SlideShare a Scribd company logo
Investment in solar and wind generation in
Australia- lessons learned
Dr Julian Eggleston
Director – Technical
Specialist
Australian Energy Market
Commission (AEMC)
Sydney, Australia
julian.eggleston@aemc.gov.au
Dr Tim Nelson
Executive General Manager
– Economic Analysis
Australian Energy Market
Commission (AEMC)
Sydney, Australia
Tim.nelson@aemc.gov.au
Tom Walker
Senior Economist
Australian Energy Market
Commission (AEMC)
Sydney, Australia
Tom.walker@aemc.gov.au
Greg Williams
Senior Economist
Australian Energy Market
Commission (AEMC)
Sydney, Australia
Greg.williams@aemc.gov.au
The Australian National Electricity Market (NEM) rules
and arrangements were developed in the 1990s when the
majority of the energy was generated from large thermal
generating units that were relatively close to the major
load centres. These generation and load centres are also
interconnected to allow energy to be transferred and
traded to improve reliability and efficiency. New
generators have open access to the network provided
they negotiate their connection with the network
operator and meet acceptable performance standards.
In the past decade changes in technology and climate
change incentives have driven an evolution in the NEM
rules and market arrangements. However, in recent
years pace of change has increased and there has been a
dramatic increase in the number of solar and wind
generating systems installed and actively being assessed.
These generating systems are smaller than the existing
thermal generating units and are generally connected in
more remote low voltage locations due to resource
availability.
The paper will discuss how the NEM has evolved under
the high volume of concurrent connection applications,
including:
• the need to coordinate generation and network
investment to avoid excessive congestion,
including the role of the Australian Energy
Market Operator’s (AEMO’s) integrated system
plan;
• the negotiation of performance standards in the
presence of multiple concurrent connection
applications, including the need for system
strength remediation;
• the impact on network losses and the associated
loss factors used to provide locational
investment signals.
I. INTRODUCTION AND CONTEXT
Like many developed economies, Australian policy makers
struggled to integrate a comprehensive climate change
policy within an energy market framework. Pollitt and
Haney (2013, p. 9) make the observation that when markets
such as the Australian National Electricity Market (NEM)
were liberalised, ‘competitiveness was the overriding
priority. Today, competitiveness, energy security and
decarbonisation are the three main energy policy priorities.’
Without a comprehensive national framework implemented
by the Commonwealth Government, a proliferation of
piecemeal state-based public policies aimed at encouraging
the adoption of new supply options with lower greenhouse
gas emission profiles have added significantly to the
existing generation capital stock. These technologies have a
distinctly different cost profile structure to existing and
competing thermal (coal and gas) units. Fuel is effectively
free (i.e. wind and sun) but with material up-front capital
costs. At a peak, there were six policies in place to drive
capital substitution or addition, including: the New South
Wales (NSW) Greenhouse Gas Abatement Scheme
(GGAS); the Commonwealth’s Large-Scale Renewable
Energy Target (LRET); the Small-Scale Renewable Energy
Target (SRES); the Queensland (QLD) 18% Gas Scheme;
various energy efficiency policies (e.g. Victorian Energy
Efficiency Target or VEET); and Victoria’s premium solar
feed-in tariffs (PFiT). A carbon price was also established
through the Clean Energy Future package but then repealed
within three-years.
Given declining demand, and significant uptake of
subsidised embedded small-scale photovoltaic (PV) and
large-scale renewable generation, there was an oversupply
of capacity with prices well below the cost of new-entry
until 2015 (see Nelson et al., 2015). This sustained low
pricing resulted in several incumbent ageing coal-fired
generators retiring over several years with the most capacity
being retired in 2017. In most cases, less than a year’s notice
was provided of the generator closure. With such little time
available to participants to replace the capacity being
withdrawn, wholesale prices increased markedly in 2017.
Prices are now at the highest they have ever been due to the
disorderly transition that has occurred. This is shown in
Figure 1.
FIGURE 1. VALUE OF NEM TRADING FROM 2001 TO 2019 (SEPARATED
INTO PRICE BANDS)
Around 5,000 MW of dispatchable generation (coal and gas)
has been retired from the NEM while approximately 18,000
MW of non-dispatchable generation (wind, solar etc.) has
been, or is in the process of being, commissioned. The
installed capacity in the market is shifting from a small
number of geographically concentrated large coal fired
power stations, located within coal regions such as the
Hunter Valley in New South Wales, to a large number of
smaller units located throughout the system where fuel (i.e.
wind and sun) is available. This has had significant impacts
on both the way in which the energy-only NEM functions;
and system security and reliability.
II. RATE OF RENEWABLE CONNECTIONS
SINCE 2015
As discussed above the rate of commissioning of grid
connected renewable solar and wind generation has
accelerated in recent years. This can be seen in Figure 2 that
shows the rate of uptake of solar and wind generation in the
NEM from 2009 to 2019.
FIGURE 2. UPTAKE OF RENEWABLE GENERATION IN THE NEM FROM
2009 TO 2019
This means that the levels of variable renewable generation
penetration in the NEM are amongst the highest in the
world, as shown in Figure 3.
FIGURE 3. UPTAKE OF VARIABLE RENEWABLE GENERATION
As well as the nature of the generation mix changing,
predominantly from coal based generation to an increased
proportion of solar and wind generation, the physical
location of the recently installed solar and wind generation
is connecting in very different locations. Figures 4 and 5
show the changes in the generation in New South Wales,
Victoria and South Australia from 2015 to 2019.
FIGURE 4. NSW, Victorian and South Australian generation IN 2015
FIGURE 5. NSW, VICTORIAN AND SOUTH AUSTRALIAN GENERATION IN
2019
0
500
1000
1500
2000
2500
3000
3500
4000
4500
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Capacity(MW)
Wind Large-scale solar
Committed
The figures show that the majority of the generation that
was connected in 2015, much of which was operating at the
commencement of the NEM in 1998, were large coal units
located relatively close to the major load centres in the state
capitals. These coal-fired power stations were connected to
strong high voltage networks (275kV, 330kV and 500kV)
with multiple parallel circuits. The Snowy scheme located
on the New South Wales and Victoria boarder also strongly
connected to major load centres of Sydney and Melbourne
(330kV). Additional gas powered intermediate and peaking
generation is also generally located near the state capitals
and strongly connected to the transmission network. The
flows on the transmission networks generally followed well-
defined patterns throughout the day, between the seasons
and from one year to the next.
In the 2000s large-scale wind generation started being
commissioned for the first time. This generally occurred in
in relatively remote locations associated with a good wind
resources and comparatively inexpensive land. However,
these wind farms were not located near the strong parts of
the existing transmission network, rather were connected to
lower voltage parts of the transmission and distribution
networks. In more recent years grid connected solar
generating systems have also been commissioned.
From 2015 the rate at which grid connected solar and wind
generation entered the market began to accelerate with most
of this generation connected in remote parts of the network.
This was largely due to a tight supply/demand dynamic
indicating resource scarcity and policy uncertainty in
relation to the Large-Scald Renewable Energy Target being
resolved. In particular:
• large quantities of grid connected solar and wind
generation have been connected in north-western
Victoria and south-western New South Wales;
• there is now around 1,500 MW of wind in rural
South Australia and, at times of minimum demand,
South Australia sometimes produces so much wind
energy, the residual energy is exported to Victoria;
and
• several large grid connected solar generation have
been connected in northern Queensland.
In each case, these generating systems were connected to the
existing networks that were originally commissioned to
supply rural cities and towns remote from the state capitals,
generally with limited or no local generation. The
commissioning of large quantities of this grid connected
variable renewable generation at these remote locations in
the network, and the associated reduction in the output from
the existing thermal generation, has dramatically changed
the flows of energy in the transmission and distribution
networks. This has caused a range of problems including:
• over-loading of the associated transmission and
distribution networks, resulting in periods where
the output of this generation is constrained during
periods of high wind or solar radiation
• low fault level, often referred to as low system
strength, resulting in potential system instability
and increased numbers of generating systems being
commissioned with synchronous condensers
• the losses in the associated networks have
increased, especially due to the long distances
between most of the new generation and the major
load centres of the state capitals.
These problems are discussed further in the following
sections.
III. COORDINATION OF GENERATION AND
NETWORK INVESTMENT
The NEM is made up of five pricing regions, which
approximately follow the political boundaries of the states
of South Australia, Victoria, Tasmania, New South Wales
and Queensland.
Under the existing transmission access regime in the NEM,
all generation and load which participates in the wholesale
market is settled on a region-wide price for its physical
output or consumption (net of losses), regardless of its
location in a region. This region-wide price is called the
'regional reference price'. When the physical output of a
generator is reduced - for example, due to the presence of a
transmission constraint - its revenue is similarly reduced.
While this approach is relatively simple, it also abstracts
away from the technical and economic realities of the
system. When constraints arise on the transmission network
within a region, the underlying cost of an additional unit of
generation to serve an additional unit of load at a particular
location (known as the 'locational marginal cost' of
generation) differs from location to location. The marginal
cost of an additional unit of generation tends to be relatively
low in areas which have an abundance of generation versus
load and limited ability for generation to flow to other areas
of the network, and vice versa.
Economic efficiency is promoted when prices reflect the
marginal cost of the provision of a particular product or
service. Numerous issues are arising in the NEM because of
the incentives created by the difference between the
locationally specific cost of an additional unit generation
and its region-wide price. Furthermore, because prices for
electricity are not locationally specific, the difference in cost
between locations (and hence the value of transmission
capacity) is not explicitly valued.
A foundational principle of the NEM when it was created
was that decisions to invest in generation capacity are made
by businesses operating in a competitive environment, rather
than by vertically integrated monopolies. Investment in
generation assets is market-driven and takes account of
expectations of future demand, the location of energy
sources, access to land and water and access to transmission.
The result is that risks associated with generation investment
rest with those businesses.
In contrast, transmission investment decisions remain the
responsibility of regional transmission network businesses,
guided by the Australian Energy Market Operator’s
(AEMO’s) Integrated System Plan. 1
Transmission
businesses are subject to incentive-based economic
regulation of their revenues for the provision of transmission
services, as well as various other obligations relating to
reliability, safety and investment decision-making processes.
Generation, transmission and storage are complements and
substitutes. They are part of an integrated system. This
implies that investment and operational decisions by
generators, storage proponents and transmission businesses
should work together to achieve overall economically
efficient outcomes.
Current locational signals such as transmission losses,
congestion and inter-regional price variation do provide a
degree of incentive for efficient generator and storage
location. However, these signals are blunt, incomplete and
imprecise.
Due to the current lack of locational price signals in the
transmission framework, investors are locating their
generation assets where the network has limited or no
capacity for the additional generation capacity to be
dispatched. Increasingly, storage may play an important role
in managing both transmission congestion and variability in
supply from generation, but storage is similarly not subject
to the locational price signals.
Further, having made a locational decision, a generator or
storage unit is not readily able to manage the risks arising
from transmission losses, congestion, and to a lesser extent,
inter-regional price variation.
In turn, a generator or storage unit which connects in a fuel-
rich area may influence the investment case for a
transmission upgrade, even if the lowest overall cost
solution was to invest in a less fuel-rich area with better
transmission infrastructure.
This situation is likely resulting in higher overall system
costs, and ultimately elevated consumer bills.
In the past, this and other problems relating to regional
pricing have tended to be modest, and so the cost of change
has outweighed the benefits. In an environment of relatively
low levels of generation and transmission investment, the
benefits of improved investment efficiency and coordination
are necessarily relatively low. Such an environment also
means that transmission risks faced by generators are
relatively predictable and stable. However, for the reasons
outlined, this is no longer the environment that the NEM
finds itself in.
These issues are being considered in Australia in order to
promote better coordination between investment in
generation by competitive entities and the regulated
monopoly network businesses. Therefore, different design
choices and trade-offs better suited to the current
environment may need to be made.
1 The exception is Victoria where decisions to augment the
transmission network are made by the Australian Energy
Market Operator (AEMO).
IV. NEGOTIATION OF PERFORMANCE
STANDARDS CONCURRENT CONNECTION
APPLICATIONS
The connection of new generating systems in the NEM can
be very competitive. This means that the individual
generator proponents treat their projects as commercial in
confidence and generally release little information on their
projects. This has become very difficult to manage in the
current environment where many connecting generating
systems are being developed and connected concurrently
and within close proximity.
New generators connecting the NEM must meet the required
technical performance standards, which were updated in
2018 to reflect the lessons learned from a 2016 black system
event in South Australia and to better reflect the
characteristics of asynchronous generation including
inverter based plant. The proponents of the connecting
generation must perform connection studies to demonstrate
that their performance meets the required standards, based
on the range of system conditions that apply at the time of
connection.
At the same time, the effective short circuit ratios (SCRs) in
the network where new generating systems are connecting
have been dropping due to their remote location and the
retirement of existing synchronous (coal) generation. These
trends have raised stability concerns and a system strength
“do no harm obligation” was placed on connecting
generators from July 2018. This requires the connecting
generator to mitigate any system stability issues that occur
as a result of connecting their generating system.
In addition, traditional power system modelling tools are
often no longer fit for purpose due to the reducing SCRs.
This means that electro-magnetic transient (EMT) modelling
is required to assess both the technical performance and do
no harm obligations of connecting generating systems.
This combination of performance and system strength
requirements, in the context of more intensive modelling
requirements, has become very challenging for generator
proponents in the current environment where multiple
concurrent projects are being assessed at once. This can
mean that a generator proponent needs to repeat many EMT
studies when a competitor’s project is connected nearby,
thus required their existing assessment to be updated.
V. IMPACT ON NETWORK LOSSES
The prices received by generators, and paid by loads, are the
product of the price calculated at the regional reference node
(located at the largest load centres in each state) and the
static marginal loss factor (MLF) for that connection point.
The prices at the regional reference nodes are calculated
from the offers submitted by the generators and represent
the cost of meeting an additional MW of load at each of the
regional reference nodes. Thus, when comparing an
increment of output from a generating system it is necessary
to also consider its marginal impact on the losses in the
transmission network, hence the use of MLFs. As well as
promoting efficient dispatch and pricing, the use of MLFs
also provides longer-term locational investment signals that
incentivise generators to connect near loads, and visa versa.
Rather than recalculating the loss factors for every 5-minute
dispatch interval, a single static MLF value is calculated that
is estimated to represent the impact of that generating
system on losses for the financial year (July to June). These
static MLFs are calculated annually by AEMO using the
generation and load patterns anticipated for the next
financial year, volume weighted by the generation or load
pattern of the generating system in question. Using annual
static MLFs, rather than real-time loss factors, is expected to
increase the liquidity of the markets for financial derivative
contracts and hence to facilitate efficient investment in new
generation. However, using annual static MLFs can
compromise the efficiency of dispatch and locational
pricing.
As discussed above, much of the new generation that has
been commissioned in the last few years has connected in
the lower voltage network and much further away from the
major load centres. This change to the generation mix has
resulted in a significant increase in the losses in the
transmission network, with an associated decrease in the
MLFs (and hence the effective price received) for this new
generation. Figures 6 and 7 show the changes in the MLFs
for New South Wales and Victoria from 2018/19 to
2019/20.
The MLFs for south-western New South Wales and north-
western Victoria fell significantly for 2019/20 due to the
dramatic increase in solar and wind generation in that area.
In one case, the MLFs of a new solar generator dropped by
approximately 25%, with a corresponding decrease in the
generator’s revenue. This has become a serious concern for
many developers and investors in these renewable
generating systems.
The AEMC is currently considering whether there is a better
approach to calculating MLFs, while retaining the locational
nature of the current approach.
Figure 6: Changes of the NSW MLFs from 2018/19 to 2019/20
source: AEMO
Figure 7: Changes of the Victorian MLFs from 2018/19 to 2019/20
source: AEMO
VI. CONCLUSION
The paper has considered how the NEM is evolving under
the high volume of concurrent connection applications for
new generation, including:
• the need to coordinate generation and network
investment to avoid excessive congestion,
including the role of the AEMO integrated system
plan;
• the negotiation of performance standards in the
presence of multiple concurrent connection
applications, including the need for system strength
remediation;
• the impact on network losses and the associated
loss factors used to provide locational investment
signals.
VII. REFERENCES
Pollitt, M. and Haney, A. 2013, ‘Dismantling a competitive
retail Electricity Market: Residential Market Reforms in
Great Britain’, The Electricity Journal, Vol. 27, No. 1, pp.
66–73.
Nelson, T., Reid, C. and McNeill, J. (2015), ‘Energy-Only
Markets and Renewable Energy Targets: Complementary
Policy or Policy Collision’, Economic Analysis and Policy,
46, 25–42.

More Related Content

What's hot

Emergence-of-hybrid renewable energy systems
Emergence-of-hybrid renewable energy systemsEmergence-of-hybrid renewable energy systems
Emergence-of-hybrid renewable energy systemsSwarnim Srivastava
 
Precincts to Support the Delivery of Zero Energy
Precincts to Support the Delivery of Zero EnergyPrecincts to Support the Delivery of Zero Energy
Precincts to Support the Delivery of Zero Energy
Turlough Guerin GAICD FGIA
 
Pct Solution For Emerging Energy Markets
Pct Solution For Emerging Energy MarketsPct Solution For Emerging Energy Markets
Pct Solution For Emerging Energy Markets
pacificcresttrans
 
IBM Wind Power Point of View
IBM Wind Power Point of ViewIBM Wind Power Point of View
IBM Wind Power Point of Viewbenhanley77
 
A Grid Dominated by Wind and Solar is Possible: South Australia Case Study
A Grid Dominated by Wind and Solar is Possible: South Australia Case StudyA Grid Dominated by Wind and Solar is Possible: South Australia Case Study
A Grid Dominated by Wind and Solar is Possible: South Australia Case Study
CatherineRizos
 
Power Sector Analysis Report 2017_Sultanate of Oman
Power Sector Analysis Report 2017_Sultanate of Oman Power Sector Analysis Report 2017_Sultanate of Oman
Power Sector Analysis Report 2017_Sultanate of Oman
Shoby P.Jacob
 
New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017
TransGrid AU
 
Energy crises in pakistan
Energy crises in pakistanEnergy crises in pakistan
Energy crises in pakistanShehzad Imran
 
ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
Power System Operation
 
Governing Infrastructure Interdependencies, Jim Watson, UKERC
Governing Infrastructure Interdependencies, Jim Watson, UKERCGoverning Infrastructure Interdependencies, Jim Watson, UKERC
Governing Infrastructure Interdependencies, Jim Watson, UKERC
UK Energy Research Centre (UKERC)
 
Energy Demand and Energy Policy, Jim Watson, UKERC
Energy Demand and Energy Policy, Jim Watson, UKERCEnergy Demand and Energy Policy, Jim Watson, UKERC
Energy Demand and Energy Policy, Jim Watson, UKERC
UK Energy Research Centre (UKERC)
 
Solar power in britain pdi
Solar power in britain pdiSolar power in britain pdi
Solar power in britain pdi
jeanphilippeguy
 
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
TransGrid AU
 
Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...
Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...
Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...
UK Energy Research Centre (UKERC)
 
The New Role of Renewable Energy Systems In Developing GCC Electricity Market
The New Role of Renewable Energy Systems In Developing GCC Electricity MarketThe New Role of Renewable Energy Systems In Developing GCC Electricity Market
The New Role of Renewable Energy Systems In Developing GCC Electricity Market
CSCJournals
 
Overview of Energy in Utah and Utah's Energy Goals
Overview of Energy in Utah and Utah's Energy GoalsOverview of Energy in Utah and Utah's Energy Goals
Overview of Energy in Utah and Utah's Energy Goals
State of Utah, Salt Lake City
 
I010326469
I010326469I010326469
I010326469
IOSR Journals
 
The UK’s Energy Policy
The UK’s Energy PolicyThe UK’s Energy Policy

What's hot (18)

Emergence-of-hybrid renewable energy systems
Emergence-of-hybrid renewable energy systemsEmergence-of-hybrid renewable energy systems
Emergence-of-hybrid renewable energy systems
 
Precincts to Support the Delivery of Zero Energy
Precincts to Support the Delivery of Zero EnergyPrecincts to Support the Delivery of Zero Energy
Precincts to Support the Delivery of Zero Energy
 
Pct Solution For Emerging Energy Markets
Pct Solution For Emerging Energy MarketsPct Solution For Emerging Energy Markets
Pct Solution For Emerging Energy Markets
 
IBM Wind Power Point of View
IBM Wind Power Point of ViewIBM Wind Power Point of View
IBM Wind Power Point of View
 
A Grid Dominated by Wind and Solar is Possible: South Australia Case Study
A Grid Dominated by Wind and Solar is Possible: South Australia Case StudyA Grid Dominated by Wind and Solar is Possible: South Australia Case Study
A Grid Dominated by Wind and Solar is Possible: South Australia Case Study
 
Power Sector Analysis Report 2017_Sultanate of Oman
Power Sector Analysis Report 2017_Sultanate of Oman Power Sector Analysis Report 2017_Sultanate of Oman
Power Sector Analysis Report 2017_Sultanate of Oman
 
New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017
 
Energy crises in pakistan
Energy crises in pakistanEnergy crises in pakistan
Energy crises in pakistan
 
ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Governing Infrastructure Interdependencies, Jim Watson, UKERC
Governing Infrastructure Interdependencies, Jim Watson, UKERCGoverning Infrastructure Interdependencies, Jim Watson, UKERC
Governing Infrastructure Interdependencies, Jim Watson, UKERC
 
Energy Demand and Energy Policy, Jim Watson, UKERC
Energy Demand and Energy Policy, Jim Watson, UKERCEnergy Demand and Energy Policy, Jim Watson, UKERC
Energy Demand and Energy Policy, Jim Watson, UKERC
 
Solar power in britain pdi
Solar power in britain pdiSolar power in britain pdi
Solar power in britain pdi
 
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
 
Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...
Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...
Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...
 
The New Role of Renewable Energy Systems In Developing GCC Electricity Market
The New Role of Renewable Energy Systems In Developing GCC Electricity MarketThe New Role of Renewable Energy Systems In Developing GCC Electricity Market
The New Role of Renewable Energy Systems In Developing GCC Electricity Market
 
Overview of Energy in Utah and Utah's Energy Goals
Overview of Energy in Utah and Utah's Energy GoalsOverview of Energy in Utah and Utah's Energy Goals
Overview of Energy in Utah and Utah's Energy Goals
 
I010326469
I010326469I010326469
I010326469
 
The UK’s Energy Policy
The UK’s Energy PolicyThe UK’s Energy Policy
The UK’s Energy Policy
 

Similar to Investment in solar and wind generation in australia lessons learned

Australia solar power sector analysis
Australia solar power sector analysisAustralia solar power sector analysis
Australia solar power sector analysis
Rajesh Sarma
 
Independent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity MarketIndependent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity Market
Turlough Guerin GAICD FGIA
 
ISO New England Remarks Made During Jan 16, 2016 Webinar
ISO New England Remarks Made During Jan 16, 2016 WebinarISO New England Remarks Made During Jan 16, 2016 Webinar
ISO New England Remarks Made During Jan 16, 2016 Webinar
Marcellus Drilling News
 
Opportunities for wind energy in NSW
Opportunities for wind energy in NSWOpportunities for wind energy in NSW
Opportunities for wind energy in NSW
NSW Environment and Planning
 
Feasibility Study of Standalone Hybrid Power System Modeled With Photovoltaic...
Feasibility Study of Standalone Hybrid Power System Modeled With Photovoltaic...Feasibility Study of Standalone Hybrid Power System Modeled With Photovoltaic...
Feasibility Study of Standalone Hybrid Power System Modeled With Photovoltaic...
inventionjournals
 
Australia solar power sector opportunity analysis
Australia solar power sector opportunity analysisAustralia solar power sector opportunity analysis
Australia solar power sector opportunity analysis
Rajesh Sarma
 
Clean Energy Australia Report
Clean Energy Australia ReportClean Energy Australia Report
Clean Energy Australia Report
Turlough Guerin GAICD FGIA
 
Download Australia solar power sector future outlook 2020
Download Australia solar power sector future outlook 2020Download Australia solar power sector future outlook 2020
Download Australia solar power sector future outlook 2020
KuicK Research
 
Australia solar power sector future outlook 2020
Australia solar power sector future outlook 2020Australia solar power sector future outlook 2020
Australia solar power sector future outlook 2020
Rajesh Sarma
 
All Energy 2017_TransGrid
All Energy 2017_TransGridAll Energy 2017_TransGrid
All Energy 2017_TransGrid
TransGrid AU
 
VRE: Solar and Wind Energy
VRE: Solar and Wind EnergyVRE: Solar and Wind Energy
VRE: Solar and Wind Energy
John Angelo Buscado
 
Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Challenges and Benefits of Integrating the Renewable Energy Technologies into...Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Power System Operation
 
IFN AiE Presentation May16 web
IFN AiE Presentation May16 webIFN AiE Presentation May16 web
IFN AiE Presentation May16 webJonathan Upson
 
ISO New England - 2016 Regional Electricity Outlook
ISO New England - 2016 Regional Electricity OutlookISO New England - 2016 Regional Electricity Outlook
ISO New England - 2016 Regional Electricity Outlook
Marcellus Drilling News
 
seminar report on optimal placement and optimal sizing of DG
seminar report on optimal placement and optimal sizing of DGseminar report on optimal placement and optimal sizing of DG
seminar report on optimal placement and optimal sizing of DG
khemraj298
 
INTRODUCTION wind energy and its type .pptx
INTRODUCTION wind energy and its type .pptxINTRODUCTION wind energy and its type .pptx
INTRODUCTION wind energy and its type .pptx
mansi21bphn002
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Energy Network marcus evans
 
The Energy Crisis | Biocity Studio
The Energy Crisis | Biocity StudioThe Energy Crisis | Biocity Studio
The Energy Crisis | Biocity Studio
Biocity Studio
 
Regulatory Burden in the Renewable Energy Sector in NSW
Regulatory Burden in the Renewable Energy Sector in NSWRegulatory Burden in the Renewable Energy Sector in NSW
Regulatory Burden in the Renewable Energy Sector in NSW
Turlough Guerin GAICD FGIA
 

Similar to Investment in solar and wind generation in australia lessons learned (20)

Australia solar power sector analysis
Australia solar power sector analysisAustralia solar power sector analysis
Australia solar power sector analysis
 
Independent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity MarketIndependent Review of the Australian National Electricity Market
Independent Review of the Australian National Electricity Market
 
ISO New England Remarks Made During Jan 16, 2016 Webinar
ISO New England Remarks Made During Jan 16, 2016 WebinarISO New England Remarks Made During Jan 16, 2016 Webinar
ISO New England Remarks Made During Jan 16, 2016 Webinar
 
Opportunities for wind energy in NSW
Opportunities for wind energy in NSWOpportunities for wind energy in NSW
Opportunities for wind energy in NSW
 
Feasibility Study of Standalone Hybrid Power System Modeled With Photovoltaic...
Feasibility Study of Standalone Hybrid Power System Modeled With Photovoltaic...Feasibility Study of Standalone Hybrid Power System Modeled With Photovoltaic...
Feasibility Study of Standalone Hybrid Power System Modeled With Photovoltaic...
 
Australia solar power sector opportunity analysis
Australia solar power sector opportunity analysisAustralia solar power sector opportunity analysis
Australia solar power sector opportunity analysis
 
Clean Energy Australia Report
Clean Energy Australia ReportClean Energy Australia Report
Clean Energy Australia Report
 
403
403403
403
 
Download Australia solar power sector future outlook 2020
Download Australia solar power sector future outlook 2020Download Australia solar power sector future outlook 2020
Download Australia solar power sector future outlook 2020
 
Australia solar power sector future outlook 2020
Australia solar power sector future outlook 2020Australia solar power sector future outlook 2020
Australia solar power sector future outlook 2020
 
All Energy 2017_TransGrid
All Energy 2017_TransGridAll Energy 2017_TransGrid
All Energy 2017_TransGrid
 
VRE: Solar and Wind Energy
VRE: Solar and Wind EnergyVRE: Solar and Wind Energy
VRE: Solar and Wind Energy
 
Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Challenges and Benefits of Integrating the Renewable Energy Technologies into...Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Challenges and Benefits of Integrating the Renewable Energy Technologies into...
 
IFN AiE Presentation May16 web
IFN AiE Presentation May16 webIFN AiE Presentation May16 web
IFN AiE Presentation May16 web
 
ISO New England - 2016 Regional Electricity Outlook
ISO New England - 2016 Regional Electricity OutlookISO New England - 2016 Regional Electricity Outlook
ISO New England - 2016 Regional Electricity Outlook
 
seminar report on optimal placement and optimal sizing of DG
seminar report on optimal placement and optimal sizing of DGseminar report on optimal placement and optimal sizing of DG
seminar report on optimal placement and optimal sizing of DG
 
INTRODUCTION wind energy and its type .pptx
INTRODUCTION wind energy and its type .pptxINTRODUCTION wind energy and its type .pptx
INTRODUCTION wind energy and its type .pptx
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
 
The Energy Crisis | Biocity Studio
The Energy Crisis | Biocity StudioThe Energy Crisis | Biocity Studio
The Energy Crisis | Biocity Studio
 
Regulatory Burden in the Renewable Energy Sector in NSW
Regulatory Burden in the Renewable Energy Sector in NSWRegulatory Burden in the Renewable Energy Sector in NSW
Regulatory Burden in the Renewable Energy Sector in NSW
 

Recently uploaded

Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
Kumar Satyam
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop.com LTD
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 

Recently uploaded (20)

Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 

Investment in solar and wind generation in australia lessons learned

  • 1. Investment in solar and wind generation in Australia- lessons learned Dr Julian Eggleston Director – Technical Specialist Australian Energy Market Commission (AEMC) Sydney, Australia julian.eggleston@aemc.gov.au Dr Tim Nelson Executive General Manager – Economic Analysis Australian Energy Market Commission (AEMC) Sydney, Australia Tim.nelson@aemc.gov.au Tom Walker Senior Economist Australian Energy Market Commission (AEMC) Sydney, Australia Tom.walker@aemc.gov.au Greg Williams Senior Economist Australian Energy Market Commission (AEMC) Sydney, Australia Greg.williams@aemc.gov.au The Australian National Electricity Market (NEM) rules and arrangements were developed in the 1990s when the majority of the energy was generated from large thermal generating units that were relatively close to the major load centres. These generation and load centres are also interconnected to allow energy to be transferred and traded to improve reliability and efficiency. New generators have open access to the network provided they negotiate their connection with the network operator and meet acceptable performance standards. In the past decade changes in technology and climate change incentives have driven an evolution in the NEM rules and market arrangements. However, in recent years pace of change has increased and there has been a dramatic increase in the number of solar and wind generating systems installed and actively being assessed. These generating systems are smaller than the existing thermal generating units and are generally connected in more remote low voltage locations due to resource availability. The paper will discuss how the NEM has evolved under the high volume of concurrent connection applications, including: • the need to coordinate generation and network investment to avoid excessive congestion, including the role of the Australian Energy Market Operator’s (AEMO’s) integrated system plan; • the negotiation of performance standards in the presence of multiple concurrent connection applications, including the need for system strength remediation; • the impact on network losses and the associated loss factors used to provide locational investment signals. I. INTRODUCTION AND CONTEXT Like many developed economies, Australian policy makers struggled to integrate a comprehensive climate change policy within an energy market framework. Pollitt and Haney (2013, p. 9) make the observation that when markets such as the Australian National Electricity Market (NEM) were liberalised, ‘competitiveness was the overriding priority. Today, competitiveness, energy security and decarbonisation are the three main energy policy priorities.’ Without a comprehensive national framework implemented by the Commonwealth Government, a proliferation of piecemeal state-based public policies aimed at encouraging the adoption of new supply options with lower greenhouse gas emission profiles have added significantly to the existing generation capital stock. These technologies have a distinctly different cost profile structure to existing and competing thermal (coal and gas) units. Fuel is effectively free (i.e. wind and sun) but with material up-front capital costs. At a peak, there were six policies in place to drive capital substitution or addition, including: the New South Wales (NSW) Greenhouse Gas Abatement Scheme (GGAS); the Commonwealth’s Large-Scale Renewable Energy Target (LRET); the Small-Scale Renewable Energy Target (SRES); the Queensland (QLD) 18% Gas Scheme; various energy efficiency policies (e.g. Victorian Energy Efficiency Target or VEET); and Victoria’s premium solar feed-in tariffs (PFiT). A carbon price was also established through the Clean Energy Future package but then repealed within three-years. Given declining demand, and significant uptake of subsidised embedded small-scale photovoltaic (PV) and large-scale renewable generation, there was an oversupply of capacity with prices well below the cost of new-entry until 2015 (see Nelson et al., 2015). This sustained low pricing resulted in several incumbent ageing coal-fired generators retiring over several years with the most capacity being retired in 2017. In most cases, less than a year’s notice was provided of the generator closure. With such little time available to participants to replace the capacity being withdrawn, wholesale prices increased markedly in 2017. Prices are now at the highest they have ever been due to the disorderly transition that has occurred. This is shown in Figure 1.
  • 2. FIGURE 1. VALUE OF NEM TRADING FROM 2001 TO 2019 (SEPARATED INTO PRICE BANDS) Around 5,000 MW of dispatchable generation (coal and gas) has been retired from the NEM while approximately 18,000 MW of non-dispatchable generation (wind, solar etc.) has been, or is in the process of being, commissioned. The installed capacity in the market is shifting from a small number of geographically concentrated large coal fired power stations, located within coal regions such as the Hunter Valley in New South Wales, to a large number of smaller units located throughout the system where fuel (i.e. wind and sun) is available. This has had significant impacts on both the way in which the energy-only NEM functions; and system security and reliability. II. RATE OF RENEWABLE CONNECTIONS SINCE 2015 As discussed above the rate of commissioning of grid connected renewable solar and wind generation has accelerated in recent years. This can be seen in Figure 2 that shows the rate of uptake of solar and wind generation in the NEM from 2009 to 2019. FIGURE 2. UPTAKE OF RENEWABLE GENERATION IN THE NEM FROM 2009 TO 2019 This means that the levels of variable renewable generation penetration in the NEM are amongst the highest in the world, as shown in Figure 3. FIGURE 3. UPTAKE OF VARIABLE RENEWABLE GENERATION As well as the nature of the generation mix changing, predominantly from coal based generation to an increased proportion of solar and wind generation, the physical location of the recently installed solar and wind generation is connecting in very different locations. Figures 4 and 5 show the changes in the generation in New South Wales, Victoria and South Australia from 2015 to 2019. FIGURE 4. NSW, Victorian and South Australian generation IN 2015 FIGURE 5. NSW, VICTORIAN AND SOUTH AUSTRALIAN GENERATION IN 2019 0 500 1000 1500 2000 2500 3000 3500 4000 4500 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Capacity(MW) Wind Large-scale solar Committed
  • 3. The figures show that the majority of the generation that was connected in 2015, much of which was operating at the commencement of the NEM in 1998, were large coal units located relatively close to the major load centres in the state capitals. These coal-fired power stations were connected to strong high voltage networks (275kV, 330kV and 500kV) with multiple parallel circuits. The Snowy scheme located on the New South Wales and Victoria boarder also strongly connected to major load centres of Sydney and Melbourne (330kV). Additional gas powered intermediate and peaking generation is also generally located near the state capitals and strongly connected to the transmission network. The flows on the transmission networks generally followed well- defined patterns throughout the day, between the seasons and from one year to the next. In the 2000s large-scale wind generation started being commissioned for the first time. This generally occurred in in relatively remote locations associated with a good wind resources and comparatively inexpensive land. However, these wind farms were not located near the strong parts of the existing transmission network, rather were connected to lower voltage parts of the transmission and distribution networks. In more recent years grid connected solar generating systems have also been commissioned. From 2015 the rate at which grid connected solar and wind generation entered the market began to accelerate with most of this generation connected in remote parts of the network. This was largely due to a tight supply/demand dynamic indicating resource scarcity and policy uncertainty in relation to the Large-Scald Renewable Energy Target being resolved. In particular: • large quantities of grid connected solar and wind generation have been connected in north-western Victoria and south-western New South Wales; • there is now around 1,500 MW of wind in rural South Australia and, at times of minimum demand, South Australia sometimes produces so much wind energy, the residual energy is exported to Victoria; and • several large grid connected solar generation have been connected in northern Queensland. In each case, these generating systems were connected to the existing networks that were originally commissioned to supply rural cities and towns remote from the state capitals, generally with limited or no local generation. The commissioning of large quantities of this grid connected variable renewable generation at these remote locations in the network, and the associated reduction in the output from the existing thermal generation, has dramatically changed the flows of energy in the transmission and distribution networks. This has caused a range of problems including: • over-loading of the associated transmission and distribution networks, resulting in periods where the output of this generation is constrained during periods of high wind or solar radiation • low fault level, often referred to as low system strength, resulting in potential system instability and increased numbers of generating systems being commissioned with synchronous condensers • the losses in the associated networks have increased, especially due to the long distances between most of the new generation and the major load centres of the state capitals. These problems are discussed further in the following sections. III. COORDINATION OF GENERATION AND NETWORK INVESTMENT The NEM is made up of five pricing regions, which approximately follow the political boundaries of the states of South Australia, Victoria, Tasmania, New South Wales and Queensland. Under the existing transmission access regime in the NEM, all generation and load which participates in the wholesale market is settled on a region-wide price for its physical output or consumption (net of losses), regardless of its location in a region. This region-wide price is called the 'regional reference price'. When the physical output of a generator is reduced - for example, due to the presence of a transmission constraint - its revenue is similarly reduced. While this approach is relatively simple, it also abstracts away from the technical and economic realities of the system. When constraints arise on the transmission network within a region, the underlying cost of an additional unit of generation to serve an additional unit of load at a particular location (known as the 'locational marginal cost' of generation) differs from location to location. The marginal cost of an additional unit of generation tends to be relatively low in areas which have an abundance of generation versus load and limited ability for generation to flow to other areas of the network, and vice versa. Economic efficiency is promoted when prices reflect the marginal cost of the provision of a particular product or service. Numerous issues are arising in the NEM because of the incentives created by the difference between the locationally specific cost of an additional unit generation and its region-wide price. Furthermore, because prices for electricity are not locationally specific, the difference in cost between locations (and hence the value of transmission capacity) is not explicitly valued. A foundational principle of the NEM when it was created was that decisions to invest in generation capacity are made by businesses operating in a competitive environment, rather than by vertically integrated monopolies. Investment in generation assets is market-driven and takes account of expectations of future demand, the location of energy sources, access to land and water and access to transmission. The result is that risks associated with generation investment rest with those businesses. In contrast, transmission investment decisions remain the responsibility of regional transmission network businesses, guided by the Australian Energy Market Operator’s
  • 4. (AEMO’s) Integrated System Plan. 1 Transmission businesses are subject to incentive-based economic regulation of their revenues for the provision of transmission services, as well as various other obligations relating to reliability, safety and investment decision-making processes. Generation, transmission and storage are complements and substitutes. They are part of an integrated system. This implies that investment and operational decisions by generators, storage proponents and transmission businesses should work together to achieve overall economically efficient outcomes. Current locational signals such as transmission losses, congestion and inter-regional price variation do provide a degree of incentive for efficient generator and storage location. However, these signals are blunt, incomplete and imprecise. Due to the current lack of locational price signals in the transmission framework, investors are locating their generation assets where the network has limited or no capacity for the additional generation capacity to be dispatched. Increasingly, storage may play an important role in managing both transmission congestion and variability in supply from generation, but storage is similarly not subject to the locational price signals. Further, having made a locational decision, a generator or storage unit is not readily able to manage the risks arising from transmission losses, congestion, and to a lesser extent, inter-regional price variation. In turn, a generator or storage unit which connects in a fuel- rich area may influence the investment case for a transmission upgrade, even if the lowest overall cost solution was to invest in a less fuel-rich area with better transmission infrastructure. This situation is likely resulting in higher overall system costs, and ultimately elevated consumer bills. In the past, this and other problems relating to regional pricing have tended to be modest, and so the cost of change has outweighed the benefits. In an environment of relatively low levels of generation and transmission investment, the benefits of improved investment efficiency and coordination are necessarily relatively low. Such an environment also means that transmission risks faced by generators are relatively predictable and stable. However, for the reasons outlined, this is no longer the environment that the NEM finds itself in. These issues are being considered in Australia in order to promote better coordination between investment in generation by competitive entities and the regulated monopoly network businesses. Therefore, different design choices and trade-offs better suited to the current environment may need to be made. 1 The exception is Victoria where decisions to augment the transmission network are made by the Australian Energy Market Operator (AEMO). IV. NEGOTIATION OF PERFORMANCE STANDARDS CONCURRENT CONNECTION APPLICATIONS The connection of new generating systems in the NEM can be very competitive. This means that the individual generator proponents treat their projects as commercial in confidence and generally release little information on their projects. This has become very difficult to manage in the current environment where many connecting generating systems are being developed and connected concurrently and within close proximity. New generators connecting the NEM must meet the required technical performance standards, which were updated in 2018 to reflect the lessons learned from a 2016 black system event in South Australia and to better reflect the characteristics of asynchronous generation including inverter based plant. The proponents of the connecting generation must perform connection studies to demonstrate that their performance meets the required standards, based on the range of system conditions that apply at the time of connection. At the same time, the effective short circuit ratios (SCRs) in the network where new generating systems are connecting have been dropping due to their remote location and the retirement of existing synchronous (coal) generation. These trends have raised stability concerns and a system strength “do no harm obligation” was placed on connecting generators from July 2018. This requires the connecting generator to mitigate any system stability issues that occur as a result of connecting their generating system. In addition, traditional power system modelling tools are often no longer fit for purpose due to the reducing SCRs. This means that electro-magnetic transient (EMT) modelling is required to assess both the technical performance and do no harm obligations of connecting generating systems. This combination of performance and system strength requirements, in the context of more intensive modelling requirements, has become very challenging for generator proponents in the current environment where multiple concurrent projects are being assessed at once. This can mean that a generator proponent needs to repeat many EMT studies when a competitor’s project is connected nearby, thus required their existing assessment to be updated. V. IMPACT ON NETWORK LOSSES The prices received by generators, and paid by loads, are the product of the price calculated at the regional reference node (located at the largest load centres in each state) and the static marginal loss factor (MLF) for that connection point. The prices at the regional reference nodes are calculated from the offers submitted by the generators and represent the cost of meeting an additional MW of load at each of the regional reference nodes. Thus, when comparing an increment of output from a generating system it is necessary to also consider its marginal impact on the losses in the transmission network, hence the use of MLFs. As well as promoting efficient dispatch and pricing, the use of MLFs
  • 5. also provides longer-term locational investment signals that incentivise generators to connect near loads, and visa versa. Rather than recalculating the loss factors for every 5-minute dispatch interval, a single static MLF value is calculated that is estimated to represent the impact of that generating system on losses for the financial year (July to June). These static MLFs are calculated annually by AEMO using the generation and load patterns anticipated for the next financial year, volume weighted by the generation or load pattern of the generating system in question. Using annual static MLFs, rather than real-time loss factors, is expected to increase the liquidity of the markets for financial derivative contracts and hence to facilitate efficient investment in new generation. However, using annual static MLFs can compromise the efficiency of dispatch and locational pricing. As discussed above, much of the new generation that has been commissioned in the last few years has connected in the lower voltage network and much further away from the major load centres. This change to the generation mix has resulted in a significant increase in the losses in the transmission network, with an associated decrease in the MLFs (and hence the effective price received) for this new generation. Figures 6 and 7 show the changes in the MLFs for New South Wales and Victoria from 2018/19 to 2019/20. The MLFs for south-western New South Wales and north- western Victoria fell significantly for 2019/20 due to the dramatic increase in solar and wind generation in that area. In one case, the MLFs of a new solar generator dropped by approximately 25%, with a corresponding decrease in the generator’s revenue. This has become a serious concern for many developers and investors in these renewable generating systems. The AEMC is currently considering whether there is a better approach to calculating MLFs, while retaining the locational nature of the current approach. Figure 6: Changes of the NSW MLFs from 2018/19 to 2019/20 source: AEMO Figure 7: Changes of the Victorian MLFs from 2018/19 to 2019/20 source: AEMO VI. CONCLUSION The paper has considered how the NEM is evolving under the high volume of concurrent connection applications for new generation, including: • the need to coordinate generation and network investment to avoid excessive congestion, including the role of the AEMO integrated system plan; • the negotiation of performance standards in the presence of multiple concurrent connection applications, including the need for system strength remediation; • the impact on network losses and the associated loss factors used to provide locational investment signals. VII. REFERENCES Pollitt, M. and Haney, A. 2013, ‘Dismantling a competitive retail Electricity Market: Residential Market Reforms in Great Britain’, The Electricity Journal, Vol. 27, No. 1, pp. 66–73. Nelson, T., Reid, C. and McNeill, J. (2015), ‘Energy-Only Markets and Renewable Energy Targets: Complementary Policy or Policy Collision’, Economic Analysis and Policy, 46, 25–42.