2. PROGRESS OF WORK
Physical & Financial Percentage
(2nd Revise):
Physical & Financial Percentage
(3rd Revise):
26th May – 25th Jun 2020
Physical Percentage Financial Percentage
Schedule
Progress
82.61 % 82.89 %
Actual
Progress
66.64 % 67.89 %
Variance - 15.97 % - 14.97 %
26th Jun – 2 0th July 2020
Physical Percentage Financial Percentage
Schedule
Progress
92.63 % 92.88 %
Actual
Progress
67.10% 68.21%
Variance - 25.53 % - 24.67 %
Contract Period : 365 days
Construction Period : 406 days
Contract Time Lapsed : 111.23 %
Contract Period : 471days
Construction Period : 430 days
Contract Time Lapsed : 91.30 %
4. No. Description Actual % Schedule %
17 Culvert (Single 1500mm dia.) 100 % 80 %
18 Culvert (Single 1800mm dia.) 100 % 100 %
19 Culvert (Twin 1800mm dia.) 100 % 100 %
20 Reinforced Inlet/Outlet head wall and
wing wall & Apron to 1.8m RC Open
drain
0% 100 %
21 Reinforced Inlet/Outlet head wall and
wing wall & Apron to 2.0m RC Open
drain
38 % 100 %
22 Filling gap between the new and
existing culvert using granular material
100 % 89 %
23 Hacking & Recast the existing culvert 20 % 100 %
24 Reinstating back of existing road
pavement
70 % 0 %
25 Reinstating back of existing road
marking
20 % 0 %
26 Spot Turfing 0 % 0 %
27 Piling 40.18 % 100 %
28 Earth Drain 30 % 74 %
5. Catch Up Plan:
1. To complete 1.8m Wide R.C Drain
2. To complete the Sump Type 1B
3. To continue and complete Sump Type 3
4. To complete forming 2m base Earth Drain
6. Progress Photos (As of 20th July 2020)
Figure 1: Delivery of 225mm THK. Blockstone riprap in progress
7. Cont.
Figure 8: Site Investigation due to underground gas pipeline with PETRONAS &
PETROS in progress