The document outlines a Lean Six Sigma project focused on improving the Military Interdepartmental Purchase Request (MIPR) process, detailing project milestones from initiation on March 9, 2018, to closure on February 21, 2019. It includes a comprehensive analysis of the current process performance, root cause identification, proposed solutions, and implementation plans to enhance efficiency and customer satisfaction. Key aspects of the project encompass data collection, operational definitions, risk analysis, and mapping of both short and long-term processes.