1. Coal Lignite Gas Diesel Total Hydro RES*(MNRE) Total
State 17979.00 250.00 2879.20 0.00 21108.20 0.00 5888.25 735.85 6624.10 27732.30
Private 22425.83 1080.00 558.00 0.00 24063.83 0.00 3241.00 25955.85 29196.85 53260.68
Central 15732.18 250.00 2344.06 0.00 18326.24 1620.00 11502.52 379.00 11881.52 31827.76
Sub Total 56137.01 1580.00 5781.26 0.00 63498.27 1620.00 20631.77 27070.70 47702.47 112820.74
State 21290.00 900.00 2849.82 0.00 25039.82 0.00 5446.50 575.98 6022.48 31062.30
Private 31947.17 500.00 4676.00 0.00 37123.17 0.00 481.00 32407.18 32888.18 70011.35
Central 20479.10 0.00 3280.67 0.00 23759.77 1840.00 1635.00 666.30 2301.30 27901.07
Sub Total 73716.27 1400.00 10806.49 0.00 85922.76 1840.00 7562.50 33649.46 41211.96 128974.72
State 20592.50 0.00 791.98 159.96 21544.44 0.00 11819.83 597.88 12417.71 33962.15
Private 13272.00 250.00 5340.24 273.70 19135.95 0.00 0.00 45768.56 45768.56 64904.51
Central 11835.02 3390.00 359.58 0.00 15584.60 3320.00 0.00 541.90 541.90 19446.50
Sub Total 45699.52 3640.00 6491.80 433.66 56264.99 3320.00 11819.83 46908.34 58728.17 118313.16
State 6970.00 0.00 100.00 0.00 7070.00 0.00 3550.22 275.11 3825.33 10895.33
Private 5553.00 0.00 0.00 0.00 5553.00 0.00 209.00 1460.21 1669.21 7222.21
Central 15233.68 0.00 0.00 0.00 15233.68 0.00 1005.20 10.00 1015.20 16248.88
Sub Total 27756.68 0.00 100.00 0.00 27856.68 0.00 4764.42 1745.32 6509.74 34366.42
State 0.00 0.00 466.36 36.00 502.36 0.00 422.00 233.25 655.25 1157.60
Private 0.00 0.00 0.00 0.00 0.00 0.00 0.00 210.30 210.30 210.30
Central 770.02 0.00 1253.60 0.00 2023.62 0.00 1522.00 30.00 1552.00 3575.62
Sub Total 770.02 0.00 1719.96 36.00 2525.98 0.00 1944.00 473.55 2417.55 4943.52
State 0.00 0.00 0.00 40.05 40.05 0.00 0.00 5.25 5.25 45.30
Private 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27.66 27.66 27.66
Central 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.10 5.10 5.10
Sub Total 0.00 0.00 0.00 40.05 40.05 0.00 0.00 38.01 38.01 78.06
State 66831.50 1150.00 7087.36 236.01 75304.86 0.00 27126.80 2423.31 29550.11 104854.98
Private 73198.00 1830.00 10574.24 273.70 85875.95 0.00 3931.00 105829.76 109760.76 195636.71
Central 64050.00 3640.00 7237.91 0.00 74927.91 6780.00 15664.72 1632.30 17297.02 99004.93
Total 204079.50 6620.00 24899.51 509.71 236108.72 6780.00 46722.52 109885.38 156607.90 399496.61
Figures at decimal may not tally due to rounding off
Abbreviation:-
Note : -
(As per latest information available with MNRE)
*Break up of RES all India as on 31.03.2022 is given below (in MW) :
4848.90 40357.58 53996.54 109885.38
A. 840 MW
1. Unit-3 (660 MW) of NABINAGAR STPP has been commissioned and added to central sector of ER & NR states as per their allocation.
2. Unit-1,2&3 (3x60 = 180 MW) of BAJOLI HOLI HPS has been commissioned and added to private sector of Himachal Pradesh.
B. 480 MW
C. 18 MW
D. March., 2022 A-B+C 378 MW
E. March., 2022 3510.75 MW
F. March., 2022 D+E 3888.75 MW
* Off-grid RES Capacity has been included from July-2021 onwards
Sector wise breakup of RES capacity as shown is provisional.
Allocation from central sector stations has been updated till 28.02.2022.
Share of Railway (900 MW) from NABI NAGAR TPP (1000 MW) is included in central sector of Bihar.
Share from private sector generating stations has been updated as per latest information available.
Renewable
Northern Region
Western Region
Southern Region
Eastern Region
North Eastern
Region
ALL INDIA INSTALLED CAPACITY (IN MW) OF POWER STATIONS
(As on 31.03.2022)
(UTILITIES)
Region Ownership/ Sector
Mode wise breakup
Grand Total
Thermal
Nuclear
Islands
ALL INDIA
SHP=Small Hydro Project (≤ 25 MW), BP=Biomass Power, U&I=Urban & Industrial Waste Power, RES=Renewable Energy Sources
1. RES include SHP, BP, U&I, Solar and Wind Energy. Installed capacity in respect of RES (MNRE) as on 31.03.2022
Small
Hydro Power
Wind Power
Bio-Power
Solar Power
Total
Capacity
BM Power/Cogen.
1. Unit-1 (60 MW) of BANDEL TPS has been retired from state sector of West Bengal.
2. Unit-1&2 (2x210 = 420 MW) of KOLAGHAT TPS has been retired from state sector of West Bengal.
Capacity Uprated during March., 2022
1. BHAKRA LEFT HPS U-3 uprated from 108 MW to 126 MW.
Net Conv. Capacity Added during
Waste to Energy
10205.61 476.75
Capacity Added during March., 2022
Capacity Retired during March., 2022
Net RES Capacity Added during
Net Capacity Added during