MiTV 2.5 Planning Feature mapping for Android
Description New features are required for the new version of MiTV RMC (rich media client) The release is scheduled in May 2011
Resources: Development: Horia Radu, Olivera Miatovici Stub development: Calin Vrabie Testing & Validation: Oana Popescu
Constraints We depend on the Graphical Design Team for UI items We depend on the Server Team for the Server Development (integration of new features) – API
Overview
Phases Preparation Development Validation
Milestones DR1 (development requirements) – 26.02.2011 MiTV API availability – 1.03.2011 Stub update – 8.03.2011 Android Graphical Design availability – 19.03.2011 Android RMC delivery – 5.05.2011
Development phase
Testing and Validation
Resources Horia Radu – part-time (50%) Calin Vrabie – two tasks in parallel, due to urgency
Risks Due to the many different teams involved in the project, the appearance of various delays is very probable and so we planned a buffer of one week.
Conclusions Gantt Project is a very useful tool for a project manager because it allows him to coordinate a project keeping track of the tasks, the resources, the milestones and how they all interact and influence each other. One big advantage of Gantt Project is the fact that it is free, while Microsoft Project is not.
Conclusions (2) Gantt Project really shows it’s power when we need to change something in the planning. The dependencies and deadlines are automatically updated when we change one task. Resource allocation is very easy and you can specify the amount of work each resource will do (full-time, part-time, etc.) Gantt Project can be used both for small projects and large ones.

Mi tv 2

  • 1.
    MiTV 2.5 PlanningFeature mapping for Android
  • 2.
    Description New featuresare required for the new version of MiTV RMC (rich media client) The release is scheduled in May 2011
  • 3.
    Resources: Development: HoriaRadu, Olivera Miatovici Stub development: Calin Vrabie Testing & Validation: Oana Popescu
  • 4.
    Constraints We dependon the Graphical Design Team for UI items We depend on the Server Team for the Server Development (integration of new features) – API
  • 5.
  • 6.
  • 7.
    Milestones DR1 (developmentrequirements) – 26.02.2011 MiTV API availability – 1.03.2011 Stub update – 8.03.2011 Android Graphical Design availability – 19.03.2011 Android RMC delivery – 5.05.2011
  • 8.
  • 9.
  • 10.
    Resources Horia Radu– part-time (50%) Calin Vrabie – two tasks in parallel, due to urgency
  • 11.
    Risks Due tothe many different teams involved in the project, the appearance of various delays is very probable and so we planned a buffer of one week.
  • 12.
    Conclusions Gantt Projectis a very useful tool for a project manager because it allows him to coordinate a project keeping track of the tasks, the resources, the milestones and how they all interact and influence each other. One big advantage of Gantt Project is the fact that it is free, while Microsoft Project is not.
  • 13.
    Conclusions (2) GanttProject really shows it’s power when we need to change something in the planning. The dependencies and deadlines are automatically updated when we change one task. Resource allocation is very easy and you can specify the amount of work each resource will do (full-time, part-time, etc.) Gantt Project can be used both for small projects and large ones.