- Lundin Gold reported strong Q1 2022 results including record quarterly gold production of 121,665 oz.
- Cash costs of $619/oz and AISC of $696/oz were below guidance. Cash flow from operations was $127 million and free cash flow was nearly $92 million.
- Construction of the south ventilation raise is ongoing and expected to be completed by end of Q2 2022. Other capital projects including the third raise of the tailings dam are ramping up.
- Exploration drilling continued during the quarter near FDN and at regional targets Barbasco and Puente Princesa.