ROLES & RESPONSIBILITIES
1) Analyse survey reports, maps, drawings, blueprints, aerial photography, and
other topographical or geologic data to plan projects.
2) Plan and design transportation or hydraulic systems and structures, following
construction and government standards, using design software and drawing
tools.
3) Compute load and grade requirements, water flow rates, and material stress
factors to determine design specifications.
4) Inspect project sites to monitor progress and ensure conformance to design
specifications and safety or sanitation standards.
5) Direct construction, operations, and maintenance activities at project site.
6) Direct or participate in surveying to lay out installations and establish
reference points, grades, and elevations to guide construction.
ROLES AND RESPONSIBILITIESROLES AND RESPONSIBILITIES
Maps Topographical data
Blueprints Aerial Photographs Site Drawings
SCOPE OF WORK
• DEALS WITHDEALS WITH DESIGNDESIGN,, CONSTRUCTIONCONSTRUCTION ANDAND MAINTENANCEMAINTENANCE
• ENGAGES IN THE DESIGN OFENGAGES IN THE DESIGN OF CONSTRUCTIONCONSTRUCTION
MANAGEMENTSMANAGEMENTS
planning scheduling
TASKS IN DIFFERENT STAGES OF
CONSTRUCTION
BRIEFING STAGE
DESIGNING STAGEDESIGNING STAGE
TENDERING STAGETENDERING STAGE
CONSTRUCTION STAGECONSTRUCTION STAGE
COMMISSIONING STAGECOMMISSIONING STAGE
BRIEFING STAGE
• APPOINT A PROJECT MANAGERAPPOINT A PROJECT MANAGER
• CARRY OUT TECHNICAL AND NON-TECHNICALCARRY OUT TECHNICAL AND NON-TECHNICAL
INVESTIGATIONSINVESTIGATIONS( soil investigation , roads, topographical( soil investigation , roads, topographical
data, etc )data, etc )
• STUDY VARIOUS ALTERNATIVES TO MAKE SUBSTANTIALSTUDY VARIOUS ALTERNATIVES TO MAKE SUBSTANTIAL
COST SAVINGS EASIERCOST SAVINGS EASIER
• PREPARE REPORT ON INVESTIGATIONS CARRIED OUT ANDPREPARE REPORT ON INVESTIGATIONS CARRIED OUT AND
THE SOLUTIONS.THE SOLUTIONS.
DESIGNING STAGE
FINALISE PROJECT SUMMARYFINALISE PROJECT SUMMARY
CARRY OUT TECHNICAL INVESTIGATIONCARRY OUT TECHNICAL INVESTIGATION
PREPARE SCHEME AND DETAILED DESIGNSPREPARE SCHEME AND DETAILED DESIGNS
PREPARE WORKING DRAWINGS & SPECIFICATIONSPREPARE WORKING DRAWINGS & SPECIFICATIONS
PREPARE FINAL COST ESTIMATEPREPARE FINAL COST ESTIMATE
PREPARE CONSTRUCTION PROGRAMME SCHEDULEPREPARE CONSTRUCTION PROGRAMME SCHEDULE
TENDERINGTENDERING
STAGESTAGE
TENDERS ARE CALLED &TENDERS ARE CALLED &
CONTRACT IS AWARDEDCONTRACT IS AWARDED
UNDER BEST AVAILABLEUNDER BEST AVAILABLE
TERMS AGREED BETWEENTERMS AGREED BETWEEN
OWNER’S TEAM ANDOWNER’S TEAM AND
CONTRACTORSCONTRACTORS
CONSTRUCTION STAGECONSTRUCTION STAGE
EXECUTION OF CONSTRUCTION WORK AS PER
DESIGN WITHIN AGREED COST, TIME AND
SPECIFIED QUALITY.
COMMISSIONING STAGECOMMISSIONING STAGE
 PERFORMANCE OF STRUCTURE IS EVALUATED ANDPERFORMANCE OF STRUCTURE IS EVALUATED AND
PROPOSED NATURE OF REPAIR AND MAINTENACEPROPOSED NATURE OF REPAIR AND MAINTENACE
ARE CONSIDEREDARE CONSIDERED
 VARIOUS RECORDS ACTUAL WORK ARE KEPTVARIOUS RECORDS ACTUAL WORK ARE KEPT
 INSPECTION OF CONSTRUCTION WORK ANDINSPECTION OF CONSTRUCTION WORK AND
REMOVAL OF DEFECTSREMOVAL OF DEFECTS
 OPERATING INTRUCTIONS AND MANUAL AREOPERATING INTRUCTIONS AND MANUAL ARE
PREPAREDPREPARED
 TESTS OF PERFORMANCE ARE CARRIED OUTTESTS OF PERFORMANCE ARE CARRIED OUT
TYPES OF DRAWINGS (CIVIL)TYPES OF DRAWINGS (CIVIL)
tender drawingstender drawings
contract drawingscontract drawings
working drawingsworking drawings
completion drawingscompletion drawings
TENDER DRAWINGSTENDER DRAWINGS
•PREPARED EARLYPREPARED EARLY
DURING BRIEFING STAGEDURING BRIEFING STAGE
•ALONG WITH TENDERALONG WITH TENDER
DOCUMENTSDOCUMENTS
•USED FOR BIDS BYUSED FOR BIDS BY
CONTRACTORSCONTRACTORS
•INFOINFORRMATION IS CLEARLYMATION IS CLEARLY
STATEDSTATED
CONTRACTCONTRACT
DRAWINGSDRAWINGS
• MORE DETAILED DESIGNMORE DETAILED DESIGN CANCAN
ONLY BE DONE AFTERONLY BE DONE AFTER
COMPLETION OF TENDERINGCOMPLETION OF TENDERING
DRAWINGSDRAWINGS
• USED FOR LEGALLY BINDINGUSED FOR LEGALLY BINDING
THE CONTRACTTHE CONTRACT
• PRINTED ON GOOD QUALITYPRINTED ON GOOD QUALITY
PAPERPAPER
• MEANT TO WITHSTAND LONGMEANT TO WITHSTAND LONG
TERMTERM
• CONTRACT DRAWINGS WILLCONTRACT DRAWINGS WILL
BE THE SAME IF THERE AREBE THE SAME IF THERE ARE
NO ALTERNATIVENO ALTERNATIVE
PROPOSALS DURINGPROPOSALS DURING
TENDERING STAGETENDERING STAGE
WORKINGWORKING
DRAWINGSDRAWINGS
• PREPARED DURING THEPREPARED DURING THE
DESIGNING STAGEDESIGNING STAGE
• REPRESENTSREPRESENTS ENGINEER’SENGINEER’S
FINAL DECISIONSFINAL DECISIONS ANDAND
DESIGNSDESIGNS
• USED FORUSED FOR
WORKING,MANUFACTURING,WORKING,MANUFACTURING,
CONSTRUCTING ANDCONSTRUCTING AND
BUILDING PURPOSESBUILDING PURPOSES
• INFORM THE ACTUAL WORKINFORM THE ACTUAL WORK
• SHOWS DETAIL DRAWINGSSHOWS DETAIL DRAWINGS
OF PARTSOF PARTS
COMPLETIONCOMPLETION
DRAWINGDRAWING
• PREPARED UPON COMPLETION STAGEPREPARED UPON COMPLETION STAGE
• ALSO KNOWN AS RECORD DRAWINGS AND AS-BUILTALSO KNOWN AS RECORD DRAWINGS AND AS-BUILT
DRAWINGSDRAWINGS
• ADDITIONS AND ALTERATIONS THAT ARE MADE DUE TOADDITIONS AND ALTERATIONS THAT ARE MADE DUE TO
UNFORESEEN SITE CONDITIONS ARE RECORDEDUNFORESEEN SITE CONDITIONS ARE RECORDED
TYPES OF DRAWINGSTYPES OF DRAWINGS
(STRUCTURAL)(STRUCTURAL)
STRUCTURAL DRAWINGSSTRUCTURAL DRAWINGS
REINFORCEMENT DRAWINGSREINFORCEMENT DRAWINGS
RECORD DRAWINGSRECORD DRAWINGS
STRUCTURAL DRAWINGSSTRUCTURAL DRAWINGS
USED TO PROGRESSUSED TO PROGRESS
ARCHITECT’SARCHITECT’S
CONCEPT BYCONCEPT BY
SPECIFYING SHAPESSPECIFYING SHAPES
& POSITIONS OF& POSITIONS OF
PARTS OFPARTS OF
STRUCTURESSTRUCTURES Parts ofParts of
structuresstructures
Example of structural drawing
REINFORCEMENT DRAWINGSREINFORCEMENT DRAWINGS
• FULLY DESCRIBE AND LOCATE ALL REINFORCEMENT INFULLY DESCRIBE AND LOCATE ALL REINFORCEMENT IN
RELATION TO THE FINISHED SURFACE OF CONCRETE ANDRELATION TO THE FINISHED SURFACE OF CONCRETE AND
TO ANY HOLES AND FIXINGSTO ANY HOLES AND FIXINGS
Example of steelExample of steel
reinforcement drawingreinforcement drawing
RECORD DRAWINGSRECORD DRAWINGS
• MODIFICATIONS TO BE MADE TO THEMODIFICATIONS TO BE MADE TO THE
ORIGINAL DRAWINGS TO CATERORIGINAL DRAWINGS TO CATER
UNFORESEEN DIFFICULTIESUNFORESEEN DIFFICULTIES ..
• SUFFIX MUST BE ADDED TO THE DRAWINGSUFFIX MUST BE ADDED TO THE DRAWING
NUMBER TO INDICATE IS A “ RECORDNUMBER TO INDICATE IS A “ RECORD
DRAWING ”DRAWING ”
REFLECTION
Through this project given by our lecturers,Through this project given by our lecturers,
we got the chance to understand who are civilwe got the chance to understand who are civil
and structural engineers, and their roles andand structural engineers, and their roles and
responsibilities in the construction fields. Notresponsibilities in the construction fields. Not
only that, we also got to know more about theonly that, we also got to know more about the
drawings they prepare in every constructiondrawings they prepare in every construction
stage. Now we know how important are civilstage. Now we know how important are civil
and structural engineers in constructing a safeand structural engineers in constructing a safe
and stable building.and stable building.
REFERENREFEREN
CESCES
WEBSITESWEBSITES
• Praveenniru (2014, October 7 ),Classification of Civil Engineering Drawings & Interpreting
Engineering Drawings, Retrieved March 9, 2015 from hubpages,
www.praveenniru.hubpages.com/hub/classification-of-civil-engineering-drawings-and-
importance-of-engineering-drawings
• Tony Cecutti P. ( 2015, January),Sample tender document, Retrieved March 9, 2015 from
Sudbury, www.greatersudbury.ca/business/engineering-standards/tender-sample-document/
• Cheryl Cairns ( 2014, March) Structural engineer Job Description, Retrieved March 9, 2015
from prospects, www.prospects.ac.uk/structural_engineer_job_&_description.htm.
• Jamshaia Sawab (-), Types of drawings by structural engineers, Retrieved March 9, 2015 from
the constructor: Civil Engineer home, www.the constructor.org/practical-guide/types-of-
drawings-by-structural-engineers/8594/
BOOKBOOK
• P.S.Gahloe Bin Dhir, (1992) Construction: Planning & Management, Daryagani, New Delhi;
NEW AGE INTERNATIONAL.

Integrated project

  • 1.
    CIVCIVIL & STRUCTURALIL& STRUCTURAL ENGINEERINGENGINEERING LEE FONG YENLEE FONG YEN ISYRAQ NASIRISYRAQ NASIR MELANIE SOON YU XINMELANIE SOON YU XIN YANG JING LOOYANG JING LOO HASSANHASSAN AZRIAZRI LOO SIAH MONLOO SIAH MONGG
  • 2.
    ROLES & RESPONSIBILITIES 1)Analyse survey reports, maps, drawings, blueprints, aerial photography, and other topographical or geologic data to plan projects. 2) Plan and design transportation or hydraulic systems and structures, following construction and government standards, using design software and drawing tools. 3) Compute load and grade requirements, water flow rates, and material stress factors to determine design specifications. 4) Inspect project sites to monitor progress and ensure conformance to design specifications and safety or sanitation standards. 5) Direct construction, operations, and maintenance activities at project site. 6) Direct or participate in surveying to lay out installations and establish reference points, grades, and elevations to guide construction.
  • 3.
    ROLES AND RESPONSIBILITIESROLESAND RESPONSIBILITIES Maps Topographical data Blueprints Aerial Photographs Site Drawings
  • 4.
    SCOPE OF WORK •DEALS WITHDEALS WITH DESIGNDESIGN,, CONSTRUCTIONCONSTRUCTION ANDAND MAINTENANCEMAINTENANCE • ENGAGES IN THE DESIGN OFENGAGES IN THE DESIGN OF CONSTRUCTIONCONSTRUCTION MANAGEMENTSMANAGEMENTS planning scheduling
  • 5.
    TASKS IN DIFFERENTSTAGES OF CONSTRUCTION BRIEFING STAGE DESIGNING STAGEDESIGNING STAGE TENDERING STAGETENDERING STAGE CONSTRUCTION STAGECONSTRUCTION STAGE COMMISSIONING STAGECOMMISSIONING STAGE
  • 6.
    BRIEFING STAGE • APPOINTA PROJECT MANAGERAPPOINT A PROJECT MANAGER • CARRY OUT TECHNICAL AND NON-TECHNICALCARRY OUT TECHNICAL AND NON-TECHNICAL INVESTIGATIONSINVESTIGATIONS( soil investigation , roads, topographical( soil investigation , roads, topographical data, etc )data, etc ) • STUDY VARIOUS ALTERNATIVES TO MAKE SUBSTANTIALSTUDY VARIOUS ALTERNATIVES TO MAKE SUBSTANTIAL COST SAVINGS EASIERCOST SAVINGS EASIER • PREPARE REPORT ON INVESTIGATIONS CARRIED OUT ANDPREPARE REPORT ON INVESTIGATIONS CARRIED OUT AND THE SOLUTIONS.THE SOLUTIONS.
  • 7.
    DESIGNING STAGE FINALISE PROJECTSUMMARYFINALISE PROJECT SUMMARY CARRY OUT TECHNICAL INVESTIGATIONCARRY OUT TECHNICAL INVESTIGATION PREPARE SCHEME AND DETAILED DESIGNSPREPARE SCHEME AND DETAILED DESIGNS PREPARE WORKING DRAWINGS & SPECIFICATIONSPREPARE WORKING DRAWINGS & SPECIFICATIONS PREPARE FINAL COST ESTIMATEPREPARE FINAL COST ESTIMATE PREPARE CONSTRUCTION PROGRAMME SCHEDULEPREPARE CONSTRUCTION PROGRAMME SCHEDULE
  • 8.
    TENDERINGTENDERING STAGESTAGE TENDERS ARE CALLED&TENDERS ARE CALLED & CONTRACT IS AWARDEDCONTRACT IS AWARDED UNDER BEST AVAILABLEUNDER BEST AVAILABLE TERMS AGREED BETWEENTERMS AGREED BETWEEN OWNER’S TEAM ANDOWNER’S TEAM AND CONTRACTORSCONTRACTORS
  • 10.
    CONSTRUCTION STAGECONSTRUCTION STAGE EXECUTIONOF CONSTRUCTION WORK AS PER DESIGN WITHIN AGREED COST, TIME AND SPECIFIED QUALITY.
  • 11.
    COMMISSIONING STAGECOMMISSIONING STAGE PERFORMANCE OF STRUCTURE IS EVALUATED ANDPERFORMANCE OF STRUCTURE IS EVALUATED AND PROPOSED NATURE OF REPAIR AND MAINTENACEPROPOSED NATURE OF REPAIR AND MAINTENACE ARE CONSIDEREDARE CONSIDERED  VARIOUS RECORDS ACTUAL WORK ARE KEPTVARIOUS RECORDS ACTUAL WORK ARE KEPT  INSPECTION OF CONSTRUCTION WORK ANDINSPECTION OF CONSTRUCTION WORK AND REMOVAL OF DEFECTSREMOVAL OF DEFECTS  OPERATING INTRUCTIONS AND MANUAL AREOPERATING INTRUCTIONS AND MANUAL ARE PREPAREDPREPARED  TESTS OF PERFORMANCE ARE CARRIED OUTTESTS OF PERFORMANCE ARE CARRIED OUT
  • 12.
    TYPES OF DRAWINGS(CIVIL)TYPES OF DRAWINGS (CIVIL) tender drawingstender drawings contract drawingscontract drawings working drawingsworking drawings completion drawingscompletion drawings
  • 13.
    TENDER DRAWINGSTENDER DRAWINGS •PREPAREDEARLYPREPARED EARLY DURING BRIEFING STAGEDURING BRIEFING STAGE •ALONG WITH TENDERALONG WITH TENDER DOCUMENTSDOCUMENTS •USED FOR BIDS BYUSED FOR BIDS BY CONTRACTORSCONTRACTORS •INFOINFORRMATION IS CLEARLYMATION IS CLEARLY STATEDSTATED
  • 15.
    CONTRACTCONTRACT DRAWINGSDRAWINGS • MORE DETAILEDDESIGNMORE DETAILED DESIGN CANCAN ONLY BE DONE AFTERONLY BE DONE AFTER COMPLETION OF TENDERINGCOMPLETION OF TENDERING DRAWINGSDRAWINGS • USED FOR LEGALLY BINDINGUSED FOR LEGALLY BINDING THE CONTRACTTHE CONTRACT • PRINTED ON GOOD QUALITYPRINTED ON GOOD QUALITY PAPERPAPER • MEANT TO WITHSTAND LONGMEANT TO WITHSTAND LONG TERMTERM • CONTRACT DRAWINGS WILLCONTRACT DRAWINGS WILL BE THE SAME IF THERE AREBE THE SAME IF THERE ARE NO ALTERNATIVENO ALTERNATIVE PROPOSALS DURINGPROPOSALS DURING TENDERING STAGETENDERING STAGE
  • 16.
    WORKINGWORKING DRAWINGSDRAWINGS • PREPARED DURINGTHEPREPARED DURING THE DESIGNING STAGEDESIGNING STAGE • REPRESENTSREPRESENTS ENGINEER’SENGINEER’S FINAL DECISIONSFINAL DECISIONS ANDAND DESIGNSDESIGNS • USED FORUSED FOR WORKING,MANUFACTURING,WORKING,MANUFACTURING, CONSTRUCTING ANDCONSTRUCTING AND BUILDING PURPOSESBUILDING PURPOSES • INFORM THE ACTUAL WORKINFORM THE ACTUAL WORK • SHOWS DETAIL DRAWINGSSHOWS DETAIL DRAWINGS OF PARTSOF PARTS
  • 19.
    COMPLETIONCOMPLETION DRAWINGDRAWING • PREPARED UPONCOMPLETION STAGEPREPARED UPON COMPLETION STAGE • ALSO KNOWN AS RECORD DRAWINGS AND AS-BUILTALSO KNOWN AS RECORD DRAWINGS AND AS-BUILT DRAWINGSDRAWINGS • ADDITIONS AND ALTERATIONS THAT ARE MADE DUE TOADDITIONS AND ALTERATIONS THAT ARE MADE DUE TO UNFORESEEN SITE CONDITIONS ARE RECORDEDUNFORESEEN SITE CONDITIONS ARE RECORDED
  • 21.
    TYPES OF DRAWINGSTYPESOF DRAWINGS (STRUCTURAL)(STRUCTURAL) STRUCTURAL DRAWINGSSTRUCTURAL DRAWINGS REINFORCEMENT DRAWINGSREINFORCEMENT DRAWINGS RECORD DRAWINGSRECORD DRAWINGS
  • 22.
    STRUCTURAL DRAWINGSSTRUCTURAL DRAWINGS USEDTO PROGRESSUSED TO PROGRESS ARCHITECT’SARCHITECT’S CONCEPT BYCONCEPT BY SPECIFYING SHAPESSPECIFYING SHAPES & POSITIONS OF& POSITIONS OF PARTS OFPARTS OF STRUCTURESSTRUCTURES Parts ofParts of structuresstructures
  • 24.
  • 25.
    REINFORCEMENT DRAWINGSREINFORCEMENT DRAWINGS •FULLY DESCRIBE AND LOCATE ALL REINFORCEMENT INFULLY DESCRIBE AND LOCATE ALL REINFORCEMENT IN RELATION TO THE FINISHED SURFACE OF CONCRETE ANDRELATION TO THE FINISHED SURFACE OF CONCRETE AND TO ANY HOLES AND FIXINGSTO ANY HOLES AND FIXINGS
  • 26.
    Example of steelExampleof steel reinforcement drawingreinforcement drawing
  • 27.
    RECORD DRAWINGSRECORD DRAWINGS •MODIFICATIONS TO BE MADE TO THEMODIFICATIONS TO BE MADE TO THE ORIGINAL DRAWINGS TO CATERORIGINAL DRAWINGS TO CATER UNFORESEEN DIFFICULTIESUNFORESEEN DIFFICULTIES .. • SUFFIX MUST BE ADDED TO THE DRAWINGSUFFIX MUST BE ADDED TO THE DRAWING NUMBER TO INDICATE IS A “ RECORDNUMBER TO INDICATE IS A “ RECORD DRAWING ”DRAWING ”
  • 29.
    REFLECTION Through this projectgiven by our lecturers,Through this project given by our lecturers, we got the chance to understand who are civilwe got the chance to understand who are civil and structural engineers, and their roles andand structural engineers, and their roles and responsibilities in the construction fields. Notresponsibilities in the construction fields. Not only that, we also got to know more about theonly that, we also got to know more about the drawings they prepare in every constructiondrawings they prepare in every construction stage. Now we know how important are civilstage. Now we know how important are civil and structural engineers in constructing a safeand structural engineers in constructing a safe and stable building.and stable building.
  • 30.
  • 31.
    WEBSITESWEBSITES • Praveenniru (2014,October 7 ),Classification of Civil Engineering Drawings & Interpreting Engineering Drawings, Retrieved March 9, 2015 from hubpages, www.praveenniru.hubpages.com/hub/classification-of-civil-engineering-drawings-and- importance-of-engineering-drawings • Tony Cecutti P. ( 2015, January),Sample tender document, Retrieved March 9, 2015 from Sudbury, www.greatersudbury.ca/business/engineering-standards/tender-sample-document/ • Cheryl Cairns ( 2014, March) Structural engineer Job Description, Retrieved March 9, 2015 from prospects, www.prospects.ac.uk/structural_engineer_job_&_description.htm. • Jamshaia Sawab (-), Types of drawings by structural engineers, Retrieved March 9, 2015 from the constructor: Civil Engineer home, www.the constructor.org/practical-guide/types-of- drawings-by-structural-engineers/8594/ BOOKBOOK • P.S.Gahloe Bin Dhir, (1992) Construction: Planning & Management, Daryagani, New Delhi; NEW AGE INTERNATIONAL.