What exactly is LUXproject?

   LUXproject is a distributed web-based project management system created on the basis of
    specific commercial and non-commercial modules developed by third-party vendors and
    open-source communities (Atlassian JIRA/GreenHopper, Atlassian Confluence, Atlassian
    FishEye, Subversion/Perforce, Cruise Control, WebDav etc.) as well as Luxoft modules.

   The System provides users with a friendly, multi-purpose environment for implementing key project tasks
    and ensuring communications.

   The main LUXproject users are project executors as well as the Customer. LUXproject supports role
    access, i.e. each project team member depending on his/her project role has certain access permissions to
    the System functional.

   LUXproject management mechanisms as well as availability of project artifacts at any time and from any
    geographic location allow company management to arrange transparent project management and always
    have current and reliable information.


   Currently, LUXproject allows to choose one of several methodologies for software development and
    maintenance projects, set up Project Management Office as well as deploy Service Desk.
LUXproject is all you need for

    Release/Iteration/Milestone scope planning and management
    Task management
    Risk management
    Communication management
    Metric gathering and statistic analysis
    Requirement gathering and management
    Requirements classification
    Requirement status management
    Requirement test coverage management
    Change management
    Test specification creation and management
    Defect Management
    Continuous Integration
    Version and non-version storage of project artifacts
    Project knowledge base
    Global search
    Flexible project reporting
Components and Architecture



                                                 Users                                                Users                       Administrator
                                                                                                                                                                                                 MS Project
                                                                                                                                                                                   SOAP      Tasks and milestones
                                                                                                                                                                                               synchronization
                               Web Container Apache Tomcat

                                                              Unified User Interface. Automatic logging of user activities in all components                                      Java-COM         MS Excel
                                                                                                                                                                                    Bridge   Timesheet and Reports
                                                                                                                                                                                                    export
                                                                                                                                          Web Access to
                                   Indexing and Search Service                              WebDAV File Management
                                                                                                                                           Source Code
                                          Apache Lucene                                          Apache Slide
                                                                                                                                             FishEye                                               MS Word
                                                                                                                                                                                 JMX          Documents import and
                                                                                                                                                                              Management            export

                LDAP                    Central                             Project Templates                        Reporting,                    Calendar and
                                     Administration                                Standard process                   Metrics,                       Planning                                      MS Outlook
                                                                                     Agile process
                                       /Security/                                        PMO                          History,                    MS Project integration                      Incoming mails storage
                                                                                                                                                     iCalendar std.
                                      OpenLDAP                                       Service Desk                    Statistics                                                   XML-RSS

       Single SignOn                                                                                                                                                                            Adobe Acrobat
                                                                                                                                                                                               Documents, Reports
                                                         Software Engineering Processes / LUXproject event-driven workflow engine
                                                                                                                                                                              Event Queue
                                  JIRA engine                 Confluence                                                                                   Interaction with
                                                                Wiki engine                Source Code            Continues                                                                      MS Share Point
                                  Management of                                                                                                           External Systems
                                                             Knowledge Base                 Repository           Integration                                                                   Cross content access
Implemented                        Requirements                                         Versioning, releases,                     Code Review
                                                                                                                                                          RFP/RFI Response
                                                                Text Search                                        / Build /                                  Subsystem,
                               Task, Resource, Time,                                        Peer review.
                               Risks, Milestones, Test
                                                           Document Versioning
                                                                                                                    Server          Crucible                MS Project, MS        RMI/IIOP
Enabled, need extra plug-ins                               Mail Indexing Service        Subversion, PerForce,
                                   Cases, Defects                                                               CruiseControl                             SharePoint, IDEA,
                                                           Document Templates                    etc                                                                                                Bugzilla
                                 Custom Workflows                                                                                                               Eclipse
                                                            Discussion Forum                                                                                                                 Automatic one-way data
                                                                                                                                                                                                 synchronization



                                                                                      Java Standard Edition 6.0
                                                                                                                                                                                              Rational Clear Quest
                                                                                                                                                                                              One-way data import




                                                                                                                                                                              4                                        4
Supported Platforms


    LUXproject supports 64bit operation systems, which ensures high performance and
     stability
    Linux Fedora core 12 i386 is recommended to be used for the LUXproject server
     deployment. The server can also be used under Windows, Solaris
    As there’s no thick client, LUXproject users can work with the System in any
     operation system

    Operation is guaranteed in browsers
      – Internet Explorer 8.x
      – FireFox 3.x

    The System works in browsers
      – Chrome
      – Safari




                                                                                       5
Key Components of the Third Parties


   JIRA 4.1.2
   GreenHopper 5.2.4
   Confluence 3.1.x
   FishEye 2.2.х
   SVN 1.6.5
   Cruise Control 2.8.3
   Crucible 2.2.1




                                      6
Role Access

                                                      Project
                                                      manager
    Flexible security policies
     for accessing LUXproject
    Access to LUXproject for              Customer
                                                                       Analysts
     all project
     stakeholders, both the
     project team and the
     customer team
    Access to LUXproject
     from all geographic points
     where Internet is                                               Developers team
     available

                            Support team

                                                      Testing team
Project template concept1

   Project template predefines a set of role settings, access permissions, information objects
    (including their attributes and workflow models), functional system
    modules, screens, reports, version control system, document templates and portal structure
    in compliance with a certain development methodology and the Customer requirements.
Project Template Concept2


The advantages of a project template:

   Opportunity to choose a configured management environment with all required
    components by one mouse-click
   Best practices from previous projects involvement
   Capability of tailoring project templates in accordance with particular project needs
   Capability of saving tailored templates for future projects

LUXproject includes several project templates:

   Project template for a traditional project which is based on RUP model with
    waterfall/iteration lifecycle (CMMI requirements support)
   Agile/SCRUM project template
   Project Management Office project template
   Support/Service Desk project template
Benefits for Customer


    Capability of profound project team involvement to facilitate higher manageability needed
     to meet ever-changing priorities and business goals
    Real- time access to project data from any geographic location, if Internet is available
    Transparent lifecycle – from business requirements to system ones, from system
     requirements through tasks to source code, requirement links to test cases and defects
    Visual representation of the reported data: flexible and easy visualization of product
     builds, project team data, and reports
    Customization of project environment to meet the Customer requirements
    Heightened project security
Program/PMO Report

   Representation of
    progress in terms of
    project milestones as
    well as releases
   Project statuses through
    color indication and % of
    completion
   Direct links to the key
    project milestones and
    releases
   Support of multi-release
    projects
   Export to Excel
Program/PMO Report for Agile Projects
    Representation of progress of
     LP-managed and manual
     Agile-projects:
      –   Project statuses through
          color indication in terms of
          quality, delivery, and last
          project info update
      –   % of work done and time
          spent
      –   Number of open/closed
          defects
    Direct links to home pages of
     LP-managed projects and to
     iteration data manual input
     forms of manual projects
    Capability to view project
     status charts showing the
     dynamics of project success
     parameters
Benefits for project manager


      Access to project data from any geographic location, if Internet is available
      Project data are represented in real-time mode
      Project activities planning and managing (via milestones/releases)
      Resource & Time Management: on-the-fly statistics for tracking the timeline of tasks
       in several projects simultaneously
      Ability to create tasks via email messages
      Risk management
      Release/build management
                Generate Roadmap, Release Notes
                Control Build status
      Ability to keep project mail within the System and make references to it
      Ability to archive completed projects and activate them back if needed
      Ability to customize a project to your needs and add new functions by yourself
Unique Reports Creation
   LUXproject allows project members
    to create unique reports according
    to their needs

   When creating reports you can use
    requests with specific fields of the
    System entities, which greatly
    extends standard Jira functional
Milestone Management

    From the Milestones screen
     Project Manager can:
       – Control statuses of
          project milestones
       – View tasks related to
          milestones
       – Navigate to View
          Issue Details screen of
          each task included in
          a milestone
       – Create new milestones
          and link them to tasks
          and other system
          entities
    Project milestones and
     tasks can be synchronized
     with Microsoft Project
Task Management

   Project planning and
    control: create
    tasks, assign them and
    monitor their statuses
   Representation of
    different task statuses
    and tasks by status
    graphic statistics
   Monitoring task
    deadlines
   Auto-notification
    subsystem and events
    calendar
Task Creation via Email

    Project Manager can create tasks in
     LUXproject by sending a task
     description email with project
     address specified in СС
      –   The task will be assigned to the
          email addressee automatically
      –   The task name will be created on
          the basis of the email subject
      –   The task description will be created
          on the basis of the email body
      –   Email attachment will also be
          included in the task in LUXproject
    Upon receipt of such email, the
     Assignee can log in LUXproject and
     start working with the task – change
     its status, comment on it, add
     artifacts as soon as they are created
MS Project Integration

   Bidirectional data exchange between MS Project and LUXproject (Jira) via plugin
    THE-Connector
     – Downloading planned tasks and milestones from MS Project to Jira
     – Importing tasks from Jira to MS Project
     – Synchronizing status and time information
Workplan Plugin
   Capability to set work start
    date, utilization % of a
    user, and work estimate
   Capability to view the
    workload of:
     – a user
     – users within a certain
         project
     – a specific JIRA group
     – users of a specific
         resource project in all
         projects
   Capability to plan
    resources and activities for
    future
Risk Management


   Log of risks for their
    estimation and
    description
    Automatic calculation
    of the next date of risk
    monitoring
   Different status tables
    (triggered, active
    risks, closed risks) and
    graphic statistics
    diagram.
   Links between risks and
    project artifacts
Project Events Report

   Report on the events
    registered in all System
    components
   Filter for:
     – Who?
     – When?
     – In which project?
   Filter for project events:
     – Project item updates
         (tasks, risks, require
         ments, defects etc.)
     – File updates
     – Page updates
     – Builds
Benefits for Analyst


   Centralized requirements repository
   Easy to use tool to manage requirements - assign, review, approve, control the requirements
    online
   Ability to notify all project teams about changes in requirements
   Requirements traceability: from business requirements to functional requirements, from
    requirements through tasks to source code and defects
   Ability to review requirements
   Graphic representation of requirements statistics
Requirements Management1

   Requirements gathering
    and management: their
    creation, assignment, con
    trol
   Requirements grouping by
    statuses and graphic
    representation of status
    statistics
   Requirements Traceability
   Automatic tracking of
    changes in linked
    requirements
Requirement Management2

   Requirements list
    can be displayed as
    a tree structure
   Requirement
    description can be
    represented as a
    wiki-page
   Requirements and
    change requests
    can be created and
    managed via Jira
    +WIKI or Jira +
    SVN
Requirements Traceability
Links Tree

   Links hierarchy is
    represented as a tree or a
    list
   Links between different
    functional elements
    (requirements, tasks, defe
    cts)
   Interactive “leaves” drilled
    down to Jira element
Requirements Traceability –
Matrix
   Ability to link requirements to
    other dependent artifacts of
    this as well as a related
    project
   Visualization of dependencies
    and their types
   Links Coverage Matrix allows
    to visualize requirements
    coverage by other artifacts
    such as test cases
   Identification of suspected
    dependencies to define which
    requirements need to be
    reviewed and confirmed to
    relevant
   Color indication of
    dependency types
Benefits for Developers


     It’s obvious which tasks are to be performed and when it should be done
     All documents and requirements needed to perform a task are linked to the assigned task
     Extended functional for release/build management
     Build management in Cruise Control right from LUXproject interface
     Build reports in real-time mode
     Ability to work with version control repository without installing a specific client
     Ability to link source code with tasks and defects from Jira
     Ability to share experience or find the needed answer in the project knowledge base
Release Management

   Creation of release
    and build
    entities, linking project
    activities to them
   Support of hierarchic
    structure of releases
    and builds
   Attributes of important
    life cycle dates of
    releases and builds
   Control of release and
    build implementation
Build Management

   Setting up Continuous
    Integration
    parameters
    (Continuous
    integration - Cruise
    Control)
   Build status online
   Results of automatic
    unit tests
   Errors/Warnings
   Ability to download
    delivery package
   Build/Release notes
Source Code Management

   Web-access to the
    project version
    control repository via
    FishEye
   Flexible filter settings
   Changelog (including
    a mechanism for
    comparing
    differences)
   Diagram of code size
    variation
   Content Search by
    directories, commit
    comments, files, file
    names
Source Code Management
    Integration with Crucible
    Capability to arrange
     code review:
       – create review card
       – select source code
           files for review
       – define review
           participants and
           due dates
    Ability to add comments
     to source code
     lines, reviewed
     file, review in general
    Track reviews status
     and statistics
    Reviews Search
Benefits for Test Team

     Test Assignment creation:
       − Assigning test cases that need to be performed
       − Assigning defects for validation
     Testing reports
     Ability to:
       − create a wiki-page with test plan description and link it to test cases
       − access requirements quickly
       − access the centralized document storage and version control repository
       − view the current build status
       − access defect statistics
      Ability to link defects to other project entities
      Ability to control requirements coverage by test cases
Test Management

   Test cases creation
   Control of test
    assignments
    implementation
   Linking defects to
    requirements, tasks, and
    test cases
   Test cases results report
   Statistics reports on
    testing
Test Manager Workplace

   Ability to analyze and
    predict release quality
   Information on testing
    progress, test case
    creation, defect
    statistics is available to
    Test Manager in a
    convenient form
   More than 20 metric
    reports on testing
   Ability to export reports
    to Excel, PDF, charts to
    graphics format
Test Manager Workplace
sample test reports
Test Manager Workplace
sample test assignment reports
Communication Management

   Project news line
   Forum to discuss
    project issues
   Project
    correspondence
    storage
Files Sharing
Non-version File Storage
   Possibility to share files within project team:
     – upload files
     – view files
     – manage files and folders
Time Tracking

   Time spent on each
    project activity
   Different time tracking
    reports
Time Tracking
SLASupport Report

   Capability to view the work
    time the issues spend in
    each of their statuses
    within the specified period
   Capability to see
    bottlenecks in the lifecycle
    of issues and stick to the
    SLA terms
Business Processes Visualization


   Ability to run an eye over a
    process workflow
   Visualization of workflow
    transitions of a certain
    issue
   Visualization of the latest
    changes history
Global Search


    Search through all
     components and
     modules of system
    Filter for detailed
     search by
     date, user, project
     etc.
                           Results of search in
                           project portal pages

                                 Results of search in
                                         Jira

                                         Results of search in
                                            file storage

                                   Results of search in
                                     version control
                                       repository
System Administration Console


   Manage project
    roles and team
    members
   Manage
    security
   Manage
    workflows,
    attributes, etc.
   Manage
    components
    (SVN, Cruise
    Control, etc.)
   Project
    configuration
    export
Localization Capabilities
   Bilingual menu system
      – Русский
      – English
   Availability of English and
    Russian project templates
   Ability to select GUI
    language for each user
   User and Administrator
    documentation in Russian
    and English
Agile Project Template

    Task management
      – Product backlog
      – Iteration backlog
      – Personal backlog
    Release and build
     management
    Risk management;
    Defect management;
    Communication
     management (Scrum
     and retrospective
     meetings);
    Configuration
     management
    Project Status Charts
Agile Project Template
    Additional tools - GreenHopper


    GreenHopper is a
     plugin for Jira that
     allows to manage
     Agile projects
      – Backlog
          management
      – Sprint and release
          planning
      – Whiteboard
          metaphora
      – Easy work with
          cards of Jira
          entities
      – Editing entities
          within their cards
          as well as editing
          entities in bulk
Agile Project Template
    GreenHopper Task Board

    Task Board displays
     tasks according to their
     statuses in a convenient
     form:
       – Cards
       – List
       – Minimized cards, as
           a full list of tasks
       – Color indication
       – Flexible filters
    It is possible to combine
     saved filters with
     custom criteria to
     display only the needed
     issues
    It is possible to drag-
     and-drop cards from
     column to column in
     order to change task
     status
    Kanban Support
Agile Project Template
    GreenHopper Burndown chart


    Burndown chart shows
     current dynamics of tasks
     implementation and
     allows to predict the time
     when activities will be
     finished
Agile Project Template
    GreenHopper Cumulative Flow chart


    Cumulative Flow chart
     allows to track cumulative
     change of work in
     progress by statuses and
     can be useful for
     identifying bottlenecks.
Project Knowledge Base

   News
   Tag cloud
   Quick Search
   Ability to import Word documents to
    wiki-pages
   Voting ability (with capability to view
    the voters list, their votes being
    anonymous )

   Useful capabilities
     – Confluence-SharePoint search is
         a great example of LUXproject
         integration with other
         knowledge management
         systems
     – Confluence Watch list helps
         Confluence administrators
         manage a list of watchers on
         any wiki-page of the knowledge
         base
Project Knowledge Base
Labels Groups Plugin

   Possibility to organize
    labels into groups
   Capability to use the
    predefined list of labels
    groups (page passport)
    to quickly label your
    WIKI content
   Capability to use page
    passport to search Wiki
    pages by labels
Project Knowledge Base
    Labels Groups Plugin. Navigation Macros

    Possibility to predefine search by particular label AND label group




   Possibility to use navigation table to quickly
    search by predefined label AND label group
Help Desk Project Template
   Requests creation
   Log of request statuses
   Graphic representation
    of request resolution
    statistics
   Report on efforts spent
    on requests
    implementation
   Knowledge base for each
    project
   Ability to link requests to
    activities of other
    projects
Benefits Summary

    Atlassian components used in LUXproject enjoy world-wide recognition due to diverse
     functional, supportability, scalability and reliability at a relatively modest price per user
    The LUXproject platform integrates all components into one environment, which
     increases capabilities of the components, and provides missing functions:
      –   Common interface and single sign on to all System components
      –   Flexible security policies customized for each project member
      –   Additional functional for risk management, test management, release
          management, requirements management
      –   Extended capabilities for reports creation as well as ready-made reports
      –   Quick search of the needed information in all System components
      –   Localization capabilities
      –   Ability to group projects into programs and monitor their statuses
      –   High level of data security
    Unique project templates developed on the basis of the best Luxoft practices and
     methodologies
    Extended capabilities of System customization in compliance with unique Customer
     processes
    Continuous System development and ability to add specific functions upon request
    Diverse functional at a modest price
LUXproject Implementation Models

LUXproject basic implementation is recommended when:
   The Customer wants to use the best practices and processes of the Luxoft company and
    chooses one or several standard project templates:
     –   Standard
     –   Agile
     –   PMO
     –   HelpDesk


   The Customer does not have similar systems that must be integrated and/or a system to
    migrate data from.


LUXproject enhanced implementation with future System customization in
  compliance with Customer’s specifics and/or data migration:
   The Customer considers his software development process to be mature and/or unique and
    wants the existing template to be customized or a new project template to be developed.
   The Customer has a different tracking system (for example, JIRA, ClearQuest, Bugzilla) and
    wants to save the historical data.
Server Requirements for LUXproject
Installation

   System requirements (up to 100 users)
     – CPU 1 x Dual Core XEON from 2.33GHz (server edition with х64 support)
     – RAM 4 GB FBD 667MHz Memory
     – ROM 100GB, SAS/SCSI, 15.000/10.000 rpm Hard Drive (2 in RAID1)
     – RAID Controller (RAID 1)
     – NIC 1x Gb NIC
     – Drive 8X DVD Drive
   System requirements (up to 500 users)
     – CPU 1 x Quad Core XEON from 2.33GHz (server edition with х64 support)
     – RAM 8 GB FBD 667MHz Memory
     – ROM 160GB, SAS/SCSI, 15.000/10.000 rpm Hard Drive (2 in RAID1)
     – RAID Controller (RAID 1)
     – NIC 1x Gb NIC
     – Drive 8X DVD Drive

   Operation system requirements
     – Linux Fedora core 11 64bit
   Data base requirements
     – MySQL 5


   Current configuration of the LUXproject production server in Luxoft
     – CPU 4x Phenom™ II 955, Memory 8GB, 2x200Gb HDD Raid1

                                                                               56
Thanks !




                Contacts:
           LUXproject@luxoft.com

LUXproject functionality overview

  • 1.
    LUXproject functionality overview R11.6 Luxoft September, 20th, 2011
  • 2.
    What exactly isLUXproject?  LUXproject is a distributed web-based project management system created on the basis of specific commercial and non-commercial modules developed by third-party vendors and open-source communities (Atlassian JIRA/GreenHopper, Atlassian Confluence, Atlassian FishEye, Subversion/Perforce, Cruise Control, WebDav etc.) as well as Luxoft modules.  The System provides users with a friendly, multi-purpose environment for implementing key project tasks and ensuring communications.  The main LUXproject users are project executors as well as the Customer. LUXproject supports role access, i.e. each project team member depending on his/her project role has certain access permissions to the System functional.  LUXproject management mechanisms as well as availability of project artifacts at any time and from any geographic location allow company management to arrange transparent project management and always have current and reliable information.  Currently, LUXproject allows to choose one of several methodologies for software development and maintenance projects, set up Project Management Office as well as deploy Service Desk.
  • 3.
    LUXproject is allyou need for  Release/Iteration/Milestone scope planning and management  Task management  Risk management  Communication management  Metric gathering and statistic analysis  Requirement gathering and management  Requirements classification  Requirement status management  Requirement test coverage management  Change management  Test specification creation and management  Defect Management  Continuous Integration  Version and non-version storage of project artifacts  Project knowledge base  Global search  Flexible project reporting
  • 4.
    Components and Architecture Users Users Administrator MS Project SOAP Tasks and milestones synchronization Web Container Apache Tomcat Unified User Interface. Automatic logging of user activities in all components Java-COM MS Excel Bridge Timesheet and Reports export Web Access to Indexing and Search Service WebDAV File Management Source Code Apache Lucene Apache Slide FishEye MS Word JMX Documents import and Management export LDAP Central Project Templates Reporting, Calendar and Administration Standard process Metrics, Planning MS Outlook Agile process /Security/ PMO History, MS Project integration Incoming mails storage iCalendar std. OpenLDAP Service Desk Statistics XML-RSS Single SignOn Adobe Acrobat Documents, Reports Software Engineering Processes / LUXproject event-driven workflow engine Event Queue JIRA engine Confluence Interaction with Wiki engine Source Code Continues MS Share Point Management of External Systems Knowledge Base Repository Integration Cross content access Implemented Requirements Versioning, releases, Code Review RFP/RFI Response Text Search / Build / Subsystem, Task, Resource, Time, Peer review. Risks, Milestones, Test Document Versioning Server Crucible MS Project, MS RMI/IIOP Enabled, need extra plug-ins Mail Indexing Service Subversion, PerForce, Cases, Defects CruiseControl SharePoint, IDEA, Document Templates etc Bugzilla Custom Workflows Eclipse Discussion Forum Automatic one-way data synchronization Java Standard Edition 6.0 Rational Clear Quest One-way data import 4 4
  • 5.
    Supported Platforms  LUXproject supports 64bit operation systems, which ensures high performance and stability  Linux Fedora core 12 i386 is recommended to be used for the LUXproject server deployment. The server can also be used under Windows, Solaris  As there’s no thick client, LUXproject users can work with the System in any operation system  Operation is guaranteed in browsers – Internet Explorer 8.x – FireFox 3.x  The System works in browsers – Chrome – Safari 5
  • 6.
    Key Components ofthe Third Parties  JIRA 4.1.2  GreenHopper 5.2.4  Confluence 3.1.x  FishEye 2.2.х  SVN 1.6.5  Cruise Control 2.8.3  Crucible 2.2.1 6
  • 7.
    Role Access Project manager  Flexible security policies for accessing LUXproject  Access to LUXproject for Customer Analysts all project stakeholders, both the project team and the customer team  Access to LUXproject from all geographic points where Internet is Developers team available Support team Testing team
  • 8.
    Project template concept1  Project template predefines a set of role settings, access permissions, information objects (including their attributes and workflow models), functional system modules, screens, reports, version control system, document templates and portal structure in compliance with a certain development methodology and the Customer requirements.
  • 9.
    Project Template Concept2 Theadvantages of a project template:  Opportunity to choose a configured management environment with all required components by one mouse-click  Best practices from previous projects involvement  Capability of tailoring project templates in accordance with particular project needs  Capability of saving tailored templates for future projects LUXproject includes several project templates:  Project template for a traditional project which is based on RUP model with waterfall/iteration lifecycle (CMMI requirements support)  Agile/SCRUM project template  Project Management Office project template  Support/Service Desk project template
  • 10.
    Benefits for Customer  Capability of profound project team involvement to facilitate higher manageability needed to meet ever-changing priorities and business goals  Real- time access to project data from any geographic location, if Internet is available  Transparent lifecycle – from business requirements to system ones, from system requirements through tasks to source code, requirement links to test cases and defects  Visual representation of the reported data: flexible and easy visualization of product builds, project team data, and reports  Customization of project environment to meet the Customer requirements  Heightened project security
  • 11.
    Program/PMO Report  Representation of progress in terms of project milestones as well as releases  Project statuses through color indication and % of completion  Direct links to the key project milestones and releases  Support of multi-release projects  Export to Excel
  • 12.
    Program/PMO Report forAgile Projects  Representation of progress of LP-managed and manual Agile-projects: – Project statuses through color indication in terms of quality, delivery, and last project info update – % of work done and time spent – Number of open/closed defects  Direct links to home pages of LP-managed projects and to iteration data manual input forms of manual projects  Capability to view project status charts showing the dynamics of project success parameters
  • 13.
    Benefits for projectmanager  Access to project data from any geographic location, if Internet is available  Project data are represented in real-time mode  Project activities planning and managing (via milestones/releases)  Resource & Time Management: on-the-fly statistics for tracking the timeline of tasks in several projects simultaneously  Ability to create tasks via email messages  Risk management  Release/build management  Generate Roadmap, Release Notes  Control Build status  Ability to keep project mail within the System and make references to it  Ability to archive completed projects and activate them back if needed  Ability to customize a project to your needs and add new functions by yourself
  • 14.
    Unique Reports Creation  LUXproject allows project members to create unique reports according to their needs  When creating reports you can use requests with specific fields of the System entities, which greatly extends standard Jira functional
  • 15.
    Milestone Management  From the Milestones screen Project Manager can: – Control statuses of project milestones – View tasks related to milestones – Navigate to View Issue Details screen of each task included in a milestone – Create new milestones and link them to tasks and other system entities  Project milestones and tasks can be synchronized with Microsoft Project
  • 16.
    Task Management  Project planning and control: create tasks, assign them and monitor their statuses  Representation of different task statuses and tasks by status graphic statistics  Monitoring task deadlines  Auto-notification subsystem and events calendar
  • 17.
    Task Creation viaEmail  Project Manager can create tasks in LUXproject by sending a task description email with project address specified in СС – The task will be assigned to the email addressee automatically – The task name will be created on the basis of the email subject – The task description will be created on the basis of the email body – Email attachment will also be included in the task in LUXproject  Upon receipt of such email, the Assignee can log in LUXproject and start working with the task – change its status, comment on it, add artifacts as soon as they are created
  • 18.
    MS Project Integration  Bidirectional data exchange between MS Project and LUXproject (Jira) via plugin THE-Connector – Downloading planned tasks and milestones from MS Project to Jira – Importing tasks from Jira to MS Project – Synchronizing status and time information
  • 19.
    Workplan Plugin  Capability to set work start date, utilization % of a user, and work estimate  Capability to view the workload of: – a user – users within a certain project – a specific JIRA group – users of a specific resource project in all projects  Capability to plan resources and activities for future
  • 20.
    Risk Management  Log of risks for their estimation and description  Automatic calculation of the next date of risk monitoring  Different status tables (triggered, active risks, closed risks) and graphic statistics diagram.  Links between risks and project artifacts
  • 21.
    Project Events Report  Report on the events registered in all System components  Filter for: – Who? – When? – In which project?  Filter for project events: – Project item updates (tasks, risks, require ments, defects etc.) – File updates – Page updates – Builds
  • 22.
    Benefits for Analyst  Centralized requirements repository  Easy to use tool to manage requirements - assign, review, approve, control the requirements online  Ability to notify all project teams about changes in requirements  Requirements traceability: from business requirements to functional requirements, from requirements through tasks to source code and defects  Ability to review requirements  Graphic representation of requirements statistics
  • 23.
    Requirements Management1  Requirements gathering and management: their creation, assignment, con trol  Requirements grouping by statuses and graphic representation of status statistics  Requirements Traceability  Automatic tracking of changes in linked requirements
  • 24.
    Requirement Management2  Requirements list can be displayed as a tree structure  Requirement description can be represented as a wiki-page  Requirements and change requests can be created and managed via Jira +WIKI or Jira + SVN
  • 25.
    Requirements Traceability Links Tree  Links hierarchy is represented as a tree or a list  Links between different functional elements (requirements, tasks, defe cts)  Interactive “leaves” drilled down to Jira element
  • 26.
    Requirements Traceability – Matrix  Ability to link requirements to other dependent artifacts of this as well as a related project  Visualization of dependencies and their types  Links Coverage Matrix allows to visualize requirements coverage by other artifacts such as test cases  Identification of suspected dependencies to define which requirements need to be reviewed and confirmed to relevant  Color indication of dependency types
  • 27.
    Benefits for Developers  It’s obvious which tasks are to be performed and when it should be done  All documents and requirements needed to perform a task are linked to the assigned task  Extended functional for release/build management  Build management in Cruise Control right from LUXproject interface  Build reports in real-time mode  Ability to work with version control repository without installing a specific client  Ability to link source code with tasks and defects from Jira  Ability to share experience or find the needed answer in the project knowledge base
  • 28.
    Release Management  Creation of release and build entities, linking project activities to them  Support of hierarchic structure of releases and builds  Attributes of important life cycle dates of releases and builds  Control of release and build implementation
  • 29.
    Build Management  Setting up Continuous Integration parameters (Continuous integration - Cruise Control)  Build status online  Results of automatic unit tests  Errors/Warnings  Ability to download delivery package  Build/Release notes
  • 30.
    Source Code Management  Web-access to the project version control repository via FishEye  Flexible filter settings  Changelog (including a mechanism for comparing differences)  Diagram of code size variation  Content Search by directories, commit comments, files, file names
  • 31.
    Source Code Management Integration with Crucible  Capability to arrange code review: – create review card – select source code files for review – define review participants and due dates  Ability to add comments to source code lines, reviewed file, review in general  Track reviews status and statistics  Reviews Search
  • 32.
    Benefits for TestTeam  Test Assignment creation: − Assigning test cases that need to be performed − Assigning defects for validation  Testing reports  Ability to: − create a wiki-page with test plan description and link it to test cases − access requirements quickly − access the centralized document storage and version control repository − view the current build status − access defect statistics  Ability to link defects to other project entities  Ability to control requirements coverage by test cases
  • 33.
    Test Management  Test cases creation  Control of test assignments implementation  Linking defects to requirements, tasks, and test cases  Test cases results report  Statistics reports on testing
  • 34.
    Test Manager Workplace  Ability to analyze and predict release quality  Information on testing progress, test case creation, defect statistics is available to Test Manager in a convenient form  More than 20 metric reports on testing  Ability to export reports to Excel, PDF, charts to graphics format
  • 35.
  • 36.
    Test Manager Workplace sampletest assignment reports
  • 37.
    Communication Management  Project news line  Forum to discuss project issues  Project correspondence storage
  • 38.
    Files Sharing Non-version FileStorage  Possibility to share files within project team: – upload files – view files – manage files and folders
  • 39.
    Time Tracking  Time spent on each project activity  Different time tracking reports
  • 40.
    Time Tracking SLASupport Report  Capability to view the work time the issues spend in each of their statuses within the specified period  Capability to see bottlenecks in the lifecycle of issues and stick to the SLA terms
  • 41.
    Business Processes Visualization  Ability to run an eye over a process workflow  Visualization of workflow transitions of a certain issue  Visualization of the latest changes history
  • 42.
    Global Search  Search through all components and modules of system  Filter for detailed search by date, user, project etc. Results of search in project portal pages Results of search in Jira Results of search in file storage Results of search in version control repository
  • 43.
    System Administration Console  Manage project roles and team members  Manage security  Manage workflows, attributes, etc.  Manage components (SVN, Cruise Control, etc.)  Project configuration export
  • 44.
    Localization Capabilities  Bilingual menu system – Русский – English  Availability of English and Russian project templates  Ability to select GUI language for each user  User and Administrator documentation in Russian and English
  • 45.
    Agile Project Template  Task management – Product backlog – Iteration backlog – Personal backlog  Release and build management  Risk management;  Defect management;  Communication management (Scrum and retrospective meetings);  Configuration management  Project Status Charts
  • 46.
    Agile Project Template Additional tools - GreenHopper  GreenHopper is a plugin for Jira that allows to manage Agile projects – Backlog management – Sprint and release planning – Whiteboard metaphora – Easy work with cards of Jira entities – Editing entities within their cards as well as editing entities in bulk
  • 47.
    Agile Project Template GreenHopper Task Board  Task Board displays tasks according to their statuses in a convenient form: – Cards – List – Minimized cards, as a full list of tasks – Color indication – Flexible filters  It is possible to combine saved filters with custom criteria to display only the needed issues  It is possible to drag- and-drop cards from column to column in order to change task status  Kanban Support
  • 48.
    Agile Project Template GreenHopper Burndown chart  Burndown chart shows current dynamics of tasks implementation and allows to predict the time when activities will be finished
  • 49.
    Agile Project Template GreenHopper Cumulative Flow chart  Cumulative Flow chart allows to track cumulative change of work in progress by statuses and can be useful for identifying bottlenecks.
  • 50.
    Project Knowledge Base  News  Tag cloud  Quick Search  Ability to import Word documents to wiki-pages  Voting ability (with capability to view the voters list, their votes being anonymous )  Useful capabilities – Confluence-SharePoint search is a great example of LUXproject integration with other knowledge management systems – Confluence Watch list helps Confluence administrators manage a list of watchers on any wiki-page of the knowledge base
  • 51.
    Project Knowledge Base LabelsGroups Plugin  Possibility to organize labels into groups  Capability to use the predefined list of labels groups (page passport) to quickly label your WIKI content  Capability to use page passport to search Wiki pages by labels
  • 52.
    Project Knowledge Base Labels Groups Plugin. Navigation Macros  Possibility to predefine search by particular label AND label group  Possibility to use navigation table to quickly search by predefined label AND label group
  • 53.
    Help Desk ProjectTemplate  Requests creation  Log of request statuses  Graphic representation of request resolution statistics  Report on efforts spent on requests implementation  Knowledge base for each project  Ability to link requests to activities of other projects
  • 54.
    Benefits Summary  Atlassian components used in LUXproject enjoy world-wide recognition due to diverse functional, supportability, scalability and reliability at a relatively modest price per user  The LUXproject platform integrates all components into one environment, which increases capabilities of the components, and provides missing functions: – Common interface and single sign on to all System components – Flexible security policies customized for each project member – Additional functional for risk management, test management, release management, requirements management – Extended capabilities for reports creation as well as ready-made reports – Quick search of the needed information in all System components – Localization capabilities – Ability to group projects into programs and monitor their statuses – High level of data security  Unique project templates developed on the basis of the best Luxoft practices and methodologies  Extended capabilities of System customization in compliance with unique Customer processes  Continuous System development and ability to add specific functions upon request  Diverse functional at a modest price
  • 55.
    LUXproject Implementation Models LUXprojectbasic implementation is recommended when:  The Customer wants to use the best practices and processes of the Luxoft company and chooses one or several standard project templates: – Standard – Agile – PMO – HelpDesk  The Customer does not have similar systems that must be integrated and/or a system to migrate data from. LUXproject enhanced implementation with future System customization in compliance with Customer’s specifics and/or data migration:  The Customer considers his software development process to be mature and/or unique and wants the existing template to be customized or a new project template to be developed.  The Customer has a different tracking system (for example, JIRA, ClearQuest, Bugzilla) and wants to save the historical data.
  • 56.
    Server Requirements forLUXproject Installation  System requirements (up to 100 users) – CPU 1 x Dual Core XEON from 2.33GHz (server edition with х64 support) – RAM 4 GB FBD 667MHz Memory – ROM 100GB, SAS/SCSI, 15.000/10.000 rpm Hard Drive (2 in RAID1) – RAID Controller (RAID 1) – NIC 1x Gb NIC – Drive 8X DVD Drive  System requirements (up to 500 users) – CPU 1 x Quad Core XEON from 2.33GHz (server edition with х64 support) – RAM 8 GB FBD 667MHz Memory – ROM 160GB, SAS/SCSI, 15.000/10.000 rpm Hard Drive (2 in RAID1) – RAID Controller (RAID 1) – NIC 1x Gb NIC – Drive 8X DVD Drive  Operation system requirements – Linux Fedora core 11 64bit  Data base requirements – MySQL 5  Current configuration of the LUXproject production server in Luxoft – CPU 4x Phenom™ II 955, Memory 8GB, 2x200Gb HDD Raid1 56
  • 57.
    Thanks ! Contacts: LUXproject@luxoft.com