LONG TERM PLANNING 
1.Create planning scenario ( MS31 ):
LONG TERM PLANNING 
Click on ‘release & save’ 
Click ‘Immediately’ 
2.Create independent requirement (MD61 ):
LONG TERM PLANNING 
3.Long term planning Stock/requirement list ( MS04 ): 
4.Run LTP ( MS02 ):
LONG TERM PLANNING 
Again check MS04,planned order created 
5.Check available capacity ( CM38 ):
LONG TERM PLANNING 
6.Copy Version ( MS64 ): 
Execute 
Check in MS04
LONG TERM PLANNING 
7.Run MRP in (MD02) & Check stock in MD04:
LONG TERM PLANNING