[INC 281 MULTIDISCIPLINARY WORKSHOP WEEKLY REPORT]                            May 2, 2012

   Name-Surname Nattawat Boonmee
      Student ID. 54261511
     Group Name IS (Water Heater)
 Engineering Team
                  Nut, Love, Go, Jum-o, Tew, Jane, Best, Su and Not.
        Members
   Product Design
                  Sa-tang, Ped, Fon, Tip, Earng, Mind
   Team Members

Weekly Progress
 Part of My responsibility My project is Water Heater, This week we have designed and built the
 finished PCB. The circuit was built has been added to check the function of each segment. We
 found that all the test circuit in each segment can be run as needed. It is the responsibility of the
 MCU interface and LED Driver. I was responsible for most of the interface microcontroller and LED
 Driver. Circuit found that the two can work together. Then we contacted the Product Design Team
 to various electronic equipment to the water heater. To the circuit in the right position. Once right
 position, we will install a circuit and wiring to make a tidy and safe. When we put the circuit wiring
 from the Product Design Products have been tested to work again. The water can be heated by the
 heat from normal water temperatures reach 40 degrees Celsius in the past. Circuit can work well
 together, whether the water level or the level of the heat.




            Figure 1. Install a circuit and wiring            Figure 2. Test overview Water heater

Engineering Analysis
Strong Point
- The circuit Circuit can work together. All sectors.
- PCB circuit size is small.

Week Point
- Although the circuit can perform as expected. But we do not have time to test the long term. To
check the stability of the circuit.
-Not sure of the compatibility with the Product Design object.


Next Week Job
-Next week, I will recorded the performance to be documented report.




                                       Department of Control System and Instrumentation Engineering
                                          KING MONGKUT’s UNIVERSITY OF TECHNOLOGY THONBURI

Nattawat#3 54261511

  • 1.
    [INC 281 MULTIDISCIPLINARYWORKSHOP WEEKLY REPORT] May 2, 2012 Name-Surname Nattawat Boonmee Student ID. 54261511 Group Name IS (Water Heater) Engineering Team Nut, Love, Go, Jum-o, Tew, Jane, Best, Su and Not. Members Product Design Sa-tang, Ped, Fon, Tip, Earng, Mind Team Members Weekly Progress Part of My responsibility My project is Water Heater, This week we have designed and built the finished PCB. The circuit was built has been added to check the function of each segment. We found that all the test circuit in each segment can be run as needed. It is the responsibility of the MCU interface and LED Driver. I was responsible for most of the interface microcontroller and LED Driver. Circuit found that the two can work together. Then we contacted the Product Design Team to various electronic equipment to the water heater. To the circuit in the right position. Once right position, we will install a circuit and wiring to make a tidy and safe. When we put the circuit wiring from the Product Design Products have been tested to work again. The water can be heated by the heat from normal water temperatures reach 40 degrees Celsius in the past. Circuit can work well together, whether the water level or the level of the heat. Figure 1. Install a circuit and wiring Figure 2. Test overview Water heater Engineering Analysis Strong Point - The circuit Circuit can work together. All sectors. - PCB circuit size is small. Week Point - Although the circuit can perform as expected. But we do not have time to test the long term. To check the stability of the circuit. -Not sure of the compatibility with the Product Design object. Next Week Job -Next week, I will recorded the performance to be documented report. Department of Control System and Instrumentation Engineering KING MONGKUT’s UNIVERSITY OF TECHNOLOGY THONBURI