SlideShare a Scribd company logo
IT Program Assessment 
U.S. Citizenship and Immigration Services (USCIS) – 
Transformation Program 
The DHS CIO conducted a review of the U.S. Citizenship and Immigration Services (USCIS) – Transformation Program in March 2012. 
Description / Background: 
The USCIS Transformation Program seeks to migrate to a modern digital processing capability, while enhancing National Security, and improving efficiencies and effectiveness. This modernization will be achieved by establishing a person-centric, account-based, biometrically supported process that will provide a higher level of service to all applicants, present data regarding a person’s immigration status history within a single view, ensure security checks are completed before an applicant is processed for any immigration benefit, and share relevant information with partner agencies. 
In November 2011, the USCIS Transformation program completed the development phase of Release A1. The program is currently in pre-deployment testing phase. The program has completed several early prototypes, which have proven invaluable for both the System Architect and the Government. The program has demonstrated its ability to begin to transition from the waterfall methodology to an adopted agile methodology. The team has involved users in all phases (including testing), which has given users the opportunity and ability to provide feedback prior to enterprise deployment phase. 
Issues and Risks: 
 
The program continues to experience schedule delays stemming from the completion of Release A1. 
 
The program continues to experience cost overruns. Testing delays have resulted in a revised cost estimate of $71M to complete Release A1/A2. A net increase of $29M above the original Releases A1 and A2 cost estimate of $42M. 
Mitigation Strategy: 
The program seeks approval from the Investment Review Board (IRB) to commit additional funding to complete Releases A1 and A2. The program received approval to commit $20.2M to continue work on Releases A1 and A2. The program must provide a programmatic update to the IRB in order to receive approval to commit the additional $8.8M. 
The program has increased programmatic governmental oversight and involvement in the management in order to reduce response time to questions or concerns that arise.
The program is not allowing any deviations from the agreed upon scope. The Program Office has engaged the DHS Privacy Office and OMB early and often to ensure these offices are fully aware the program’s status. 
Stakeholders are involved in all phases, including testing, to help ensure acceptance. Customers are provided with awareness program updates to help familiarize them with the new forms and interface design. To mitigate any concerns of reduced functionality, the program is holding outreach engagement sessions with all stakeholders and informing other agencies of the revised solution architecture and capabilities. The program is striving to accurately set expectations for the capabilities and functions to be delivered in Release A1 and to ensure that all transitional processes are correct and fully vetted prior to the start of training sessions. 
As a result of the IRB, the following mitigation strategies were recommended: 
 
Focus on completing the testing and delivery of Release A1 before committing to a full A2 development. 
 
Establish an ESC to provide governance oversight. 
 
Implement a productivity analysis. 
Assessment: 
The program’s schedule slipped approximately 14 weeks due to issues discovered during System Acceptance and User Acceptance Testing. As a result of testing delays, the program experienced a net program increase of $29M above the original cost estimate for Releases A1 and A2. Implementation of the transformation program has been delayed due to changes in deployment strategy and insufficiently defined requirements. Per the Investment Review Board’s recommendation, the program has established an Executive Steering Committee (ESC) made up of key DHS and USCIS leadership to review and make decisions on issues impacting the cost, schedule and performance of the program. 
The Office of Inspector General recommended to “ensure that process documentation provides sufficient detail; develop and implement a governance structure to enable streamlined decision making; and ensure that staff with the necessary skills are in place.” In February 2012, the program briefed the DHS Investment Review Board and several mitigation strategies were recommended. 
Although progress has been made, challenges still remain. This program remains under the watchful leadership of both the USCIS and DHS CIO. The CIO assesses the USCIS Transformation Program as a Moderately High Risk investment. 
Score: 2

More Related Content

What's hot

Enterprise Software Implementation
Enterprise Software ImplementationEnterprise Software Implementation
Enterprise Software Implementation
brh184
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure ReportCheryl Burcham
 
Rymer Resume Complete Master 0915
Rymer Resume Complete Master 0915Rymer Resume Complete Master 0915
Rymer Resume Complete Master 0915Robert Rymer
 
Major Financial Institution Rationlizes Project Budgeting Process
Major Financial Institution Rationlizes Project Budgeting ProcessMajor Financial Institution Rationlizes Project Budgeting Process
Major Financial Institution Rationlizes Project Budgeting Process
UMT
 
Project audit & review checklist
Project audit & review checklistProject audit & review checklist
Project audit & review checklistRam Srivastava
 
Project audit & closure
Project audit & closureProject audit & closure
Project audit & closure
Gopalakrishnan P
 
Za project & project cycle management
Za   project & project cycle managementZa   project & project cycle management
Za project & project cycle management
hamza khwaja
 
Software Engineering I by hmftj
Software Engineering I by hmftj Software Engineering I by hmftj
Generic Presentation EEIS
Generic Presentation EEISGeneric Presentation EEIS
Generic Presentation EEISJim Thayer
 
QualiHM: A Requirement Engineering Toolkit for Efficient User Interface Design
QualiHM: A Requirement Engineering Toolkit for Efficient User Interface DesignQualiHM: A Requirement Engineering Toolkit for Efficient User Interface Design
QualiHM: A Requirement Engineering Toolkit for Efficient User Interface Design
Mohamed Boukhebouze
 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
Bhawani N Prasad
 
12. project proposal
12. project proposal12. project proposal
12. project proposal
gryndel
 
GEF Project Cycle Streamlining
GEF Project Cycle StreamliningGEF Project Cycle Streamlining
Resume -Suniel Puri
Resume -Suniel PuriResume -Suniel Puri
Resume -Suniel PuriSuniel Puri
 
Program management audit checklist
Program management audit checklistProgram management audit checklist
Program management audit checklist
Bob Prieto
 
How to survive a Project Management Audit Dec 2-2014
How to survive a Project Management Audit Dec 2-2014How to survive a Project Management Audit Dec 2-2014
How to survive a Project Management Audit Dec 2-2014rhenderson08
 
Agile Program Management Process
Agile Program Management ProcessAgile Program Management Process
Agile Program Management Process
Glen Alleman
 
Program Analyst & Contracting Officer
Program Analyst & Contracting OfficerProgram Analyst & Contracting Officer
Program Analyst & Contracting OfficerCorey Hamilton
 

What's hot (19)

Enterprise Software Implementation
Enterprise Software ImplementationEnterprise Software Implementation
Enterprise Software Implementation
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
 
Rymer Resume Complete Master 0915
Rymer Resume Complete Master 0915Rymer Resume Complete Master 0915
Rymer Resume Complete Master 0915
 
Major Financial Institution Rationlizes Project Budgeting Process
Major Financial Institution Rationlizes Project Budgeting ProcessMajor Financial Institution Rationlizes Project Budgeting Process
Major Financial Institution Rationlizes Project Budgeting Process
 
Project audit & review checklist
Project audit & review checklistProject audit & review checklist
Project audit & review checklist
 
Project audit & closure
Project audit & closureProject audit & closure
Project audit & closure
 
Za project & project cycle management
Za   project & project cycle managementZa   project & project cycle management
Za project & project cycle management
 
Software Engineering I by hmftj
Software Engineering I by hmftj Software Engineering I by hmftj
Software Engineering I by hmftj
 
Generic Presentation EEIS
Generic Presentation EEISGeneric Presentation EEIS
Generic Presentation EEIS
 
QualiHM: A Requirement Engineering Toolkit for Efficient User Interface Design
QualiHM: A Requirement Engineering Toolkit for Efficient User Interface DesignQualiHM: A Requirement Engineering Toolkit for Efficient User Interface Design
QualiHM: A Requirement Engineering Toolkit for Efficient User Interface Design
 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
 
12. project proposal
12. project proposal12. project proposal
12. project proposal
 
GEF Project Cycle Streamlining
GEF Project Cycle StreamliningGEF Project Cycle Streamlining
GEF Project Cycle Streamlining
 
Project closure and audit
Project closure and auditProject closure and audit
Project closure and audit
 
Resume -Suniel Puri
Resume -Suniel PuriResume -Suniel Puri
Resume -Suniel Puri
 
Program management audit checklist
Program management audit checklistProgram management audit checklist
Program management audit checklist
 
How to survive a Project Management Audit Dec 2-2014
How to survive a Project Management Audit Dec 2-2014How to survive a Project Management Audit Dec 2-2014
How to survive a Project Management Audit Dec 2-2014
 
Agile Program Management Process
Agile Program Management ProcessAgile Program Management Process
Agile Program Management Process
 
Program Analyst & Contracting Officer
Program Analyst & Contracting OfficerProgram Analyst & Contracting Officer
Program Analyst & Contracting Officer
 

Similar to Itpa uscis-transformation2012

Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyTimothy Cochran
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12
Jason Uyder
 
IT 625 Final Project Case Study Medical Informatics Backgroun.docx
IT 625 Final Project Case Study Medical Informatics Backgroun.docxIT 625 Final Project Case Study Medical Informatics Backgroun.docx
IT 625 Final Project Case Study Medical Informatics Backgroun.docx
priestmanmable
 
Overall project management
Overall project managementOverall project management
Overall project management
Desh Kapoor
 
Egf Mgt Strengthening Program
Egf Mgt Strengthening ProgramEgf Mgt Strengthening Program
Egf Mgt Strengthening Program
Roy Consulta
 
Partners in Protection-Feb2008
Partners in Protection-Feb2008Partners in Protection-Feb2008
Partners in Protection-Feb2008
MatrixDesign
 
Hr action plan
Hr action planHr action plan
Hr action plan
David Lumempouw
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
tigcap
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
tigcap
 
JamesCarr461FinalProject
JamesCarr461FinalProjectJamesCarr461FinalProject
JamesCarr461FinalProjectJames Carr
 
John Karagiannis CV
John Karagiannis CVJohn Karagiannis CV
Leonard Smith Resume.docxGE only
Leonard Smith Resume.docxGE onlyLeonard Smith Resume.docxGE only
Leonard Smith Resume.docxGE onlyLeonard Smith
 
M&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburM&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taibur
Dr. Md. Taibur Rahman
 
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docxUnit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
willcoxjanay
 
How to Implement & Manage an Energy Management Program
How to Implement & Manage an Energy Management ProgramHow to Implement & Manage an Energy Management Program
How to Implement & Manage an Energy Management Program
Energy Advantage
 
Monitoring and Evaluation Policy
Monitoring and Evaluation PolicyMonitoring and Evaluation Policy
Monitoring and Evaluation PolicyKomal Zahra
 
Developing and Implementing an Audit Program Model in the Uniform Guidance Era
Developing and Implementing an Audit Program Model in the Uniform Guidance Era Developing and Implementing an Audit Program Model in the Uniform Guidance Era
Developing and Implementing an Audit Program Model in the Uniform Guidance Era
April Heyward
 
New Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceNew Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceSusan Schanta
 
Project Management Process
Project Management ProcessProject Management Process
Project Management Process
Adepitan Oluwasoro, PMP, CSM, MBA
 

Similar to Itpa uscis-transformation2012 (20)

PM
PMPM
PM
 
Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the Company
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12
 
IT 625 Final Project Case Study Medical Informatics Backgroun.docx
IT 625 Final Project Case Study Medical Informatics Backgroun.docxIT 625 Final Project Case Study Medical Informatics Backgroun.docx
IT 625 Final Project Case Study Medical Informatics Backgroun.docx
 
Overall project management
Overall project managementOverall project management
Overall project management
 
Egf Mgt Strengthening Program
Egf Mgt Strengthening ProgramEgf Mgt Strengthening Program
Egf Mgt Strengthening Program
 
Partners in Protection-Feb2008
Partners in Protection-Feb2008Partners in Protection-Feb2008
Partners in Protection-Feb2008
 
Hr action plan
Hr action planHr action plan
Hr action plan
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
JamesCarr461FinalProject
JamesCarr461FinalProjectJamesCarr461FinalProject
JamesCarr461FinalProject
 
John Karagiannis CV
John Karagiannis CVJohn Karagiannis CV
John Karagiannis CV
 
Leonard Smith Resume.docxGE only
Leonard Smith Resume.docxGE onlyLeonard Smith Resume.docxGE only
Leonard Smith Resume.docxGE only
 
M&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburM&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taibur
 
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docxUnit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
Unit 1 Due Date7122015Deliverable Length1–2 pages and projec.docx
 
How to Implement & Manage an Energy Management Program
How to Implement & Manage an Energy Management ProgramHow to Implement & Manage an Energy Management Program
How to Implement & Manage an Energy Management Program
 
Monitoring and Evaluation Policy
Monitoring and Evaluation PolicyMonitoring and Evaluation Policy
Monitoring and Evaluation Policy
 
Developing and Implementing an Audit Program Model in the Uniform Guidance Era
Developing and Implementing an Audit Program Model in the Uniform Guidance Era Developing and Implementing an Audit Program Model in the Uniform Guidance Era
Developing and Implementing an Audit Program Model in the Uniform Guidance Era
 
New Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceNew Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program Assurance
 
Project Management Process
Project Management ProcessProject Management Process
Project Management Process
 

Itpa uscis-transformation2012

  • 1. IT Program Assessment U.S. Citizenship and Immigration Services (USCIS) – Transformation Program The DHS CIO conducted a review of the U.S. Citizenship and Immigration Services (USCIS) – Transformation Program in March 2012. Description / Background: The USCIS Transformation Program seeks to migrate to a modern digital processing capability, while enhancing National Security, and improving efficiencies and effectiveness. This modernization will be achieved by establishing a person-centric, account-based, biometrically supported process that will provide a higher level of service to all applicants, present data regarding a person’s immigration status history within a single view, ensure security checks are completed before an applicant is processed for any immigration benefit, and share relevant information with partner agencies. In November 2011, the USCIS Transformation program completed the development phase of Release A1. The program is currently in pre-deployment testing phase. The program has completed several early prototypes, which have proven invaluable for both the System Architect and the Government. The program has demonstrated its ability to begin to transition from the waterfall methodology to an adopted agile methodology. The team has involved users in all phases (including testing), which has given users the opportunity and ability to provide feedback prior to enterprise deployment phase. Issues and Risks:  The program continues to experience schedule delays stemming from the completion of Release A1.  The program continues to experience cost overruns. Testing delays have resulted in a revised cost estimate of $71M to complete Release A1/A2. A net increase of $29M above the original Releases A1 and A2 cost estimate of $42M. Mitigation Strategy: The program seeks approval from the Investment Review Board (IRB) to commit additional funding to complete Releases A1 and A2. The program received approval to commit $20.2M to continue work on Releases A1 and A2. The program must provide a programmatic update to the IRB in order to receive approval to commit the additional $8.8M. The program has increased programmatic governmental oversight and involvement in the management in order to reduce response time to questions or concerns that arise.
  • 2. The program is not allowing any deviations from the agreed upon scope. The Program Office has engaged the DHS Privacy Office and OMB early and often to ensure these offices are fully aware the program’s status. Stakeholders are involved in all phases, including testing, to help ensure acceptance. Customers are provided with awareness program updates to help familiarize them with the new forms and interface design. To mitigate any concerns of reduced functionality, the program is holding outreach engagement sessions with all stakeholders and informing other agencies of the revised solution architecture and capabilities. The program is striving to accurately set expectations for the capabilities and functions to be delivered in Release A1 and to ensure that all transitional processes are correct and fully vetted prior to the start of training sessions. As a result of the IRB, the following mitigation strategies were recommended:  Focus on completing the testing and delivery of Release A1 before committing to a full A2 development.  Establish an ESC to provide governance oversight.  Implement a productivity analysis. Assessment: The program’s schedule slipped approximately 14 weeks due to issues discovered during System Acceptance and User Acceptance Testing. As a result of testing delays, the program experienced a net program increase of $29M above the original cost estimate for Releases A1 and A2. Implementation of the transformation program has been delayed due to changes in deployment strategy and insufficiently defined requirements. Per the Investment Review Board’s recommendation, the program has established an Executive Steering Committee (ESC) made up of key DHS and USCIS leadership to review and make decisions on issues impacting the cost, schedule and performance of the program. The Office of Inspector General recommended to “ensure that process documentation provides sufficient detail; develop and implement a governance structure to enable streamlined decision making; and ensure that staff with the necessary skills are in place.” In February 2012, the program briefed the DHS Investment Review Board and several mitigation strategies were recommended. Although progress has been made, challenges still remain. This program remains under the watchful leadership of both the USCIS and DHS CIO. The CIO assesses the USCIS Transformation Program as a Moderately High Risk investment. Score: 2