Government of Romania

Global Environment Facility

The World Bank

Integrated Nutrients Pollution Control Project
LN 4873 – RO
WBTF 050327-RO

MINISTRY OF ENVIRONMENT AND CLIMATE CHANGE
ROMANIA
Naiana Milea - PMU Director
Methodology for evaluating the reduction of nutrients discharge
in the Project area
a) use of analysis data provided by a ground and surface water monitoring
program performed by ANAR, in the Project area, using 124 piezometers and 84
surface water sampling points;
b) use of proxies to estimate the reduced N & P discharge into the water bodies.
Stress reduction measurements: Pollution reduction practices
Type on
intervention

Achievements

Stress reduction

Manure
Management
investments

Completed in 34 communes, (50% of the
localities included in the Project): 39
communal level manure storage, 1236
individual household storage facilities, 29
sets of equipment for manure management

51,120 kg
N/year, 29,820 kg
P/year.

Municipal
waste water

New/extension of domestic wastewater
6,400 kg N/year,
sewerage systems and treatment plants in 16 1,025 kg P/year,
villages receiving also investments for
62,735 kg BOD/year.
livestock manure proper management at
community level.

Promotion of
the Code of
Good
Agricultural
Practices

reduced or conservative tillage, nutrient
management plans with soil testing, use of
leguminous plants in crop rotation, use of
organic fertilizers, plantation of buffer strips
and vegetative barriers, public awareness
and better information, etc

10,320kg N/year-2012;
24,000kg N/year-2015
in Project area
Stress reduction measurements: Agricultural pollution reduction practices

Year

Manure properly
stored and used (t)

Nutrient reduction (kg)

N

P2O5

K2O

2011

2,400

8,640

5,040

11,520

2012

7,200

25,920

15,120

34,560

2013

14,200

51,120

29,820

68,160

Forecast 2014

39,000

140,400

81,900

187,200

Forecast 2015

112,500

405,000

236,250

540,000

Target for end of Project: 300,000 kg N/year

Integrated Nutrients Pollution Control Project

  • 1.
    Government of Romania GlobalEnvironment Facility The World Bank Integrated Nutrients Pollution Control Project LN 4873 – RO WBTF 050327-RO MINISTRY OF ENVIRONMENT AND CLIMATE CHANGE ROMANIA Naiana Milea - PMU Director
  • 2.
    Methodology for evaluatingthe reduction of nutrients discharge in the Project area a) use of analysis data provided by a ground and surface water monitoring program performed by ANAR, in the Project area, using 124 piezometers and 84 surface water sampling points; b) use of proxies to estimate the reduced N & P discharge into the water bodies.
  • 3.
    Stress reduction measurements:Pollution reduction practices Type on intervention Achievements Stress reduction Manure Management investments Completed in 34 communes, (50% of the localities included in the Project): 39 communal level manure storage, 1236 individual household storage facilities, 29 sets of equipment for manure management 51,120 kg N/year, 29,820 kg P/year. Municipal waste water New/extension of domestic wastewater 6,400 kg N/year, sewerage systems and treatment plants in 16 1,025 kg P/year, villages receiving also investments for 62,735 kg BOD/year. livestock manure proper management at community level. Promotion of the Code of Good Agricultural Practices reduced or conservative tillage, nutrient management plans with soil testing, use of leguminous plants in crop rotation, use of organic fertilizers, plantation of buffer strips and vegetative barriers, public awareness and better information, etc 10,320kg N/year-2012; 24,000kg N/year-2015 in Project area
  • 4.
    Stress reduction measurements:Agricultural pollution reduction practices Year Manure properly stored and used (t) Nutrient reduction (kg) N P2O5 K2O 2011 2,400 8,640 5,040 11,520 2012 7,200 25,920 15,120 34,560 2013 14,200 51,120 29,820 68,160 Forecast 2014 39,000 140,400 81,900 187,200 Forecast 2015 112,500 405,000 236,250 540,000 Target for end of Project: 300,000 kg N/year