PROGRESS OF EXPANTION PROJECT. 
1. New Basic Sol Preparation (Mixing) Unit. 
- To replace current unit. 
2. Softbag Mitsubishi Line. 
- Preparation (Mixing) unit for single bag. 
- Preparation (Mixing) unit for double bag. 
- Softbag line ( Single bag & double bag) 
3. Latest estimate time schedule. 
- New Basic Sol Preparation Unit. 
- Softbag line ( delay for 2 months ) 
Presenting by SA
Expansion project Team* 
Coordinator 
Sjamsu 
Valid / Product 
Muhklis/Tattik 
FAT, Trial 
Mukti 
Cost Control 
Leo 
ME/Civil 
Mujiono/Djoko 
Leader 
BK 
Team Advisors 
AB,JC,OKMT,IKW 
Lisences 
Totok 
cGMP Consultant 
RM, BS 
* Recommendation (need your advice )
1. New Basic Sol Preparation (Mixing) Unit. 
- To replace current unit. 
Why, What and How. 
WHY TO REPLACE 
- Does not meet cGMP. 
- Old equipments ( 30 years) 
- So far only fixing with used tank 
- Bechmark from OPF, PTWB, . 
Guangzou, Tianjin
1. New Basic Sol Preparation (Mixing) Unit. 
- To replace current unit. 
Why, What and How. 
WHAT TO REPLACE 
- Method. (follow cGMP) 
- Equipments. ( Tanks, Filter, Pipings, etc) 
- Supports. ( Water Treatment, PSG & 
. Distillation Unit, HVAC, RO, CIP/SIP, etc) 
- Building. ( Weight room, locker room, etc)
1. New Basic Sol Preparation (Mixing) Unit. 
- To replace current unit. 
Why, What and How. 
1 NEW PREPARATION PROJECT : BUILDINGS 
2 NEW PREPARATION PROJECT : TANKS 
BUILDING : 
WHAT TO REPLACE 
- Method. (follow cGMP) 
- Equipments. ( Tanks, Filter, Pipings, etc) 
- Supports. ( Water Treatment, PSG & 
. Distillation Unit, HVAC, RO, CIP/SIP, etc) 
- Building. ( Weight room, locker room, etc) 
a Preparation & WFI Storage Room 1st floor 
USD 52,500 9,300 488,250 
b - Locker Room 
USD 36,750 9,300 341,775 
c - Preparation & WFI Storage Room 2nd floor USD 
73,500 9,300 683,550 
d - WTP Building USD 
60,750 9,300 564,975 
e - Fuel Tank Relocating Work IDR 
300,000,000 1 300,000 
Total Building 2,378,550 
MACHINERIES : 
a - Preparation Tank - 12 ton USD 
320,000 9,300 2,976,000 
b - Preparation Tank - 5 ton USD 
90,000 9,300 837,000 
c WFI Storage Tank USD 
60,000 9,300 558,000 
4,371,000 
3 NEW PREPARATION PROJECT : SUPPORTING 
FACTORY EQUIPMENT : 
a - Reverse Osmosis ( RO ) USD 125,000 9,300 1,162,500 
b - Demin Water ( DI ) Unit, Demin Storage Tank USD 100,000 9,300 930,000 
c - Pure Steam Generator ( PSG ) EUR 110,000 11,718 1,288,980 
d Distiller Unit EUR 262,000 11,718 3,070,116 
e - High Ventilation Air Conditioning ( HVAC ) IDR 1,150,000,000 1 1,150,000 
f - Electrical System IDR 400,000,000 1 400,000 
g CIP / SIP Water System IDR 2,250,000,000 1 2,250,000 
h - Mechanical System IDR 2,200,000,000 1 2,200,000 
Total Factory Equipment 12,451,596 
GRAND TOTAL 19,201,146
1. New Basic Sol Preparation (Mixing) Unit. 
- To replace current unit. 
Why, What and How. 
3 NEW PREPARATION PROJECT : SUPPORTING 
HOW TO REPLACE 
- Learnt via OPF. 
. What is the latest method & the best designer 
- Method & Cost study to : 
- Iwai (Japan), Morimatsu (Japan in China) and 
. Jebsen & J (Pharmaplan in MSia) 
- Iwai will be deleted. 
. Focus on Jebsen & Morimatsu 
FACTORY EQUIPMENT : 
a - Reverse Osmosis ( RO ) USD 125,000 9,300 1,162,500 
b - Demin Water ( DI ) Unit, Demin Storage Tank USD 100,000 9,300 930,000 
c - Pure Steam Generator ( PSG ) EUR 110,000 11,718 1,288,980 
d - Distiller Unit EUR 262,000 11,718 3,070,116 
Total est cost from 3 designers 
(Exclude Building Rp 2.3 M) 
Iwai : Rp 25.2 M 
Morimatsu : Rp 9.4 M 
Jebsen & J : 2nd week April 
e - High Ventilation Air Conditioning ( HVAC ) IDR 1,150,000,000 1 1,150,000 
f - Electrical System IDR 400,000,000 1 400,000 
g - CIP / SIP Water System IDR 2,250,000,000 1 2,250,000 
h - Mechanical System IDR 2,200,000,000 1 2,200,000 
Total Factory Equipment 12,451,596 
GRAND TOTAL 19,201,146
PROGRESS OF EXPANTION PROJECT. 
2. Softbag Mitsubishi Line. 
- Preparation (Mixing) unit for single bag. 
- Preparation (Mixing) unit for double bag. 
- Softbag line ( Single bag & double bag) 
But, we never stop the study and prepare the new 
look of Architecture Building and chase up OPF 
Dear Board member, please give us your 
preference than we can start the civil work
PROGRESS OF EXPANTION PROJECT. 
3. Latest estimate time schedule. 
- New Basic Sol Preparation Unit. 
- Softbag line ( delay for 2 months )

Project expantion

  • 1.
    PROGRESS OF EXPANTIONPROJECT. 1. New Basic Sol Preparation (Mixing) Unit. - To replace current unit. 2. Softbag Mitsubishi Line. - Preparation (Mixing) unit for single bag. - Preparation (Mixing) unit for double bag. - Softbag line ( Single bag & double bag) 3. Latest estimate time schedule. - New Basic Sol Preparation Unit. - Softbag line ( delay for 2 months ) Presenting by SA
  • 2.
    Expansion project Team* Coordinator Sjamsu Valid / Product Muhklis/Tattik FAT, Trial Mukti Cost Control Leo ME/Civil Mujiono/Djoko Leader BK Team Advisors AB,JC,OKMT,IKW Lisences Totok cGMP Consultant RM, BS * Recommendation (need your advice )
  • 3.
    1. New BasicSol Preparation (Mixing) Unit. - To replace current unit. Why, What and How. WHY TO REPLACE - Does not meet cGMP. - Old equipments ( 30 years) - So far only fixing with used tank - Bechmark from OPF, PTWB, . Guangzou, Tianjin
  • 4.
    1. New BasicSol Preparation (Mixing) Unit. - To replace current unit. Why, What and How. WHAT TO REPLACE - Method. (follow cGMP) - Equipments. ( Tanks, Filter, Pipings, etc) - Supports. ( Water Treatment, PSG & . Distillation Unit, HVAC, RO, CIP/SIP, etc) - Building. ( Weight room, locker room, etc)
  • 5.
    1. New BasicSol Preparation (Mixing) Unit. - To replace current unit. Why, What and How. 1 NEW PREPARATION PROJECT : BUILDINGS 2 NEW PREPARATION PROJECT : TANKS BUILDING : WHAT TO REPLACE - Method. (follow cGMP) - Equipments. ( Tanks, Filter, Pipings, etc) - Supports. ( Water Treatment, PSG & . Distillation Unit, HVAC, RO, CIP/SIP, etc) - Building. ( Weight room, locker room, etc) a Preparation & WFI Storage Room 1st floor USD 52,500 9,300 488,250 b - Locker Room USD 36,750 9,300 341,775 c - Preparation & WFI Storage Room 2nd floor USD 73,500 9,300 683,550 d - WTP Building USD 60,750 9,300 564,975 e - Fuel Tank Relocating Work IDR 300,000,000 1 300,000 Total Building 2,378,550 MACHINERIES : a - Preparation Tank - 12 ton USD 320,000 9,300 2,976,000 b - Preparation Tank - 5 ton USD 90,000 9,300 837,000 c WFI Storage Tank USD 60,000 9,300 558,000 4,371,000 3 NEW PREPARATION PROJECT : SUPPORTING FACTORY EQUIPMENT : a - Reverse Osmosis ( RO ) USD 125,000 9,300 1,162,500 b - Demin Water ( DI ) Unit, Demin Storage Tank USD 100,000 9,300 930,000 c - Pure Steam Generator ( PSG ) EUR 110,000 11,718 1,288,980 d Distiller Unit EUR 262,000 11,718 3,070,116 e - High Ventilation Air Conditioning ( HVAC ) IDR 1,150,000,000 1 1,150,000 f - Electrical System IDR 400,000,000 1 400,000 g CIP / SIP Water System IDR 2,250,000,000 1 2,250,000 h - Mechanical System IDR 2,200,000,000 1 2,200,000 Total Factory Equipment 12,451,596 GRAND TOTAL 19,201,146
  • 6.
    1. New BasicSol Preparation (Mixing) Unit. - To replace current unit. Why, What and How. 3 NEW PREPARATION PROJECT : SUPPORTING HOW TO REPLACE - Learnt via OPF. . What is the latest method & the best designer - Method & Cost study to : - Iwai (Japan), Morimatsu (Japan in China) and . Jebsen & J (Pharmaplan in MSia) - Iwai will be deleted. . Focus on Jebsen & Morimatsu FACTORY EQUIPMENT : a - Reverse Osmosis ( RO ) USD 125,000 9,300 1,162,500 b - Demin Water ( DI ) Unit, Demin Storage Tank USD 100,000 9,300 930,000 c - Pure Steam Generator ( PSG ) EUR 110,000 11,718 1,288,980 d - Distiller Unit EUR 262,000 11,718 3,070,116 Total est cost from 3 designers (Exclude Building Rp 2.3 M) Iwai : Rp 25.2 M Morimatsu : Rp 9.4 M Jebsen & J : 2nd week April e - High Ventilation Air Conditioning ( HVAC ) IDR 1,150,000,000 1 1,150,000 f - Electrical System IDR 400,000,000 1 400,000 g - CIP / SIP Water System IDR 2,250,000,000 1 2,250,000 h - Mechanical System IDR 2,200,000,000 1 2,200,000 Total Factory Equipment 12,451,596 GRAND TOTAL 19,201,146
  • 7.
    PROGRESS OF EXPANTIONPROJECT. 2. Softbag Mitsubishi Line. - Preparation (Mixing) unit for single bag. - Preparation (Mixing) unit for double bag. - Softbag line ( Single bag & double bag) But, we never stop the study and prepare the new look of Architecture Building and chase up OPF Dear Board member, please give us your preference than we can start the civil work
  • 8.
    PROGRESS OF EXPANTIONPROJECT. 3. Latest estimate time schedule. - New Basic Sol Preparation Unit. - Softbag line ( delay for 2 months )