BUG PROJECT
Information as a basis to
establish transboundary
cooperation: The experience
of the Bug Pilot Project
Małgorzata Landsberg-Uczciwek
Voivodeship Inspectorate of Environmental Protection in Szczecin
Teresa Zań
Regional Water Management Board in Warsaw
The Bug River basin is
situated in the north-west part
of Ukraine, south-western
Belarus and the central-
eastern part of Poland and is
within the Baltic Sea
catchment area. The total
area of the Bug basin is
39.4 thousand km2
, which is
19.3% of the Vistula basin.
The area of the basin
belongs to the different
administrative regions
in each country.
Ukraine – 27.4%,
Belarus – 23.4%,
Poland – 49.2 %
of total area.
Transboundary co-operation in the basin
In the agreement between Poland and the USSR on
co-operation in water management (1964), the countries
established monitoring networks on the bordering part of
the river Bug.
Before 1992
After 1992
Ukraine
The agreement between the Governments of the Republic
of Poland and Ukraine on co-operation in the field of water
management on rivers crossing their mutual border
(Kiev, October 10, 1996).
Belarus
The agreement between the Ministry of Environmental
Protection, Natural Resources and Forestry of Poland, and
the State Committee of the Belarus Republic for Ecology,
on co-operation in the field of environmental protection
(May 20, 1992).
Polish-Ukrainian Committee for Co-operation in the Field
of Boundary Waters :
• a working group for planning,
• a working group for protection against pollution,
• a working group for flood protection, river regulation
and land melioration,
• a working group for hydro-meteorology and hydro-
geology,
• a working group for accidental pollution control.
Pilot Project
• The Pilot Project under the UNECE Water
Convention started in January 1997
and finished in May 2003.
• The Memorandum of Understanding (MoU)
was signed in 1997.
• to demonstrate the implementation of the UNECE
Guidelines on Water Quality Monitoring and Assessment
of Transboundary River;
• to initiate and/or improve bilateral and multilateral
co-operation, leading to institutional
strengthening and capacity building under the
Convention;
• to prepare effective and efficient monitoring and
assessment programmes which are sustainable
in the specific economic contexts of the
countries concerned;
• to support approximation to European Union
environmental legislation in CEEC countries.
Pilot Project - objectives
Project realization
Importance of inception phase
• Important part of the information exchange has
started:
- the very first approach to the common
understanding of the transboundary river basin
management, problems/issues in the Bug basin
and quality of water (new for each country),
- learning about water policy and willingness to
use European Union legislation (important for
Poland),
- political and institutional structure of water
management in each country.
Inception phase - lessons learnt
• Necessity to make enough available time
for good understanding of the Project.
The river basin approach, integrated water
management, environmental issues and
concerns, the principle of public
participation.
• Invitation for the right institution and right
people for cooperation (administrative division
and political structure).
Identification and review of water
management issues
• Legislation, national strategy plans and
water policy (function/uses, problems/issues
– information needs)
The area of the Bug River basin is covered
by three riparian countries with different
political and economic systems. Poland was
in the process of accession to the EU,
Ukraine adapts its legislation to the laws of
the European Council, while Belarus uses a
separate legislative system.
Identification and review of water
management issues
• The key steps to formulate information
needs are:
- identifying functions/uses and
problems/issues of the Bug basin water
and
- relations between the functions of the
basin, the utilisation of the water and the
problems occurring in the basin.
Functions and uses of the Bug basin water
(inventory+policy))
Water
use/function
Belarus Poland Ukraine Common concern
surface
waters
ground
waters
surface
waters
ground
-waters
surface
waters
ground
-waters
surface
waters
ground-
waters
Ecological
function + ++ ++ ++
Drinking water
supply o + ++* ++ o + ++* ++
Industrial water
supply o ++ o ++ o + o ++
Agriculture
+ + ++ o + + ++ +
Fish farms
o o + o + o + o
Recreation and
angling + ++ + + ++
Transport of
sewage ++ ++ ++ ++
(++) accordingly important, (+) moderately important and (O) not important of water uses
Relations between the functions of the basin, the utilisation of the water and
the problems occurring in the basin (inventory, policy and experts assessment)
Problems Use/Functions
Ecological
function
Supply of
drinking
water*
Agri-
culture**
Fish-
farms
Recreati
on and
angling
Supplies
for the
industry**
Transport
medium
including
sewage
Impact on
Zegrzyns
kie Lake
Pollution by
nutrients and
eutrophication
+++ +++
***
+ +++ + + +++
Microbiological
pollution
+ ++ + + +++ + +++
Organic pollution +++ ++ + + +++ +
Accidental pollution + + + + + + +
High variability of
flows
+ + +
Flood hazard River
regulation, damming
and draining
+ + + + + + +
Pollution by toxic
substances
+ + + + + +
accordingly moderately not important as common concern
Identification and review of water
management issues – lessons learnt
• Difficulties to agree upon the most
important,functions/uses of the Bug River water
(ecological?),
• problems/issues - differences in common understanding
of water quality,
• Identifying the reasons for the problems (lack of proper
data),
• common criteria for assessment due to differences in
legislation and technical possibility of labs.
Report No. 3 deals with the information needs, selection of
indicative parameters and a critical evaluation of the existing
monitoring programmes in view of fitness for purpose.
INVENTORY
of available information
SURVEYS
if information is lacking
Identification of
USES/FUNCTIONS
CRITERIA/TARGETS
for functions/uses and issues
WATER LEGISLATION
including classification systems
ANALYSIS OF WATER
MANAGEMENT ISSUES
INFORMATION
NEEDS
STRATEGIES
for monitoring and assessment
RECOMMENDATIONS
for improvement
Information on the Bug River basin scale
The Report No. 2 - Identification and Review of Water
Management Issues - can be regarded as the first step in
the development of a River Basin Management Plan.
It describes the river basin, the functions and uses of the
river and its tributaries, the actual quality status
compared to the requirements of the functions and the
main problems and causes identified from this
comparison.
ACHIEVEMENTS
ACHIEVEMENTS
Awareness of the information meaning
• The execution of the inventory stage has
made aware the people responsible for water
quality assessment, that getting information
is one of the weakest points of
the management process.
• The necessity to collect and process data
from different sectors of economy by river
basins has arisen.
ACHIEVEMENTS
Closer to the EU legislation
• Most of the methods and standards used in
the Pilot Project and set in
the Recommendation Report are based on
the regulations of the European Union.
Practical implementation of co-operation
Surveys and field trips
• Joint study trips, samplings, workshops and
discussions bring the co-operating people closer
together within the countries as well as internationally.
This enhances the quality of co-operation.
ACHIEVEMENTS
Practical implementation of co-operation
Surveys and field trips
• The first data exchange between Poland, Ukraine
and Belarus conceived on such a large scale which
also includes data relevant for water management
analysis.
Exchange of data
ACHIEVEMENTS
• The proposal of the trilateral agreement
on co-operation in transboundary waters,
• Polish-Ukrainian-Belorusian working group on
the implementation of the Pilot Project,
• The Pilot Project on implementation of the UNECE
guidelines for groundwaters,
• Acceptation of the Report No. 3 by Polish-Ukrainian
Committee for Co-operation in the Field of Boundary
Waters.
Perspective of further co-operation
ACHIEVEMENTS
• Respect the differences in legislative systems
and levels of making particular decisions and
ralities which limit co-operation between
countries.
How to organise co-operation practically
Practical implementation of co-operation
Surveys and field trips
ACHIEVEMENTS
• Lack of a trilateral agreement forming the legal
basis of the Early Warning System.
• Transboundary information collection and
exchange system.
• Assessment of diffuse pollution, risk assessment
and toxicological examinations were not
performed according to the reference
conditions of the Pilot Project.
Which tasks have not been completed?
Summary
The realization of the Pilot Project for the Bug River
basin opens a new chapter in the transboundary co-
operation between Poland, Ukraine and Belarus. This
co-operation covers the whole river basin and its basic
assumption is the close relationship between
monitoring and assessment and water management.
Summary
It is crucial that the Pilot Project will be implemented
immediately after its completion. This will ensure
that recent experiences are used in routine
monitoring. However the full implementation of the
proposed changes can be difficult because of
financial constraints, therefore this implementation
should be gradual but constant.
Thank you for your attention

More Related Content

What's hot

3 neno kukuric- igrac - global tba activities twap
3  neno kukuric- igrac - global tba activities twap3  neno kukuric- igrac - global tba activities twap
3 neno kukuric- igrac - global tba activities twap
groundwatercop
 
5 batyr hajiyev -unece - convention&groundwater
5 batyr hajiyev -unece - convention&groundwater5 batyr hajiyev -unece - convention&groundwater
5 batyr hajiyev -unece - convention&groundwater
groundwatercop
 
Follow-up to COP21 & COP22 Outcomes, INBO
Follow-up to COP21 & COP22 Outcomes, INBOFollow-up to COP21 & COP22 Outcomes, INBO
Follow-up to COP21 & COP22 Outcomes, INBO
OECD Governance
 
Inbo central asia v02
Inbo central asia v02Inbo central asia v02
Inbo central asia v02
groundwatercop
 
GBF 2015, April 16th, Presentation of Mr. Volker Frobarth
GBF 2015, April 16th, Presentation of Mr. Volker FrobarthGBF 2015, April 16th, Presentation of Mr. Volker Frobarth
GBF 2015, April 16th, Presentation of Mr. Volker Frobarth
Green Bridge Forum
 
Aureli groundwater management in the syr darya
Aureli groundwater management in the syr daryaAureli groundwater management in the syr darya
Aureli groundwater management in the syr darya
groundwatercop
 
Belarus
BelarusBelarus
7 neno kukuric- igrac - assessment and ims-sdc
7 neno kukuric- igrac - assessment and ims-sdc7 neno kukuric- igrac - assessment and ims-sdc
7 neno kukuric- igrac - assessment and ims-sdc
groundwatercop
 
UNDP GEF Danube Regional Project:GEF Danube - Black Sea Strategic Partnership
UNDP GEF Danube Regional Project:GEF Danube - Black Sea Strategic PartnershipUNDP GEF Danube Regional Project:GEF Danube - Black Sea Strategic Partnership
UNDP GEF Danube Regional Project:GEF Danube - Black Sea Strategic Partnership
Iwl Pcu
 
Day2 4 kinyaga_legal_andinstitutional_namibia
Day2 4 kinyaga_legal_andinstitutional_namibiaDay2 4 kinyaga_legal_andinstitutional_namibia
Day2 4 kinyaga_legal_andinstitutional_namibia
groundwatercop
 
Item 6b. Strategic planning for delivering water sector reform and SDGs
Item 6b. Strategic planning for delivering water sector reform and SDGsItem 6b. Strategic planning for delivering water sector reform and SDGs
Item 6b. Strategic planning for delivering water sector reform and SDGs
OECD Environment
 
MRC Procedures - IWRM tool for basin development planning
MRC Procedures - IWRM tool for basin development planningMRC Procedures - IWRM tool for basin development planning
MRC Procedures - IWRM tool for basin development planning
Water, Land and Ecosystems (WLE)
 
2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne
2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne
2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne
Environmental Protection Agency, Ireland
 
International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...
Iwl Pcu
 
Capitalising on river flow data to meet changing national needs a uk perspe...
Capitalising on river flow data to meet changing national needs   a uk perspe...Capitalising on river flow data to meet changing national needs   a uk perspe...
Capitalising on river flow data to meet changing national needs a uk perspe...
hydrologywebsite1
 
Digital Water - The Water Framework Directive data management and visualisati...
Digital Water - The Water Framework Directive data management and visualisati...Digital Water - The Water Framework Directive data management and visualisati...
Digital Water - The Water Framework Directive data management and visualisati...
Environmental Protection Agency, Ireland
 
Unece convention&groundwater paris
Unece convention&groundwater parisUnece convention&groundwater paris
Unece convention&groundwater paris
groundwatercop
 
Rio danubio europa-wolfgangstaltzer
Rio danubio europa-wolfgangstaltzerRio danubio europa-wolfgangstaltzer
Rio danubio europa-wolfgangstaltzer
Expresso das Idéias Produções
 
Situational analysis republic of tajikistan eng
Situational analysis republic of tajikistan engSituational analysis republic of tajikistan eng
Situational analysis republic of tajikistan eng
groundwatercop
 

What's hot (19)

3 neno kukuric- igrac - global tba activities twap
3  neno kukuric- igrac - global tba activities twap3  neno kukuric- igrac - global tba activities twap
3 neno kukuric- igrac - global tba activities twap
 
5 batyr hajiyev -unece - convention&groundwater
5 batyr hajiyev -unece - convention&groundwater5 batyr hajiyev -unece - convention&groundwater
5 batyr hajiyev -unece - convention&groundwater
 
Follow-up to COP21 & COP22 Outcomes, INBO
Follow-up to COP21 & COP22 Outcomes, INBOFollow-up to COP21 & COP22 Outcomes, INBO
Follow-up to COP21 & COP22 Outcomes, INBO
 
Inbo central asia v02
Inbo central asia v02Inbo central asia v02
Inbo central asia v02
 
GBF 2015, April 16th, Presentation of Mr. Volker Frobarth
GBF 2015, April 16th, Presentation of Mr. Volker FrobarthGBF 2015, April 16th, Presentation of Mr. Volker Frobarth
GBF 2015, April 16th, Presentation of Mr. Volker Frobarth
 
Aureli groundwater management in the syr darya
Aureli groundwater management in the syr daryaAureli groundwater management in the syr darya
Aureli groundwater management in the syr darya
 
Belarus
BelarusBelarus
Belarus
 
7 neno kukuric- igrac - assessment and ims-sdc
7 neno kukuric- igrac - assessment and ims-sdc7 neno kukuric- igrac - assessment and ims-sdc
7 neno kukuric- igrac - assessment and ims-sdc
 
UNDP GEF Danube Regional Project:GEF Danube - Black Sea Strategic Partnership
UNDP GEF Danube Regional Project:GEF Danube - Black Sea Strategic PartnershipUNDP GEF Danube Regional Project:GEF Danube - Black Sea Strategic Partnership
UNDP GEF Danube Regional Project:GEF Danube - Black Sea Strategic Partnership
 
Day2 4 kinyaga_legal_andinstitutional_namibia
Day2 4 kinyaga_legal_andinstitutional_namibiaDay2 4 kinyaga_legal_andinstitutional_namibia
Day2 4 kinyaga_legal_andinstitutional_namibia
 
Item 6b. Strategic planning for delivering water sector reform and SDGs
Item 6b. Strategic planning for delivering water sector reform and SDGsItem 6b. Strategic planning for delivering water sector reform and SDGs
Item 6b. Strategic planning for delivering water sector reform and SDGs
 
MRC Procedures - IWRM tool for basin development planning
MRC Procedures - IWRM tool for basin development planningMRC Procedures - IWRM tool for basin development planning
MRC Procedures - IWRM tool for basin development planning
 
2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne
2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne
2. 2nd Cycle Draft River Basin Management Plan - Colin Byrne
 
International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...
 
Capitalising on river flow data to meet changing national needs a uk perspe...
Capitalising on river flow data to meet changing national needs   a uk perspe...Capitalising on river flow data to meet changing national needs   a uk perspe...
Capitalising on river flow data to meet changing national needs a uk perspe...
 
Digital Water - The Water Framework Directive data management and visualisati...
Digital Water - The Water Framework Directive data management and visualisati...Digital Water - The Water Framework Directive data management and visualisati...
Digital Water - The Water Framework Directive data management and visualisati...
 
Unece convention&groundwater paris
Unece convention&groundwater parisUnece convention&groundwater paris
Unece convention&groundwater paris
 
Rio danubio europa-wolfgangstaltzer
Rio danubio europa-wolfgangstaltzerRio danubio europa-wolfgangstaltzer
Rio danubio europa-wolfgangstaltzer
 
Situational analysis republic of tajikistan eng
Situational analysis republic of tajikistan engSituational analysis republic of tajikistan eng
Situational analysis republic of tajikistan eng
 

Similar to Information as a basis to establish transboundary cooperation: the experience of the Bug pilot project (Malgorzata Landsberg) - Powerpoint - 4.7mb

1. European Union Water Initiative plus for the Eastern Partnership
1.	European Union Water Initiative plus for the Eastern Partnership1.	European Union Water Initiative plus for the Eastern Partnership
1. European Union Water Initiative plus for the Eastern Partnership
EU Water Initiative plus for Eastern Partnership
 
Master ppt whole project report 2021
Master ppt whole project report 2021Master ppt whole project report 2021
Master ppt whole project report 2021
OECD Environment
 
Mr. Bo N Jacobsen IEWP @ Workshop on River Basin Management Planning and Gove...
Mr. Bo N Jacobsen IEWP @ Workshop on River Basin Management Planning and Gove...Mr. Bo N Jacobsen IEWP @ Workshop on River Basin Management Planning and Gove...
Mr. Bo N Jacobsen IEWP @ Workshop on River Basin Management Planning and Gove...
India-EU Water Partnership
 
Mr.Edouard Boinet IEWP @ Workshop on River Basin Management Planning and Gove...
Mr.Edouard Boinet IEWP @ Workshop on River Basin Management Planning and Gove...Mr.Edouard Boinet IEWP @ Workshop on River Basin Management Planning and Gove...
Mr.Edouard Boinet IEWP @ Workshop on River Basin Management Planning and Gove...
India-EU Water Partnership
 
EU4Environment water and data regional launch event
EU4Environment water and data regional launch eventEU4Environment water and data regional launch event
EU4Environment water and data regional launch event
OECD Environment
 
EU4Env water and data regional launch event
EU4Env water and data regional launch eventEU4Env water and data regional launch event
EU4Env water and data regional launch event
OECD Environment
 
Information and transboundary cooperation – challenges and responses (Frances...
Information and transboundary cooperation – challenges and responses (Frances...Information and transboundary cooperation – challenges and responses (Frances...
Information and transboundary cooperation – challenges and responses (Frances...
Iwl Pcu
 
Information and transboundary cooperation – challenges and responses (Frances...
Information and transboundary cooperation – challenges and responses (Frances...Information and transboundary cooperation – challenges and responses (Frances...
Information and transboundary cooperation – challenges and responses (Frances...
Iwl Pcu
 
EU4Environment Water and Data_Azerbaijan NPD Thematic Session 1
EU4Environment Water and Data_Azerbaijan NPD Thematic Session 1EU4Environment Water and Data_Azerbaijan NPD Thematic Session 1
EU4Environment Water and Data_Azerbaijan NPD Thematic Session 1
OECD Environment
 
River basin management plans and results of public consultation in Lithuania
River basin management plans and results of public consultation in LithuaniaRiver basin management plans and results of public consultation in Lithuania
River basin management plans and results of public consultation in Lithuania
Pomcert
 
WP5-Activity_5.1_and_5.2_Trieste.July.2016_Integrated_VVvar3.0
WP5-Activity_5.1_and_5.2_Trieste.July.2016_Integrated_VVvar3.0WP5-Activity_5.1_and_5.2_Trieste.July.2016_Integrated_VVvar3.0
WP5-Activity_5.1_and_5.2_Trieste.July.2016_Integrated_VVvar3.0
Vesna Vidmar
 
International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...
Iwl Pcu
 
Day1 1 ross_overview
Day1 1 ross_overviewDay1 1 ross_overview
Day1 1 ross_overview
groundwatercop
 
Item 6 b. euwi npd green_tf_ppt_final
Item 6 b. euwi npd green_tf_ppt_finalItem 6 b. euwi npd green_tf_ppt_final
Item 6 b. euwi npd green_tf_ppt_final
OECD Environment
 
Improvement of governance and access to drinking water and sanitation in the ...
Improvement of governance and access to drinking water and sanitation in the ...Improvement of governance and access to drinking water and sanitation in the ...
Improvement of governance and access to drinking water and sanitation in the ...
EU Water Initiative plus for Eastern Partnership
 
“EUWI+ Project Progress and changes occurred in previous period. Georgia” by ...
“EUWI+ Project Progress and changes occurred in previous period. Georgia” by ...“EUWI+ Project Progress and changes occurred in previous period. Georgia” by ...
“EUWI+ Project Progress and changes occurred in previous period. Georgia” by ...
EU Water Initiative plus for Eastern Partnership
 
Third IDMP CEE workshop: IDMP CEE progress and plans by Sabina Bokal
Third IDMP CEE workshop: IDMP CEE progress and plans by Sabina BokalThird IDMP CEE workshop: IDMP CEE progress and plans by Sabina Bokal
Third IDMP CEE workshop: IDMP CEE progress and plans by Sabina Bokal
Global Water Partnership Central and Eastern Europe
 
Third IDMP CEE workshop: Development of GIS Based Communication Technology Pl...
Third IDMP CEE workshop: Development of GIS Based Communication Technology Pl...Third IDMP CEE workshop: Development of GIS Based Communication Technology Pl...
Third IDMP CEE workshop: Development of GIS Based Communication Technology Pl...
Global Water Partnership Central and Eastern Europe
 
Integrated Management of Land- Based Activities in the Sao Francisco River Ba...
Integrated Management of Land- Based Activities in the Sao Francisco River Ba...Integrated Management of Land- Based Activities in the Sao Francisco River Ba...
Integrated Management of Land- Based Activities in the Sao Francisco River Ba...
Iwl Pcu
 
Participative River Basin Management Planning by Yunona Videnina and Pierre H...
Participative River Basin Management Planning by Yunona Videnina and Pierre H...Participative River Basin Management Planning by Yunona Videnina and Pierre H...
Participative River Basin Management Planning by Yunona Videnina and Pierre H...
EU Water Initiative plus for Eastern Partnership
 

Similar to Information as a basis to establish transboundary cooperation: the experience of the Bug pilot project (Malgorzata Landsberg) - Powerpoint - 4.7mb (20)

1. European Union Water Initiative plus for the Eastern Partnership
1.	European Union Water Initiative plus for the Eastern Partnership1.	European Union Water Initiative plus for the Eastern Partnership
1. European Union Water Initiative plus for the Eastern Partnership
 
Master ppt whole project report 2021
Master ppt whole project report 2021Master ppt whole project report 2021
Master ppt whole project report 2021
 
Mr. Bo N Jacobsen IEWP @ Workshop on River Basin Management Planning and Gove...
Mr. Bo N Jacobsen IEWP @ Workshop on River Basin Management Planning and Gove...Mr. Bo N Jacobsen IEWP @ Workshop on River Basin Management Planning and Gove...
Mr. Bo N Jacobsen IEWP @ Workshop on River Basin Management Planning and Gove...
 
Mr.Edouard Boinet IEWP @ Workshop on River Basin Management Planning and Gove...
Mr.Edouard Boinet IEWP @ Workshop on River Basin Management Planning and Gove...Mr.Edouard Boinet IEWP @ Workshop on River Basin Management Planning and Gove...
Mr.Edouard Boinet IEWP @ Workshop on River Basin Management Planning and Gove...
 
EU4Environment water and data regional launch event
EU4Environment water and data regional launch eventEU4Environment water and data regional launch event
EU4Environment water and data regional launch event
 
EU4Env water and data regional launch event
EU4Env water and data regional launch eventEU4Env water and data regional launch event
EU4Env water and data regional launch event
 
Information and transboundary cooperation – challenges and responses (Frances...
Information and transboundary cooperation – challenges and responses (Frances...Information and transboundary cooperation – challenges and responses (Frances...
Information and transboundary cooperation – challenges and responses (Frances...
 
Information and transboundary cooperation – challenges and responses (Frances...
Information and transboundary cooperation – challenges and responses (Frances...Information and transboundary cooperation – challenges and responses (Frances...
Information and transboundary cooperation – challenges and responses (Frances...
 
EU4Environment Water and Data_Azerbaijan NPD Thematic Session 1
EU4Environment Water and Data_Azerbaijan NPD Thematic Session 1EU4Environment Water and Data_Azerbaijan NPD Thematic Session 1
EU4Environment Water and Data_Azerbaijan NPD Thematic Session 1
 
River basin management plans and results of public consultation in Lithuania
River basin management plans and results of public consultation in LithuaniaRiver basin management plans and results of public consultation in Lithuania
River basin management plans and results of public consultation in Lithuania
 
WP5-Activity_5.1_and_5.2_Trieste.July.2016_Integrated_VVvar3.0
WP5-Activity_5.1_and_5.2_Trieste.July.2016_Integrated_VVvar3.0WP5-Activity_5.1_and_5.2_Trieste.July.2016_Integrated_VVvar3.0
WP5-Activity_5.1_and_5.2_Trieste.July.2016_Integrated_VVvar3.0
 
International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...
 
Day1 1 ross_overview
Day1 1 ross_overviewDay1 1 ross_overview
Day1 1 ross_overview
 
Item 6 b. euwi npd green_tf_ppt_final
Item 6 b. euwi npd green_tf_ppt_finalItem 6 b. euwi npd green_tf_ppt_final
Item 6 b. euwi npd green_tf_ppt_final
 
Improvement of governance and access to drinking water and sanitation in the ...
Improvement of governance and access to drinking water and sanitation in the ...Improvement of governance and access to drinking water and sanitation in the ...
Improvement of governance and access to drinking water and sanitation in the ...
 
“EUWI+ Project Progress and changes occurred in previous period. Georgia” by ...
“EUWI+ Project Progress and changes occurred in previous period. Georgia” by ...“EUWI+ Project Progress and changes occurred in previous period. Georgia” by ...
“EUWI+ Project Progress and changes occurred in previous period. Georgia” by ...
 
Third IDMP CEE workshop: IDMP CEE progress and plans by Sabina Bokal
Third IDMP CEE workshop: IDMP CEE progress and plans by Sabina BokalThird IDMP CEE workshop: IDMP CEE progress and plans by Sabina Bokal
Third IDMP CEE workshop: IDMP CEE progress and plans by Sabina Bokal
 
Third IDMP CEE workshop: Development of GIS Based Communication Technology Pl...
Third IDMP CEE workshop: Development of GIS Based Communication Technology Pl...Third IDMP CEE workshop: Development of GIS Based Communication Technology Pl...
Third IDMP CEE workshop: Development of GIS Based Communication Technology Pl...
 
Integrated Management of Land- Based Activities in the Sao Francisco River Ba...
Integrated Management of Land- Based Activities in the Sao Francisco River Ba...Integrated Management of Land- Based Activities in the Sao Francisco River Ba...
Integrated Management of Land- Based Activities in the Sao Francisco River Ba...
 
Participative River Basin Management Planning by Yunona Videnina and Pierre H...
Participative River Basin Management Planning by Yunona Videnina and Pierre H...Participative River Basin Management Planning by Yunona Videnina and Pierre H...
Participative River Basin Management Planning by Yunona Videnina and Pierre H...
 

More from Iwl Pcu

Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)
Iwl Pcu
 
Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)
Iwl Pcu
 
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Iwl Pcu
 
Understanding the audience (IWC8)
Understanding the audience (IWC8)Understanding the audience (IWC8)
Understanding the audience (IWC8)
Iwl Pcu
 
Effective slide designing
Effective slide designingEffective slide designing
Effective slide designing
Iwl Pcu
 
How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)
Iwl Pcu
 
Presentation vs Publication
Presentation vs PublicationPresentation vs Publication
Presentation vs Publication
Iwl Pcu
 
Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)
Iwl Pcu
 
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6
Iwl Pcu
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
Iwl Pcu
 

More from Iwl Pcu (20)

Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)Flood and Drought Management Tools (IWC8)
Flood and Drought Management Tools (IWC8)
 
Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)Caribbean Wastewater - Innovative Solutions (IWC8)
Caribbean Wastewater - Innovative Solutions (IWC8)
 
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
Large Marine Ecosystems: Megaregional Best Practices for LME Assessment and M...
 
Understanding the audience (IWC8)
Understanding the audience (IWC8)Understanding the audience (IWC8)
Understanding the audience (IWC8)
 
Effective slide designing
Effective slide designingEffective slide designing
Effective slide designing
 
How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)How to communicate science effectively (IWC8 Presentation)
How to communicate science effectively (IWC8 Presentation)
 
Presentation vs Publication
Presentation vs PublicationPresentation vs Publication
Presentation vs Publication
 
Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)Introduction to Nutrient Roundtable (IWC8)
Introduction to Nutrient Roundtable (IWC8)
 
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
GEF Oceanic Fisheries Management Project – Towards Transformation Change (IWC...
 
TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1TDA/SAP Methodology Training Course Module 2 Section 1
TDA/SAP Methodology Training Course Module 2 Section 1
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10
 
TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10TDA/SAP Methodology Training Course Module 2 Section 10
TDA/SAP Methodology Training Course Module 2 Section 10
 
TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9TDA/SAP Methodology Training Course Module 2 Section 9
TDA/SAP Methodology Training Course Module 2 Section 9
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7TDA/SAP Methodology Training Course Module 2 Section 7
TDA/SAP Methodology Training Course Module 2 Section 7
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 
TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6TDA/SAP Methodology Training Course Module 2 Section 6
TDA/SAP Methodology Training Course Module 2 Section 6
 
TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5TDA/SAP Methodology Training Course Module 2 Section 5
TDA/SAP Methodology Training Course Module 2 Section 5
 

Information as a basis to establish transboundary cooperation: the experience of the Bug pilot project (Malgorzata Landsberg) - Powerpoint - 4.7mb

  • 1. BUG PROJECT Information as a basis to establish transboundary cooperation: The experience of the Bug Pilot Project Małgorzata Landsberg-Uczciwek Voivodeship Inspectorate of Environmental Protection in Szczecin Teresa Zań Regional Water Management Board in Warsaw
  • 2. The Bug River basin is situated in the north-west part of Ukraine, south-western Belarus and the central- eastern part of Poland and is within the Baltic Sea catchment area. The total area of the Bug basin is 39.4 thousand km2 , which is 19.3% of the Vistula basin.
  • 3. The area of the basin belongs to the different administrative regions in each country. Ukraine – 27.4%, Belarus – 23.4%, Poland – 49.2 % of total area.
  • 4. Transboundary co-operation in the basin In the agreement between Poland and the USSR on co-operation in water management (1964), the countries established monitoring networks on the bordering part of the river Bug. Before 1992
  • 5. After 1992 Ukraine The agreement between the Governments of the Republic of Poland and Ukraine on co-operation in the field of water management on rivers crossing their mutual border (Kiev, October 10, 1996). Belarus The agreement between the Ministry of Environmental Protection, Natural Resources and Forestry of Poland, and the State Committee of the Belarus Republic for Ecology, on co-operation in the field of environmental protection (May 20, 1992).
  • 6. Polish-Ukrainian Committee for Co-operation in the Field of Boundary Waters : • a working group for planning, • a working group for protection against pollution, • a working group for flood protection, river regulation and land melioration, • a working group for hydro-meteorology and hydro- geology, • a working group for accidental pollution control.
  • 7. Pilot Project • The Pilot Project under the UNECE Water Convention started in January 1997 and finished in May 2003. • The Memorandum of Understanding (MoU) was signed in 1997.
  • 8. • to demonstrate the implementation of the UNECE Guidelines on Water Quality Monitoring and Assessment of Transboundary River; • to initiate and/or improve bilateral and multilateral co-operation, leading to institutional strengthening and capacity building under the Convention; • to prepare effective and efficient monitoring and assessment programmes which are sustainable in the specific economic contexts of the countries concerned; • to support approximation to European Union environmental legislation in CEEC countries. Pilot Project - objectives
  • 10. Importance of inception phase • Important part of the information exchange has started: - the very first approach to the common understanding of the transboundary river basin management, problems/issues in the Bug basin and quality of water (new for each country), - learning about water policy and willingness to use European Union legislation (important for Poland), - political and institutional structure of water management in each country.
  • 11. Inception phase - lessons learnt • Necessity to make enough available time for good understanding of the Project. The river basin approach, integrated water management, environmental issues and concerns, the principle of public participation. • Invitation for the right institution and right people for cooperation (administrative division and political structure).
  • 12. Identification and review of water management issues • Legislation, national strategy plans and water policy (function/uses, problems/issues – information needs) The area of the Bug River basin is covered by three riparian countries with different political and economic systems. Poland was in the process of accession to the EU, Ukraine adapts its legislation to the laws of the European Council, while Belarus uses a separate legislative system.
  • 13. Identification and review of water management issues • The key steps to formulate information needs are: - identifying functions/uses and problems/issues of the Bug basin water and - relations between the functions of the basin, the utilisation of the water and the problems occurring in the basin.
  • 14. Functions and uses of the Bug basin water (inventory+policy)) Water use/function Belarus Poland Ukraine Common concern surface waters ground waters surface waters ground -waters surface waters ground -waters surface waters ground- waters Ecological function + ++ ++ ++ Drinking water supply o + ++* ++ o + ++* ++ Industrial water supply o ++ o ++ o + o ++ Agriculture + + ++ o + + ++ + Fish farms o o + o + o + o Recreation and angling + ++ + + ++ Transport of sewage ++ ++ ++ ++ (++) accordingly important, (+) moderately important and (O) not important of water uses
  • 15. Relations between the functions of the basin, the utilisation of the water and the problems occurring in the basin (inventory, policy and experts assessment) Problems Use/Functions Ecological function Supply of drinking water* Agri- culture** Fish- farms Recreati on and angling Supplies for the industry** Transport medium including sewage Impact on Zegrzyns kie Lake Pollution by nutrients and eutrophication +++ +++ *** + +++ + + +++ Microbiological pollution + ++ + + +++ + +++ Organic pollution +++ ++ + + +++ + Accidental pollution + + + + + + + High variability of flows + + + Flood hazard River regulation, damming and draining + + + + + + + Pollution by toxic substances + + + + + + accordingly moderately not important as common concern
  • 16. Identification and review of water management issues – lessons learnt • Difficulties to agree upon the most important,functions/uses of the Bug River water (ecological?), • problems/issues - differences in common understanding of water quality, • Identifying the reasons for the problems (lack of proper data), • common criteria for assessment due to differences in legislation and technical possibility of labs.
  • 17. Report No. 3 deals with the information needs, selection of indicative parameters and a critical evaluation of the existing monitoring programmes in view of fitness for purpose. INVENTORY of available information SURVEYS if information is lacking Identification of USES/FUNCTIONS CRITERIA/TARGETS for functions/uses and issues WATER LEGISLATION including classification systems ANALYSIS OF WATER MANAGEMENT ISSUES INFORMATION NEEDS STRATEGIES for monitoring and assessment RECOMMENDATIONS for improvement
  • 18. Information on the Bug River basin scale The Report No. 2 - Identification and Review of Water Management Issues - can be regarded as the first step in the development of a River Basin Management Plan. It describes the river basin, the functions and uses of the river and its tributaries, the actual quality status compared to the requirements of the functions and the main problems and causes identified from this comparison. ACHIEVEMENTS
  • 19. ACHIEVEMENTS Awareness of the information meaning • The execution of the inventory stage has made aware the people responsible for water quality assessment, that getting information is one of the weakest points of the management process. • The necessity to collect and process data from different sectors of economy by river basins has arisen.
  • 20. ACHIEVEMENTS Closer to the EU legislation • Most of the methods and standards used in the Pilot Project and set in the Recommendation Report are based on the regulations of the European Union.
  • 21. Practical implementation of co-operation Surveys and field trips • Joint study trips, samplings, workshops and discussions bring the co-operating people closer together within the countries as well as internationally. This enhances the quality of co-operation. ACHIEVEMENTS
  • 22. Practical implementation of co-operation Surveys and field trips • The first data exchange between Poland, Ukraine and Belarus conceived on such a large scale which also includes data relevant for water management analysis. Exchange of data ACHIEVEMENTS
  • 23. • The proposal of the trilateral agreement on co-operation in transboundary waters, • Polish-Ukrainian-Belorusian working group on the implementation of the Pilot Project, • The Pilot Project on implementation of the UNECE guidelines for groundwaters, • Acceptation of the Report No. 3 by Polish-Ukrainian Committee for Co-operation in the Field of Boundary Waters. Perspective of further co-operation ACHIEVEMENTS
  • 24. • Respect the differences in legislative systems and levels of making particular decisions and ralities which limit co-operation between countries. How to organise co-operation practically Practical implementation of co-operation Surveys and field trips ACHIEVEMENTS
  • 25. • Lack of a trilateral agreement forming the legal basis of the Early Warning System. • Transboundary information collection and exchange system. • Assessment of diffuse pollution, risk assessment and toxicological examinations were not performed according to the reference conditions of the Pilot Project. Which tasks have not been completed?
  • 26. Summary The realization of the Pilot Project for the Bug River basin opens a new chapter in the transboundary co- operation between Poland, Ukraine and Belarus. This co-operation covers the whole river basin and its basic assumption is the close relationship between monitoring and assessment and water management.
  • 27. Summary It is crucial that the Pilot Project will be implemented immediately after its completion. This will ensure that recent experiences are used in routine monitoring. However the full implementation of the proposed changes can be difficult because of financial constraints, therefore this implementation should be gradual but constant.
  • 28.
  • 29. Thank you for your attention