[INC 281 MULTIDISCIPLINARY WORKSHOP WEEKLY REPORT]                          May 2, 2012

 Name-Surname Chaiyarak Paiboonsuk
    Student ID. 54261533
   Group Name IS Company
    Engineering Jane,Best,Not,Su,Jum-O,Nut,Tew,Go,BenZ,Much
 Team Members

 Product Design
                Zatang,Ped,Fon,Tip,Earng.Mind
 Team Members


Weekly Progress
 We have installed engineering a circuit of into the structure of the water heater's
 architecture.
 And tested the use of the water heater. Almost all the works have been able to
 work.




                                                   Test

Engineering Analysis
Strong Point

-
Weak Point

water heater Circuit can actually work. The water temperature is uncertain due to the volume of
water flow are not equal.

Next Week Job
Modify circuit is error and ready test it.




                                        Department of Control System and Instrumentation Engineering
                                           KING MONGKUT’s UNIVERSITY OF TECHNOLOGY THONBURI

54261533

  • 1.
    [INC 281 MULTIDISCIPLINARYWORKSHOP WEEKLY REPORT] May 2, 2012 Name-Surname Chaiyarak Paiboonsuk Student ID. 54261533 Group Name IS Company Engineering Jane,Best,Not,Su,Jum-O,Nut,Tew,Go,BenZ,Much Team Members Product Design Zatang,Ped,Fon,Tip,Earng.Mind Team Members Weekly Progress We have installed engineering a circuit of into the structure of the water heater's architecture. And tested the use of the water heater. Almost all the works have been able to work. Test Engineering Analysis Strong Point - Weak Point water heater Circuit can actually work. The water temperature is uncertain due to the volume of water flow are not equal. Next Week Job Modify circuit is error and ready test it. Department of Control System and Instrumentation Engineering KING MONGKUT’s UNIVERSITY OF TECHNOLOGY THONBURI