The document provides information on forward-looking statements and disclaimers related to Lundin Gold's Fruta del Norte gold project in Ecuador. It notes that forward-looking statements involve inherent risks and uncertainties that could cause actual results to differ materially. The technical information is based on a 2016 technical report and was reviewed by qualified persons. Unless otherwise indicated, all dollar values are in US dollars.
The document discusses forward-looking statements and information regarding Lundin Gold's Fruta del Norte gold project in Ecuador. It summarizes that project funding is substantially complete, underground mine development is on track, and process plant construction is well underway. The first gold from the project is expected in Q4 2019.
The document provides an overview of Lundin Gold Inc., including forward-looking statements and disclaimers. It summarizes Lundin Gold's Fruta del Norte gold project in Ecuador, which is expected to begin production in late 2019. The project has over 4 million ounces of gold reserves and is projected to produce over 300,000 ounces annually at attractive costs. Lundin Gold also discusses the project's status, financing package, management team, and commitments to sustainability.
The document provides an overview and update of the Fruta del Norte gold mining project in Ecuador. It summarizes that the project remains on schedule and budget with first gold production expected in Q4 2019. Underground mine development has advanced over 3.3 km to date. The project has received necessary permits and financing and construction is 34% complete. An update to the project estimate found opportunities to lower costs while increasing production over the 15 year mine life.
The document discusses Lundin Gold's Fruta del Norte gold project in Ecuador. It states that project funding is substantially complete based on current estimates. Construction is underway on plant facilities and infrastructure, with first gold expected in Q4 2019. The document also summarizes Lundin Gold's capital structure, exploration plans for additional resources along the mineralized trend, and highlights of the Fruta del Norte project including mine life, annual production estimates, and high gold grades.
- The corporate presentation provides an overview of Lundin Gold's Fruta del Norte gold mine in Ecuador, highlighting its first half 2020 results, second half 2020 outlook, and future growth potential.
- Operations were temporarily suspended in March 2020 due to COVID-19 but restarted in July 2020. Gold production for 2020 is estimated to be 200,000-220,000 ounces.
- Lundin Gold is evaluating opportunities to increase throughput at the mine and mill to 4,000-4,500 tonnes per day by 2021.
- Exploration drilling is planned at the high priority Barbasco target later in 2020 to test for extensions of the Fruta del Norte deposit.
- Lundin Gold has restarted operations at its Fruta del Norte gold mine in Ecuador after a three month suspension due to COVID-19.
- Production is expected to be between 200,000-220,000 ounces of gold for 2020 as the mine ramps up over the next three months.
- Strict COVID-19 protocols are in place to protect workers, including quarantines, testing, physical distancing, and increased sanitization.
- Lundin Gold has restarted operations at its Fruta del Norte gold mine in Ecuador after a three month suspension due to COVID-19.
- Production is expected to be between 200,000-220,000 ounces of gold for 2020 as the mine ramps up over the next three months.
- Strict COVID-19 protocols are in place to protect workers, including quarantines, testing, physical distancing, and increased sanitization.
The document discusses forward-looking statements and information regarding Lundin Gold's Fruta del Norte gold project in Ecuador. It summarizes that project funding is substantially complete, underground mine development is on track, and process plant construction is well underway. The first gold from the project is expected in Q4 2019.
The document provides an overview of Lundin Gold Inc., including forward-looking statements and disclaimers. It summarizes Lundin Gold's Fruta del Norte gold project in Ecuador, which is expected to begin production in late 2019. The project has over 4 million ounces of gold reserves and is projected to produce over 300,000 ounces annually at attractive costs. Lundin Gold also discusses the project's status, financing package, management team, and commitments to sustainability.
The document provides an overview and update of the Fruta del Norte gold mining project in Ecuador. It summarizes that the project remains on schedule and budget with first gold production expected in Q4 2019. Underground mine development has advanced over 3.3 km to date. The project has received necessary permits and financing and construction is 34% complete. An update to the project estimate found opportunities to lower costs while increasing production over the 15 year mine life.
The document discusses Lundin Gold's Fruta del Norte gold project in Ecuador. It states that project funding is substantially complete based on current estimates. Construction is underway on plant facilities and infrastructure, with first gold expected in Q4 2019. The document also summarizes Lundin Gold's capital structure, exploration plans for additional resources along the mineralized trend, and highlights of the Fruta del Norte project including mine life, annual production estimates, and high gold grades.
- The corporate presentation provides an overview of Lundin Gold's Fruta del Norte gold mine in Ecuador, highlighting its first half 2020 results, second half 2020 outlook, and future growth potential.
- Operations were temporarily suspended in March 2020 due to COVID-19 but restarted in July 2020. Gold production for 2020 is estimated to be 200,000-220,000 ounces.
- Lundin Gold is evaluating opportunities to increase throughput at the mine and mill to 4,000-4,500 tonnes per day by 2021.
- Exploration drilling is planned at the high priority Barbasco target later in 2020 to test for extensions of the Fruta del Norte deposit.
- Lundin Gold has restarted operations at its Fruta del Norte gold mine in Ecuador after a three month suspension due to COVID-19.
- Production is expected to be between 200,000-220,000 ounces of gold for 2020 as the mine ramps up over the next three months.
- Strict COVID-19 protocols are in place to protect workers, including quarantines, testing, physical distancing, and increased sanitization.
- Lundin Gold has restarted operations at its Fruta del Norte gold mine in Ecuador after a three month suspension due to COVID-19.
- Production is expected to be between 200,000-220,000 ounces of gold for 2020 as the mine ramps up over the next three months.
- Strict COVID-19 protocols are in place to protect workers, including quarantines, testing, physical distancing, and increased sanitization.
This document provides an overview of the Fruta del Norte Gold Project in Ecuador. It summarizes that first gold production is expected in Q4 2019, with the project being fully funded and 82% construction complete. It also notes that the project is located within a major under-explored mineralized trend, presenting exploration upside potential.
- Lundin Gold restarted operations at its Fruta del Norte gold mine in Ecuador in July 2020 after a three month suspension due to COVID-19.
- Production guidance for 2020 is 200,000-220,000 ounces of gold with cash costs of $715-780 per ounce and all-in sustaining costs of $770-850 per ounce.
- The mill is currently running at near design throughput and the mine is ramping up over the next three months. Lundin Gold also has a strong financial position.
Calibre Mining Corp is a gold producer with multi-asset production and exploration opportunities in Nicaragua. It operates the Libertad and Limon processing hubs and mining spokes including Pavon Norte, which was brought into production in under 18 months. Calibre aims to grow production organically through near-mill discoveries and expanding emerging districts like Eastern Borosi, which currently hosts an inferred resource of 700,000 ounces of gold. Exploration is ongoing across Calibre's land package of over 2,000 square kilometers to discover new resources that can be fed into the surplus processing capacity at Libertad.
This document is a corporate presentation from SSR Mining Inc. that contains forward-looking statements regarding future production, costs, exploration and development plans. It cautions readers that actual results may differ due to risks and uncertainties. It also provides qualifications for the scientific and technical information presented.
This document provides an overview of Lundin Gold's Fruta del Norte gold project in Ecuador. It summarizes that first gold production is expected in Q4 2019 and commercial production in 2020. The mine has probable reserves of 5 million ounces of gold at an average grade of 8.74 g/t. The project is fully funded with construction 65% complete. Exploration potential is also discussed, with high priority targets identified within the underexplored Suarez pull-apart basin structure.
The document discusses Goldquest Corp's Romero gold-copper project in the Dominican Republic. It highlights results from a 2016 pre-feasibility study that showed the project has an after-tax NPV of $203 million and IRR of 28% at $1,300/oz gold price. The study outlined probable mineral reserves of 7 million tonnes grading 3.72 g/t gold and 0.88% copper containing 1.12 million ounces of gold equivalent. The project is planned as an underground mine producing over 100,000 ounces of gold equivalent annually at average all-in sustaining costs of $595/oz over a 7 year mine life. Goldquest also discusses exploration potential from the surrounding 50km
The document discusses Agnico Eagle's Meadowbank and Meliadine gold projects located in Nunavut, Canada. It provides an overview of Agnico Eagle's history with the Meadowbank mine, including permitting and infrastructure development, and describes the geology, challenges, and current status of the mine. It also gives a brief introduction to the Meliadine project and Agnico Eagle's plans to further explore and develop the site.
- The document discusses the Brucejack gold mine located in British Columbia, Canada. It provides details on the mine's high-grade gold reserves, planned production levels over an 18 year mine life, and robust project economics.
- Construction of the Brucejack mine has been advancing over the past few years, with ore now being introduced to the mill. Commissioning of the mine is nearing completion.
- The mine has the potential for further exploration in the surrounding areas to expand resources. Community engagement efforts have focused on employment and commercial opportunities for local First Nations groups.
Crocodile Gold Corporate Presentation May 2014Crocodile Gold
This document summarizes a presentation about Crocodile Gold Corporation, a mid-tier Australian gold producer. Some key points:
- Crocodile Gold generated over $12 million in operating cash flow in Q1 2014 and over $67 million in 2013, while decreasing costs.
- Production has increased from 155,000 ounces in 2012 to 210,000 ounces in 2013, and they are on track to produce 200,000-210,000 ounces in 2014.
- The company has a sizable gold resource base of over 7 million ounces and is focusing on underground exploration to extend mine life at all projects.
This document provides an overview of Crocodile Gold Corp, a mid-tier Australian gold producer. It discusses Crocodile Gold's growing gold production and cash flow generation, decreasing costs, sizable gold resources, and focus on advancing growth projects like the Big Hill project. The document also summarizes Crocodile Gold's 2013-2014 operational performance and milestones, production across its three main mines, and its strategy of divesting non-core assets.
This document contains forward-looking statements and cautions investors about various risks and uncertainties. It also notes that resource estimates do not equal reserves under SEC standards. The company's Round Top project currently contains no proven or probable reserves. Finally, the document provides select financial highlights and details from a preliminary economic assessment of the Round Top project, noting high potential value but inherent uncertainties.
This document provides an overview of Lundin Gold Inc. and its Fruta del Norte gold mine project in Ecuador. It summarizes key details about the project including reserves and mine plan details, capital and operating costs, financing, management team experience, and environmental permitting. It also discusses Lundin Gold's commitments to business sustainability and contributions to local economic development in Ecuador.
This document provides a summary of NovaGold Resources Inc.'s 2015 year-end financial results and project update conference call. It includes an introduction and sections on corporate updates from the President & CEO, fourth quarter financials from the VP & CFO, closing remarks from the President & CEO, and a question and answer session. Key points include progress made on permitting for the Donlin Gold project, technical studies conducted for the Galore Creek project, community outreach efforts, 2015 project funding amounts, operating performance and cash flow highlights, and the 2016 budget. The Donlin Gold project is described as one of the largest and highest-grade gold deposits in the world with significant exploration potential.
Donlin Gold is a large-scale gold project located in Alaska that is a joint venture between NOVAGOLD (50%) and Barrick Gold (50%). The project is expected to be one of the largest gold mines in the world, with an estimated 27-year mine life and average annual production of over 1 million ounces of gold per year during its first five full years of operation. Donlin Gold has significant exploration potential along an 8km mineralized trend and its high-grade ore of 2.24 g/t is double the industry average grade of 1.12 g/t. The project's economics are highly sensitive to gold price, with its after-tax NPV increasing over 20 times from $6.
The document discusses forward-looking statements and disclaimers around Lundin Gold's project. It provides an overview of Lundin Gold's capital structure, management team experience, the Fruta del Norte project in Ecuador, and recent project updates. Key points include Lundin Gold's experienced management team, the large, high-grade nature of the Fruta del Norte gold deposit, plans for average annual production of 325,000 ounces over a 15-year mine life, and that construction is underway with first gold production expected in Q4 2019.
- Lundin Gold held a conference call to discuss its third quarter 2020 results and provide an operational update
- In Q3 2020, Lundin mined 265,298 tonnes of ore, processed 324,000 tonnes at an average daily rate of 3,340 tpd with average head grade of 10.4 g/t, and produced 94,250 ounces of gold
- Strict COVID-19 protocols have been implemented at site with only 34 cases identified and no current active cases
- Exploration drilling is expected to start in early 2021 at the high priority Barbasco target located within the same basin as Fruta del Norte
- Throughput expansion and resource expansion drilling programs are also planned to increase production over the
The document provides disclaimers and forward-looking statements regarding Lundin Gold's Fruta del Norte gold project in Ecuador. It summarizes that Fruta del Norte is a large, high-grade gold deposit within a major mineralized trend. Construction is underway and first gold production is expected in Q4 2019. The project has attractive economics with low costs and financing in place.
Probe Metals is a well-funded Canadian gold explorer advancing its Val-d'Or East project in Quebec. A preliminary economic assessment shows the potential for the project to be a 12.5-year mine producing over 200,000 ounces of gold per year on average. The project currently has over 1.8 million ounces of gold in the measured and indicated categories and 2.3 million ounces in inferred. Probe Metals is planning a large 162,000-meter drill program in 2022 and has over $31 million in cash and investments to advance the project.
The document summarizes information about Novagold Resources Inc., a gold development company, and its two main projects: Donlin Gold in Alaska and Galore Creek in British Columbia. Donlin Gold is described as one of the largest gold development projects in the world with projected annual production of over 1 million ounces of gold over a 27-year mine life. Global gold supply is noted to be declining as new discoveries become increasingly rare, suggesting future scarcity and upward pressure on gold prices.
Belo Sun Corporate Presentation Aug 2014 belosunhelia
Belo Sun Mining Corporation presented a corporate presentation in August 2014 that outlined key details about their Volta Grande gold project in Brazil. The presentation highlighted that Volta Grande has measured and indicated resources of 5.1 million ounces of gold and inferred resources of 2.5 million ounces. It also summarized the project's infrastructure advantages and experienced management team. Belo Sun believes there are opportunities to expand resources through further exploration of target areas around the existing deposits.
This document provides an overview and summary of Lundin Gold's Fruta del Norte gold project in Ecuador. Key points include:
- First gold production is expected in Q4 2019 and commercial production is scheduled for 2020. The mine has a projected 15-year lifespan.
- The project contains probable reserves of over 5 million ounces of gold and is fully funded with construction 73% complete.
- Lundin Gold expects average annual gold production of over 310,000 ounces during the first 13 years of mine operations.
- The Fruta del Norte deposit is located within a major underexplored mineralized trend that represents significant exploration upside potential for Lundin Gold.
This document provides an overview and summary of Lundin Gold's Fruta del Norte gold project in Ecuador. Key points include:
- First gold production is expected in Q4 2019 and commercial production is anticipated to exceed 310,000 ounces per year.
- The mine has probable reserves of 5 million ounces of gold and is fully funded with construction 73% complete.
- Exploration potential exists within the underexplored 64,400 hectare land package around Fruta del Norte located within a major gold-silver mineralized trend. Priority targets include Barbasco, Puente-Princesa, and Gata Salvaje.
This document provides an overview of the Fruta del Norte Gold Project in Ecuador. It summarizes that first gold production is expected in Q4 2019, with the project being fully funded and 82% construction complete. It also notes that the project is located within a major under-explored mineralized trend, presenting exploration upside potential.
- Lundin Gold restarted operations at its Fruta del Norte gold mine in Ecuador in July 2020 after a three month suspension due to COVID-19.
- Production guidance for 2020 is 200,000-220,000 ounces of gold with cash costs of $715-780 per ounce and all-in sustaining costs of $770-850 per ounce.
- The mill is currently running at near design throughput and the mine is ramping up over the next three months. Lundin Gold also has a strong financial position.
Calibre Mining Corp is a gold producer with multi-asset production and exploration opportunities in Nicaragua. It operates the Libertad and Limon processing hubs and mining spokes including Pavon Norte, which was brought into production in under 18 months. Calibre aims to grow production organically through near-mill discoveries and expanding emerging districts like Eastern Borosi, which currently hosts an inferred resource of 700,000 ounces of gold. Exploration is ongoing across Calibre's land package of over 2,000 square kilometers to discover new resources that can be fed into the surplus processing capacity at Libertad.
This document is a corporate presentation from SSR Mining Inc. that contains forward-looking statements regarding future production, costs, exploration and development plans. It cautions readers that actual results may differ due to risks and uncertainties. It also provides qualifications for the scientific and technical information presented.
This document provides an overview of Lundin Gold's Fruta del Norte gold project in Ecuador. It summarizes that first gold production is expected in Q4 2019 and commercial production in 2020. The mine has probable reserves of 5 million ounces of gold at an average grade of 8.74 g/t. The project is fully funded with construction 65% complete. Exploration potential is also discussed, with high priority targets identified within the underexplored Suarez pull-apart basin structure.
The document discusses Goldquest Corp's Romero gold-copper project in the Dominican Republic. It highlights results from a 2016 pre-feasibility study that showed the project has an after-tax NPV of $203 million and IRR of 28% at $1,300/oz gold price. The study outlined probable mineral reserves of 7 million tonnes grading 3.72 g/t gold and 0.88% copper containing 1.12 million ounces of gold equivalent. The project is planned as an underground mine producing over 100,000 ounces of gold equivalent annually at average all-in sustaining costs of $595/oz over a 7 year mine life. Goldquest also discusses exploration potential from the surrounding 50km
The document discusses Agnico Eagle's Meadowbank and Meliadine gold projects located in Nunavut, Canada. It provides an overview of Agnico Eagle's history with the Meadowbank mine, including permitting and infrastructure development, and describes the geology, challenges, and current status of the mine. It also gives a brief introduction to the Meliadine project and Agnico Eagle's plans to further explore and develop the site.
- The document discusses the Brucejack gold mine located in British Columbia, Canada. It provides details on the mine's high-grade gold reserves, planned production levels over an 18 year mine life, and robust project economics.
- Construction of the Brucejack mine has been advancing over the past few years, with ore now being introduced to the mill. Commissioning of the mine is nearing completion.
- The mine has the potential for further exploration in the surrounding areas to expand resources. Community engagement efforts have focused on employment and commercial opportunities for local First Nations groups.
Crocodile Gold Corporate Presentation May 2014Crocodile Gold
This document summarizes a presentation about Crocodile Gold Corporation, a mid-tier Australian gold producer. Some key points:
- Crocodile Gold generated over $12 million in operating cash flow in Q1 2014 and over $67 million in 2013, while decreasing costs.
- Production has increased from 155,000 ounces in 2012 to 210,000 ounces in 2013, and they are on track to produce 200,000-210,000 ounces in 2014.
- The company has a sizable gold resource base of over 7 million ounces and is focusing on underground exploration to extend mine life at all projects.
This document provides an overview of Crocodile Gold Corp, a mid-tier Australian gold producer. It discusses Crocodile Gold's growing gold production and cash flow generation, decreasing costs, sizable gold resources, and focus on advancing growth projects like the Big Hill project. The document also summarizes Crocodile Gold's 2013-2014 operational performance and milestones, production across its three main mines, and its strategy of divesting non-core assets.
This document contains forward-looking statements and cautions investors about various risks and uncertainties. It also notes that resource estimates do not equal reserves under SEC standards. The company's Round Top project currently contains no proven or probable reserves. Finally, the document provides select financial highlights and details from a preliminary economic assessment of the Round Top project, noting high potential value but inherent uncertainties.
This document provides an overview of Lundin Gold Inc. and its Fruta del Norte gold mine project in Ecuador. It summarizes key details about the project including reserves and mine plan details, capital and operating costs, financing, management team experience, and environmental permitting. It also discusses Lundin Gold's commitments to business sustainability and contributions to local economic development in Ecuador.
This document provides a summary of NovaGold Resources Inc.'s 2015 year-end financial results and project update conference call. It includes an introduction and sections on corporate updates from the President & CEO, fourth quarter financials from the VP & CFO, closing remarks from the President & CEO, and a question and answer session. Key points include progress made on permitting for the Donlin Gold project, technical studies conducted for the Galore Creek project, community outreach efforts, 2015 project funding amounts, operating performance and cash flow highlights, and the 2016 budget. The Donlin Gold project is described as one of the largest and highest-grade gold deposits in the world with significant exploration potential.
Donlin Gold is a large-scale gold project located in Alaska that is a joint venture between NOVAGOLD (50%) and Barrick Gold (50%). The project is expected to be one of the largest gold mines in the world, with an estimated 27-year mine life and average annual production of over 1 million ounces of gold per year during its first five full years of operation. Donlin Gold has significant exploration potential along an 8km mineralized trend and its high-grade ore of 2.24 g/t is double the industry average grade of 1.12 g/t. The project's economics are highly sensitive to gold price, with its after-tax NPV increasing over 20 times from $6.
The document discusses forward-looking statements and disclaimers around Lundin Gold's project. It provides an overview of Lundin Gold's capital structure, management team experience, the Fruta del Norte project in Ecuador, and recent project updates. Key points include Lundin Gold's experienced management team, the large, high-grade nature of the Fruta del Norte gold deposit, plans for average annual production of 325,000 ounces over a 15-year mine life, and that construction is underway with first gold production expected in Q4 2019.
- Lundin Gold held a conference call to discuss its third quarter 2020 results and provide an operational update
- In Q3 2020, Lundin mined 265,298 tonnes of ore, processed 324,000 tonnes at an average daily rate of 3,340 tpd with average head grade of 10.4 g/t, and produced 94,250 ounces of gold
- Strict COVID-19 protocols have been implemented at site with only 34 cases identified and no current active cases
- Exploration drilling is expected to start in early 2021 at the high priority Barbasco target located within the same basin as Fruta del Norte
- Throughput expansion and resource expansion drilling programs are also planned to increase production over the
The document provides disclaimers and forward-looking statements regarding Lundin Gold's Fruta del Norte gold project in Ecuador. It summarizes that Fruta del Norte is a large, high-grade gold deposit within a major mineralized trend. Construction is underway and first gold production is expected in Q4 2019. The project has attractive economics with low costs and financing in place.
Probe Metals is a well-funded Canadian gold explorer advancing its Val-d'Or East project in Quebec. A preliminary economic assessment shows the potential for the project to be a 12.5-year mine producing over 200,000 ounces of gold per year on average. The project currently has over 1.8 million ounces of gold in the measured and indicated categories and 2.3 million ounces in inferred. Probe Metals is planning a large 162,000-meter drill program in 2022 and has over $31 million in cash and investments to advance the project.
The document summarizes information about Novagold Resources Inc., a gold development company, and its two main projects: Donlin Gold in Alaska and Galore Creek in British Columbia. Donlin Gold is described as one of the largest gold development projects in the world with projected annual production of over 1 million ounces of gold over a 27-year mine life. Global gold supply is noted to be declining as new discoveries become increasingly rare, suggesting future scarcity and upward pressure on gold prices.
Belo Sun Corporate Presentation Aug 2014 belosunhelia
Belo Sun Mining Corporation presented a corporate presentation in August 2014 that outlined key details about their Volta Grande gold project in Brazil. The presentation highlighted that Volta Grande has measured and indicated resources of 5.1 million ounces of gold and inferred resources of 2.5 million ounces. It also summarized the project's infrastructure advantages and experienced management team. Belo Sun believes there are opportunities to expand resources through further exploration of target areas around the existing deposits.
This document provides an overview and summary of Lundin Gold's Fruta del Norte gold project in Ecuador. Key points include:
- First gold production is expected in Q4 2019 and commercial production is scheduled for 2020. The mine has a projected 15-year lifespan.
- The project contains probable reserves of over 5 million ounces of gold and is fully funded with construction 73% complete.
- Lundin Gold expects average annual gold production of over 310,000 ounces during the first 13 years of mine operations.
- The Fruta del Norte deposit is located within a major underexplored mineralized trend that represents significant exploration upside potential for Lundin Gold.
This document provides an overview and summary of Lundin Gold's Fruta del Norte gold project in Ecuador. Key points include:
- First gold production is expected in Q4 2019 and commercial production is anticipated to exceed 310,000 ounces per year.
- The mine has probable reserves of 5 million ounces of gold and is fully funded with construction 73% complete.
- Exploration potential exists within the underexplored 64,400 hectare land package around Fruta del Norte located within a major gold-silver mineralized trend. Priority targets include Barbasco, Puente-Princesa, and Gata Salvaje.
The corporate presentation provides an overview of Lundin Gold's operations and outlook. It discusses restarting operations after a temporary COVID-19 suspension, with plans to ramp up milling and mining. Production is expected to be 200,000-220,000 ounces of gold in 2020. Exploration will also begin on high priority targets within the company's land package. Strict COVID-19 protocols are in place to protect the workforce as operations continue.
The virtual town hall presentation provided an overview of Lundin Gold's Fruta del Norte gold mine in Ecuador, including:
1) Highlights from the third quarter of 2020, including gold production, costs, and financial results.
2) Details on the underground mine development and plans to expand throughput.
3) Exploration plans to expand resources at nearby targets like Barbasco.
4) Status updates on remaining construction projects and COVID-19 safety protocols.
5) Details on community support programs during the COVID-19 pandemic.
- Lundin Gold declared commercial production at its Fruta del Norte gold mine in Ecuador ahead of schedule in Q1 2020, producing over 51,000 ounces of gold.
- Operations were temporarily suspended in March due to COVID-19 but the company is working to restart operations safely in Q3 2020.
- With a strong financial position and low costs of production, Lundin Gold is well positioned to ramp up operations at Fruta del Norte as one of the few multi-million ounce, high-grade gold assets currently in production.
- The corporate presentation provides an overview of Lundin Gold's Fruta del Norte gold mine in Ecuador, which began commercial production in late 2019.
- The mine is expected to produce an average of 325,000 ounces of gold per year with an all-in sustaining cost of $621 per ounce and generate significant free cash flow in the coming years.
- Lundin Gold aims to be a catalyst for sustainable development in Ecuador by focusing on local employment, procurement, and economic diversification in the surrounding communities.
- Lundin Gold reported strong Q1 2022 results including record quarterly gold production of 121,665 oz.
- Cash costs of $619/oz and AISC of $696/oz were below guidance. Cash flow from operations was $127 million and free cash flow was nearly $92 million.
- Construction of the south ventilation raise is ongoing and expected to be completed by end of Q2 2022. Other capital projects including the third raise of the tailings dam are ramping up.
- Exploration drilling continued during the quarter near FDN and at regional targets Barbasco and Puente Princesa.
Lundin Gold Corporate Presentation, December 2017lundingold
The document provides disclaimers and forward-looking statements regarding Lundin Gold's Fruta del Norte gold project in Ecuador. It notes that forward-looking statements involve inherent risks and uncertainties that could cause actual results to differ from expectations. The technical information is based on a 2016 technical report and was reviewed by qualified persons. The document also provides important information for US investors regarding the use of certain mineral resource terms.
This presentation summarizes Solitario's gold and zinc projects for the April 16-18, 2013 European Gold Forum. It discusses the Mt. Hamilton gold project which is undergoing permitting and has robust economics with over 750,000 ounces of gold resources. The Bongará zinc project is being advanced through prefeasibility and feasibility studies and is fully funded by partner Votorantim Metais. Solitario also has exploration joint ventures including the high-grade Pachuca Norte silver project and the Pedra Branca platinum project. Solitario is well positioned with a pipeline of projects and experienced management while maintaining a strong balance sheet.
The document discusses forward-looking statements and disclaimers regarding Lundin Gold's Fruta del Norte gold project in Ecuador. It notes that forward-looking statements involve inherent risks and uncertainties that could cause actual results to differ from expectations. It also provides context around the technical information on the project, including that it is based on a 2016 technical report. The document contains important information for US investors regarding mineral resource classifications.
The document summarizes the Rosita copper-gold-silver project located in Nicaragua. Key points include:
- The project has a historic resource of 245 million lbs of copper, 160,000 oz of gold and 2.6 million oz of silver from past production.
- Drilling has identified mineralization below and adjacent to the Santa Rita open pit with highlights including 29.54 g/t gold over 8m.
- Existing stockpiles contain an inferred resource of 8 million tonnes with 108.5 million lbs of copper, 118,500 oz of gold and 2.4 million oz of silver.
- The project is located in a prolific mining district of Nicaragua with established infrastructure and a pro
Avion Gold Corporation is a gold producer in Mali with production of 51,000 ounces in 2009 and projected production of 75,000-85,000 ounces in 2010, and plans to ramp up production to 200,000 ounces per year by 2012. The company has a significant land package in Mali and Burkina Faso totaling over 500 square kilometers that contains a measured and indicated resource of over 1.7 million ounces of gold and an inferred resource of over 2 million ounces. Avion is currently trading at a significant discount to its peers given its large resource base and production growth profile.
Avion Gold Corporation is a gold producer in Mali with production expected to increase from 75,000 ounces in 2010 to 200,000 ounces by 2012, and has exploration properties in Mali and Burkina Faso containing over 3 million ounces of gold resources. The company is significantly undervalued compared to its peers based on cash flow and net asset value multiples, and has an experienced management team and board as well as major institutional shareholders.
Avion Gold Corporation is a gold producer in Mali with production expected to increase from 75,000 ounces in 2010 to 200,000 ounces by 2012, and has exploration properties in Mali and Burkina Faso containing over 3 million ounces of gold resources. The company is undervalued relative to its peers based on its large gold resource, increasing production profile, and low-cost production.
1. The document discusses Alder Resources' Rosita copper-gold-silver project in Nicaragua, which hosts an inferred resource of 8 million tonnes in existing stockpiles.
2. Historic production at the Santa Rita deposit extracted 245 million lbs of copper, 160,000 oz of gold, and 2.6 million oz of silver. Alder's drilling has identified mineralization below and adjacent to the open pit.
3. Alder is earning a 65% interest in the project by spending $4 million on exploration and issuing shares to the option partner. Management believes there is potential to expand resources at Santa Rita and nearby targets.
- Lundin Gold declared commercial production at its Fruta del Norte gold mine in Ecuador ahead of schedule in Q1 2020.
- The mine is expected to produce an average of 325,000 ounces of gold per year with an all-in sustaining cost of $621/oz and generate $20.9 million from initial gold sales in 2019.
- Exploration potential exists within the company's land holdings near Fruta del Norte, with priority targets including Barbasco that shows similarities to the existing mine.
Avion Resources owns gold mining properties in Mali, West Africa. As of July 2010, Avion had estimated mineral resources of 1.7 million ounces of gold measured and indicated and 2.1 million ounces inferred. Avion produced 51,000 ounces of gold in 2009 and expects production to increase to 75,000-85,000 ounces in 2010. The company plans to ramp up production to 200,000 ounces per year by 2012 through mine expansions and exploration. Avion has a strong balance sheet with $36 million in cash and its cash costs are expected to decline from $650 per ounce currently to $525 per ounce over a 10-year mine life.
This document provides an overview of Avion Gold Corporation, a gold producer in Mali, West Africa. It summarizes the company's assets and growth plans. Avion produced 51,000 ounces of gold in 2009 and expects production of 75,000-85,000 ounces in 2010. Through exploration and acquisitions, the company aims to increase its resource base and ramp up production to 200,000 ounces per year by 2012. Avion has a large land package in Mali with exploration potential and low-cost production. The company trades at a significant discount to its peers and aims to generate value for shareholders through organic growth.
Avion Gold Corporation is a gold producer in Mali, West Africa with growing production. In 2009 it produced 51,000 ounces of gold and estimates production of 75,000-85,000 ounces in 2010. It aims to ramp up production to 200,000 ounces per year by 2012 through mine expansions and exploration. Avion has acquired several properties with over 3 million ounces of gold resources. It is significantly undervalued compared to peers based on cash flow and asset value multiples and has an experienced management team and board to continue growing production and resources in the region.
Avion Gold Corporation is a gold mining company with operations in Mali, West Africa. The company produced 51,000 ounces of gold in 2009 and aims to ramp up production to 200,000 ounces per year by 2012. Avion has a large land package with several deposits and exploration targets that could significantly increase its resource base. The company trades at a discount to its peers based on cash flow and net asset value multiples. Management plans to continue expanding production and resources through organic growth from exploration and potential acquisitions.
Similar to Lundin Gold Sept 2018 Corporate Presentation (20)
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil. The project has a 1.4 million ounce open pit reserve and a positive pre-feasibility study showing a 33% IRR and $399 million NPV at $1,550 gold price. Tristar is advancing permitting and aims to receive its installation license in 2024 to begin construction of a 3.6 million tonne per year operation. The project has significant exploration upside to expand resources along strike and at depth.
20240314 Calibre March 2024 Investor Presentation (FINAL).pdfAdnet Communications
Calibre Mining is creating a high growth, cash flow focused mid-tier gold producer in the Americas. It has 3 producing mines, 3 growth assets, 4.1M ounces of gold reserves, and is forecast to produce 275-300k ounces in 2024. Calibre aims to grow production to over 460k ounces annually by 2026 through organic growth from its assets and ongoing exploration and development projects. These include the high-grade Valentine Gold Mine in Canada, which began production in early 2025. Calibre has a track record of delivering production growth and increasing reserves, and sees potential for further discovery and resource expansion across its portfolio.
This document provides an overview of Lundin Gold's exploration activities and goals. In 2023, Lundin Gold conducted over 35,000 meters of near-mine drilling and over 8,000 meters of regional drilling to explore for new discoveries. Conversion drilling totaled over 11,000 meters to replace depleted reserves. The 2024 exploration program budget is $42 million, making it the largest program conducted on Lundin Gold's land package. Near-mine drilling is extending known mineralization at the Bonza Sur and FDNS targets. Regional drilling aims to make new discoveries of large gold deposits.
The document provides an overview of Strategic Resources' corporate presentation from March 2024. It discusses a three phase plan to develop an iron pelletizing facility and eventually the fully permitted BlackRock mine in Quebec. Phase 1 would produce direct reduction grade iron ore pellets using third party feedstock. Phase 2 could produce direct reduced iron or hot briquetted iron. Phase 3 involves building the BlackRock mine and facilities to produce high purity pig iron, vanadium, and titanium products. The presentation outlines the project's economics, location advantages, and potential to support the green transition in steelmaking.
This document provides an overview of Tristar Gold Inc., a gold mining company developing the Castle of Dreams gold project in Brazil. Key points include:
- The Castle of Dreams project has a 1.4 million ounce gold reserve identified in a 2021 PFS study, with potential to expand further.
- The PFS outlined an 11-year mine life with average annual production of 121,000 ounces at an AISC of $900/ounce and post-tax IRR of 28% at $1,550 gold.
- Tristar is advancing permitting for the project and aims to receive the installation license in 2023 to begin construction in 2024.
- The management team
Strategic Resources Corporate Presentation - March 2024 UpdateAdnet Communications
Strategic Resources presented on their corporate projects in March 2024. They outlined a three phase plan to build an iron pelletizing facility using third party feed as Phase 1. This would produce direct reduction grade pellets for sale at a premium to iron concentrate prices. Phase 2 would involve building a direct reduction plant to convert pellets to DRI or HBI. Phase 3 is the construction of Strategic's BlackRock mine and metallurgical facility in Quebec to produce high purity pig iron, titanium slag, and vanadium slag. The presentation highlighted Strategic's products as high value steel inputs that support the green transition to electric arc furnace steelmaking.
Strategic Resources is presenting on their corporate projects in March 2024. The presentation outlines their phased approach to developing the BlackRock iron ore project in Quebec, beginning with a merchant iron pellet plant using third party feed (Phase 1), followed by direct reduction and hot briquetted iron production (Phase 2), and ultimately the construction of the BlackRock mine and metallurgical facility (Phase 3). Strategic also discusses their leased site at the deep water Port of Saguenay that will be critical infrastructure for shipping iron ore pellets and products internationally. The presentation provides an overview of the economics for the Phase 1 merchant pellet plant and Strategic's capital structure.
OJP data from firms like Vicinity Jobs have emerged as a complement to traditional sources of labour demand data, such as the Job Vacancy and Wages Survey (JVWS). Ibrahim Abuallail, PhD Candidate, University of Ottawa, presented research relating to bias in OJPs and a proposed approach to effectively adjust OJP data to complement existing official data (such as from the JVWS) and improve the measurement of labour demand.
BONKMILLON Unleashes Its Bonkers Potential on Solana.pdfcoingabbar
Introducing BONKMILLON - The Most Bonkers Meme Coin Yet
Let's be real for a second – the world of meme coins can feel like a bit of a circus at times. Every other day, there's a new token promising to take you "to the moon" or offering some groundbreaking utility that'll change the game forever. But how many of them actually deliver on that hype?
Falcon stands out as a top-tier P2P Invoice Discounting platform in India, bridging esteemed blue-chip companies and eager investors. Our goal is to transform the investment landscape in India by establishing a comprehensive destination for borrowers and investors with diverse profiles and needs, all while minimizing risk. What sets Falcon apart is the elimination of intermediaries such as commercial banks and depository institutions, allowing investors to enjoy higher yields.
1. Elemental Economics - Introduction to mining.pdfNeal Brewster
After this first you should: Understand the nature of mining; have an awareness of the industry’s boundaries, corporate structure and size; appreciation the complex motivations and objectives of the industries’ various participants; know how mineral reserves are defined and estimated, and how they evolve over time.
Abhay Bhutada, the Managing Director of Poonawalla Fincorp Limited, is an accomplished leader with over 15 years of experience in commercial and retail lending. A Qualified Chartered Accountant, he has been pivotal in leveraging technology to enhance financial services. Starting his career at Bank of India, he later founded TAB Capital Limited and co-founded Poonawalla Finance Private Limited, emphasizing digital lending. Under his leadership, Poonawalla Fincorp achieved a 'AAA' credit rating, integrating acquisitions and emphasizing corporate governance. Actively involved in industry forums and CSR initiatives, Abhay has been recognized with awards like "Young Entrepreneur of India 2017" and "40 under 40 Most Influential Leader for 2020-21." Personally, he values mindfulness, enjoys gardening, yoga, and sees every day as an opportunity for growth and improvement.
"Does Foreign Direct Investment Negatively Affect Preservation of Culture in the Global South? Case Studies in Thailand and Cambodia."
Do elements of globalization, such as Foreign Direct Investment (FDI), negatively affect the ability of countries in the Global South to preserve their culture? This research aims to answer this question by employing a cross-sectional comparative case study analysis utilizing methods of difference. Thailand and Cambodia are compared as they are in the same region and have a similar culture. The metric of difference between Thailand and Cambodia is their ability to preserve their culture. This ability is operationalized by their respective attitudes towards FDI; Thailand imposes stringent regulations and limitations on FDI while Cambodia does not hesitate to accept most FDI and imposes fewer limitations. The evidence from this study suggests that FDI from globally influential countries with high gross domestic products (GDPs) (e.g. China, U.S.) challenges the ability of countries with lower GDPs (e.g. Cambodia) to protect their culture. Furthermore, the ability, or lack thereof, of the receiving countries to protect their culture is amplified by the existence and implementation of restrictive FDI policies imposed by their governments.
My study abroad in Bali, Indonesia, inspired this research topic as I noticed how globalization is changing the culture of its people. I learned their language and way of life which helped me understand the beauty and importance of cultural preservation. I believe we could all benefit from learning new perspectives as they could help us ideate solutions to contemporary issues and empathize with others.
Falcon stands out as a top-tier P2P Invoice Discounting platform in India, bridging esteemed blue-chip companies and eager investors. Our goal is to transform the investment landscape in India by establishing a comprehensive destination for borrowers and investors with diverse profiles and needs, all while minimizing risk. What sets Falcon apart is the elimination of intermediaries such as commercial banks and depository institutions, allowing investors to enjoy higher yields.
In a tight labour market, job-seekers gain bargaining power and leverage it into greater job quality—at least, that’s the conventional wisdom.
Michael, LMIC Economist, presented findings that reveal a weakened relationship between labour market tightness and job quality indicators following the pandemic. Labour market tightness coincided with growth in real wages for only a portion of workers: those in low-wage jobs requiring little education. Several factors—including labour market composition, worker and employer behaviour, and labour market practices—have contributed to the absence of worker benefits. These will be investigated further in future work.
[4:55 p.m.] Bryan Oates
OJPs are becoming a critical resource for policy-makers and researchers who study the labour market. LMIC continues to work with Vicinity Jobs’ data on OJPs, which can be explored in our Canadian Job Trends Dashboard. Valuable insights have been gained through our analysis of OJP data, including LMIC research lead
Suzanne Spiteri’s recent report on improving the quality and accessibility of job postings to reduce employment barriers for neurodivergent people.
Decoding job postings: Improving accessibility for neurodivergent job seekers
Improving the quality and accessibility of job postings is one way to reduce employment barriers for neurodivergent people.
2. 2
Disclaimers
All statements, other than statements of historical fact, made and information contained in this presentation and responses to questions constitute
“forward-looking information” or “forward-looking statements” as those terms are defined under Canadian securities laws ( “forward-looking statements”).
Forward-looking statements may be identified by terminology such “believes”, “anticipates”, “expects”, “is expected”, “scheduled”, “estimates”, “pending”,
“intends”, “plans”, “forecasts”, “targets”, or “hopes”, or variations of such words and phrases or statements that certain actions, events or results “may”,
“could”, “would”, “will”, “should” “might”, “will be taken”, or “occur” and similar expressions).
By their nature, forward-looking statements involve assumptions, inherent risks and uncertainties, many of which are difficult to predict, and are usually
beyond the control of management, that could cause actual results to be materially different from those expressed by these forward-looking. Lundin Gold
believes that the expectations reflected in these forward-looking statements are reasonable as of the date made, but no assurance can be given that these
expectations will prove to be correct. In particular, this presentation contains forward-looking statements pertaining to: timing of first gold production and
commercial production, scheduling, gold and silver price and exchange rate assumptions, cash flow forecasts, projected capital and operating costs, metal
or mineral recoveries, mine life and production rates, the Company's potential plans and operating performance, changes to the mine plan, the estimation
of mineral reserves or the tonnage, potential production from and viability of the Company's Project, access to funding, the terms of the Company’s
smelting contracts, performance of the Company's contractors, construction and infrastructure development.
There can be no assurance that such statements will prove to be accurate, as Lundin Gold's actual results and future events could differ materially from
those anticipated as a result of the factors discussed in the "Risk Factors" section in Lundin Gold’s Annual Information Form dated March 20, 2018, which is
available on SEDAR at www.sedar.com. Forward-looking information should not be unduly relied upon.
The technical information contained in this presentation relating to the Fruta Del Norte Project is based on a Technical Report prepared for the Company
entitled “Fruta del Norte Project, Ecuador, NI 43-101 Technical Report on Feasibility Study” dated June 15, 2016 with an effective date of April 30, 2016 (the
"Technical Report"). Information of a scientific and technical nature in this presentation was reviewed and approved by Ron Hochstein, P.Eng., Lundin
Gold’s President and Chief Executive Officer, and Stephen Leary, MAusIMM CP(Geo), an independent consultant to Lundin Gold, both of whom are
Qualified Persons within the meaning of National Instrument 43-101 - Standards of Disclosure for Mineral Projects (“NI 43-101”).
Unless otherwise indicated, all dollar values herein are in US dollars.
Important Information for US Investors
This presentation may use the terms “measured", “indicated“, “inferred" and “historical” mineral resources. U.S. investors are advised that, while such
terms are recognized and required by Canadian regulations, the Securities and Exchange Commission does not recognize them. “Inferred mineral
resources" and “historical estimates” have a great amount of uncertainty as to their existence and great uncertainty as to their economic feasibility. It
cannot be assumed that all or any part of an inferred mineral resource or a historical estimate will ever be upgraded to a higher category. Under Canadian
rules, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies. Further, historical estimates are not
recognized under Canada’s NI 43-101. U.S. investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever
be converted to mineral reserves.
This presentation is not an offer of securities for sale in the United States or in any other jurisdiction. The Company’s securities have not been and will not
be registered under the United States Securities Act of 1933, as amended and may not be offered or sold within the United States absent registration or an
application exemption from registration.
3. 3
Project is on schedule and on budget
Building a Leading Gold
Company
First gold expected Q4 2019
Underground mine development at
over 2.9 km
Fruta del Norte within a major mineralized
trend - significant exploration upside exists
15 year mine life estimated to produce
4.6 million ounces of gold
Committed 63% of planned capex
and construction 27% complete
4. 4
Fruta del Norte Gold
Project Capex
Capital Cost as of August 2018 (based on UPE estimate)
• Committed or incurred $431 million
• Incurred $249 million
Source: See Lundin Gold news release dated September 19, 2018
PPR
US$ (M)
UPE
US$ (M)
Capital Expenditures
(to first gold)
$730 $734
Pre Production
Revenue
($131) ($128)
Pre Production Cost $85 $86
TOTAL CAPEX $684 $692
5. 5
Project is Fully Financed
Project finance package of
$300 million with Orion Mine
Finance and Blackstone
Tactical Opportunities
Private Placement of $400
million
Senior debt facility for $350
million from lenders syndicate
✓ Completed May 2017 ✓ Completed March 2018 ✓ Completed July 2018
• Gold pre-pay term credit
facility of $150 million
• Stream credit facility of
$150 million
• Offtake agreement for up to
2.5 million ounces refined
gold
• Newcrest investment of $250
million
• Lundin Family Trusts
investment of $50 million
• Orion investment of $100
million
• ING Capital LLC
• Société Générale
• Caterpillar Financial Services
Corporation
• Bank of Nova Scotia
• KfW IPEX-Bank GmbH
• Natixis
• Bank of Montreal
6. 6
Capital Structure
Share Price1 C$4.86
Shares Outstanding2 213.2 M
Market capitalization1 C$1,036 M
52 week high/low1 C$5.57/C$4.07
Cash position3 $393.5 M
Major Shareholders1:
• Newcrest Mining Limited
• Lundin Family Trust
• Orion Mine Finance
• Kinross
• CD Capital
• Kopernik Global
• Mackenzie Financial
• Invesco Canada
1. As at September, 17, 2018
2. As at August 31, 2018
3. As at June 30, 2018
7. 7
UPE Optimizes Mine
Plan and Lowers AISC
Finding from the Update of the Project Estimate
(“UPE”) include:
• Reconfirmed construction schedule with first mine production
planned in Q2 2019 and first gold production planned in Q4
2019
• Reduced period of capital payback to 3.5 years from 4 years
with improved IRR to 17.5% from 16.3%
• Increased NPV 5% by 10% to $786 million from $717 million
• Estimated AISC reduced to $583 per ounce of gold from $609
per ounce of gold
• Estimated operating cost per tonne decreased 7.3% from
$111.84 to $103.65
• Estimated total gold production increased by 73,000 ounces to
4.6 million ounces over a 15 year mine life
• Total estimated capital expenditures increased only by 1.2%
from $684 million to $692 million
8. 8
Probable Reserves Represent Only 67%
of Indicated Resources
South
North
Height300m
Grade of Ore Blocks
3-5 – 5.0 g/t Au
5.0 – 10.0 g/t Au
> 10.0 g/t Au
Main Area of Reserves
and Resources
Fruta del Norte not fully
defined to the south
Probable Reserves =
5.02 mil oz @ 8.74 g/t Au
See the Technical Report and the Lundin Gold news release dated
September 19, 2018
9. 9
Fruta del Norte is Within a Major Mineralized
Trend
Bonza Trend
Alejandro
Puente
Princesa
Rio Blanco
Robles
Emperador
• 64,400 ha of prospective exploration acreage
including the Bonza Las Peñas trend, which hosts
Fruta del Norte
• Suarez Pull-Apart Basin extends 16 km south of
Fruta del Norte, doubling the most prospective
trend
• Significant exploration upside exists - numerous
key targets with epithermal geochemical
signatures along the trend have yet to be drilled
• ZTEM resistivity geophysical survey recently
completed
• Exploration drill program completed and assay
results being interpreted and compared with
other epithermal systems in the Suarez Pull-Apart
Basin
FDN
10. 10
Fruta del Norte will be a Large, High-
Grade Gold Mine1
AuGrade(g/t)
Kozs/year
1. See Lundin Gold news release dated September 19, 2018
2. S&P Global Intelligence, 2016 Top Producing Projects - Gold
0
2
4
6
8
10
12
0
100
200
300
400
500
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
Koz/year Au Grade
• First gold production anticipated in
Q4 of next year
• 15 year mine life
• Average annual gold production
during first 13 years expected to
exceed 330,000 ozs per year
• Fruta del Norte is projected to be
in the top tier of gold producers
when in commercial production2
• On a production and cost basis
11. 11
Project Progress at End of August 2018
Overall
• Project is on schedule for first ore and first gold
Mine Development
• Contractor progress to date is 2.9 km of development out of a total of 4.6 km to first stope and 8.1
km overall
Engineering
• 60% complete at the end of August
Procurement
• All mine equipment placed :
• CAT- Scoops and Trucks
• Epiroc - Drills and Bolters
• McLean Engineering - Service Equipment
• Major process and electrical equipment placed:
• Telesmith - Crushing
• Outotec - Grinding, Flotation and Filtration
• FLSmidth - Gravity, CIL/ADR, Detox, Gold Room,
Paste Plant
• ABB - Substation & Major Electrical
Construction
• 27% complete
• Critical paths being maintained
12. 12
Mine Development as at August 2018
Kuri:
• Total decline and auxiliary development
advance of 1.4 km with decline face to
1.2 km
• August average of 6.1 m/day vs target
of 4.7 m/day in August
K’isa:
• Total decline and auxiliary development
advance of 1.5 km with decline face to
1.3 km
• August average of 6.1 m/day vs target
of 4.3 m/day in August
Underground Mine Portals
13. 13
Underground Mine Development
South Vent Shaft
Mine Development as at August 31, 2018
K’isa
Kuri
• Both declines have crossed the Machinaza Fault and have gone under the
Machinaza River, with no water inflows
14. 14
Mine Waste Storage Process Plant Portal Platform
Portals
Site Plan for Plant and Mine Area
15. 15
Process Plant Concrete 30% Complete
• Grinding building steel erection is
underway
• Carbon-in-leach tank bases are complete
• Mill process equipment arriving on site
and the grinding mill components are on
route
Carbon-in-leach tank bases
18. 18
Site-Wide Infrastructure
in Progress
Tailing Storage Facility
• Tailing storage facility construction ongoing
North Access Road
• Construction crews working from both ends have now met
• Road expected to be completed in September
42 km, 230 kV Powerline
• Material procurement in progress and towers are on route
• Construction, both onsite and offsite, is underway
Water Management
• Three major water management ponds completed at mine
and process plant
• Tailings polishing pond excavation complete and liner
underway
20. 20
Major Permits in Place
Construction camp
• Received Environmental License for
Fruta del Norte in October 2016
• Exploitation and Investment Protection
Agreements signed in December 2016
• Environmental License for the powerline
received January 2018
• Mountain Pass Quarry Administrative
Act and Environmental License received
21. 21
First Gold Expected Q4 of Next Year
Fruta del Norte
Development Timeline
2017 2018 2019 2020
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
North Access Road
Mountain Pass Quarry Development
River Road - √ COMPLETED
Site Earthworks and Construction
Camp - √ COMPLETED
U/G Mine Development
Process Plant Detailed Engineering
Process Plant Construction
Power Line Construction
Tailings Construction
Process Plant Commissioning
Paste Plant Detailed Engineering and
Construction
First Ore to Mill/Commercial
Production
22. 22
AISC Now $583 Per Ounce Gold
PPR
Cash Cost
(US$ per oz
Au)1
UPE
Cash Cost
(US$ per oz
Au)1
On site operating
costs
$424 $408
Treatment &
refining
$83 $78
Royalties &
production taxes
$76 $74
Silver by-product ($22) ($23)
Cash Costs $561 $537
Sustaining Capital
& Closure
$49 $46
All-in Sustaining
Costs
$609 $583
Source: See Lundin Gold news releases dated May 30, 2017 and September 19, 2018.
Numbers may not add due to rounding
Estimated AISC reduced $26
or 4% as a result of:
• Mining cost savings
• Lower treatment charges
23. 23
0
250
500
750
1,000
1,250
1,500
0 25 50 75 100
Global Low AISC Producer1
1. SNL Metals and Mining, public company filings
2. Bloomberg spot gold as at September 17, 2018
AllInSustainingCost(US$/0z)
Fruta del Norte
AISC $583/oz
Gold Price ~$1201/oz2
Percentage (%) of Global Production
24. 24
Lundin Gold is
Committed to Business
Sustainability
• There is strong community support for the
development of Fruta del Norte
• Ongoing engagement with a wide range of
stakeholders:
• Community risk roundtables
• Frequent community meetings
• Open door policy
• Community assemblies
• As at August 2018, 51% of Lundin Gold staff are from
local communities
• Jointly-defined local procurement strategy in place
• Community investment focuses on:
• Community infrastructure
• Strengthening existing local economic activity through local
value chains and local procurement
25. 25
Lundin Gold vs. Peers on EV/Au
Reserves Basis1
1. As at August 17, 2018, C$
Source: Bloomberg and public company filings
$632
$461
$377
$308
$287
$193$181
$158$142$140
$130
$48$37
$17
$0
$200
$400
$600
$800
Mean $221
Median $162
EV/AuReserves
26. 26
Project is on schedule and on budget
Building a Leading Gold
Company
Fruta del Norte is a large, high grade gold
deposit under construction
Underground mine development at
over 2.9 km
Construction is reaching its peak with more
than 1,300 on site daily
First gold expected Q4 2019
Committed 63% of planned capex
and construction 27% complete
28. 28
Ecuador is an Emerging Mining
Jurisdiction
• Development of attractive mining framework has lead to an
influx of major mining companies
29. 29
Fruta del Norte is Among the Largest and
Highest Grade Gold Projects in the World
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Contained Reserves ('000 oz Au) Contained Reserves and Resources ('000 oz Au)
0.7
1.0 1.0
0.7
0.8
0.7
(‘000ouncesAu)
14.7
Gold Grade, Reserves (g/t Au)
0.7
8.7
8.4
6.3
Source: SNL Metals and Mining, public company filings
1.7
7.7
1.4
1.2
1.4
30. 30
Non-Executive Board of Directors
Lukas Lundin – Chairman
• 37 years of recognizing value and superior global investment opportunities in the natural resource sector
• Pursuit of highly prospective properties around the world has resulted in numerous resource discoveries, including the multi million-ounce
Veladero gold discovery
• Has led several companies through highly profitable business acquisitions and mergers such as Lundin Mining Corporation's $3.3 billion merger
with EuroZinc Mining
Carmel Daniele
• Founder and CIO of CD Capital UK Ltd., the fund manager of a
number of private equity and mining funds
• 25 years of natural resources investment experience, 10 years
of which were spent with Newmont Mining/Normandy
Ian Gibbs
• Canadian chartered accountant that has held a variety of prominent
positions with Lundin Group of companies, currently serving as CFO
of Africa Oil Corp.
• Former CFO of Tanganyika Oil, where he played a pivotal role in the
recent $2 billion acquisition by Sinopec International Petroleum
Chantal Gosselin
• 25 years of combined experience in the mining industry and
capital markets
• Has held positions as VP and PM at Goodman Investment
Counsel and Senior Mining Analyst at Sun Valley Gold LLP, as
well as various mine-site management positions in Canada,
Peru and Nicaragua
Ashley Heppenstall
• Lead Director of Lundin Gold since 2015
• Has worked with Lundin Group public companies since 1993, most
recently as the President, CEO and Finance Director of Lundin
Petroleum AB
Craig Jones
• Executive General Manager of Newcrest Mining’s Wafi-Golpu
project in Papua New Guinea
• Has been with Newcrest Mining since 2008 and has held a
number of senior management positions including General
Manager Projects, Executive General Manager Projects and
Asset Management, and Executive General Manager at many of
Newcrest Mining’s operations
Paul McRae
• Senior VP of Lundin Mining Corp.
• Global reputation in project and construction management in the
mining industry for both surface and underground projects of all
scales and complexities, and was most recently responsible for the
successful development of Lundin Mining’s Eagle Mine in Northern
Michigan
Michael Nossal
• Chief Development Officer of Newcrest Mining
• Has more than 30 years of resource industry experience in
Australia and internationally and has worked extensively in the
gold sector and base metals
Istvan Zoelli
• Portfolio Manager at Orion Mine Finance, a mining-focused
investment business providing flexible capital investment solutions to
mining companies in the base and precious metals sector
• Has international finance experience and been responsible for
investments in mining, oil/gas and power companies
31. 31
Management Team with Extensive
Mining Experience
Ron F. Hochstein - President, CEO & Director
• 35 years in the mining industry, including more than 20 year working with the Lundin Group
• Worked with a number of resource companies, most recently as President and CEO of Denison Mines
Corp. from 2009 to 2015
Alessandro Bitelli - EVP, CFO
• 30 years experience in the resource industry and in public accounting, both in Europe and North
America
• Former CFO of Redback Mining, which was acquired by Kinross in 2010 for $9.2 billion
David Dicaire - VP, Projects
• 35 years in the mining, engineering and construction industry, leading both Owners and EPCM teams on
a variety of global projects
• Project Director for Freeport McMoRan’s US$4.6 billion Cerro Verde Expansion Project in Peru, and
previously worked on Agua Rica Mine in Argentina (Glencore, prev. Xstrata) and Quellaveco Mine in Peru
(Anglo American)
Xavier Ochoa - General Manager
• 30 years experience in mining and engineering roles at projects across North and South America
• Most recently worked for McEwan Mining as their Chief Operating Officer and worked at their Goldbar
(Nevada) and Fenix (Mexico) mines
Nathan Monash - VP, Business Sustainability
• 15 years experience in resource business sustainability
• Worked extensively with the IFC, guiding extractive industry clients on the structure and
implementation of sustainable development strategies
32. 32
Project Team with Global Mine
Development Experience
Louis Gignac
Project Advisor
• Rosebel Mine, Suriname (IAMGold)
• Essakane Mine, Burkina Faso (IAMGold)
• Omai Gold Mine, Guyana (Mahida Gold, prev. IAMGold)
Matt Gignac
Project Director
• Rosebel Mine, Suriname (IAMGold)
• Merian Mine, Suriname (Newmont)
• Mouska Mine, Canada (IAMGold)
Meredith Arnould
Project Business Manager
• Cerro Verde Mine, Peru (Freeport McMoRan)
• Mount Milligan Mine, Canada (Centerra, prev. Thompson
Creek)
• Endako Mine, Canada (Centerra, prev. Thompson Creek)
Doug Moore
Mine Development Manager
• Carlin East Mine, USA (Newmont)
• Buckhorn Mine, USA (Kinross)
• Lac des Iles Mine, Canada (North American Palladium)
William Matheson
Construction Manager
• Yanacocha Mine Phase 1, Peru (Newmont)
• Carlota Mine, USA (KGHM International)
• Sierra Gorda Mine, Chile (KGHM International)
Nic Hamel
Construction Manager
• Merian Mine Phase 1, Suriname (Newmont)
• Merian Mine Phase 2, Suriname (Newmont)
• Lower Mattagami Hydroelectric Project , Ontario (Kiewit)
Juan Carlos Contreras
Mill Manager
• El Peñón Mine, Chile (Yamana)
• Can Can Mine, Chile (COPEC S.A.)
• Tambo de Oro Mine, Chile (HMC Gold)
Murray Wright
Supply Chain Manager
• Kansanshi Mine, Zambia (First Quantum)
• Tasiast Mine, Mauritania (Kinross)
• Otjikoto Mine, Namibia (B2 Gold)
33. 33
Mineral Resources
NI 43-101 Mineral Resources - Mineral Resources, inclusive of Mineral Reserves as at December 15, 2015
Category
Tonnage
(M t)
Grade
(g/t Au)
Contained Metal
(M oz Au)
Grade
(g/t Ag)
Tonnage
(M oz Ag)
Indicated 23.8 9.61 7.35 12.9 9.89
Inferred 11.6 5.69 2.13 10.8 4.05
Notes:
1. The Qualified Person for the estimate is Mr. David Ross, P.Geo., an employee of RPA. The estimate has an effective date of 31 December, 2015.
2. Mineral Resources are reported inclusive of Mineral Reserves; Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
3. Mineral Resources are reported at a cut-off grade of 3.5 g/t Au; which was calculated using a long term gold price of US$1,500/oz.
4. Mineral Resources are constrained within underground mineable shapes that assume a minimum thickness of 2 m; metallurgical recovery of 94%; total operating
costs of US$145/t milled (mining cost of US$60/t milled; process costs of US$35/t milled; G&A costs of US$15/t milled; surface infrastructure costs of US$28/t
milled; concentrate transport and treatment costs of US$7/t milled); royalties of US$71/oz and selling costs of US$65/oz.
5. Numbers may not add due to rounding.
6. For information with respect to the key assumptions, parameters and risks associated with the results of the Technical Report for the Project, the Mineral
Resource and Mineral Reserve estimates included therein and other technical information, please refer to the Technical Report.
34. 34
Mineral Reserves
Probable Mineral Reserves(1)
Technical Report PPR(2)(3)(4)(5) UPE(2)(3)(4)(5)
Mt 15.5 16.8 17.8
Au (g/t) 9.67 9.16 8.74
Au (Moz) 4.82 4.94 5.02
Ag (g/t) 12.7 12.6 12.1
Ag (Moz) 6.34 6.79 6.95
1) Except as set out below, the assumptions, parameters and risks associated with the results of the Technical Report for the Project, the Mineral Resource and Mineral Reserve estimates
included therein, the PPR and the UPE, are as set out in the Technical Report.
2) All Mineral Reserves in this table are Probable Mineral Reserves. No Proven Mineral Reserves were estimated.
3) PPR estimates are as at MY 30, 2017 and UPE estimates are as at September 19, 2018.
4) Mineral Reserves were estimated using key inputs listed in the table below:
Key Inputs for Mineral Reserve Estimate PPR UPE
Gold Price ($/oz) 1,250 1,250
TS ($/t) 57 48
Overhand D&F ($/t) 79 81
Underhand D&F ($/t) 85 71
Process, Surface Ops, G&A ($/t) 58 58
Dilution Factor (%) 10 10
Concentrate Transport & Treatment ($/t) 9 9
Royalty ($/oz) 71 71
Gold Metallurgical Recovery (%) 91.7 91.7
5) Gold cut-off grades for the different mining methods are listed in the table below:
Gold Cut-off Grade (g/t) PPR UPE
Transverse Stope 4.1 3.8
Overhand D&F 4.8 5.0
Underhand D&F 5.1 5.0
Note: An increased cut-off grade was used in the PPR Overhand D&F for the initial
years of 6.5 g/t.
6) The average silver metallurgical recovery is 81.6%. The silver price assumption was $20/oz. Silver was not considered in the calculation of the cut-off grade.
7) Tonnages are rounded to the nearest 1,000 t, gold grades are rounded to two decimal places, and silver grades are rounded to one decimal place. Tonnage and grade measurements are
in metric units; contained gold and silver are reported as thousands of troy ounces.
8) Rounding as required by reporting guidelines may result in summation differences.
35. 35
Life of Mine Operating Cost by Area
Area
PPR Cash Cost
($/t)
PPR Cash Cost
($/oz Au payable)
UPE Cash
Cost ($/t)
UPE Cash Cost
($/oz Au payable)
Mining 54.98 208.48 47.85 188.40
Process 32.44 123.00 27.60 108.71
Surface 4.21 15.96 6.17 24.32
General & Administration 20.21 76.65 22.02 86.74
Total Operating Cost 111.84 424.09 103.65 408.20
Source: See September 19, 2018 news release
Numbers may not add due to rounding
36. 36
Fruta del Norte Gold Project Economics
PPR UPE
After Tax
Net Present Value at a 5% discount rate
(NPV5)
$717 million $786 million
Internal Rate of Return (IRR) 16.3% 17.5%
Capital Payback (years) 4.0 3.5
See September 19, 2018 news release
All figures are reported on a 100% equity project basis valuation. Capital payback is calculated based on start of
commercial production. Economic valuation is presented using a start date of July 1, 2017
38. 38
Lundin Gold Valuation Potential1
EV/AuReserves
$367
$286
$193
$140
$100
$77
$140
$0
$100
$200
$300
$400
PVG 2013
• Feasibility study
PVG 2014
• Pre-construction
activities
PVG 2015
• Pre-construction activities
• Early construction works
• U/G mine development PVG 2016
• Full project execution
• Continued U/G mine development
• Updated mineral reserves
LUG 2017
• Pre-construction activities
• Early construction works
• U/G mine development
PVG 2017
• Production
Current LUG
EV/Au Reserves2
1. As at December 31, 2017
2. As at September 14, 2018
Source: Bloomberg and public company filings
39. 39
Local Employment in Action
Employment Lundin Gold and Contractors - End of August 2018
Ring 2
Yantzaza Canton
RING 1
RING 2
RING 3
RING 4
758
278
199
1,303
28%
10%
7%
5%
49%
129
Ring 1
Los Encuentros
and the
surrounding
communities of
Playón and Rio
Blanco
Ring 3
Zamora Province
Ring 4
Rest of Ecuador
LUG Employees %
Ring 1 528 38%
Ring 2 175 13%
Ring 3 138 10%
Ring 4 436 31%
Ex-Pat 117 8%
Total 2,667 100%
Contractors %
Ring 1 270 17%
Ring 2 168 11%
Ring 3 155 10%
Ring 4 934 60%
Ex-Pat 43 2%
Total 1570 100%
40. 40
Local Procurement
40
• Jointly-defined local procurement strategy:
• Definition of local and meaning of “prioritization” in procurement process
• Reserve List
• Certification process is first step, with ongoing support
• Number of local suppliers approximately 300
0
500
1,000
1,500
2,000
2,500
3,000
3,500
Ring 1 Ring 2 Ring 3 Average Spend 2017 Average Spend 2018
$1,035
$2,057
Local Purchasing Lundin Gold (AESA + AMSA)
Payments Made
$USD‘000s
41. 41
Analyst Coverage
Firm Analyst Rating and Target Price (C$)
BMO Capital Markets Brian Quast Outperform Buy, $6.75
CIBC World Markets David Haughton Hold, $6.00
Cormark Securities Tyron Breytenbach Buy, $9.00
Echelon Wealth Partners Ryan Walker Buy $9.00
VIII Capital Craig Stanley Buy, $6.90
GMP Securities Steve Butler Buy, $8.85
Haywood Securities Kerry Smith Buy, $7.75
Kepler Cheuvreux Ola Sodermark Hold, $5.511
Nordea Equity Research Christian Kopfer Buy, $7.401
Paradigm Capital Don MacLean Speculative Buy, $9.00
Pareto Securities Jack Garman Buy, $7.20
Scotia Capital Inc. Trevor Turnbull Outperform Buy, $7.00
TD Securities Daniel Earle Speculative Buy, $8.00
1. Nordea and Kepler Cheurvreux price target converted from SEK to CAD (6.35 SEK = 1 CAD)
Lundin Gold is followed by the analysts listed above. Note that any opinion, estimates or forecasts regarding the Company made by these analysts
are the analysts’ opinions and do not represent opinions, estimates or forecasts of the Company or its management. Lundin Gold does not imply
endorsement by the analyst coverage referenced above.