Division ITEM OF PERCENTAGE RATE-TENDER OF CONTRACTORS Name of work - CONSTRUCTION OF RCC OVER HEAD TANK AT WORK SHOPCOMPOUND KALPIPARA Name of contractor.................................................................... GENERAL RULES AND DIRECTIONS FOR THE GUIDANCE OF CONTRACTORS 1. All works proposed for execution by contract will be notified in a from of invitation to tender pasted on a board hung up in the office of and signed by the Sub-Divisional Officer kgkg -------------------------------------------------------------------------------------------Executive Engineer This from will state the work to be carried out, as well as the date for submitting and opening tenders, And the time allowed for carrying out the work also the amount of carnets money to be deposited with the tender and the amount of the security deposit to be deposited by the successful tenderer and the percentages, if any to be deducted from bills, this set of contract documents consisting of copies of drawing and details of the proposed work specifications schedule of quantities of various items of the works and a form of the printed conditions of contract together with the form of tender to be used signed for the purposes of identification by the Sub-Divisional Officer and approved by the authority competent to make -----------------------------Executive Engineer the contract shall be available for public inspection at the Office of the Sub-Divisional Officer kgkg -------------------------------------------------------------------------------------------Executive Engineer during the office hours. 2. In the even of the tender being submitted by a firm, it must be signed separately by each member there of in the event of the absence of any partner it must be signed on behalf by a person holding a power-of attorney authorizing him to do so. 3. Receipt for payments made on account of work when executed by a firm must also be signed by the several partners, except where the contractors are described in their tender as a firm in which case the receipt must be signed in the name of the firm by one of the partners or by some-other persons having authority to give receipts for the firm. 4. Any contractor who submits a tender shall fill up the prescribed form of tender striking out alternative office on page 3 of the form not applicable to the case. Tenderers which propose any alteration in the work specified in the form of notice inviting tender or in the time allowed for carrying out the work or which contain any other conditions of any sort, or are not filled up in English or not accompanied by the deposit of earnest money notified, will be liable to rejection. Tenders shall have the name of the work to which they refer written outside the envelope. 5. (1) The Executive Engineer; or his duly authorized assistant will open tender in the presence of any intending contractors who may be present at the time and will enter the amounts of several tenders in a comparative statements in a suitable form. In the event of a tender being accepted, a receipt for the earnest money forwarded here with shall thereupon be given to the contractor, who shall thereupon for the purpose of identification, sign copies of the specification and other documents mentioned in rule I. In the event of a tender being rejected the earnest money forwarded with such unaccepted tender shall thereupon be returned to the contractor making the same. (2) When tenders are received by the Sub-Divisional Office he will open and deal with them in the manner specified above, and will submit then to the Executive Engineer for orders. The earnest money if in currency notes shall be credited in the cash-book and paid into the Treasury, a receipt in Account Form No. 3 being given to the party tendering. If earnest money in preferred in any of the securities specified in Rule 9, it shall be entered in the register of securities. Account form 85 and 86, Earnest money received in currency notes shall be returned to unsuccessful tenderers as soon as their tender are rejected the usual stamp receipt being taken. 6. The accepting authority shall have the right of rejecting all or any of the tenders.
  • 11. 7. The receipt of an accountant or a clerk for the earnest money paid by the contractor will not be considered as any acknowledgement if Payment to the Sub-Divisional Officer and - ------------------------------------------------------------------------------------- Executive Engineer Contractor shall be responsible for seeing that he procures a receipt signed by the Sub- Divisional Officer- gkkgkkgkgkgkg-------------------------------------------------------------------------- kExecutive Engineer 8. The memorandum of work tendered for shall be filled in and completed in the office of the Sub Divisional Officer offer the tender form is issued kgkgkgkgkglkglkgkfkgfkgkgfgkfkgflkg k Executive Engineer 9. The amount of earnest money should ordinarily be........................................................... (a) When the amount of the tender does not exceed Rs. 2000 50 (b) When exceeding Rs. 2,000 and not exceeding Rs. 5000 100 (c) When exceeding Rs. 5,000 and not exceeding Rs. 10000 200 (d) For each additional Rs. 5,000 or portion of Rs. 5000 a further sum of 100 Such earnest money shall be deposited by the contractor in Government treasury or sub treasury as laid down in paragraphs 340 (b) (1) 344 and 345 (b) of the Financial Handbook. Volume V, part I, Account Rules and the receipted treasury challan attached to the tender Note- The Officer calling for tender may, in special cases where it would nbe inconvenient for tenderers the deposit money into Government treasury, relax the rule an permit contractors to deposit earnest money with in cash or currency notes up to a limit of Rs. 100 instead of it a treasury, such deposits should be treated as "Public Works Department Depostit"
  • 12. CONSTRUCTION OF RCC OVER HEAD TANK AT WORK SHOPCOMPOUND KALPIPARA Bill of Quantity Sl. No. Item of work No L (m) B (m) H/D (m) Content 1- Supply of all material, labor T&P etc. complete for conatruction of a R.C.C. over head thank of 50kl capacity at 15.00m. Staging above ground level and 1.00m. Wide P.C.C apron around with 15cm semi circlure PCC drain, 1.00m. Wide RCC stair case from G.L. up to balcony M.S.I. ladder with hand rails on both side from balcony to top dome and inside the tank body 1.00m wide RCC bolcony around the thank at the junction point of vertical and conical wall with proper railing of 20mm dia medium grade G.I. pipe in 3 row on both side of staircase case , balcony, at the dome and at each landing on RCC posts space at not more than 1.50 interval proper ventilattor at top dome water level indicator lightening conductor as latest ISI on electrcity rule 0.60m. dia main hol cover hinged with locking arrangement, fixing and jointion vertical pipes for inlet, outlet over flow and washout withall jointing materials for proper completion and other supplementry works including excavation in all type of soils painting of all expose surface and steel pipe work with three coats of approvad cement paint or anticorrosive paints and assumad safe vearing capacity of soil has been taken as 8.00mt./sqm. 1 - - - 1 job 2- Supplying laying jointing of 80 mm dia medium grade G.I. pipe I.S. 1239 part (i) 1979 complete with fitting and refilling etc. complete 1x20 6.00 - - 120.00RM 3- Supply of 80 dia copper alloy gate valve class (i) I.S. 778-1980 with iron wheel head etc. complete. 1x4 - - - 04 No. 4- Supplying and fixing of 80mm dia G.I. elbow ISI make including cost of all material labour T&P etc. complete. 1x12 - - - 12 No. 5- Supplying and fixing of 80 mm dia G.I. socket ISI make including cost of all material labour T&P etc. complete. 1x20 - - - 20 No.
  • 13. "I or "We" TENDER FOR WORKS Hereby tender for the execution for the Governor of Uttar Pradesh of the work specified in the underwritten memorandum within the time specified in each memorandum at the rate specified there in and in accordance, in all respects, with the specifications, designs drawings and instructions, in writing referred to in rule I herein and in clause 2 of the conditions of contract and with such materials as are provided for by and in all other respects in accordance with such conditions so for as applicable (a) if several sub work are included, they should-be detailed in a separate list (b) Vide rule 9 on page 2 (c)Strike out the alternative and attach signature to it MEMORANDUM (a) General description (b) Estimate cost Rs. (c) Earnest money Rs. (d) Time allowed for the work from date of written order to commence Months. (c) TENDERED Rate...................... ... (c) ANCTIONDED Item No Item of work approximate number of quantity unit per (f) in figure (f) in Word s N.B.-When tenders are to be submitted at a percentage above or below the rate in the sanctioned estimate the information in all the columns should be filled by the Sub Divisional Officer/ Executive Engineer. 2.2--In the case of works when contractors are required to quote their own rates for the different item of works the column (f) should be left blank for tendereres to fill in Rs. P. BILL OF QUANTITY ATTACHED uksV%&vko”;d Mªkbax vf/k”kklh vfHk;Urk ds dk;kZy; ls i`Fkd ls izkIr dh tk ldsxhA
  • 14. "I or "We" Strike out the alternative and attach signature to it _______________tender at______________percent above the rates entered above or _________________________tender at the above rates, should this tender be accepted___________ hereby agreed to abide by and fulfil all the terms and provisions of the conditions of contract annexed to the approved set of contract documents' or in default thereof to forfeit and pay to Governor of Utter Pradesh or his successors-in-office the dums of money mentioned in the said conditions. Give particulars and number. The sum Rs.___________is here with forwarded in currency notes as earnest money the full value of which shall be retained by government on account of the security deposit specified in clause I of to the conditions of contract. Signature of Witness to contractor's Signature Dated the _____________________day of _________________200 __________________________ ___________________ Signature of contractor before submission tender Witness_________________________ Address_________________________ Occupation_______________________ Here enter Recommended or Non Recommended Signature Date_____________Sub Divisional Officer___________Sub-Division ______________________ ______________________ Signature Date_______________Executive Officer________________Division ______________________ ______________________ Signature & official designation of the accepting authority Date___________Superintending Engineer______________Division Irrigation Works The above tender is hereby accepted by me on behalf on the Governor Uttar Pradesh. _______________________ Date the__________________day of _____________________200
  • 16. I.D. From No. 111 CONDITIONS OF CONTRACT Clause 1: The person or persons whose tender is accepted (hereinafter called the contractor) shall within one week after his or their tender has been accepted, deposit with Government of Uttar Pradesh (hereinafter called the "Government") either in cash or in securities as provided in paragraphs 614 and 615 of the Financial Handbook, volume VI such as will with the earnest money deposited with the tender amount to rupees.......................................of the cost of contract where any security so deposited is not payable to bearer, the contractor shall endorse to transfer into the said Government in such a manner that the sum represented by it can be realized without the consent or assistance of the contractor, the contractor shall permit Government at the time of making any payment to him for work done under the contract t deduct 10% (ten percent) of all money so payable on account of security deposit until such dedicators along with the sum already deposited as earnest money to be adjusted in the last deduction will amount to 10% of the cost of contract. Security Deposit The amount of the security money shall, if not withheld on account on breach of contract be refunded after six month of the date of completion of the work or after payment of the final bill whichever is later, subject to the conditions that in case of building work of the first rainy season comprising of June, July, August, September is fully covered with in the period of six months mentioned above the amount of security money if not withheld on account of breach of contract, be refunded after the expire of the first rainy season comprising of the months mentioned above or after the payment of the final bill which ever is later. Provided that in case the payment of the final bill is not made within six month of the completions of the works 75% of the amount of the security money can be refunded with the prior approval of the authority next higher to the person accepting the contract on behalf of the government. All compensation or other sum of money payable by the contractor to Govt. under the terms of his contract may be deducted from or realized by the sale of the sufficient part of his security deposit, or from the interest arising there from or from any sum which may be due or may become due to the contractor by Govt. or on any account whatsoever and in the event of his security deposit being reduced by the reason of any such deduction or sale as aforesaid, the contractor shall within ten days there after made good in case or Govt. securities endorsed aforesaid any sums which may have been deducted from, or raised by sale of his security deposit or any part thereof. EXPLANATION- For the purposes of this clause if the work under this contract includes construction, reconstruction or repair of any structure having proof over it, the whole work will be classed as building work. CLAUSE-2(A) Time is the essence of the contract. The contractor shall commence &-shall complete the work covered by the tender on the dates fixed by the...................................Engineer for the commencement and completion of such work & shall in the interval between those dates keep the work upto the schedule of quantities and dates and dates shown in the progress Statement be signed by the contractor and attached to the tender. If the work fails in arrears of the progress Statement either in Quantity or in time, then for every day that the work is so in arrears the contractor shall be liable to pay as compensation an amount equal to one percent or such similar amount as the...............................................Engineer (Whose decision in writing shall be final) may decide on the estimated cost of the whole work provided always that the entire amount of compensation to be paid under the provisions of the clause shall not exceed 10% of the estimated cost of the work as shown in the tender. [CLAUSE-2.B To be used instead of 2 (A) when the latter is from the nature of the work impracticable] CLAUSE-2.B Time is the essence of the contract. The contractor shall commence & shall complete the work within the period specific in the tender. Such period shall be reckoned from the date on which the order to commence work is given to the contractor. The contractor shall at all times during such period proceed with the work with due diligence and he shall pay as compensation an amount equal to one percent or such smaller amount as the.........................................................................Engineer (whose decision in Compensation for delay
  • 17. writing shall be final) may decide on the amount of the amount of the estimated cost of the whole work as shown in the tender for every day that the work remains uncommented or unfinished after the proper dates and further in order to ensure good progress during the execution of the work the contractor shall be bound in all cases in which the time allowed of any work exceeds one months to complete on-fourth of the value or quantity (as the .............................................Engineer may determine) of the whole of the work before on-forth of the whole time allowed under the contract has elapsed, one half of the value or quantity (as the........................................... Engineer may determine) of the work before one-half of such time has elapsed and three- fourths of the value or quantity (as the................................ Engineer may determine) of this work before three-fourths of such time has elapsed if the contractor fails to comply with his condition he shall be liable to pay as compensation an amount equal to one present of such smaller amount as.........................................Engineer (whose decision in writing shall be final) may decide on the estimated cost of the whole work for every day that the quantity of work for every day that quantity of work remains incomplete, Provided always that the entire amount of compensation to be paid under the provisions of the clause shall not exceed 10% on the estimated cost of the work as shown in the tender CLAUSE-3(i) In any in which under any clause or clauses of this contract amounting to the whole of his security deposit (whether paid in one sum or deducted by installment) the .........................................Engineer shall have power to adopt such of the following courses as he may deem best. Action by which whole of security deposit is forfeited (a) He may rescind the contract by giving the contractor ................days notice of rescission signed by the...................................Engineer and may then take the whole of the contractor's security deposit for the use of Govt. as compensation for the loss caused by the contractor's default. (b) He may, after giving the contractor..........................................days notice in writing of his intension to do so, measure up the work done by the contractor and then employ and pay labourers and supply or produce materials and carry out all or any part of the work himself on behalf of Govt. debiting the contractor with the actual cost and crediting him at the contract rates with the value of the work so done, and may postpone till completion of the work, so taken over assessment of the compensation to be paid by the contractor, if any work is so taken over by the.....................................Engineer the certificate in writing of the Executive Engineer or the Sub-divisional Office as to its cost and value shall be final and conclusive against the contractor. (c) He may, after giving the contractor..........................................days notice in writing of his intension to do so, measure up the work done by the contractor take the work out of his hand and give a contractor for its completion to another contractor and may postpone till the completion of the work. The assessment of the compensation to be paid by the original contractor. If the.............................Engineer elects to give the completion of the work to another contractor the original contractor shall pay any expenses which may be incurred in excess of the sum which would have been paid to him if the whole work had been carried out by him, and a certificate in writing of the...................................Engineer or of the ..................................... shall be final and conclusive as against the original contractor as to the amount of any such expenses. (i) If the...................................................Engineer does not desire to do so the work, the contractor shall not be entitled to compensation for any loss sustained by him by reason of his having purchased or procured any materials, or entered into any engagements, or made any advances on account of or with a view to the execution of the performance of the contract, and shall not be entitled to recover or be paid or be given credit for any sum for any work there of actually performed by him under this contract, unless and until the Executive Engineer or the Sub-Divisional Officer acting under this order shall have certified in writing the performance of such work and the value thereof the contractor shall only be entitled to be paid the value as so certified. (ii) If upon any occasion the..........................................Engineer abstains from exercising the powers given to him by this clause such
  • 18. abstention shall not prevent him from exercising such powers upon a subsequent occasion if the contractor again makes default, not shall such abstention absolve the contractor from liability to pay compensation for any default which he may have made. CLAUSE 4.If the...............................................Engineer exercise any of the powers given to him by clause 3 he may, if he so desires take, possession of all or an tools, plants, materials and stores in or upon the work, or the side thereof and belonging to the contractor or procured by him and intended to be used for he execution of the work or any part thereof, and pay or allow the contractor for the same at the contract rates, or in the case of these not being applicable, at current market rates to be certified by the Executive Engineer, whose certificate thereof shall be final, and if the...........................Engineer does not desire to do so the Executive Engineer may be notice in writing to the contractor or his clerk if the works foreman of other authorized agent required him to remove such tools, plants, materials or stores from the premises (with in a time to be specified in such notice), and if the contractor fails to comply with any such requisition, the Executive Engineer as to expenses of any such removal and the amount of the proceeds and expenses of any such shall be final and conclusive against the contractor. Contractor remains liable to pay compensation if action not taken under clause 3 Power to take possession of or require removal of or sell contractor's plant CLAUSE 5. If the contractor desires an extension of the time for completion of the work on the ground of any unavoidable hindrance to its execution having arisen, he shall apply in writing to the................................ Engineer within 30 days the existence of such hindrance first becomes known to him, and the........................................ Engineer shall if in his opinion (which shall be final) reasonable ground be shown thereof, authorize such extension of time as may, in his opinion be necessary or proper. Extension of time CLAUSE 6. On completion of the work the contractor shall send a registered notice to the Sub-Divisional Officer (hereinafter called Engineer- in- charge) given the date of completion and shall also send a copy of such notice to the Executive Engineer, and shall request the Engineer –in- charge to give him a certificate of completion No Such certificate will be given not shall the work be considered to be complete until the contractor has removed from the premises on which the work has been executed all scaffolding, surplus materials and rubbish, and cleaned all wood-work, doors, windows, walls, floors or other parts of any building in, upon or about which the work has been executed or of which he may have had possession for the purpose of the execution thereof and, if the contractor fails to do so or before the date fixed or completion of the work the Engineer-in-charge may do so, and may sell such scaffoldings and materials as have not been removed by the contractor and the contractor shall forthwith pay all expenses so incurred and shall have no claim in respect of any such scaffolding, surplus materials as aforesaid except for any sum actually realized by the sale thereof. On completion the work shall be measured by the Engineer-in-charge, whose measurements shall be binding and conclusive against the contractor. Final Certificates CLAUSE 7. In the case of work estimated to cost more than rupees one thousand, the contractor shall, on submitting the bill thereof be entitled to receive a monthly payment proportionate to the part thereof then approved for such purpose by the Engineer-in-charge, whose certificate of approval and passing of the sum to payable shall be final and conclusive against the contractor, But any such payments will only be mane as advances to be credited to Government in the final settlement of accounts, with the contractor and not as payment for work completed and passed, and the making of any such payment shall not either preclude the Executive Engineer or Sub-Divisional Officer from requiring the contractor to remove or reconstruct any work on the ground that such work is bad, unsound, imperfect or unskilled or prevent Government form enforcing any claim against the contractor on account of any default by him or conclude, determine or affect in any way the powers of the Engineer-in-charge under payment on intermediate certificate to be regarded as advance these conditions or any of them as to final settlement and adjustment of the
  • 19. accounts or otherwise in any other way very or effect the contractor. The Engineer-in-charge's certificate of the measurement and of the total amount payable for the work shall be final and biding on all parties. CLAUSE 8. If the contractor abandons, or is unable to complete the work the................................Engineer may certificate in writing the value of the work done by the contractor towards the completion of the contract. Such a certificate shall be final and conclusive against the contractor and he will not be paid more than the value of such work as so certified is respective of the contract rates. liability to complete the work. CLAUSE 9- When the estimate on which a tender is made includes lump sum in respect of parts of the work, the contractor shall be entitled to payment in respect of the items of work involved, or the part of the work in question at the same rates as are payable under this contract for other such items of work, unless the part of the work in question is not in the opinion of the Engineer-in-charge, capable of measurements in which case the Engineer-in-charge may pay such lump sum as he may determine to be the value thereof, and the certificate in writing of the Engineer-in-charge shall be final and conclusive against contractor as to the basis upon which payment is to be made is such case and as the amount to be paid. Lump sum estimates CLAUSE 10. Evers month on or before a date to be fixed by the Engineer-in-charge the contractor shall if so required, submit a bill for all works executed by him during the previous month and the Engineer-in-charge shall take or cause to be taken all measurements necessary for checking the contractor's bill and adjusting his claim as speedily as possible. If the contractor does not submit his bill within the time so fixed the Engineer-in- charge may after giving the contractor..........................................day's notice in writing measure or depute some one to measure such work in the presence of the contractor whose signature on the list of measurements shall be sufficient authority to the Engineer-in-charge to draw up, a bill based on such measurements and any bills so drawn up shall be binding on the contractor. If the contractor fails to attend when such measurements are taken, such measurements shall be binding on him, and if he attends but refuses to sign the list of measurements the matter shall be referred to the immediate superior of the Engineer-in-charge whose decision shall be binding on the contractor. Bills to be submitted monthly CLAUSE 11. The contractor shall submit all bill on the printed for which will be supplied to him at the office of the Engineer-in-charge and all items in such bills shall be charged at the rates specified in the tender or in the case of any extra work ordered in pursuance of these conditions, and not mentioned or provided for in the tender, at the rates hereinafter provided in such work. Bills to be printed form CLAUSE 12. If the specification or estimate of the work provides for the use of any special description of materials to be supplied form the Engineer-in –charge's store, or if it is required that the contractor shall use certain stored to be provided by the Engineer-in-charge mentioned being so for as practicable and for the convenience of the contractor specified in the schedule hereto annexed but not so as in any way to control the meaning or effect of this contract) the contractor shall be supplied with which materials and stores may from time to time be required by him for the purposes of the contract but only for such purposes and he shall pay for the same at the rates specified in the said schedule or if no rates are so specified at cost price at defined in clause 13 thereof Stores supply by Government All materials so supplied to the contractor will become the property of the contractor, but shall not on any account be removed from the site of the work until the whole work is certified to be completed by the Executive Engineer except with the written permission of the Executive Engineer, and shall at all times be open to inspection by the Engineer-in-charge shall however have the opinion to take over any such materials, if unused at time of the completion or termination of the contractor at the specified issue rate or the current market rat, whichever is less. CLAUSE 13. All articles requires by the contractor for the contraction of
  • 20. the work and which the contractor is to supply himself, shall be obtained by the contractor from the firms with which the Director of Industries has made arrangements and if for the supply of any articles no such arrangements have been made, any such articles supplied by the contractor shall conform to such specification and/or tests, if any, as may be prescribed by the Director of Industries in consolation with the consuming department . CLAUSE 14. The contractor shall obtain from the stores of the Engineer-in-charge all such imported stores or materials as may be requires in any part thereof for making up articles required thereof for in connection therewith. The value of such stores and articles as may be supplied to the contractor by the Engineer-in-charge will be debited to the contractor in his account at the rates shown in the Schedule attached to the contract and if they are not entered in the Schedule they will be debited at the cost price, which for the purposes of this contract shall include the cost of carriage and all other expenses whatever which shall has been incurred in obtaining delivery of the same at the store aforesaid. The Executive Engineer may issue materials to the contractor from existing stock if he asked for any excess of those entered in the Schedule. In such cases the price charged will be the stock rate or the market rate which ever is greater. Stores imported from Europe to be obtained from Government CLAUSE 15. The contractor shall execute the whole and every part of the work in the most substantial and workman like manner and in every respect in strict accordance with the specification both as regards materials and otherwise. The contractor shall also conform exactly, fully and faithfully to the designs, drawings and instructions in writing relating to the work signed by the Engineer-in-charge and lodged in his office, and the contractor shall be entitled to inspect the same during office hours and may at his own expense have copies of the specifications and of all such designs, drawings and instructions as aforesaid made for own use. Work to be executed in accordance within Specifications drawings orders, etc. CLAUSE 16. The Engineer-in-charge shall have power to make such alteration in additions to, the original specifications, drawings, designs and instructions as may appear to him to be necessary or advisable during the progress of the work, and the contractor shall be bound to carry out the work in accordance with any instructions which may be given to him in writing signed by the Engineer-in-charge and such alteration shall not invalidate the contract, and any additional work which the contractor may be so directed to do shall be carried by the contractor on the same conditions in all respects on which be agreed to do the main work, and at the same rates as are specified in the tender for the main work. The time for the completion of the work shall be extended in the proportion that the additional work bears to the original contract work, and the certificate of the Engineer-in-charge shall be conclusive as to such proportion. If the additional work includes any item for which on rates is specified hereunder then the contractor shall carry out the work at the rate entered in the schedule of rates of the direct but if the schedule does not contain any rate for such work, then the contractor shall not begin such work until a rate in respect of such work has been settled by mutual agreement between him and the Engineer-in-charge with the approval of the officer accepting the contractor any if they are unable to agree upon a rate within two weeks from the date when the contractor received the order, the Engineer-in- charge may be a notice in writing cancel the order for such work and carry it out in such work carry it out in such manner as he may think best in the event of a dispute, the decision of the Superintending Engineer shall be final and binding on the contractor. Alteration in specification and designs. Do not invalidate contract Extension of time in consequence of all contract Rate for additional work not in estimate or schedule of rate of district. CLAUSE 17. The Executive Engineer acting on the writing order of his immediate superior, may at any time by notice in writing to the contractor either stop the work altogether or reduce or cut it down. If the work is stopped altogether, the contractor will only be paid for work done and expenses legitimately incurred by him on, or preparation for the execution for the work up to the date on which such notice is received by him such expenses shall be assessed by the Executive Engineer, whose decision shall be final and binding on the contractor. If work is cut down the No compensation or alteration in a restriction of work to be carried out contractor will be paid for the work as so cut down but in neither case will be paid any compensation whatever for the loss of profit which he might have made if he had been allowed to complete all the work
  • 21. included in the tender. CLAUSE 18. If the Engineer-in-charge is satisfied that the construction of any part of the work is faulty all that materials used in the same are inferior to those for which the specification provides or that any materials or articles provided by the contractor are not in accordance with the contract, he may notwithstanding that such work, materials or articles may have been passed, certified or paid for, serve the contractor with notice in writing specifying the work, materials or articles of which he complaints and requiring the contractor to remedy such defects or to replace such materials within a specified period of time. Action and compensation payable in case of hand work If the contractor fails to comply, in all respects with the requirements of any such notice within ten days after the expiration of the period specified in that notice, the Engineer-in-charge may himself remedy such defects, or as the case may be replace such materials or articles, and contractor shall pay all expenses incurred by the Engineer – in-charge in so doing and the certificate in writing of the Engineer-in- charge as to the amount of any such expense shall be final and binding upon the contractor. CLAUSE 19. All works ;under or in the course of extension or executed in pursuance of the contract shall at all times be open for inspection and supervision by the Engineer-in-charge and his subordinates and the contractor shall at all times during the usual working hours, and on any other occasion of which he shall have all responsible notice either himself be present to receive orders and instructions, or have responsible agent duly accredited in writing present for that purpose, Orders given to any such agent have the same affect as order given to the contractor himself. Work to open to inspection. CLAUSE 19.(A) No labourer below the age of 14 years shall be employed on the work CLAUSE 19. (B) The contractor shall pay to his labourers a fair wage. CLAUSE 19. (C) The contractor before he commences the work shall (s)post in a conspicuous place on the work a notice giving the rates of wages which have been certified as fair by the Executive Engineer, and (b) send a copy of the notice to the Executive Engineer. CLAUSE 19. (D) The contractor shall be responsible to comply with the provisions of the labour laws in force in state of Uttar Pradesh including the Minimum wages Act or any enactment in supersession, extension or modification thereof which may be passed at any time or from time to time by a competent legislative body any may have effect in the state of Uttar Pradesh and the Rules and Regulations made there under or any amendments or modifications thereof for the time being in force. All expenses in connection. with the compliance of such laws and rules shall be borne by the contractor, and the contractor, shall neither demand nor claim nor shall be entitled to any additional payment for the reason that he failed to take into account any such expense in his tender or that any subsequent amendments in such laws or rules have changed the basis on which he worked out such expenses while submitting his tender. In every case in which by virtue of the provisions of the labour laws in force in the State of Uttar Pradesh and the rules and regulations made there under, the Government is obliged to pay any sum in the execution of the work Government will recover from the contractor the amount so paid, and without prejudice to the other rights of the Government, the Government shall be at liberty to recover such amount or any part thereof deducting it either from the security money deposited by the contractor or to his credit under clause I of these conditions or from any other sum due by the Government to the contractor whether under this contract or otherwise. Vide G.O. No. 1331 IBD-50/XXIII-IB-89—B.W. dated 26 may 1950
  • 22. CLAUSE 20, In order that the work may be measured and the correct dimensions thereon taken, the contractor shall not cover up any part of the same or otherwise place it beyond reach of measurement until he has either obtained the consent in writing of Engineer-in-charge or of his subordinate in charge of the work or until he has given to the Engineer –in-charge or to such subordinate five days notice in writing that the work is ready for measurement. If the contractor, covers up any work or places it beyond of the measurement without such consent and before the expiration of the period of such notice, the contractor shall either, as he may elects tip such work at his own expense order that it may be measured or shall forfeit the price of such work and of the materials used in its contractions. Contractor or responsible agent to be present. CLAUSE 21. All works to be executed under the contract shall be executed under the direction and subject to the approval in all respect of the Engineer-in-charge for the time being, who shall be entitled to direct at what points or points and in what manner they are to be commences, and from time to time carried on. Notice to be given before work is covered up. CLAUSE 22. Except where otherwise specified in the contract the decision of the.............................................................................Engineer for the time being shall be final conclusive and binding on all parties to the contract upon all questions relating to the meeting of the specifications, designs, drawings and instructions herein before mentioned. The decisions of such Engineer as to the quality of workmanship or materials used on the work, or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs or drawings, specifications, estimates, instructions, over of these conditions or otherwise concerning the work or the execution of failure to execute the same whether arising during the progress of the work or after the completion or abandonment of the contract by the contractor, shall also be final, conclusive and binding on the contractor. Direction of work. CLAUSE 23. If the contractor or his work people or servants shall break, deface, injure or destroy any part of a building in which they may be working or any building, road fence enclosure are grass land or cultivated ground contiguous to the premises on which the work or any part of it is being executed or if any damage shall happen to the work while in progress from any cause due to the negligence of responsibility (the decision of the Executive Engineer shall be final), the contractor shall at his own expense make good such damage, or in default, the Engineer-in-charge may cause the same to be made good and the contractor shall, pay any expense so incurred and certificate of the Engineer-in-charge as to the amount of such expenses shall be final and binding on the contractor. Decision of Engineer to be final. Contractor liable for damage done and for imperfections for three months after certificate. CLAUSE 24. The contractor shall supply at his own cost all materials (except such special materials, if any as may in accordance with the contractor be supplied from the Engineer-in- charge's stores), plant, tools, appliances, implements, ladders, cordage tackle, scaffolding and temporary works requisite for the proper execution of the work whether original, altered or substituted and whether included in the specifications or other documents forming part of the contract or referred to in these conditions or not or which may ne necessary for the purpose of satisfying or complying with the requirements of the Engineer-in- charge as to any matter as to which under these conditions he is entitled to be satisfied or which he is entitled to require, and shall pay for the carriage of all such things to and from the work. The contractor shall also supply without charge workmen with the means and materials necessary for the purpose of setting out works. and for counting, weighing and assisting in the measurement or examination of the work, or materials at any time. If the contractor fails to do so the same may be provided by the Engineer-in-charge and the contractor shall pay the cost of the same as certified by the Engineer-in-charge whose certificate shall be final. The contractor shall also provide all necessary fencing and lights required to protect the public from accident and shall bear the expenses of defense of every suit, action or other proceeding at law that may be brought by any person for injury sustained owing to neglect of the above precautions, and shall also pay any damages and costs which may be awarded in any such suit action or proceeding to any such persons or, which nay with the consent of the contractor be paid to compromise any claim by any such Contractor to supply plant, ladders scaffolding, etc. And liable for damages arising from non provision of light fencing, etc. Female labour not to be
  • 23. person. employed CLAUSE 25. The contractor shall not employ female labour in the execution of the work of any part thereof within the limits of a cantonment Work not to sub-let CLAUSE 26. The contractor shall not assign or sub-let the contract without the written approval of the...........................................................Engineer and if the contractor does or attempts so to do or becomes insolvent or commences any insolvency proceedings or makes attempts to make an composition with his creditors, or if he or any of his servants or agents either directly or indirectly, or gives, offers or promises any bride, gratuity gift loan, perquisite, reward or advantage pecuniary or otherwise to any public officer or person in the employ of Government in any way relating to his office or employments, or if any such officer or person shall become in any way directly or indirectly interested in the contract without having first obtained the permission in writing of the Government, the.........................................Engineer may thereupon by notice in writing resend the contract, and the security deposit of the contractor shall thereupon stand forfeited and be absolutely at the disposal of Government and the same consequences shall ensure as if the contract had been rescinded under clause 3 hereof and in addition the contractor shall not be entitled to recover or be paid for any work there for actually performed under the contract. CLAUSE 27. Any sum payable by the contractor as compensation under any of these conditions shall be deemed to be reasonable compensation for the act or default in respect of which the same becomes payable without proof of the actual amount of damages or loss sustained. CLAUSE 28. In the case of a tender by partners, the contractor shall the name of the members of the firm and shall notify to the Engineer-in-charge any change in the constitution of the firm as soon a such change occurs. CLAUSE 29. In the case of any class of work for which there in no such specification as is mentioned in rule, such work shall be carried out in accordance with the district specification, and if there is no district specification, the work shall be carried out in all respects in accordance with instructions and requirements of the Engineer-in-charge. Contract may rescinded and security deposit forfeited for subletting bribing or if contractor becomes insolvent Sum payable way of compensation be considered reasonable compensation without reference to actual loss Changes in constitution firm Action where specification Definition work CLAUSE 30. In these conditions unless there is something in the subject or context repugnant to such an interpretation, the expressions "work" mean the work to be done or executed under the contract whether such work is permanent or temporary and where it is original altered substituted or additional CLAUSE 31. The additions and deductions on account of the percentage referred to at page 3 of the accepted tender will be calculated on the gross, and not the net amounts of the bills for the work done. Contractor percentage whether applied to net or amount of bills CLAUSE 32 (1). In every case in which by virtue of the provisions of section 12 sub-section (1) of the Workmen's Compensation Act, 1932 Government is obliged to pay compensation to a workman employed by the contractor or by any sub-contractor from him in the execution of the work Government will recover from the contractor the amount of the compensation so paid, and without prejudice to the rights of the Government under section 12 sub-section (2) of the said Act, Government shall be at liberty to recover such amount or any part thereof by deduction it either from the security money deposited by the contractor or the his credit under clause 1 of these condition pr from any other sum due by Government to the contractor whether under this contract or otherwise. (Strike out the clause in cases of an item rate contract) CLAUSE 32 (2). Government shall not be bound to contest any claim made against it under section 12 sub-section (1) of the said Act, excepts on the Compensation to workmen.
  • 24. written request of the contractor and upon his giving to Government full security for all costs for which Government might become liable in consequence of contesting the claim CLAUSE 33. Not withstanding anything stipulated in the aforesaid clauses. Government shall have power to retain any sum due to the contractor. (s) and set off all claims against him (there) whether arising out of the particulars contract or out of any other transaction or in partnership with others. CLAUSE 34. All disputes in respect or contract arising between contractor and the department will be put up to the Superintending Engineer ............................................circle irrigation work ........................... and his decision shall be final and legally binding on both parties. CLAUSE 34.(A) (i) If the contractor considers any record or any ruling of the Engineer-in-charge or of his representatives in respect of any of the provision of this contract to be unfair of considers any work demanded by his to be outside the requirements of the contract he shall immediately ask upon such record or ruling being made or such work being damaged ask in writing for written instructions or decisions, no receipt whereof he shall proceed without and delay to confirm to the record or ruling or to perform the work demanded and within 15 days after date of receipt of the written instructions or decisions he may file written protest up objection is are made on record in the manner herein specified and within the time limit stated ruling, instruction or decision of the Engineer-in-charge shall be conclusive and binding on the contractor, instruction and/or decisions of the Engineer-in-charge contained in letter transmitting drawing to the contractor shall be considered as written instructions, subject to protest objections as herein provided. CLAUSE 34.(A) (ii) If the contractor is dissatisfied with the final decision of the Engineer-in-charge on the protest or objection made by the contractor in accordance with the procedure prescribed in clause 34(i) the contractor may within twenty-eight (28) days after receiving notice on such decision give notice in writing to the Engineer-in-charge requiring that the matter be submitted to arbitration and furnishing detailed particulars of the dispute of difference specified clearly that point at issue it the contractor fails to give such notice within the period of 28 days as stipulated above the decision of the Engineer-in-charge shall be conclusive and binding on the contractor. CLAUSE 34-A(iii) Every dispute, difference or question which may at any time arise between the parties here to any person claiming them couching or arising out in respect of this deed or the subject matter thereof shall be referred to the arbitration of....................................... or any person nominated by him. It will be no objection to any such appointment that the arbitrator so appointed is a Government servant that he had to deal with the matters to which the contract relates and that in the course of his duties as Government servant he had expressed views on all or any of the matters in dispute or difference. In the event of the arbitrator to nom the matter is originally referred being transferred of vacating his office or being unable to act for any person............................ . a hall either upon the reference himself or appoint another person to act as arbitrator such person shall be entitled to proceed with the reference from the stage it was left by his predecessor, it is also a term of this contract that no person other than a person appointed as aforesaid should act as arbitrator and if form any reason that is not possible, the matter is not to referred to arbitration at all. in all cases where the amount of the claim in dispute is Rs. 50,000/- (Rupees Fifty thousand) and above the arbitrator shall give reason for the award it is a term of the contract that the party invoking the arbitration shall specify the dispute or dispute to be referred to arbitration together with the amount or amounts claimed in respect of each dispute. Subject as aforesaid the provision of the arbitration Act 1940 or any statutory modification or re-enactment thereof and the rules made there
  • 25. under and for the time being in force shall apply to the arbitration proceedings. The arbitrator may form time to time with the consent of the parities enlarges the time for making and publishing the award. CLAUSE-34 (A) (iv) The cost of such arbitration shall be borne by the parties or party as decided by the arbitrator. CLAUSE-34 (B) (i) If under the contract has not been completed when a dispute is referred to arbitration the work shall continue the arbitration proceeding and no payment due to the contractor within the provision of the contract shall be withheld on account of arbitration proceeding unless authoresses or required by the arbitrator. CLAUSE-34 (B) (ii) Every dispute difference or question which may at any time arise between the parties here to any person claiming under them couching or arising out in respect of this deed or the subject matter, thereof shall be referred to the arbitration of............................................ or any person nominated by him. It will be not objection to any such appointment that the arbitrator so appointed is a Government servant that he had to deal with the matter to which the contract relate and that in the course of his duties Government servant he had expressed views on all or any of the matters in disputes or differences in the event of the arbitrator to whom the matter is originally referred or being transferred or vacating his office or being unable to act for any reason......................................shall either enter upon the reference himself or appoint another person to act as arbitrator. Such person shall be entitled to proceed with the reference from the stage it was left by his Predecessor it is also a term of this contract that no person other than a person appointed as aforesaid should act as arbitrator and if for any reason that is not possible the matter is not to be referred to arbitration at all. In all cases where the amount of the claim in dispute is Rs. 50,000/- (Rupees fifty thousand) and above the arbitrator shall give reason for the award. CLAUSE-34 (B) (iii) It is a term of the contract that the party invoking the arbitrator shall specify the dispute or disputes to be referred to arbitration together with the amount or amounts claimed in respect of each dispute. Subject as aforesaid the provisions of the Arbitration Act. 1940 or any statutory modification or re-enactment thereof and the rules made there under and for the time being in force shall apply to the arbitration proceedings. The arbitrator may form time to time with the consent of the parities enlarges the time for making and publishing the award. CLAUSE-35 Quantities are liable to variation on either sides without entitling the contractor to compensation on his account CLAUSE-36 Contractor shall himself make proper living accommodation water and sanitary arrangements etc. for labour which ordinarily should be arrangement through Employment Exchange, will give preference to Ex- serviceman, He will have to remove any undesirable labour if ordered by the department. CLAUSE-37 Claims not preferred within 48 hours of occurrence are liable to be rejected. CLAUSE-38 No extra payments shall be made to the contractor for making profiles and naming as in connection with the execution with the execution of work as per G.O. No. 355-3B/66XXXIII-IB-IT dated 22-06-1966 CLAUSE-39 During the course of construction if any emergency is forwarded arisen due to any clause or claims of works the contractor shall send a registered cover notice to the...................................... Engineer-in- charge within a fortnight of the origin of the claims. If he fails to do so or if he post pones submission of such claims till the work he will be entitled to on compensation.
  • 26. CLAUSE-40 The Contractor shall not influence or direct labour borne on the muster Roll or by any other contractor by paying higher wages or providing extra facilities with –out the permission of the Executive Engineer and if he does so contrary to the above, will be responsible for the loss of or damage caused or claimed by other parties and the decision of the Executive Engineer as to the amount of such damage shall be final and binding on both parties. CLAUSE-41 This agreement is subject to the standard specifications The clearance of site shall be done by the contractor at his own expenses. CLAUSE-42 Income Tax at the rate of 2% shall be deducted from the bill in terms of sub-section (I) of section 194 (c) of Income Tax Act XVI of 1972 CLAUSE-43 FOR FAMILY PLANNING PURPOSEN IS CONTRACT. The contractor agrees to persuade all his labour and other employees, including casual labour employed by him, to adopt family planning techniques (including vasectomy and Tubectony) in lines with the policies and programme announced by the State Government from time to time in relation to the State Government is so for as may be applicable and to furnish to Engineer-in-charge monthly report in this behalf. G.O. No. 5032/76-23/C-3/1975/76 Date 8 Sept. 1976
  • 27. Schedule showing (approximate) material to be supplied from the Public work Stores for works contracted to be executed and the rates at which they are to be charged for. vide clause 12 of Conditions. Particulars Rates at which the materials will be charged to the contractor Place of delivery Unit Rs. P. Signature of Contractor Signature of sub-Divisional Officer Executive Engineer
  • 28. Schecule Of Consumption Of Material To Be Used For Different Item Of Works Sl.No. Item of Work Unit Cement of Bags 1. Cement concrete mix 1:4:8 Cum 3.25 (Natural Aggregates.) 3.40 (Crushed Aggregates.) 2. Cement concrete 1:3:6 Cum 4.15 (Natural Aggregates.) 4.30 (Crushed Aggregates.) 3. Cement concrete 1:2:4 Cum 5.76 (Natural Aggregates.) 6.10 (Crushed Aggregates.) 4. (A) Ist Class brick work in 1:4 Cement mortar. Cum 2.00 (B) Ist Class brick work in 1:3 Cement mortar. Cum 2.60 5. Cement Pointing (Struck) 1:2 Cement mortar Sqm 0.055 6. (A) Cement plastering 12.5 mm. thick in 1:4 Cement sand mortar. Sqm 0.110 (B) -----------do-----------in 1:5 Sqm 0.095 (C) -----------do-----------in 1:6 Sqm 0.079 7. Reinforcement steel M.Tonne As per Quantity placed according to Drawing as intered in M.B. _____________________________________________________________________________ SCHEDULE-B
  • 29. Sl.No. Item of Work Unit Places of Issue Rate 1. Cement in bags of 50 Kg as received from Factory Bags Govt. Store at Kalpipara Rs. per bag 215/- 2. Steel for reinforcement M.T. ..............do.............. 31500/- 3. Structural steel (M.S. plate, angle iron gierders, Flats & channels etc.) M.T. ..............do.............. - 4. Max phalt M.T. ..............do.............. - 5. Rubber seal R.M. ..............do.............. - 6. Copper seal R.M. ..............do.............. - 7. Joint filler Board/Themocol S.M. ..............do.............. - 8. Pressure observation pipes. R.M. ..............do.............. - 9. Sheet piles M.T. ..............do.............. - _____________________________________________________________________________ SCHEDULE-C
  • 30. Sl.No. Name of equipment which can be given on rent to the Contractor if available with department Hire charges per month or part there of [Calender months] Unit Places of Issue 1. Electric/Diesel concrete mixer Each Govt. Store at......................... 2. Electric/Petrol vibrater Each ...........do........... 3. Electric welding set 75/- Each ...........do........... 4. Diesel welding set 125/- Each ...........do........... 5. Shuttering plate 2/- S.M. ...........do........... 6. Steel shoulding for shuttering 20/- M.T. ...........do........... 7. Electric/Diesel pumps (5 H.P. to 10 H.P.) 125/- Each ...........do........... 8. Bore Hole pump. 175/- Each ...........do........... _____________________________________________________________________________ SCHEDULE-D
  • 31. CHAPTER - 1 SPECIAL CONDITION OF CONTRACT 1.1 DEFINITIONS : For the purpose of these specifications comprising conditions of contract amendments, the following words will have the meanings herein assigned to them: 1.1-1 The "GOVERNMENT" shall mean the Government of Uttar Pradesh. 1.1-2 The "GOVERNOR" nominated by President of India from time to time, shall mean the adminstrative head of the State of Uttar Pradesh. 1.1-3 The "CHIEF ENGINEER" shall mean the Chief Engineer, Irrigation Department, Uttar Pradesh. 1.1-4 The "SUPERINTENDING ENGINEER" shall mean the Superintending Engineer-in-charge of the work. 1.1-5 The "EXECUTIVE ENGINEER" shall mean the officer so designated authorised by the Govt. of Uttar Pradesh who shall work under the general administrative control of the Superintending Engineer and will be the in charge of the entire operation pertaining to the contract. 1.1-6 The "ASSISTANT ENGINEER" or "Sub-Divisional Officer" shall mean the officer so designated and authorised by the Govt. of Uttar Pradesh who shall be in actual in charge of field operations. 1.1-7 The "ENGINEER IN CHARGE" shall mean the Executive Engineer in Charge of the work. The Engineer may delegate any of his powers to his authorised representatives. Wherever the word "Engineer-in-charge" occurs in the text of the contract, it would be taken to imply the Engineer-in-charge as aforesaid or his authorised representative, or representatives as the case may be. 1.1-8 The "CONTRACTOR" shall mean the tenderes whether a firm, registered company, partnership or an individual whose tender shall be accepted and shall include its legal representative, successors and assigness. 1.1-9 The word "WORK" or "WORKS" wherever used in this contract shall be hold to comprise not only works of construction but also all accessories there to and all matters and things pertaining to the work executed or to be carried out unet the contract, whether such works permanent or temporary and whether it is original, altered, substituted or additional including clearance of site on the completion of construction. Wherever the context so require the words "WORK" or "WORKS" shall also include all temporary establishments such as hutting, quarters, offices, store sheds, workshop, roads, foundations or plant and machinery required for the work. 1.1-10 The word "SPECIFICATION" shall mean collectively all the terms and stipulations contained in the conditions of contract, technical provisions and annexires, and corrections and amendments to the specifications. 1.1-11 The word "DRAWINGS" shall mean collectively all accompanying general drawings as well as all detailed drawing which may be issued by the Engineer-in- charge from time to time during the period of construction. 1.1-12 The word "TONES" wherever used in this contract shall mean metric tonnes of 1000 Kg. unless otherwise specified. 1.1-13 Wherever fogures are shown after the word "ELEVATIONS, REDUCED LEVEL" or any abbriviation thereof or when figures representing "ELEVATION" or "REDUCED LEVEL" are given the shall mean the height in metres above the mean sea level unless otherwise specified. 1.1-14 The words used in contract in the singular number shall be interpreted to lincude the plural number and the plural, the singular number. 1.1-15 The words "Plant" "MACHINERY" and "EQUIPMENT" shall mean and include plant machinery, tools and other equipment necessary for the work as per specifications and plans in a workman I like manner. 1.1-16 "RATES" or "TENDERED RATES" shall mean the rates as entered in the "Schedule of Quantities and Bids" by the contractor and is accepted by the government or its authorised representative. The rate shall include all taxes such
  • 32. as sales tax toll tax etc. all duties an royalties etc. and all incudental charges required for the completion of particular item or work. 1.1-17 The "WORK SITE" shall mean the site of propsed work as detailed in specification or any other place where works are to be executed under the contract and such land in the vicinity of of works as may be notified by the Engineer-in-charge as the work site. 1.1-18 The word "MONTH" shall mean the calender month. 1.1-19 The word "WRITING" include any manucript, type witten, cyclostyled or printed statement under and over signature or seal as the case may be. 1.1-20 The word "SUB CONTRACTOR" shall mean the person named in the contract for any part of the work or any person to whom any part of contract has been sublet by the contractor with the consent in writing the Engineer-in-charge and the heirs, legal representative, successors and assigness of such persons. 1.1-21 "CONTRACT & CONTRACT DOCUMENT" shall mean the agreement in I.D. Form No. 112 and its component parts. 1.1-22 Matric system shall be followed in all interpretations and execution of the work in this contract. Any conversion found necessary shall be in accordance with figures given in Indian standard conversion Factor and Conversion Table (I.S. 786-1956) and its subsequent revisions. 1.1-23 The "PARAGRAPH" shall mean clause also. 1.1-24 The word "SUBSTRUCTURE" shall mean the portion of the structure below the level of rich wearing coat level of the floor, and the word "SUPERSTRUCTURE" shall mean the portion of the structure from and above the level of the rich wearing coat level at the floor. DEATH ; BANKRUPTCY OF CONTRACTOR 1.2 If the contractor dies or commits any act of bankruptcy or being a corporation, commences to be wound up, except for reconstitution purpose or carries on its business under a receiver, the executors, successor or the representatives in law of the estate of the contractor or any such receiver, liquidator or any person in whom the contract may become vested shall forth with give notice there of in writing to the Engineer-in-charge and shall for one month during which he shall take all reasonble steps to prevent stoppage of work have the option to carry out the contract subject to his or their providing such guarantee as may be required by the Engineer-in-charge but not exceeding the value of the work at the time remaining unexecuted. In the event of stopage of the work the period of the option under this clause shall be fourteen days only, provided that should the above option not be exercised the contract may be terminated by the Government by giving notice in writing to the contractor and the Engineer-in-charge by exercise the same power which he could exercise and will have same right which the would have under clause 3 of I.D. from 111 if the work had been taken out of the contractor's hand. ACCESS TO THE CONTRACTOR'S BOOKS 1.3 Whenever it is considered necessary by the Engineer-in-charge to ascertain the actual cost of the extra items or claims be shall direct the contractor to produce the personnel, invoices of materials and any other data relevant to the item or neccessary to determine its cost act and the contractor shall when so required furnish information pertaining to the aforesaid items in the mode and manner that may be specified. CONTRACT DOCUMENTS AND MATTERS TO BE TREATED AS CONFIDENTIAL 1.4 All documents, correspondence, decision and other matters concerning the contract shall be considered as of confidential and restricted nature by the contractor and he shall not divulge or allow access there to any unauthorised persons of any kind. USE OF CONSTRUCTION FACILITIES TO OTHER CONTRACTORS AND GOVERNMENT EMPLOYEES 1.5 The government may undertake or award other contract for additional work at or in the vicinity of the works under this tender and the contractor shall fully
  • 33. co-operate with such other contractor and Government employees and carefully fit in his work of such additional works as may be directed by the Engineer-in-charge. The contractor shall not commit or permit any act which will interfere with the performance of the work being done by government to use the roads, bridges, lighting installation and any other facilities constructed or acquired by the available without entailling any increases in the cost to the contractor for maintenance or operation for such facilities. FINDS OF THE WORKS 1.6 Any finds in the area of work such as relies of fossils or articles of other value or any minerals etc shall be the absolute property of the Government of Uttar Pradesh and shall be handed over intact by the contractor to the Engineer-in-charge. The contractor shall take reasonable precautions to prevent articles or things and shall immediatly, on discovery therof and before removal, acquaint the Engineer-in- charge of such Discovery. 1.7 ERRORS OMISSIONS AND DISCREPANCIES 1.7-1 If the contractor discovers any error, omission and discrepancies on the contract drawings or specifications or in the work undertaken and performed by him, he shall immediately notify the Engineer-in-charge and the latter shall promptly verify and set right the same. The contractor shall not take advantage or errors or omissions as full instruction shall be available to the contractor. Should any error or omission and prior to the correction thereof if the contractor proceeds with any work affected thereby, he shall do so at own risk and the work so done shall not be considered as work done under the contract and in performance thereof. However payment for extra works done as a result of error of omissions in designs, drawings or specifications issued by the Engineer-in-charge shall be made to the contractor to the extent of quantities of work done before the errors or omissions were discovered or were brought to the notice in writing. 1.7-2 The drawing and specifications are to be considered as explanatory of each other and should anythins appear in the former but is not described in the latter no advantage shall be taken by the contractor of any such omission. In case of disagreement between specifications and drawing, the conditions of the specifications shall govern the contract should any discrepancies, however appearor should any misunderstanding as to the dimensions or the quantity of the materials for the proper executions of the work or as to the measurements or quantity and valuation of the works executed arise under this contract or as extra item, the same shall be explaines by the Engineer-in-charge. 1.7-3 In case of errors, omissions and/or disagreement between the drawing and specification, the following order of preference shall apply. (i) Between the written or shown description one in the specifications the letter shall apply. (ii) Between the quantities shown in the schedule of quqntities and those arrived at from drawings, the letter shall apply. (iii) Between the written description of the item in the schedule of quantities an the detailed description in the specification of the same item, the latter shall be adopted. (iv) Figured dimensions shall supercede sealed dimensions, drawing to a larger scale shall take precedence over those on smaller scale. 1.7-4 Special directions incorporated in the drawing shall be complied with strictly. 1.7-5 Drawing issued as construction drawing from time to time will supercede the once previously issued. 1.8 THE SITE 1.8-1 The is understood and agreed that contractor has satisfied himself as to the nature and location of the works general and local conditions or and particularly those being on transport, handling or storage of materials, disposal of spoils, availability of labour, weather conditions or similar physical conditions at the work site, sub soil water, hydrology and configuration of ground, the character, quality and quantity of the surface materials to be encountered, the character or equipment
  • 34. and facilities needs preominiary to and during the execution of the work and all other matters which may in any default or failure by the work or the cost thereof under this contract. Any default or failure by the contractor to acquaint himself with all the information conerning these conditions will not relieve from responsibility for the execution of the contract unless the contract provides that the the responsibility thereof is assumed by the Government. 1.8-2 The information and date states herein and incorporated in the contract elsewhere is for information only and the Engineer-in-charge does not guarantee that the available records shown completely the existing condition and does not guarantee any interpertations of these data or correctness of information. The contractor shall assume full responsibility for any deductions or conclusions drawn there from by him. 1.9 DRAWING Index map and drawing showing plan and cross-sections areenclosed. 1.10 ROADS IN WORK AREA The kachcha or pucca roads constucted by Government in work area and in coloney will be available for use by the contractor subject to the conditions implsed by Engineer-in-charge. The addition to the roads constructed at his own cost all the roads requited in addition to the roads constructed by the Government. 1.11 CONTRACTOR NOT TO DISPOSE OFF SOIL ETC. The contractor shall not dispose off or remove except for the purpose of fulfilment of this contract, sand, stone, clay, ballast, earth, trees and shurbh or site of the work and all such materials and produce shall remain property of the Government, Government may upon request from the contractor or if so stipulated in the conditions of the contract, allow the contractor to use any of the above materials for the works free of cost. 1.12 LAND The contractor will be permitted to use the land if available with the Irrigation Department and remarked for the construction camp, free of cost during the period of the contract. Such use of land shall not interfere with any part or work of the contractor or of the Government in the vicinity. If no such land is in possession of the Irrigation Department the same will be acquired by the contractor at his own cost by private negotiations and no claim shall be admissibe to him on this on account. 1.13 EMPLOYMENT OF LABOUR BROUGHT BY OTHER CONTRACTOR If the contractor takes away any labour brought and employed by other contractors of the Government working in the project, he shall be liable to pay compensation equal to the project the original contractor would have continued with him and he will also have made if the return the labour this employed. The decision of the Engineer-in-charge shall be final and binding on the contractor. 1.14 RATES FOR INCREASE IN QUANTITIES If there is any increase in the quantities due to any reason, whatsoever the access quantity more than that provided in the schedule of bids shall be paid either at the tendered rates or at the departmental schedule of lates of operating at the time of entering in to the agreement whichever is the minimum. 1.15 JURIDICTION The contract shall be governed by the laws of Govt. of U.P./Govt. of India, for the time being inforce & shall subject to the juridiction of this district Court at Bahraich.