SlideShare a Scribd company logo
1 of 44
Download to read offline
Whitstable Town Hall Meeting -

Cromwell Road Embankment Works

Thursday 3rd May 2012 – St Marys Hall, Whitstable – 18:30




 Rev Paul Wilson and John Burrows
Before We Start…….

• Fire Evacuation Procedure
• Fire Exits
• Mobile Phones
• Any Members of the Press ?
• Filming
Agenda

• Residents Concerns – Julie Wassmer
• Geotechnics Report – Simon Abbott
• Track Geometry – Jordan Faulkner
• Environmental Issues – Glen Brown
• Work Scope and Method – Martin Pope
• Notification Policy & Lessons Learnt – Glen Brown
• Summary
• Questions Session
Resident’s Concerns and
Objections
Clay Embankments and the
Problems Associated with
Vegetation

Simon Abbott (BEng), CGeol, FGS, – Senior Asset Engineer (Geotechnics)
Earthwork Assets
Three principal geotechnical asset types we are responsible for;




Soil                              Emb                              R oc
       Cutt                              ank                            k Cu
            ings                             men                               tting
                                                ts                                   s




Continued process of examination, maintenance, investigation, assessment and remediation
Geological Context & Construction
                      Sensitivity to Moisture Change
                      •Gault
                      •London Clay
                      •Weald Clay




                               BGS Swell-Shrink Potential Map
1960’s compared to 2012




Historically little vegetation aside from grass and low scrub on embankments and cuttings
1960’s compared to 2012




      Car parks highlighted for point of reference
Trees – good or bad?
                       Cuttings – bad
Trees – good or bad?
                       Chelsfield Cutting
Trees – good or bad? Embankments..
 It is misunderstood that mature vegetation only has
 positive impacts on slopes.
 High water demand trees have a detrimental effect on
 the condition of particular embankments (next slide)
 Tall trees impose high loads as a result of wind
 loading.
 Leaf fall
 Signal Sighting
Modern Understanding of Geotechnics

Land take pressures during railway
construction mean assets are typically
over steep

Settlement & Heave up to 50mm
between summer and winter.
                                         Permanent outward spreading of embankment
Leading industry research
Soil Moisture Deficit (SMD)
                         Ashford’s Square 174
                                                Faversham’s Squares 163 & 164


SMD = Amount of
rainfall (mm) that the
ground can absorb
before reaching
saturation.
SMD of 0 = saturated
SMD of 200 = dry




                                                                                15
SMD Chart 163 VIR
                                         Gillingham to Herne Bay
                                               Rate of SMD rise in Morec Square 163                                       2009
                                                                                                                          2010

   350                                                                                                                    2011
                                                                                                                          2012


   300



   250



   200




   150



   100



   50



    0
     01-Jan   01-Feb   01-Mar   01-Apr     01-May    01-Jun    01-Jul    01-Aug       01-Sep   01-Oct   01-Nov   01-Dec          01-Jan




                                                                                                                                          16
How the line side vegetation should be


We always endeavour to
leave trees at the toe




                           Remedial scheme
                           necessitated removal of
                           trees on inner verge.
What Happens if we don’t manage the
vegetation on our clay embankments?
Serviceability and Delayed Failure
              Delayed failure is associated with long
              term shrink-swell induced by vegetation
References:

• Briggs, K (2010). Charing Embankment: Climate Change
  Impacts on Embankment Hydrology. Cooling Prize 2010 Winning
  Submission.
• Loveridge, F.A et al (2010). The impact of climate and climate
  change on UK Infrastructure slopes.
• Smethurst, J.A etc al (2005). Seasonal changes in pore water
  pressure in a grass covered cut slope in London Clay.
• O’Brien, A.S.O et al (2004). Old Railway Embankment Clay Fill –
  Laboratory Experiments, Numerical Modelling and Field
  Behaviour.
• CIRIA Special Publication C592 (2003). Infrastructure
  Embankments – condition appraisal and remedial techniques.
Track Geometry




Jordan Faulkner – Track Maintenance Engineer (Faversham)
Network Rail Standards – Track Maintenance

Working to Network Rail standards
that are applied nationally for
inspection and maintenance of track.
The standard specifies:

• Minimum frequencies for
inspections.
• Processes for carrying out
inspections.
• Details those track geometry faults
which require action.
Good track geometry
Whitstable track geometry


                            • Shows vertical and
                            lateral rail alignment.

                            • Super Red eighth =
                            eighth within in
                            maximum SD band.

                            • Eighths within
                            maximum SD band
                            pose an increased
                            risk of an incident.
Whitstable track geometry

                            Standards state:

                            •Engineers must use other
                            asset information and/or
                            arrange more detailed
                            examinations where needed
                            to identify root causes.

                            • Standards require that we
                            take appropriate action to
                            improve track geometry
                            quality by tackling the
                            underlying causes.

                            • Also faults shall be repaired
                            before they affect the safe
                            performance of the track.
Track Geometry

Photos from 2011
Clay Bank Vegetation Management
Ashford to Maidstone line - Hollingbourne
Station
Ashford to Maidstone line - Charing Station
Evidence of TQ affected by trees on
Ashford to Hastings line.




                     Individual Trees
Track - Summary

 Repeat maximum SD (Super Red) track geometry
• Increased safety risk.
• Increased inspection frequencies.
• Condition of track speed restriction for 13+ weeks in
summer 2011.
• There is a limit to work that can be completed in
summer due to the risk of track buckles.
• Already undertaking maintenance work 3 times more
frequent than similar track.
• Large number of speeds across East Kent in 2011.
• Component deterioration – increased maintenance –
component deterioration.
Environmental Concerns and Summary of
 Vegetation Management




Angela Cruickshanks – Infrastructure Maintenance Environmental Specialist
(BSc/MSc Environmental Consultancy, AIEMA)

Martin Pope – Infrastructure Maintenance Programme Manager

  Date 00.00.00                                                             32
Environmental Concerns

• Pre-work survey completed by Network Rail to identify if any
  protected areas in the vicinity or any protected trees are present
• Daily site inspection recorded by the contractor to identify any
  nesting birds in the area of work
• Risk of nesting birds identified by Network Rail in the work
  package plan and provided to the contractor
• Consultation with Natural England to advise on the scope of the
  works
• Site walkouts completed to identify nests by the Network Rail
  Environment Specialist, Lineside Engineer and Programme
  Manager

      Presentation title to go here                                    33
Environmental Legislation/Mitigation

• Under the Wildlife and Countryside Act 1981, all wild birds, their
  eggs and nests are protected
• It is an offence to intentionally take, damage or destroy the nest
  of any bird while in use or being built.
• There is no reference in the Wildlife and Countryside Act 1981 to
  specific dates when vegetation work cannot be carried out as
  birds potentially nest all year round and is dependant on climate
• Contractor advised to create an exclusion zone of 2m
  surrounding any potential nests identified as per the company
  corporate guidance
Proposed Plan

• Phase 1 - Remove all younger Sycamore re-growth close to the
  lineside first and any dense shrubbery which restricts access to
  larger trees
• Phase 2 – Re-Survey the large Sycamore trees for nest which
  may be covered by the ivy. NB The ivy indicates poor health of
  the trees and some trees identified as decaying
• Any larger trees where birds are not nesting shall be removed in
  accordance with the specifications discussed.
• A proposal to use other Network Rail land to create a dense
  woodland to compensate for the woodland habitat removed at
  Whitstable in a habitat trading scheme
Network Rail’s ongoing Vegetation Management

• In addition to the specifications already discussed there are a number of other
  specifications where Network Rail are required, in accordance with Company
  Standards, to proactively manage vegetation on Network Rail controlled
  infrastructure. One such specification is to clear, up to 5 metres laterally from
  the running line, maintain clear of all woody vegetation. The area vertically
  above shall also be maintained clear of all vegetation. This excludes general
  ground and scrub clearance for the safe removal of trees on embankments.
The Network Rail

Pre Notification Policy



Glen Brown – Maintenance Protection Co-ordinator
Pre Notification of Works Policy

• Maintenance is the general day-to-day upkeep of the railway which keeps the
  trains running, for instance looking after tracks, signals, power supply and
  vegetation. Engineering is the larger scale infrastructure work, for example
  track replacement and upgrade works.

• When we are planning engineering works near residential areas, we aim to
  send letters to local people 10 days before the work begins. The letters explain
  what we plan to do and when we expect the works to start and finish.

• For maintenance work (such as emergency repairs or general up-keep), it is not
  possible for us to tell the people who live nearby. This is because maintenance
  work takes place every day and night of the year on the railway all over the
  country which makes it impractical to give advance notice to all the people
  affected by every job.
Pre Notification of Works Policy

• The vegetation works carried out in the Whitstable area are classified
  as maintenance works. Due to the timescales involved, letter drops
  were done in good will at Cromwell Road several days before work was
  due to start on this side of the railway.

• If we can, we will work on the plants and trees near the railway during
  the day between Monday and Friday, but sometimes we have to work
  at nights or weekends so that we can keep our staff safe and the trains
  running.

• If we are working in an area for a prolonged period, we try to let our
  neighbours know through letter drops. We will also contact the
  appropriate local authority informally and if necessary submit a formal
  activity and noise application to obtain consent.
Lessons Learnt –

Cromwell Road Tree Clearance



Glen Brown – Maintenance Protection Co-ordinator
What we could have done much better…

• Network Rail standard letter templates were not used as the contractor was
asked to manage this process without full guide lines on our process being
provided.

• Our contractors have been fully re-briefed on the NR pre-
notification policy and the new updated templates to use.


• Letters should have been more descriptive of the works being carried out so
as to avoid confusion that all trees were being removed from the embankment.

• The words “Vegetation Clearance” are open to interpretation and very rarely mean
all vegetation. These have been changed to be more descriptive on our new
template.
and how we are making it better?

• Letters should have been distributed to affected residents 10 days in advance
of the works through our postal service – Via post.

• All larger scale vegetation works are to be notified to the MPC so that letters
can be sent out 14 days in advance as we do with all engineering projects or
road closures etc.


• Managing the publics expectations when stopping works was not handled
well.
• Information given to the public was reactive and did not explain that the site
must by law be left safe and that this may require a bit more time of noise to
achieve.
Questions & Answers
• THANK YOU FOR ATTENDING AND GOODNIGHT.

More Related Content

What's hot

Jan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 RepairJan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 RepairHonolulu Civil Beat
 
Ec news 5 hydroseeding, consultancy
Ec news 5 hydroseeding, consultancyEc news 5 hydroseeding, consultancy
Ec news 5 hydroseeding, consultancyerosioncontrol
 
Foundation Stabilization for Reservoir Geomembrane, India
Foundation Stabilization for Reservoir Geomembrane, IndiaFoundation Stabilization for Reservoir Geomembrane, India
Foundation Stabilization for Reservoir Geomembrane, IndiaPRS Mediterranean
 
Garland Modified Brochure 2013
Garland Modified Brochure 2013Garland Modified Brochure 2013
Garland Modified Brochure 2013Thomas McIntosh
 
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...Blake Morgan
 
Peatland Development Challenges – A Case Study from Kampar Peninsula, Riau, I...
Peatland Development Challenges – A Case Study from Kampar Peninsula, Riau, I...Peatland Development Challenges – A Case Study from Kampar Peninsula, Riau, I...
Peatland Development Challenges – A Case Study from Kampar Peninsula, Riau, I...GlobalEnvironmentCentre
 
Non conventional materials
Non conventional materialsNon conventional materials
Non conventional materialsGraciella Santos
 
Officine Maccaferri Spa: Rockfall protection & Natural hazard mitigation
Officine Maccaferri Spa: Rockfall protection & Natural hazard mitigationOfficine Maccaferri Spa: Rockfall protection & Natural hazard mitigation
Officine Maccaferri Spa: Rockfall protection & Natural hazard mitigationMaccaferri World
 
Engineered sportfield solutions llc
Engineered sportfield solutions llcEngineered sportfield solutions llc
Engineered sportfield solutions llcJames Little
 
Soil organic carbon: thresholds and soil structure quality
Soil organic carbon: thresholds and soil structure qualitySoil organic carbon: thresholds and soil structure quality
Soil organic carbon: thresholds and soil structure qualityExternalEvents
 
Spectra halfday pdf
Spectra halfday pdfSpectra halfday pdf
Spectra halfday pdfhtrdano
 
Ground improvement using vibro-stone technique
Ground improvement using vibro-stone techniqueGround improvement using vibro-stone technique
Ground improvement using vibro-stone techniqueAhmed Abdullah
 
Green Building Resource Guide for Residential Construction - Build It Green
Green Building Resource Guide for Residential Construction - Build It GreenGreen Building Resource Guide for Residential Construction - Build It Green
Green Building Resource Guide for Residential Construction - Build It GreenFlanna489y
 
Organic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationOrganic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationUniversity of Wisconsin-Madison
 

What's hot (15)

Jan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 RepairJan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 Repair
 
Ec news 5 hydroseeding, consultancy
Ec news 5 hydroseeding, consultancyEc news 5 hydroseeding, consultancy
Ec news 5 hydroseeding, consultancy
 
Foundation Stabilization for Reservoir Geomembrane, India
Foundation Stabilization for Reservoir Geomembrane, IndiaFoundation Stabilization for Reservoir Geomembrane, India
Foundation Stabilization for Reservoir Geomembrane, India
 
Garland Modified Brochure 2013
Garland Modified Brochure 2013Garland Modified Brochure 2013
Garland Modified Brochure 2013
 
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
 
Vegetative barriers implecations on soil properties
Vegetative barriers   implecations on soil propertiesVegetative barriers   implecations on soil properties
Vegetative barriers implecations on soil properties
 
Peatland Development Challenges – A Case Study from Kampar Peninsula, Riau, I...
Peatland Development Challenges – A Case Study from Kampar Peninsula, Riau, I...Peatland Development Challenges – A Case Study from Kampar Peninsula, Riau, I...
Peatland Development Challenges – A Case Study from Kampar Peninsula, Riau, I...
 
Non conventional materials
Non conventional materialsNon conventional materials
Non conventional materials
 
Officine Maccaferri Spa: Rockfall protection & Natural hazard mitigation
Officine Maccaferri Spa: Rockfall protection & Natural hazard mitigationOfficine Maccaferri Spa: Rockfall protection & Natural hazard mitigation
Officine Maccaferri Spa: Rockfall protection & Natural hazard mitigation
 
Engineered sportfield solutions llc
Engineered sportfield solutions llcEngineered sportfield solutions llc
Engineered sportfield solutions llc
 
Soil organic carbon: thresholds and soil structure quality
Soil organic carbon: thresholds and soil structure qualitySoil organic carbon: thresholds and soil structure quality
Soil organic carbon: thresholds and soil structure quality
 
Spectra halfday pdf
Spectra halfday pdfSpectra halfday pdf
Spectra halfday pdf
 
Ground improvement using vibro-stone technique
Ground improvement using vibro-stone techniqueGround improvement using vibro-stone technique
Ground improvement using vibro-stone technique
 
Green Building Resource Guide for Residential Construction - Build It Green
Green Building Resource Guide for Residential Construction - Build It GreenGreen Building Resource Guide for Residential Construction - Build It Green
Green Building Resource Guide for Residential Construction - Build It Green
 
Organic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationOrganic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research Station
 

Similar to Network Rail presentation whitstable may2012 (1)

IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET Journal
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET Journal
 
Design of openpit mining
Design of openpit miningDesign of openpit mining
Design of openpit miningSATYANARAYANA I
 
Geoscience in Offshore Renewables
Geoscience in Offshore RenewablesGeoscience in Offshore Renewables
Geoscience in Offshore RenewablesFarida Ismayilova
 
Beach Road, Porous Pavement and Then Some
Beach Road, Porous Pavement and Then SomeBeach Road, Porous Pavement and Then Some
Beach Road, Porous Pavement and Then Somemecocca5
 
IRJET- Study on the Behavior of Slope using Soil Nailing and Shotcreting
IRJET-  	  Study on the Behavior of Slope using Soil Nailing and ShotcretingIRJET-  	  Study on the Behavior of Slope using Soil Nailing and Shotcreting
IRJET- Study on the Behavior of Slope using Soil Nailing and ShotcretingIRJET Journal
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaStephen McKnight
 
Peatland monitoring iucn conference v.4
Peatland monitoring iucn conference v.4Peatland monitoring iucn conference v.4
Peatland monitoring iucn conference v.4Jeremy LeLean
 
Landslide identification and mitigation sarulla geothermal power plant rev 2
Landslide identification and mitigation sarulla geothermal power plant rev 2Landslide identification and mitigation sarulla geothermal power plant rev 2
Landslide identification and mitigation sarulla geothermal power plant rev 2Jefry Ramli
 
Balancing Wetland Preservation and Stormwater Management: a case study
Balancing Wetland Preservation and Stormwater Management: a case studyBalancing Wetland Preservation and Stormwater Management: a case study
Balancing Wetland Preservation and Stormwater Management: a case studyAndrew T. Der & Associates, LLC
 

Similar to Network Rail presentation whitstable may2012 (1) (20)

Wetlands and Stormwater Management
Wetlands and Stormwater ManagementWetlands and Stormwater Management
Wetlands and Stormwater Management
 
IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling Methods
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil Erosion
 
Design of openpit mining
Design of openpit miningDesign of openpit mining
Design of openpit mining
 
Geoscience in Offshore Renewables
Geoscience in Offshore RenewablesGeoscience in Offshore Renewables
Geoscience in Offshore Renewables
 
Tailings dams
Tailings damsTailings dams
Tailings dams
 
Aoc sediment update_part2
Aoc sediment update_part2Aoc sediment update_part2
Aoc sediment update_part2
 
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
 
4RVanoh .pptx
4RVanoh .pptx4RVanoh .pptx
4RVanoh .pptx
 
Beach Road, Porous Pavement and Then Some
Beach Road, Porous Pavement and Then SomeBeach Road, Porous Pavement and Then Some
Beach Road, Porous Pavement and Then Some
 
James riverpartnership2003
James riverpartnership2003James riverpartnership2003
James riverpartnership2003
 
IRJET- Study on the Behavior of Slope using Soil Nailing and Shotcreting
IRJET-  	  Study on the Behavior of Slope using Soil Nailing and ShotcretingIRJET-  	  Study on the Behavior of Slope using Soil Nailing and Shotcreting
IRJET- Study on the Behavior of Slope using Soil Nailing and Shotcreting
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
 
Peatland monitoring iucn conference v.4
Peatland monitoring iucn conference v.4Peatland monitoring iucn conference v.4
Peatland monitoring iucn conference v.4
 
Wetlands and Stormwater Management
Wetlands and Stormwater ManagementWetlands and Stormwater Management
Wetlands and Stormwater Management
 
Green Infrastructure Maintenance Workshop
Green Infrastructure Maintenance WorkshopGreen Infrastructure Maintenance Workshop
Green Infrastructure Maintenance Workshop
 
Landslide identification and mitigation sarulla geothermal power plant rev 2
Landslide identification and mitigation sarulla geothermal power plant rev 2Landslide identification and mitigation sarulla geothermal power plant rev 2
Landslide identification and mitigation sarulla geothermal power plant rev 2
 
PIC 2 Display Boards
PIC 2 Display BoardsPIC 2 Display Boards
PIC 2 Display Boards
 
Balancing Wetland Preservation and Stormwater Management: a case study
Balancing Wetland Preservation and Stormwater Management: a case studyBalancing Wetland Preservation and Stormwater Management: a case study
Balancing Wetland Preservation and Stormwater Management: a case study
 
Wetlands and Stormwater Management
Wetlands and Stormwater ManagementWetlands and Stormwater Management
Wetlands and Stormwater Management
 

Recently uploaded

Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 

Recently uploaded (20)

Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 

Network Rail presentation whitstable may2012 (1)

  • 1. Whitstable Town Hall Meeting - Cromwell Road Embankment Works Thursday 3rd May 2012 – St Marys Hall, Whitstable – 18:30 Rev Paul Wilson and John Burrows
  • 2. Before We Start……. • Fire Evacuation Procedure • Fire Exits • Mobile Phones • Any Members of the Press ? • Filming
  • 3. Agenda • Residents Concerns – Julie Wassmer • Geotechnics Report – Simon Abbott • Track Geometry – Jordan Faulkner • Environmental Issues – Glen Brown • Work Scope and Method – Martin Pope • Notification Policy & Lessons Learnt – Glen Brown • Summary • Questions Session
  • 5. Clay Embankments and the Problems Associated with Vegetation Simon Abbott (BEng), CGeol, FGS, – Senior Asset Engineer (Geotechnics)
  • 6. Earthwork Assets Three principal geotechnical asset types we are responsible for; Soil Emb R oc Cutt ank k Cu ings men tting ts s Continued process of examination, maintenance, investigation, assessment and remediation
  • 7. Geological Context & Construction Sensitivity to Moisture Change •Gault •London Clay •Weald Clay BGS Swell-Shrink Potential Map
  • 8. 1960’s compared to 2012 Historically little vegetation aside from grass and low scrub on embankments and cuttings
  • 9. 1960’s compared to 2012 Car parks highlighted for point of reference
  • 10. Trees – good or bad? Cuttings – bad
  • 11. Trees – good or bad? Chelsfield Cutting
  • 12. Trees – good or bad? Embankments.. It is misunderstood that mature vegetation only has positive impacts on slopes. High water demand trees have a detrimental effect on the condition of particular embankments (next slide) Tall trees impose high loads as a result of wind loading. Leaf fall Signal Sighting
  • 13. Modern Understanding of Geotechnics Land take pressures during railway construction mean assets are typically over steep Settlement & Heave up to 50mm between summer and winter. Permanent outward spreading of embankment
  • 15. Soil Moisture Deficit (SMD) Ashford’s Square 174 Faversham’s Squares 163 & 164 SMD = Amount of rainfall (mm) that the ground can absorb before reaching saturation. SMD of 0 = saturated SMD of 200 = dry 15
  • 16. SMD Chart 163 VIR Gillingham to Herne Bay Rate of SMD rise in Morec Square 163 2009 2010 350 2011 2012 300 250 200 150 100 50 0 01-Jan 01-Feb 01-Mar 01-Apr 01-May 01-Jun 01-Jul 01-Aug 01-Sep 01-Oct 01-Nov 01-Dec 01-Jan 16
  • 17. How the line side vegetation should be We always endeavour to leave trees at the toe Remedial scheme necessitated removal of trees on inner verge.
  • 18. What Happens if we don’t manage the vegetation on our clay embankments?
  • 19. Serviceability and Delayed Failure Delayed failure is associated with long term shrink-swell induced by vegetation
  • 20. References: • Briggs, K (2010). Charing Embankment: Climate Change Impacts on Embankment Hydrology. Cooling Prize 2010 Winning Submission. • Loveridge, F.A et al (2010). The impact of climate and climate change on UK Infrastructure slopes. • Smethurst, J.A etc al (2005). Seasonal changes in pore water pressure in a grass covered cut slope in London Clay. • O’Brien, A.S.O et al (2004). Old Railway Embankment Clay Fill – Laboratory Experiments, Numerical Modelling and Field Behaviour. • CIRIA Special Publication C592 (2003). Infrastructure Embankments – condition appraisal and remedial techniques.
  • 21. Track Geometry Jordan Faulkner – Track Maintenance Engineer (Faversham)
  • 22. Network Rail Standards – Track Maintenance Working to Network Rail standards that are applied nationally for inspection and maintenance of track. The standard specifies: • Minimum frequencies for inspections. • Processes for carrying out inspections. • Details those track geometry faults which require action.
  • 24. Whitstable track geometry • Shows vertical and lateral rail alignment. • Super Red eighth = eighth within in maximum SD band. • Eighths within maximum SD band pose an increased risk of an incident.
  • 25. Whitstable track geometry Standards state: •Engineers must use other asset information and/or arrange more detailed examinations where needed to identify root causes. • Standards require that we take appropriate action to improve track geometry quality by tackling the underlying causes. • Also faults shall be repaired before they affect the safe performance of the track.
  • 27. Clay Bank Vegetation Management
  • 28. Ashford to Maidstone line - Hollingbourne Station
  • 29. Ashford to Maidstone line - Charing Station
  • 30. Evidence of TQ affected by trees on Ashford to Hastings line. Individual Trees
  • 31. Track - Summary Repeat maximum SD (Super Red) track geometry • Increased safety risk. • Increased inspection frequencies. • Condition of track speed restriction for 13+ weeks in summer 2011. • There is a limit to work that can be completed in summer due to the risk of track buckles. • Already undertaking maintenance work 3 times more frequent than similar track. • Large number of speeds across East Kent in 2011. • Component deterioration – increased maintenance – component deterioration.
  • 32. Environmental Concerns and Summary of Vegetation Management Angela Cruickshanks – Infrastructure Maintenance Environmental Specialist (BSc/MSc Environmental Consultancy, AIEMA) Martin Pope – Infrastructure Maintenance Programme Manager Date 00.00.00 32
  • 33. Environmental Concerns • Pre-work survey completed by Network Rail to identify if any protected areas in the vicinity or any protected trees are present • Daily site inspection recorded by the contractor to identify any nesting birds in the area of work • Risk of nesting birds identified by Network Rail in the work package plan and provided to the contractor • Consultation with Natural England to advise on the scope of the works • Site walkouts completed to identify nests by the Network Rail Environment Specialist, Lineside Engineer and Programme Manager Presentation title to go here 33
  • 34. Environmental Legislation/Mitigation • Under the Wildlife and Countryside Act 1981, all wild birds, their eggs and nests are protected • It is an offence to intentionally take, damage or destroy the nest of any bird while in use or being built. • There is no reference in the Wildlife and Countryside Act 1981 to specific dates when vegetation work cannot be carried out as birds potentially nest all year round and is dependant on climate • Contractor advised to create an exclusion zone of 2m surrounding any potential nests identified as per the company corporate guidance
  • 35. Proposed Plan • Phase 1 - Remove all younger Sycamore re-growth close to the lineside first and any dense shrubbery which restricts access to larger trees • Phase 2 – Re-Survey the large Sycamore trees for nest which may be covered by the ivy. NB The ivy indicates poor health of the trees and some trees identified as decaying • Any larger trees where birds are not nesting shall be removed in accordance with the specifications discussed. • A proposal to use other Network Rail land to create a dense woodland to compensate for the woodland habitat removed at Whitstable in a habitat trading scheme
  • 36. Network Rail’s ongoing Vegetation Management • In addition to the specifications already discussed there are a number of other specifications where Network Rail are required, in accordance with Company Standards, to proactively manage vegetation on Network Rail controlled infrastructure. One such specification is to clear, up to 5 metres laterally from the running line, maintain clear of all woody vegetation. The area vertically above shall also be maintained clear of all vegetation. This excludes general ground and scrub clearance for the safe removal of trees on embankments.
  • 37. The Network Rail Pre Notification Policy Glen Brown – Maintenance Protection Co-ordinator
  • 38. Pre Notification of Works Policy • Maintenance is the general day-to-day upkeep of the railway which keeps the trains running, for instance looking after tracks, signals, power supply and vegetation. Engineering is the larger scale infrastructure work, for example track replacement and upgrade works. • When we are planning engineering works near residential areas, we aim to send letters to local people 10 days before the work begins. The letters explain what we plan to do and when we expect the works to start and finish. • For maintenance work (such as emergency repairs or general up-keep), it is not possible for us to tell the people who live nearby. This is because maintenance work takes place every day and night of the year on the railway all over the country which makes it impractical to give advance notice to all the people affected by every job.
  • 39. Pre Notification of Works Policy • The vegetation works carried out in the Whitstable area are classified as maintenance works. Due to the timescales involved, letter drops were done in good will at Cromwell Road several days before work was due to start on this side of the railway. • If we can, we will work on the plants and trees near the railway during the day between Monday and Friday, but sometimes we have to work at nights or weekends so that we can keep our staff safe and the trains running. • If we are working in an area for a prolonged period, we try to let our neighbours know through letter drops. We will also contact the appropriate local authority informally and if necessary submit a formal activity and noise application to obtain consent.
  • 40. Lessons Learnt – Cromwell Road Tree Clearance Glen Brown – Maintenance Protection Co-ordinator
  • 41. What we could have done much better… • Network Rail standard letter templates were not used as the contractor was asked to manage this process without full guide lines on our process being provided. • Our contractors have been fully re-briefed on the NR pre- notification policy and the new updated templates to use. • Letters should have been more descriptive of the works being carried out so as to avoid confusion that all trees were being removed from the embankment. • The words “Vegetation Clearance” are open to interpretation and very rarely mean all vegetation. These have been changed to be more descriptive on our new template.
  • 42. and how we are making it better? • Letters should have been distributed to affected residents 10 days in advance of the works through our postal service – Via post. • All larger scale vegetation works are to be notified to the MPC so that letters can be sent out 14 days in advance as we do with all engineering projects or road closures etc. • Managing the publics expectations when stopping works was not handled well. • Information given to the public was reactive and did not explain that the site must by law be left safe and that this may require a bit more time of noise to achieve.
  • 44. • THANK YOU FOR ATTENDING AND GOODNIGHT.