Tristar Gold is developing the Castelo de Sonhos gold project in Brazil. The project has a 1.4 million ounce open pit reserve and a positive pre-feasibility study showing a 33% IRR and $399 million NPV at $1,550 gold price. Tristar is advancing permitting and aims to receive its installation license in 2024 to begin construction of a 3.6 million tonne per year operation. The project has significant exploration upside to expand resources along strike and at depth.
This document provides an overview of Tristar Gold Inc. and its Castelo de Sonhos gold project in Pará, Brazil. Key points include:
- The Castelo de Sonhos project has a mineral resource of 1.8Moz indicated and 0.7Moz inferred gold, with a 2021 PFS outlining a 1.4Moz open pit reserve.
- The PFS showed strong economics for an 11-year open pit mine, including a 28% IRR at $1,550/oz gold and annual production averaging 121koz gold.
- Permitting is advancing, with environmental license applications submitted and community engagement ongoing. Production is targeted to begin following permit receipt anticipated
This document provides an overview of Tristar Gold Inc., a gold mining company developing the Castle of Dreams gold project in Brazil. Key points include:
- The Castle of Dreams project has a 1.4 million ounce gold reserve identified in a 2021 PFS study, with potential to expand further.
- The PFS outlined an 11-year mine life with average annual production of 121,000 ounces at an AISC of $900/ounce and post-tax IRR of 28% at $1,550 gold.
- Tristar is advancing permitting for the project and aims to receive the installation license in 2023 to begin construction in 2024.
- The management team
1) Tristar Gold is developing the Castelo de Sonhos gold project in Pará State, Brazil which has a 1.4 million ounce open pit reserve and potential for multi-million ounces.
2) A PFS showed strong economics for the project, with a 28% IRR at $1,550 gold and $321 million NPV.
3) Tristar is working towards obtaining the LP permit in 2023 to advance the project towards production.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil into a major new gold mine. The project has a positive pre-feasibility study showing strong economics, including a 28% post-tax IRR. Tristar is advancing through permitting and expects to receive an installation license in 2023, allowing construction to begin. Drilling has outlined mineral resources of 1.8Moz indicated and 0.7Moz inferred gold, and the project has significant exploration upside to expand resources at depth and along strike.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil into a major new gold mine. The project has a positive pre-feasibility study showing strong economics, including a 28% post-tax IRR. Tristar is advancing the project toward construction and permitting, with an environmental license application submitted and positive community support. The project also has significant exploration potential to expand resources along strike and at depth.
This presentation provides an overview of Tristar Gold's Castelo de Sonhos gold project in Brazil. Key points include:
- The project has a mineral reserve of 1.4 million ounces of gold based on a positive 2021 PFS showing a pre-tax IRR of 33% and NPV of $400 million.
- Permitting is advancing with a town hall meeting scheduled for November and license application submitted in July 2022.
- The project has potential for resource expansion as drilling has only tested targets to 120m depth while mineralization extends laterally and at depth across the 19km long reefs.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil. The project has a 1.4 million ounce open pit reserve and a positive pre-feasibility study showing a 33% IRR and $399 million NPV at $1,550 gold price. Tristar is advancing permitting and aims to receive its installation license in 2024 to begin construction of a 3.6 million tonne per year operation. The project has significant exploration upside to expand resources along strike and at depth.
This document provides an overview of Tristar Gold Inc. and its Castelo de Sonhos gold project in Pará, Brazil. Key points include:
- The Castelo de Sonhos project has a mineral resource of 1.8Moz indicated and 0.7Moz inferred gold, with a 2021 PFS outlining a 1.4Moz open pit reserve.
- The PFS showed strong economics for an 11-year open pit mine, including a 28% IRR at $1,550/oz gold and annual production averaging 121koz gold.
- Permitting is advancing, with environmental license applications submitted and community engagement ongoing. Production is targeted to begin following permit receipt anticipated
This document provides an overview of Tristar Gold Inc., a gold mining company developing the Castle of Dreams gold project in Brazil. Key points include:
- The Castle of Dreams project has a 1.4 million ounce gold reserve identified in a 2021 PFS study, with potential to expand further.
- The PFS outlined an 11-year mine life with average annual production of 121,000 ounces at an AISC of $900/ounce and post-tax IRR of 28% at $1,550 gold.
- Tristar is advancing permitting for the project and aims to receive the installation license in 2023 to begin construction in 2024.
- The management team
1) Tristar Gold is developing the Castelo de Sonhos gold project in Pará State, Brazil which has a 1.4 million ounce open pit reserve and potential for multi-million ounces.
2) A PFS showed strong economics for the project, with a 28% IRR at $1,550 gold and $321 million NPV.
3) Tristar is working towards obtaining the LP permit in 2023 to advance the project towards production.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil into a major new gold mine. The project has a positive pre-feasibility study showing strong economics, including a 28% post-tax IRR. Tristar is advancing through permitting and expects to receive an installation license in 2023, allowing construction to begin. Drilling has outlined mineral resources of 1.8Moz indicated and 0.7Moz inferred gold, and the project has significant exploration upside to expand resources at depth and along strike.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil into a major new gold mine. The project has a positive pre-feasibility study showing strong economics, including a 28% post-tax IRR. Tristar is advancing the project toward construction and permitting, with an environmental license application submitted and positive community support. The project also has significant exploration potential to expand resources along strike and at depth.
This presentation provides an overview of Tristar Gold's Castelo de Sonhos gold project in Brazil. Key points include:
- The project has a mineral reserve of 1.4 million ounces of gold based on a positive 2021 PFS showing a pre-tax IRR of 33% and NPV of $400 million.
- Permitting is advancing with a town hall meeting scheduled for November and license application submitted in July 2022.
- The project has potential for resource expansion as drilling has only tested targets to 120m depth while mineralization extends laterally and at depth across the 19km long reefs.
Tristar Gold is developing its Castelo de Sonhos gold project in Brazil into a major new gold mine. The project has a mineral reserve of 1.4 million ounces of gold, with potential to increase through further exploration. A 2021 PFS showed strong economics, with a post-tax IRR of 28% and NPV of $321 million at $1,550 gold. Tristar is advancing permitting and aims to obtain the final operating license to begin construction.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil's Pará state. Key points:
- 2021 PFS showed positive economics, including a 28% post-tax IRR and 1.4Moz gold reserve.
- Current focus is on permitting, with the key permit application submitted in July 2022.
- Project has significant exploration upside along 19km of mineralized structure and at depth below known deposits.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil. The project has a resource of 1.8Moz indicated and 0.7Moz inferred, and a 1.4Moz open pit reserve. A 2021 PFS outlined an 11-year mine plan producing 121koz gold annually with strong economics. Tristar has submitted permit applications and is advancing the project towards construction. The company aims to unlock additional value through exploration as the resource remains open for expansion.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil. The project has a resource of 1.8Moz indicated and 0.7Moz inferred, with a 1.4Moz open pit reserve outlined in the 2021 PFS. The PFS showed strong economics including a 28% post-tax IRR and $321M NPV at $1,550 gold price. Current focus is on permitting, with key permit applications submitted in July 2022. Upside potential exists to expand resources near reserves and at untested targets on the 17,177ha property.
Tristar Gold is a gold mining company developing its flagship Castelo de Sonhos project in Brazil. The project has a positive pre-feasibility study showing strong economics, including a 28% post-tax IRR. Tristar has advanced permitting and recently submitted its key permit application. The company aims to continue advancing the project towards production to become Brazil's next mid-tier gold producer.
Tristar Gold is developing the Castelo de Sonhos gold project in Pará state, Brazil into a major new gold mine. The project has a mineral reserve of 1.4 million ounces of gold and a positive pre-feasibility study showing a 28% post-tax IRR. Tristar is advancing permitting and aims to obtain the final installation license to begin construction. The project has significant exploration upside to expand resources along strike and at depth around the existing reserves.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil into a major new gold mine. The project has a mineral reserve of 1.4 million ounces of gold, with a preliminary feasibility study showing strong economics including a 28% post-tax IRR. Tristar is advancing the project toward construction and permitting, with the final town hall meeting planned for November 2022 to obtain the necessary operating license.
Tristar Gold is developing the Castelo de Sonhos gold project in Pará state, Brazil into a major gold mine. The project has a mineral reserve of 1.4 million ounces of gold, with potential to increase significantly. A 2021 prefeasibility study showed strong economics, with a 28% post-tax IRR and $321 million NPV at $1,550 per ounce gold price. Tristar is advancing permitting and aims to begin construction upon receiving its prior license.
- Tristar Gold is developing the Castelo de Sonhos gold project in Brazil which has 1.4Moz of gold reserves from an open pit resource.
- A 2021 PFS showed strong economics for an 11-year mine with average annual production of 121koz of gold and an after-tax IRR of 28%.
- Permitting is the current focus with key permit applications submitted in July 2022 and ongoing engagement with stakeholders.
- The project benefits from road access, grid power, and proximity to the town of Castelo de Sonhos, positioning it for advancement to construction.
The document is a corporate presentation for Tristar Gold Inc. that provides an overview of the company and its Castelo de Sonhos gold project in Brazil. Some key highlights from the Preliminary Feasibility Study include average annual production of 121,000 ounces of gold over an 11-year mine life, an after-tax IRR of 28% and NPV of $321 million at a $1,550 gold price, initial capital costs of $261 million, and an all-in sustaining cost of $900 per ounce. The project is located in a mining-friendly jurisdiction in Brazil and has significant potential for resource growth and project expansion.
TriStar Gold is a gold exploration and development company with a project in Brazil called Castelo de Sonhos. The project currently has an inferred mineral resource of 1.3 million ounces of gold. A preliminary economic assessment showed positive economics for the project with a post-tax IRR of 43% and NPV of $264 million. TriStar is working to advance the project through further drilling, permitting, and a pre-feasibility study. The company sees potential to expand resources through exploration of additional targets on the large property.
TriStar Gold is a gold exploration and development company focused on its flagship Castelo de Sonhos project in Brazil. The project contains an open pittable gold resource of over 1.3 million ounces and has shown positive economics in a preliminary economic assessment. TriStar is currently undertaking a pre-feasibility study and expanding exploration efforts through drilling and artificial intelligence targeting. Upcoming catalysts include a resource update in the first half of 2021 and pre-feasibility study results in the summer of 2021.
The document provides an overview of TriStar Gold's Castelo de Sonhos gold project in Brazil, including:
- The project has an indicated resource of 40.1Mt at 1.2g/t for 1.5Moz gold and inferred resource of 22.2Mt at 1.0g/t for 0.7Moz gold.
- A preliminary economic assessment showed potential for positive economics with an after-tax IRR of 43% and NPV of $264 million at a gold price of $1,250/oz.
- The company is currently working on a prefeasibility study to further advance the project.
The document provides an overview of TriStar Gold Inc. and its Castelo de Sonhos gold project in Brazil. Some key points:
- TriStar has outlined an Indicated resource of 1.5Moz gold and Inferred resource of 0.7Moz gold at Castelo de Sonhos.
- A preliminary economic assessment showed promising economics for the project, with a post-tax IRR of 43% and NPV of $264M using $1,250/oz gold.
- Upcoming catalysts include an updated resource estimate in H1 2021 and PFS results in the summer of 2021. Exploration is also ongoing to expand resources.
- Baseline studies, permitting activities
The document provides an overview of TriStar Gold Inc. and its Castelo de Sonhos gold project in Brazil. Some key points:
- TriStar has outlined an Indicated resource of 1.5Moz gold and Inferred resource of 0.7Moz gold at Castelo de Sonhos.
- A preliminary economic assessment showed the project could have a post-tax IRR of 43% and NPV of $264M at a gold price of $1,250/oz.
- Metallurgical test work achieved up to 98% gold recovery. Permitting, engineering studies, and resource expansion drilling are ongoing.
- Upcoming catalysts include an updated resource estimate in H
TriStar Gold is a gold exploration and development company with its flagship Castelo de Sonhos project in Brazil. The project has an indicated resource of 1.5Moz gold and inferred resource of 0.7Moz gold. A preliminary economic assessment showed the project has potential for positive economics with a post-tax IRR of 43% at a gold price of $1,250/oz. TriStar is working to advance the project with ongoing exploration drilling, metallurgical testing, engineering studies, and permitting activities in preparation for a pre-feasibility study.
TriStar Gold is a gold exploration and development company with its flagship Castelo de Sonhos project in Brazil. The project currently has an indicated resource of 1.5Moz gold and inferred resource of 0.7Moz gold. A preliminary economic assessment showed the project could have a post-tax IRR of 43% and NPV of $264M at a gold price of $1,250/oz. TriStar is working to advance the project with ongoing exploration drilling, metallurgical testing, engineering studies, and permitting activities in preparation for a pre-feasibility study.
Troilus Gold is advancing the past producing Troilus gold and copper mine in Quebec, Canada. The mine was previously in production from 1996-2010, producing over 2 million ounces of gold and nearly 70,000 tonnes of copper from open pit mining. Troilus Gold acquired the property in 2017 and has since outlined an indicated mineral resource of 3.9 million ounces of gold equivalent and an inferred resource of 1.2 million ounces of gold equivalent on the property. The company also benefits from existing infrastructure at the site, including access roads, power lines, a permitted tailings facility, and a 50 MW substation that was used during the previous mining operation.
TriStar Gold Inc. is a gold exploration and development company with its flagship Castelo de Sonhos project in Brazil. The presentation provides an overview of the project including its large inferred and indicated resource of 1.3Moz gold, positive preliminary economic assessment results showing a post-tax IRR of 43%, and upcoming pre-feasibility study. The presentation also outlines the company's exploration plans targeting resource growth and new discoveries through drilling and artificial intelligence modeling.
The document is a corporate presentation for TriStar Gold Inc., a gold exploration and development company. Some key points:
- TriStar's main project is the Castelo de Sonhos gold project in Brazil which has an initial resource of 1.3 million ounces of gold.
- A preliminary economic assessment showed strong economics for the project, with a post-tax IRR of 43% and NPV of $264 million at a $1,250 gold price.
- Upcoming catalysts include an updated resource estimate in H1 2021 and prefeasibility study results in the summer of 2021. Exploration is also ongoing to expand resources and find new targets like CDS Deeps.
Tristar Gold is developing its Castelo de Sonhos gold project in Brazil into a major new gold mine. The project has a mineral reserve of 1.4 million ounces of gold, with potential to increase through further exploration. A 2021 PFS showed strong economics, with a post-tax IRR of 28% and NPV of $321 million at $1,550 gold. Tristar is advancing permitting and aims to obtain the final operating license to begin construction.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil's Pará state. Key points:
- 2021 PFS showed positive economics, including a 28% post-tax IRR and 1.4Moz gold reserve.
- Current focus is on permitting, with the key permit application submitted in July 2022.
- Project has significant exploration upside along 19km of mineralized structure and at depth below known deposits.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil. The project has a resource of 1.8Moz indicated and 0.7Moz inferred, and a 1.4Moz open pit reserve. A 2021 PFS outlined an 11-year mine plan producing 121koz gold annually with strong economics. Tristar has submitted permit applications and is advancing the project towards construction. The company aims to unlock additional value through exploration as the resource remains open for expansion.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil. The project has a resource of 1.8Moz indicated and 0.7Moz inferred, with a 1.4Moz open pit reserve outlined in the 2021 PFS. The PFS showed strong economics including a 28% post-tax IRR and $321M NPV at $1,550 gold price. Current focus is on permitting, with key permit applications submitted in July 2022. Upside potential exists to expand resources near reserves and at untested targets on the 17,177ha property.
Tristar Gold is a gold mining company developing its flagship Castelo de Sonhos project in Brazil. The project has a positive pre-feasibility study showing strong economics, including a 28% post-tax IRR. Tristar has advanced permitting and recently submitted its key permit application. The company aims to continue advancing the project towards production to become Brazil's next mid-tier gold producer.
Tristar Gold is developing the Castelo de Sonhos gold project in Pará state, Brazil into a major new gold mine. The project has a mineral reserve of 1.4 million ounces of gold and a positive pre-feasibility study showing a 28% post-tax IRR. Tristar is advancing permitting and aims to obtain the final installation license to begin construction. The project has significant exploration upside to expand resources along strike and at depth around the existing reserves.
Tristar Gold is developing the Castelo de Sonhos gold project in Brazil into a major new gold mine. The project has a mineral reserve of 1.4 million ounces of gold, with a preliminary feasibility study showing strong economics including a 28% post-tax IRR. Tristar is advancing the project toward construction and permitting, with the final town hall meeting planned for November 2022 to obtain the necessary operating license.
Tristar Gold is developing the Castelo de Sonhos gold project in Pará state, Brazil into a major gold mine. The project has a mineral reserve of 1.4 million ounces of gold, with potential to increase significantly. A 2021 prefeasibility study showed strong economics, with a 28% post-tax IRR and $321 million NPV at $1,550 per ounce gold price. Tristar is advancing permitting and aims to begin construction upon receiving its prior license.
- Tristar Gold is developing the Castelo de Sonhos gold project in Brazil which has 1.4Moz of gold reserves from an open pit resource.
- A 2021 PFS showed strong economics for an 11-year mine with average annual production of 121koz of gold and an after-tax IRR of 28%.
- Permitting is the current focus with key permit applications submitted in July 2022 and ongoing engagement with stakeholders.
- The project benefits from road access, grid power, and proximity to the town of Castelo de Sonhos, positioning it for advancement to construction.
The document is a corporate presentation for Tristar Gold Inc. that provides an overview of the company and its Castelo de Sonhos gold project in Brazil. Some key highlights from the Preliminary Feasibility Study include average annual production of 121,000 ounces of gold over an 11-year mine life, an after-tax IRR of 28% and NPV of $321 million at a $1,550 gold price, initial capital costs of $261 million, and an all-in sustaining cost of $900 per ounce. The project is located in a mining-friendly jurisdiction in Brazil and has significant potential for resource growth and project expansion.
TriStar Gold is a gold exploration and development company with a project in Brazil called Castelo de Sonhos. The project currently has an inferred mineral resource of 1.3 million ounces of gold. A preliminary economic assessment showed positive economics for the project with a post-tax IRR of 43% and NPV of $264 million. TriStar is working to advance the project through further drilling, permitting, and a pre-feasibility study. The company sees potential to expand resources through exploration of additional targets on the large property.
TriStar Gold is a gold exploration and development company focused on its flagship Castelo de Sonhos project in Brazil. The project contains an open pittable gold resource of over 1.3 million ounces and has shown positive economics in a preliminary economic assessment. TriStar is currently undertaking a pre-feasibility study and expanding exploration efforts through drilling and artificial intelligence targeting. Upcoming catalysts include a resource update in the first half of 2021 and pre-feasibility study results in the summer of 2021.
The document provides an overview of TriStar Gold's Castelo de Sonhos gold project in Brazil, including:
- The project has an indicated resource of 40.1Mt at 1.2g/t for 1.5Moz gold and inferred resource of 22.2Mt at 1.0g/t for 0.7Moz gold.
- A preliminary economic assessment showed potential for positive economics with an after-tax IRR of 43% and NPV of $264 million at a gold price of $1,250/oz.
- The company is currently working on a prefeasibility study to further advance the project.
The document provides an overview of TriStar Gold Inc. and its Castelo de Sonhos gold project in Brazil. Some key points:
- TriStar has outlined an Indicated resource of 1.5Moz gold and Inferred resource of 0.7Moz gold at Castelo de Sonhos.
- A preliminary economic assessment showed promising economics for the project, with a post-tax IRR of 43% and NPV of $264M using $1,250/oz gold.
- Upcoming catalysts include an updated resource estimate in H1 2021 and PFS results in the summer of 2021. Exploration is also ongoing to expand resources.
- Baseline studies, permitting activities
The document provides an overview of TriStar Gold Inc. and its Castelo de Sonhos gold project in Brazil. Some key points:
- TriStar has outlined an Indicated resource of 1.5Moz gold and Inferred resource of 0.7Moz gold at Castelo de Sonhos.
- A preliminary economic assessment showed the project could have a post-tax IRR of 43% and NPV of $264M at a gold price of $1,250/oz.
- Metallurgical test work achieved up to 98% gold recovery. Permitting, engineering studies, and resource expansion drilling are ongoing.
- Upcoming catalysts include an updated resource estimate in H
TriStar Gold is a gold exploration and development company with its flagship Castelo de Sonhos project in Brazil. The project has an indicated resource of 1.5Moz gold and inferred resource of 0.7Moz gold. A preliminary economic assessment showed the project has potential for positive economics with a post-tax IRR of 43% at a gold price of $1,250/oz. TriStar is working to advance the project with ongoing exploration drilling, metallurgical testing, engineering studies, and permitting activities in preparation for a pre-feasibility study.
TriStar Gold is a gold exploration and development company with its flagship Castelo de Sonhos project in Brazil. The project currently has an indicated resource of 1.5Moz gold and inferred resource of 0.7Moz gold. A preliminary economic assessment showed the project could have a post-tax IRR of 43% and NPV of $264M at a gold price of $1,250/oz. TriStar is working to advance the project with ongoing exploration drilling, metallurgical testing, engineering studies, and permitting activities in preparation for a pre-feasibility study.
Troilus Gold is advancing the past producing Troilus gold and copper mine in Quebec, Canada. The mine was previously in production from 1996-2010, producing over 2 million ounces of gold and nearly 70,000 tonnes of copper from open pit mining. Troilus Gold acquired the property in 2017 and has since outlined an indicated mineral resource of 3.9 million ounces of gold equivalent and an inferred resource of 1.2 million ounces of gold equivalent on the property. The company also benefits from existing infrastructure at the site, including access roads, power lines, a permitted tailings facility, and a 50 MW substation that was used during the previous mining operation.
TriStar Gold Inc. is a gold exploration and development company with its flagship Castelo de Sonhos project in Brazil. The presentation provides an overview of the project including its large inferred and indicated resource of 1.3Moz gold, positive preliminary economic assessment results showing a post-tax IRR of 43%, and upcoming pre-feasibility study. The presentation also outlines the company's exploration plans targeting resource growth and new discoveries through drilling and artificial intelligence modeling.
The document is a corporate presentation for TriStar Gold Inc., a gold exploration and development company. Some key points:
- TriStar's main project is the Castelo de Sonhos gold project in Brazil which has an initial resource of 1.3 million ounces of gold.
- A preliminary economic assessment showed strong economics for the project, with a post-tax IRR of 43% and NPV of $264 million at a $1,250 gold price.
- Upcoming catalysts include an updated resource estimate in H1 2021 and prefeasibility study results in the summer of 2021. Exploration is also ongoing to expand resources and find new targets like CDS Deeps.
Similar to TriStar Gold Corporate Presentation May 2024 (20)
20240314 Calibre March 2024 Investor Presentation (FINAL).pdfAdnet Communications
Calibre Mining is creating a high growth, cash flow focused mid-tier gold producer in the Americas. It has 3 producing mines, 3 growth assets, 4.1M ounces of gold reserves, and is forecast to produce 275-300k ounces in 2024. Calibre aims to grow production to over 460k ounces annually by 2026 through organic growth from its assets and ongoing exploration and development projects. These include the high-grade Valentine Gold Mine in Canada, which began production in early 2025. Calibre has a track record of delivering production growth and increasing reserves, and sees potential for further discovery and resource expansion across its portfolio.
This document provides an overview of Lundin Gold's exploration activities and goals. In 2023, Lundin Gold conducted over 35,000 meters of near-mine drilling and over 8,000 meters of regional drilling to explore for new discoveries. Conversion drilling totaled over 11,000 meters to replace depleted reserves. The 2024 exploration program budget is $42 million, making it the largest program conducted on Lundin Gold's land package. Near-mine drilling is extending known mineralization at the Bonza Sur and FDNS targets. Regional drilling aims to make new discoveries of large gold deposits.
The document provides an overview of Strategic Resources' corporate presentation from March 2024. It discusses a three phase plan to develop an iron pelletizing facility and eventually the fully permitted BlackRock mine in Quebec. Phase 1 would produce direct reduction grade iron ore pellets using third party feedstock. Phase 2 could produce direct reduced iron or hot briquetted iron. Phase 3 involves building the BlackRock mine and facilities to produce high purity pig iron, vanadium, and titanium products. The presentation outlines the project's economics, location advantages, and potential to support the green transition in steelmaking.
Strategic Resources Corporate Presentation - March 2024 UpdateAdnet Communications
Strategic Resources presented on their corporate projects in March 2024. They outlined a three phase plan to build an iron pelletizing facility using third party feed as Phase 1. This would produce direct reduction grade pellets for sale at a premium to iron concentrate prices. Phase 2 would involve building a direct reduction plant to convert pellets to DRI or HBI. Phase 3 is the construction of Strategic's BlackRock mine and metallurgical facility in Quebec to produce high purity pig iron, titanium slag, and vanadium slag. The presentation highlighted Strategic's products as high value steel inputs that support the green transition to electric arc furnace steelmaking.
Strategic Resources is presenting on their corporate projects in March 2024. The presentation outlines their phased approach to developing the BlackRock iron ore project in Quebec, beginning with a merchant iron pellet plant using third party feed (Phase 1), followed by direct reduction and hot briquetted iron production (Phase 2), and ultimately the construction of the BlackRock mine and metallurgical facility (Phase 3). Strategic also discusses their leased site at the deep water Port of Saguenay that will be critical infrastructure for shipping iron ore pellets and products internationally. The presentation provides an overview of the economics for the Phase 1 merchant pellet plant and Strategic's capital structure.
This corporate presentation provides an overview of Strategic Resources' plans to develop a high-purity pig iron production facility in Quebec, Canada. It outlines a three-phase approach, beginning with the construction of an iron pelletizing plant using third-party feed, then expanding to produce direct reduced iron and hot briquetted iron, and ultimately developing the BlackRock mine and production facilities to produce high-purity pig iron and other products. The presentation notes that Strategic's products will be high-value steelmaking inputs and that the BlackRock project is well-positioned near infrastructure to access markets. It argues the company is well-positioned to help enable the transition to lower-carbon electric arc furnace steel
The document summarizes exploration results from a nickel-copper-PGM discovery in Michigan's Upper Peninsula made by Bitterroot Resources Ltd. and Below Exploration Inc. Drilling has intersected disseminated, blebby, and semi-massive sulphide mineralization at the LM Property, including one intercept grading 5.16% nickel and 1.18% copper over 0.75 meters. Assays of rip-up clasts have returned grades of up to 7.13% nickel and 7.91% copper. The results indicate the potential for high grade massive sulphide mineralization at the site, similar to nearby Eagle Mine.
The document is a corporate presentation for Silver One Resource Inc. outlining their business and projects. It discusses their flagship Candelaria Mine Project in Nevada, which was a past-producing silver mine with a large unexploited historic resource. It also mentions their Phoenix Silver Project in Arizona and Cherokee Project in Nevada. The presentation provides an overview of silver's increasing demand profile, particularly from green technologies, and the long-term bullish outlook for silver prices. It summarizes the history and resource at Candelaria, and Silver One's plans to advance exploration and metallurgical work to increase the project's value.
Calibre Mining aims to become a high growth, cash flow focused mid-tier gold producer in the Americas. It currently has three producing mines, three growth assets, 4.0 million ounces of gold reserves, and plans to produce 275,000-300,000 ounces in 2024. Calibre recently acquired the Valentine Gold Mine in Canada, adding 4.0 million ounces of resources. The company has a track record of delivering production growth and reserve increases, and sees potential for further discovery and resource expansion across its portfolio to increase production to over 500,000 ounces by 2026.
How MJ Global Leads the Packaging Industry.pdfMJ Global
MJ Global's success in staying ahead of the curve in the packaging industry is a testament to its dedication to innovation, sustainability, and customer-centricity. By embracing technological advancements, leading in eco-friendly solutions, collaborating with industry leaders, and adapting to evolving consumer preferences, MJ Global continues to set new standards in the packaging sector.
𝐔𝐧𝐯𝐞𝐢𝐥 𝐭𝐡𝐞 𝐅𝐮𝐭𝐮𝐫𝐞 𝐨𝐟 𝐄𝐧𝐞𝐫𝐠𝐲 𝐄𝐟𝐟𝐢𝐜𝐢𝐞𝐧𝐜𝐲 𝐰𝐢𝐭𝐡 𝐍𝐄𝐖𝐍𝐓𝐈𝐃𝐄’𝐬 𝐋𝐚𝐭𝐞𝐬𝐭 𝐎𝐟𝐟𝐞𝐫𝐢𝐧𝐠𝐬
Explore the details in our newly released product manual, which showcases NEWNTIDE's advanced heat pump technologies. Delve into our energy-efficient and eco-friendly solutions tailored for diverse global markets.
Profiles of Iconic Fashion Personalities.pdfTTop Threads
The fashion industry is dynamic and ever-changing, continuously sculpted by trailblazing visionaries who challenge norms and redefine beauty. This document delves into the profiles of some of the most iconic fashion personalities whose impact has left a lasting impression on the industry. From timeless designers to modern-day influencers, each individual has uniquely woven their thread into the rich fabric of fashion history, contributing to its ongoing evolution.
SATTA MATKA SATTA FAST RESULT KALYAN TOP MATKA RESULT KALYAN SATTA MATKA FAST RESULT MILAN RATAN RAJDHANI MAIN BAZAR MATKA FAST TIPS RESULT MATKA CHART JODI CHART PANEL CHART FREE FIX GAME SATTAMATKA ! MATKA MOBI SATTA 143 spboss.in TOP NO1 RESULT FULL RATE MATKA ONLINE GAME PLAY BY APP SPBOSS
3 Simple Steps To Buy Verified Payoneer Account In 2024SEOSMMEARTH
Buy Verified Payoneer Account: Quick and Secure Way to Receive Payments
Buy Verified Payoneer Account With 100% secure documents, [ USA, UK, CA ]. Are you looking for a reliable and safe way to receive payments online? Then you need buy verified Payoneer account ! Payoneer is a global payment platform that allows businesses and individuals to send and receive money in over 200 countries.
If You Want To More Information just Contact Now:
Skype: SEOSMMEARTH
Telegram: @seosmmearth
Gmail: seosmmearth@gmail.com
The Steadfast and Reliable Bull: Taurus Zodiac Signmy Pandit
Explore the steadfast and reliable nature of the Taurus Zodiac Sign. Discover the personality traits, key dates, and horoscope insights that define the determined and practical Taurus, and learn how their grounded nature makes them the anchor of the zodiac.
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Neil Horowitz
On episode 272 of the Digital and Social Media Sports Podcast, Neil chatted with Brian Fitzsimmons, Director of Licensing and Business Development for Barstool Sports.
What follows is a collection of snippets from the podcast. To hear the full interview and more, check out the podcast on all podcast platforms and at www.dsmsports.net
Top mailing list providers in the USA.pptxJeremyPeirce1
Discover the top mailing list providers in the USA, offering targeted lists, segmentation, and analytics to optimize your marketing campaigns and drive engagement.
Discover timeless style with the 2022 Vintage Roman Numerals Men's Ring. Crafted from premium stainless steel, this 6mm wide ring embodies elegance and durability. Perfect as a gift, it seamlessly blends classic Roman numeral detailing with modern sophistication, making it an ideal accessory for any occasion.
https://rb.gy/usj1a2
Top 10 Free Accounting and Bookkeeping Apps for Small BusinessesYourLegal Accounting
Maintaining a proper record of your money is important for any business whether it is small or large. It helps you stay one step ahead in the financial race and be aware of your earnings and any tax obligations.
However, managing finances without an entire accounting staff can be challenging for small businesses.
Accounting apps can help with that! They resemble your private money manager.
They organize all of your transactions automatically as soon as you link them to your corporate bank account. Additionally, they are compatible with your phone, allowing you to monitor your finances from anywhere. Cool, right?
Thus, we’ll be looking at several fantastic accounting apps in this blog that will help you develop your business and save time.
The Most Inspiring Entrepreneurs to Follow in 2024.pdfthesiliconleaders
In a world where the potential of youth innovation remains vastly untouched, there emerges a guiding light in the form of Norm Goldstein, the Founder and CEO of EduNetwork Partners. His dedication to this cause has earned him recognition as a Congressional Leadership Award recipient.
Call8328958814 satta matka Kalyan result satta guessing➑➌➋➑➒➎➑➑➊➍
Satta Matka Kalyan Main Mumbai Fastest Results
Satta Matka ❋ Sattamatka ❋ New Mumbai Ratan Satta Matka ❋ Fast Matka ❋ Milan Market ❋ Kalyan Matka Results ❋ Satta Game ❋ Matka Game ❋ Satta Matka ❋ Kalyan Satta Matka ❋ Mumbai Main ❋ Online Matka Results ❋ Satta Matka Tips ❋ Milan Chart ❋ Satta Matka Boss❋ New Star Day ❋ Satta King ❋ Live Satta Matka Results ❋ Satta Matka Company ❋ Indian Matka ❋ Satta Matka 143❋ Kalyan Night Matka..
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Final ank Satta Matka Dpbos Final ank Satta Matta Matka 143 Kalyan Matka Guessing Final Matka Final ank Today Matka 420 Satta Batta Satta 143 Kalyan Chart Main Bazar Chart vip Matka Guessing Dpboss 143 Guessing Kalyan night
2. 2
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
DISCLAIMERS
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this
presentation. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.
Certain statements contained in this presentation may constitute forward-looking statements under Canadian securities legislation which are not historical facts and are made pursuant to the "safe
harbour" provisions under the United States Private Securities Litigation Reform Act of 1995. Generally, forward-looking information can be identified by the use of forward-looking terminology such as
"expects" or "it is expected", or variations of such words and phrases or statements that certain actions, events or results "will" occur. Forward looking statements in this press release include all estimates
from the PFS such as the cash flow, IRR, NPVs, cash cost, AISC, initial capital, life of mine production, average annual production and payback period time. Such forward-looking statements are based upon
the Company's reasonable expectations and business plan at the date hereof, which are subject to change depending on economic, political and competitive circumstances and contingencies. Readers are
cautioned that such forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause a change in such assumptions and the actual outcomes and estimates to
be materially different from those estimated or anticipated future results, achievements or position expressed or implied by those forward-looking statements. Risks, uncertainties and other factors that
could cause the Company's plans to change include changes in demand for and price of gold and other commodities (such as fuel and electricity) and currencies; changes or disruptions in the securities
markets; legislative, political or economic developments in Brazil; the need to obtain permits and comply with laws and regulations and other regulatory requirements; the possibility that actual results of
work may differ from projections/expectations or may not realize the perceived potential of the Company's projects; risks of accidents, equipment breakdowns and labour disputes or other unanticipated
difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in development programs; operating or technical difficulties in connection with exploration, mining or development
activities; the speculative nature of gold exploration and development, including the risks of diminishing quantities of grades of reserves and resources; and the risks involved in the exploration,
development and mining business. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-
looking statements or forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. The Company disclaims any intention or obligation to
update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable securities laws.
Notes: Estimated All In Sustaining Costs per ounce of gold produced is a Non-GAAP measure that is equal to the total of site mining costs, site and corporate G&A costs, royalties and production taxes,
realized gains/losses on hedging transactions, community and permitting costs relating to current operations, refining costs, site based non-cash remuneration, inventory write-downs, stripping costs,
byproduct credits, reclamation costs, and sustaining costs related to exploration and studies, capital exploration, capitalized stripping and underground mine development, and capital expenditures, divided
by the estimated total ounces of gold produced during the life of the mine. Cash costs per ounce of gold produced is also a non-GAAP financial measure and is equal to on-site mining and processing costs,
on-site general and administration costs, realized gains and losses on hedges due to operating costs, community and permitting costs related to current operations, third party refining and transportation
costs, non-cash site remuneration costs, stripping costs, stockpile and inventory write-downs, exploration costs related to current operations and by-product credits all divided by ounces of gold cost
produced.
Guilherme Gomides Ferreira MAIG of GE21, a qualified person as defined in National Instrument 43-101 has reviewed and approved the technical information contained in this presentation and approves
its publication.
1 Please see Technical Report titled ‘Castelo de Sonhos Project, Pre-Feasibility Study’ by Leonardo de Moraes Soares – MAIG, Guilherme Gomides – MAIG, Ricardo Reis de Paula – MAIG, Porfirio Cabaleiro
– FAIG, Andries Jacobus Strauss – Pr.Eng. ECSA, and Martin Paul Boland – CGeol. GSL effective October 4, 2021
3. 3
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
Brazil’s Next Major Gold Mine
✓ Two large mine start ups in
2024:
• G Mining; Pará State
(expected H2 2024)
• Hochschild; Goiás State
(first gold pour Feb 2024)
1.4 Million oz open pit reserve1
Next steps
• LP permit
Permitted multi-million-ounce
reserve
3
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
Belem
Pará
State
4. 4
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
CASTELO DE
SONHOS
DEVELOPMENT
THE PROJECT
• Large resource1:
• 1.8Moz Indicated plus
0.7Moz inferred
• Investments from Royal
Gold (Aug 2019) and
Auramet (Apr 2022)
ADVANCING TO
CONSTRUCTION
• Oct 2021 PFS (pretax)1:
• $1,550 gold
• IRR 33%
• NPV5 $399M
• $2,000 gold
• IRR 54%
• NPV5 $811M
STRAIGHTFORWARD
MINING
• Mineralization at surface
• 98% gold recovery
• Environmentally clean
• No sulphides
SIGNIFICANT
UPSIDE
• Resource open on strike
and at depth
• ~19km of mineralized
conglomerate reef at the
site
6. 6
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
33%
$1,550 Gold
54%
$2,000 Gold
1.4M Ounces
Current Gold
reserves
121koz/yr
LOM annual production
over 11-yr mine life
146koz/yr
Esperança South,
year 1-6
US$261M
Initial capital
Incl. 20% contingency
$900/oz
AISC
IRR Pre-Tax
COMPELLING ECONOMICS
PFS Base Case: $1,550 Gold
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
US$399M
$1,550 Gold
US$811M
$2,000 Gold
NPV5%
Pre-Tax
US$628M
$1,800 Gold
Please footnote 1 on Slide 2 for Disclosure
7. 7
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
PFS PRODUCTION &
PROPOSED LAYOUT
TWO-PHASE
MINING
• Years 1-6, the higher
grade Esperança South
deposit
• Years 7-11, the
Esperança East and
Center deposits
PROCESS
DESIGN
• 3.6Mtpa plant: CIL
• Feed grades:
• 1.3 g/t gold in
Phase 1,
• 0.8 g/t gold in
Phase 2
• 98% gold recovery
Please footnote 1 on Slide 2 for Disclosure
8. 8
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
Chairman & Director
Mark Jones III
CEO, President &
Director
Nick Appleyard
Independent Director
Carlos Vilhena
Independent Director
ChairofAuditCommittee
Jessica Van Den
Akker
Independent Director
Mark Isto
Lead Independent
Director
Rod McKeen
Independent Director
Eric Zaunscherb
Chief Financial Officer
Scott Brunsdon
Chief Operating Officer
Marcus Brewster
MANAGEMENT & BOARD OF DIRECTORS
9. 9
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
Involved and Invested
BOARD OF DIRECTORS
Our closest community
ESPERANÇA IV
Currently being rebuilt
ESPERANÇA IV SCHOOL
Important to all of us
LOCAL FLORA & FAUNA
Our neighbors are always welcome
A VISIT FROM
LOCAL CYCLISTS
They are the future of the region
EDUCATING THE NEXT
GENERATION
Keeping people and nature healthy
DELIVERING PLANTS
ESG Leadership
Focus on health,
education, and
environment
14. 14
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
Region
INDICATED CATEGORY INFERRED CATEGORY
Tonnes
(Mt)
Grade
(g/t Au)
Ounces
(Moz)
Tonnes
(Mt)
Grade
(g/t Au)
Ounces
(Moz)
Esperança South 29.0 1.3 1.2 10.0 1.2 0.4
Esperança East 5.0 0.8 0.1 12.8 0.7 0.3
Esperança Center 19.1 0.7 0.4 3.3 0.9 0.1
PROJECT TOTAL 53.1 1.0 1.8 26.0 0.9 0.7
Region Tonnes
(Mt)
Grade
(g/t Au)
Ounces
(Moz)
Esperança South 24.2 1.3 1.0
Esperança East 3.1 0.8 0.1
Esperança Center 11.4 0.8 0.3
PROBABLE RESERVES 38.7 1.1 1.4
MINERAL RESERVES
all Probable Classification
MINERAL RESOURCES
Inclusive of Reserves
Further details available in the October 5th 2021 press release entitled “TriStar Gold Announces Positive PFS with 1.4
Moz Gold Reserves and pre-tax 33% IRR and $400 million NPV”
14
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
15. 15
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
TSXV:
TSG
|
OTCQB:
TSGZF
Chairman & Director
Mark Jones III
NEAR-MINE UPSIDE POTENTIAL
Down – dip extensional potential:
Needs to be tested with a “what if”
analysis and optimisation sensitivity
work to focus drilling
Extensions between scheduled pits:
E.g. Esperanca South (ES)
Higher grade paleochannels have
been identified and mapped: to be
used for focused drilling down dip of
ES and Arrias
Strike extension potential: to the
south and north of Esperanca South
16. 16
Tristar
Gold
|
TSXV:
TSG
|
OTCQB:
TSGZF
TSXV:
TSG
|
OTCQB:
TSGZF
ADDITIONAL TARGETS – UPSIDE POTENTIAL
More than 50% of the known
16km strike length yet to be
properly explored and evaluated.
Untested gold-in-soil geochemical
anomalies.
Current outcrop represents the
rim of a large basin and therefore
there are deep targets for both
down-dip paleoplacer and
hydrothermal targets.