SlideShare a Scribd company logo
Hills Road cycle lanes – revisited
A survey carried out during December 2016 on behalf of
the Hills Road Area Residents Association
James Berry
29th December 2016
On 21st August 2016, immediately after the cycle lanes were completed on the section of Hills
Road from Long Road to Cherry Hinton Road, my wife and I carried out a detailed survey. This
identified a number of issues, including:
 Obsolete dual-use signage on the western side of Hills Road
 Unidentified bus stops on the eastern side of Hills Road
 Extended verges on the western side of Hills Road
 Unfinished pavements
 Confusing signs
 Abandoned equipment
I updated our survey in December, and was pleased that considerable progress had been made.
However, there is still work to do, which is outlined in this report.
This survey incorporates observations by members of the Hills Road Area Residents Association.
Photographs overleaf: Abandoned equipment illustrated in the survey on 21st August 2016
Action taken since survey on 21st August 2016
 The pavement on the western side of Hills Road has been resurfaced.
 On the western side of Hills Road, from Luard Road to Long Road, the dual-use signposts
and the white line, separating pedestrians and cyclists, have been removed.
 Almost all of the abandoned equipment and confusing signs have been removed.
 Planting has taken place along most of the Homerton College frontage and on the two bus
stops on the eastern side of Hills Road.
 The bus stops outside 267 Hills Road and the EF Language School now display illuminated
online signs with bus times, and the EF Language School has a bus stop sign.
 The troughs on the eastern side of Hills Road have been filled with gravel, ready for planting.
 Plastic white posts have been installed in the troughs on the western side of Hills Road, from
numbers 256 to 282, to help the sedum grow and discourage vehicles from mounting the
pavement.
Photographs overleaf: top left – resurfaced pavement; top right – plastic white posts;
bottom left – Homerton College planting; bottom right – troughs ready for planting.
Summary of action remaining
Cycle signage on western side of Hills Road
Install a sign at the junction of Luard Road and Hills Road to make it clear that the pavement from
Luard Road to Long Road is for pedestrian use only.
Bus stops on eastern side of Hills Road
Install a bus stop sign outside 269 Hills Road.
Extended verges on western side of Hills Road
Landscape the verges.
Abandoned equipment and signs
Remove the two concrete sections near the junction of Hills Road and Cavendish Avenue.
Incomplete sedum planting
(1) Plant sedum on the eastern side. (2) Dig out the troughs on the western side, and prepare with
soil and gravel, before relaying the sedum strips.
Incomplete pavements
Resurface the pavements outside 256, 258, 260 and 285 Hills Road.
Cycle signage on western side of Hills Road
Before the construction of the cycle lanes, the pavement on the western side of Hills Road was
dual-use, shared by cyclists and pedestrians.
Since our last report, the pavement has been resurfaced and the dual-use white line, separating
pedestrians and cyclists, has been removed from Long Road to Luard Road. The blue dual-use
signposts near the entrance to The Perse School and outside 288 Hills Road have also been taken
away. However, the white line remains from Luard Road to Homerton College, and there is
nothing to indicate to cyclists travelling south from Luard Road that the pavement is for
pedestrians only. As a result, many cyclists continue to cycle on the pavement.
Action: Install a sign at the junction of Luard Road and Hills Road to make it clear that the
pavement is for pedestrian use only.
Photographs overleaf: left - sign required at Luard Road junction to signify end of dual-use; right– dual-use white line from
Luard Road to Homerton College.
Bus stops on eastern side of Hills Road
There are two bus stops on the eastern side of Hills Road – one next to the EF Language School
and one outside 269 Hills Road. When we carried out our survey in August, there was nothing to
identify these as bus stops, which must have been confusing for both passengers and bus drivers.
Now both bus stops have been planted and have Real Time Passenger Information displays.
However, while the stop next to the EF Language School has a bus stop sign, the one outside 269
Hills Road doesn’t.
Action: Install a bus stop sign outside 269 Hills Road.
Photographs overleaf: top left – Real Time Passenger Information display; top right – bus stop sign next to
EF Language School; bottom left – planting; bottom right- missing bus stop sign outside 269 Hills Road
Extended verges on western side of Hills Road
The extended verges on the western side of Hills Road were not laid properly. Concrete, rubble
and stones were left from the installation of new street lights. The soil was simply tipped in and
wasn’t pressed down. Seeds were scattered without watering. Then the contractors dumped
equipment on the verges and in some cases ploughed them up with their vehicles. Generally, the
verges are below pavement level, which will make mowing difficult. It is not surprising that the
verges are generally a mixture of bare earth and weeds.
Grant Weller (Project Manager – Cycling Infrastructure Team) confirmed on 6 September that:
“With regards the extended verges, they are due to be landscaped at the start of the planting
season which will be towards the end of September/early October. They will be planted with a
variety of low maintenance, drought resistance scrubs and plants. Not wishing to leave these
excavations open for any period of time they were immediately filled with the topsoil
originally specified, a British Standard grade topsoil. Inevitably, areas like this will attract
weeds if left unattended but prior to planting they will be removed and a layer of bark
nuggets placed amongst the new plants to act as a future weed suppressant.”
Action: Landscape the extended verges.
Photographs overleaf: examples of poor quality verges
Abandoned equipment
Barriers, traffic cones, road signs, sandbags and planks have now been taken away from both
sides of Hills Road. The large pile of soil at the Hills Avenue junction has gone and the compound
for cabins and equipment at the entrance to Luard Road has been removed.
However, there are still two concrete sections near the junction of Hills Road and Cavendish
Avenue.
Action: Remove the two concrete sections
Photograph overleaf: Concrete sections near Cavendish Avenue junction.
Incomplete sedum planting
The sedum troughs on the eastern side of Hills Road were properly prepared by professional
landscape gardeners, with layers of soil and gravel. The sedum has yet to be planted.
On the western side of Hills Road, soil was tipped into the troughs and the sedum strips were
simply thrown down. In many places, the sedum has failed to grow.
Action: (1) Plant sedum on the eastern side. (2) Dig out the troughs on the western side, and
prepare properly, with soil and gravel, before relaying the sedum strips.
Photographs overleaf: top left – sedum has taken root in places; top right – poorly laid sedum;
bottom left – gravel laid on top of sedum; gravel laid properly on eastern side
Incomplete pavements
The pavements on both sides of Hills Rod have been resurfaced (in technical terms “overlaid with
slurry seal”). However, the section outside 285 Hills Road was missed. And the section outside
256, 258 and 260 Hills Road was not completed satisfactorily, leaving a number of depressions
which fill with water and soggy leaves. We observed that the puddles remained for 6 days in
December, and froze over on cold nights, presenting a safety hazard.
Action: Resurface the pavement outside 256, 258, 260 and 285 Hills Road.
Photographs overleaf: top left – two puddles outside 258 Hills Road; top right – pavement not resurfaced outside 285
Hills Road; bottom left – puddle outside 256 Hills Road; bottom right - puddle outside 260 Hills Road
Hills Road Cycle Lanes revisited

More Related Content

What's hot

East Don Trail - Design Concepts
East Don Trail - Design ConceptsEast Don Trail - Design Concepts
East Don Trail - Design Concepts
Toronto Public Consultation Unit
 
Lower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 ConstructionLower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 Construction
Toronto Public Consultation Unit
 
2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan
E'ville Eye
 
Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)
knelischer
 
Jasper Downtown/Riverfront Plan Presentation May 21, 2014
Jasper Downtown/Riverfront Plan Presentation May 21, 2014Jasper Downtown/Riverfront Plan Presentation May 21, 2014
Jasper Downtown/Riverfront Plan Presentation May 21, 2014
Matthew Crane
 
City of Rochester, Main Street Makeover
City of Rochester, Main Street MakeoverCity of Rochester, Main Street Makeover
City of Rochester, Main Street Makeover
Fishbeck, Thompson, Carr & Huber, Inc.
 
S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015
Naoise
 
GROC 2014 Year End Review
GROC 2014 Year End ReviewGROC 2014 Year End Review
GROC 2014 Year End Review
mygroc
 
2015 member meeting presentation
2015 member meeting presentation2015 member meeting presentation
2015 member meeting presentation
mygroc
 
Wellesley application summary brochure
Wellesley application summary brochureWellesley application summary brochure
Wellesley application summary brochure
Kurt Mueller
 
Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016
Fairfax County
 
Fort Allen Park HPB Presentation 2.15.12
Fort Allen Park HPB Presentation 2.15.12Fort Allen Park HPB Presentation 2.15.12
Fort Allen Park HPB Presentation 2.15.12
EasternPromenade
 
Emmp community presentations_anc oct 15 presentation final rev1
Emmp community presentations_anc oct 15 presentation final rev1Emmp community presentations_anc oct 15 presentation final rev1
Emmp community presentations_anc oct 15 presentation final rev1
RamaChilamkurthy
 
My Urban Walk Poster
My Urban Walk PosterMy Urban Walk Poster
My Urban Walk Poster
Isaac Swanson
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
Toronto Public Consultation Unit
 
Steeles Bridge EA PIC#2 powerpoint 04_01_2017
Steeles Bridge  EA PIC#2 powerpoint 04_01_2017Steeles Bridge  EA PIC#2 powerpoint 04_01_2017
Steeles Bridge EA PIC#2 powerpoint 04_01_2017
Paul B. Martin
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
VDOT Northern Virginia
 
Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014
Fairfax County
 
Steeles Avenue East Bridge Study PIC 1
Steeles Avenue East Bridge Study PIC 1Steeles Avenue East Bridge Study PIC 1
Steeles Avenue East Bridge Study PIC 1
Toronto Public Consultation Unit
 

What's hot (19)

East Don Trail - Design Concepts
East Don Trail - Design ConceptsEast Don Trail - Design Concepts
East Don Trail - Design Concepts
 
Lower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 ConstructionLower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 Construction
 
2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan2011 04-26 powell-street_urban_design_plan
2011 04-26 powell-street_urban_design_plan
 
Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)
 
Jasper Downtown/Riverfront Plan Presentation May 21, 2014
Jasper Downtown/Riverfront Plan Presentation May 21, 2014Jasper Downtown/Riverfront Plan Presentation May 21, 2014
Jasper Downtown/Riverfront Plan Presentation May 21, 2014
 
City of Rochester, Main Street Makeover
City of Rochester, Main Street MakeoverCity of Rochester, Main Street Makeover
City of Rochester, Main Street Makeover
 
S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015
 
GROC 2014 Year End Review
GROC 2014 Year End ReviewGROC 2014 Year End Review
GROC 2014 Year End Review
 
2015 member meeting presentation
2015 member meeting presentation2015 member meeting presentation
2015 member meeting presentation
 
Wellesley application summary brochure
Wellesley application summary brochureWellesley application summary brochure
Wellesley application summary brochure
 
Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016
 
Fort Allen Park HPB Presentation 2.15.12
Fort Allen Park HPB Presentation 2.15.12Fort Allen Park HPB Presentation 2.15.12
Fort Allen Park HPB Presentation 2.15.12
 
Emmp community presentations_anc oct 15 presentation final rev1
Emmp community presentations_anc oct 15 presentation final rev1Emmp community presentations_anc oct 15 presentation final rev1
Emmp community presentations_anc oct 15 presentation final rev1
 
My Urban Walk Poster
My Urban Walk PosterMy Urban Walk Poster
My Urban Walk Poster
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
 
Steeles Bridge EA PIC#2 powerpoint 04_01_2017
Steeles Bridge  EA PIC#2 powerpoint 04_01_2017Steeles Bridge  EA PIC#2 powerpoint 04_01_2017
Steeles Bridge EA PIC#2 powerpoint 04_01_2017
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
 
Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014
 
Steeles Avenue East Bridge Study PIC 1
Steeles Avenue East Bridge Study PIC 1Steeles Avenue East Bridge Study PIC 1
Steeles Avenue East Bridge Study PIC 1
 

Similar to Hills Road Cycle Lanes revisited

FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
Toronto Public Consultation Unit
 
Sp2- pedestrian safety presentation 10.08.12 final
Sp2- pedestrian safety presentation 10.08.12 finalSp2- pedestrian safety presentation 10.08.12 final
Sp2- pedestrian safety presentation 10.08.12 final
cityofevanston
 
Restoring Westmeadows Meander
Restoring Westmeadows MeanderRestoring Westmeadows Meander
Restoring Westmeadows Meander
Tony Smith
 
Sp3 follow up power point pedestrian safety presentation 09.24.12 final
Sp3 follow up power point pedestrian safety presentation 09.24.12 finalSp3 follow up power point pedestrian safety presentation 09.24.12 final
Sp3 follow up power point pedestrian safety presentation 09.24.12 final
cityofevanston
 
Quander Road Walkway
Quander Road WalkwayQuander Road Walkway
Quander Road Walkway
Fairfax County
 
Wincobank Presentation
Wincobank PresentationWincobank Presentation
Wincobank Presentation
bridgetingle
 
Memorandum to mr.k.j.george. mla doc3
Memorandum to mr.k.j.george. mla doc3Memorandum to mr.k.j.george. mla doc3
Memorandum to mr.k.j.george. mla doc3
Arumugam Rajagopal
 
The Chatsworth Park Quarry
The Chatsworth Park QuarryThe Chatsworth Park Quarry
The Chatsworth Park Quarry
Chatsworth Historical Society
 
Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...
Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...
Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...
Fairfax County
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Crosstown TO
 
Restore Mass Ave at State Department
Restore Mass Ave at State DepartmentRestore Mass Ave at State Department
Restore Mass Ave at State Department
savetrees
 
Slide Presentation from Public Update Meeting no.1 - A Story of the Park: Peo...
Slide Presentation from Public Update Meeting no.1 - A Story of the Park: Peo...Slide Presentation from Public Update Meeting no.1 - A Story of the Park: Peo...
Slide Presentation from Public Update Meeting no.1 - A Story of the Park: Peo...
MemParkTomorrow
 
NostalgicOutdoors™- Acadia National Park- Carriage Road Trails
NostalgicOutdoors™- Acadia National Park- Carriage Road TrailsNostalgicOutdoors™- Acadia National Park- Carriage Road Trails
NostalgicOutdoors™- Acadia National Park- Carriage Road Trails
NostalgicOutdoors™
 
The Highline
 The Highline The Highline
The Highline
shruticharhate
 
Hunter Mill District 2018 Paving and Restriping: Public Information Meeting M...
Hunter Mill District 2018 Paving and Restriping: Public Information Meeting M...Hunter Mill District 2018 Paving and Restriping: Public Information Meeting M...
Hunter Mill District 2018 Paving and Restriping: Public Information Meeting M...
Fairfax County
 
Lennar sherwin-williams-park-design
Lennar sherwin-williams-park-designLennar sherwin-williams-park-design
Lennar sherwin-williams-park-design
E'ville Eye
 
Potosi Sidewalk Plan
Potosi Sidewalk PlanPotosi Sidewalk Plan
Potosi Sidewalk Plan
Brody Johnson
 
City council 9 17-13 19th street sidewalks
City council 9 17-13 19th street sidewalksCity council 9 17-13 19th street sidewalks
City council 9 17-13 19th street sidewalks
City of San Angelo Texas
 
Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016
StittsvilleCentral.ca
 
Public Meeting #2 Presentation - November 11, 2014
Public Meeting #2 Presentation - November 11, 2014Public Meeting #2 Presentation - November 11, 2014
Public Meeting #2 Presentation - November 11, 2014
Thomas Downs
 

Similar to Hills Road Cycle Lanes revisited (20)

FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
 
Sp2- pedestrian safety presentation 10.08.12 final
Sp2- pedestrian safety presentation 10.08.12 finalSp2- pedestrian safety presentation 10.08.12 final
Sp2- pedestrian safety presentation 10.08.12 final
 
Restoring Westmeadows Meander
Restoring Westmeadows MeanderRestoring Westmeadows Meander
Restoring Westmeadows Meander
 
Sp3 follow up power point pedestrian safety presentation 09.24.12 final
Sp3 follow up power point pedestrian safety presentation 09.24.12 finalSp3 follow up power point pedestrian safety presentation 09.24.12 final
Sp3 follow up power point pedestrian safety presentation 09.24.12 final
 
Quander Road Walkway
Quander Road WalkwayQuander Road Walkway
Quander Road Walkway
 
Wincobank Presentation
Wincobank PresentationWincobank Presentation
Wincobank Presentation
 
Memorandum to mr.k.j.george. mla doc3
Memorandum to mr.k.j.george. mla doc3Memorandum to mr.k.j.george. mla doc3
Memorandum to mr.k.j.george. mla doc3
 
The Chatsworth Park Quarry
The Chatsworth Park QuarryThe Chatsworth Park Quarry
The Chatsworth Park Quarry
 
Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...
Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...
Lee District 2018 Paving and Restriping: Public Information Meeting-March 7, ...
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
 
Restore Mass Ave at State Department
Restore Mass Ave at State DepartmentRestore Mass Ave at State Department
Restore Mass Ave at State Department
 
Slide Presentation from Public Update Meeting no.1 - A Story of the Park: Peo...
Slide Presentation from Public Update Meeting no.1 - A Story of the Park: Peo...Slide Presentation from Public Update Meeting no.1 - A Story of the Park: Peo...
Slide Presentation from Public Update Meeting no.1 - A Story of the Park: Peo...
 
NostalgicOutdoors™- Acadia National Park- Carriage Road Trails
NostalgicOutdoors™- Acadia National Park- Carriage Road TrailsNostalgicOutdoors™- Acadia National Park- Carriage Road Trails
NostalgicOutdoors™- Acadia National Park- Carriage Road Trails
 
The Highline
 The Highline The Highline
The Highline
 
Hunter Mill District 2018 Paving and Restriping: Public Information Meeting M...
Hunter Mill District 2018 Paving and Restriping: Public Information Meeting M...Hunter Mill District 2018 Paving and Restriping: Public Information Meeting M...
Hunter Mill District 2018 Paving and Restriping: Public Information Meeting M...
 
Lennar sherwin-williams-park-design
Lennar sherwin-williams-park-designLennar sherwin-williams-park-design
Lennar sherwin-williams-park-design
 
Potosi Sidewalk Plan
Potosi Sidewalk PlanPotosi Sidewalk Plan
Potosi Sidewalk Plan
 
City council 9 17-13 19th street sidewalks
City council 9 17-13 19th street sidewalksCity council 9 17-13 19th street sidewalks
City council 9 17-13 19th street sidewalks
 
Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016
 
Public Meeting #2 Presentation - November 11, 2014
Public Meeting #2 Presentation - November 11, 2014Public Meeting #2 Presentation - November 11, 2014
Public Meeting #2 Presentation - November 11, 2014
 

Recently uploaded

2024欧洲杯比分投注-2024欧洲杯比分投注推荐-2024欧洲杯比分投注|【​网址​🎉ac99.net🎉​】
2024欧洲杯比分投注-2024欧洲杯比分投注推荐-2024欧洲杯比分投注|【​网址​🎉ac99.net🎉​】2024欧洲杯比分投注-2024欧洲杯比分投注推荐-2024欧洲杯比分投注|【​网址​🎉ac99.net🎉​】
2024欧洲杯比分投注-2024欧洲杯比分投注推荐-2024欧洲杯比分投注|【​网址​🎉ac99.net🎉​】
ramaysha335
 
欧洲杯赌钱-欧洲杯赌钱比赛投注-欧洲杯赌钱比赛投注官网|【​网址​🎉ac22.net🎉​】
欧洲杯赌钱-欧洲杯赌钱比赛投注-欧洲杯赌钱比赛投注官网|【​网址​🎉ac22.net🎉​】欧洲杯赌钱-欧洲杯赌钱比赛投注-欧洲杯赌钱比赛投注官网|【​网址​🎉ac22.net🎉​】
欧洲杯赌钱-欧洲杯赌钱比赛投注-欧洲杯赌钱比赛投注官网|【​网址​🎉ac22.net🎉​】
arcosarturo900
 
MISS TEEN HYDERABAD 2024 - WINNER RYKA TANDON
MISS TEEN HYDERABAD 2024 - WINNER RYKA TANDONMISS TEEN HYDERABAD 2024 - WINNER RYKA TANDON
MISS TEEN HYDERABAD 2024 - WINNER RYKA TANDON
DK PAGEANT
 
Navigating the World of Topsoil: A Guide to the Right Choice for Your Garden
Navigating the World of Topsoil: A Guide to the Right Choice for Your GardenNavigating the World of Topsoil: A Guide to the Right Choice for Your Garden
Navigating the World of Topsoil: A Guide to the Right Choice for Your Garden
nerissacampuzano
 
一比一原版美国俄亥俄大学毕业证(OU学位证)如何办理
一比一原版美国俄亥俄大学毕业证(OU学位证)如何办理一比一原版美国俄亥俄大学毕业证(OU学位证)如何办理
一比一原版美国俄亥俄大学毕业证(OU学位证)如何办理
mjjbdpo2
 
Stag Elevators | Leading Home Elevator Company in India
Stag Elevators | Leading Home Elevator Company in IndiaStag Elevators | Leading Home Elevator Company in India
Stag Elevators | Leading Home Elevator Company in India
Stag Elevators
 
The Uttoxeter and Cheadle Voice Issue 123
The Uttoxeter and Cheadle Voice Issue 123The Uttoxeter and Cheadle Voice Issue 123
The Uttoxeter and Cheadle Voice Issue 123
Noel Sergeant
 
快速办理(加拿大CBU毕业证书)卡普顿大学毕业证毕业完成信一模一样
快速办理(加拿大CBU毕业证书)卡普顿大学毕业证毕业完成信一模一样快速办理(加拿大CBU毕业证书)卡普顿大学毕业证毕业完成信一模一样
快速办理(加拿大CBU毕业证书)卡普顿大学毕业证毕业完成信一模一样
ubopub
 
一比一原版(UoL毕业证)伦敦大学毕业证如何办理
一比一原版(UoL毕业证)伦敦大学毕业证如何办理一比一原版(UoL毕业证)伦敦大学毕业证如何办理
一比一原版(UoL毕业证)伦敦大学毕业证如何办理
qghuhwa
 
欧洲杯下注-欧洲杯下注买球网-欧洲杯下注买球网站|【​网址​🎉ac10.net🎉​】
欧洲杯下注-欧洲杯下注买球网-欧洲杯下注买球网站|【​网址​🎉ac10.net🎉​】欧洲杯下注-欧洲杯下注买球网-欧洲杯下注买球网站|【​网址​🎉ac10.net🎉​】
欧洲杯下注-欧洲杯下注买球网-欧洲杯下注买球网站|【​网址​🎉ac10.net🎉​】
brendonbrash97589
 
一比一原版塔夫斯大学毕业证Tufts成绩单一模一样
一比一原版塔夫斯大学毕业证Tufts成绩单一模一样一比一原版塔夫斯大学毕业证Tufts成绩单一模一样
一比一原版塔夫斯大学毕业证Tufts成绩单一模一样
stgq9v39
 
MISS RAIPUR 2024 - WINNER POONAM BHARTI.
MISS RAIPUR 2024 - WINNER POONAM BHARTI.MISS RAIPUR 2024 - WINNER POONAM BHARTI.
MISS RAIPUR 2024 - WINNER POONAM BHARTI.
DK PAGEANT
 
美洲杯投注冠军赔率揭晓!谁将问鼎南美之王?|【​网址​🎉ac22.net🎉​】
美洲杯投注冠军赔率揭晓!谁将问鼎南美之王?|【​网址​🎉ac22.net🎉​】美洲杯投注冠军赔率揭晓!谁将问鼎南美之王?|【​网址​🎉ac22.net🎉​】
美洲杯投注冠军赔率揭晓!谁将问鼎南美之王?|【​网址​🎉ac22.net🎉​】
callottermanha18096
 

Recently uploaded (13)

2024欧洲杯比分投注-2024欧洲杯比分投注推荐-2024欧洲杯比分投注|【​网址​🎉ac99.net🎉​】
2024欧洲杯比分投注-2024欧洲杯比分投注推荐-2024欧洲杯比分投注|【​网址​🎉ac99.net🎉​】2024欧洲杯比分投注-2024欧洲杯比分投注推荐-2024欧洲杯比分投注|【​网址​🎉ac99.net🎉​】
2024欧洲杯比分投注-2024欧洲杯比分投注推荐-2024欧洲杯比分投注|【​网址​🎉ac99.net🎉​】
 
欧洲杯赌钱-欧洲杯赌钱比赛投注-欧洲杯赌钱比赛投注官网|【​网址​🎉ac22.net🎉​】
欧洲杯赌钱-欧洲杯赌钱比赛投注-欧洲杯赌钱比赛投注官网|【​网址​🎉ac22.net🎉​】欧洲杯赌钱-欧洲杯赌钱比赛投注-欧洲杯赌钱比赛投注官网|【​网址​🎉ac22.net🎉​】
欧洲杯赌钱-欧洲杯赌钱比赛投注-欧洲杯赌钱比赛投注官网|【​网址​🎉ac22.net🎉​】
 
MISS TEEN HYDERABAD 2024 - WINNER RYKA TANDON
MISS TEEN HYDERABAD 2024 - WINNER RYKA TANDONMISS TEEN HYDERABAD 2024 - WINNER RYKA TANDON
MISS TEEN HYDERABAD 2024 - WINNER RYKA TANDON
 
Navigating the World of Topsoil: A Guide to the Right Choice for Your Garden
Navigating the World of Topsoil: A Guide to the Right Choice for Your GardenNavigating the World of Topsoil: A Guide to the Right Choice for Your Garden
Navigating the World of Topsoil: A Guide to the Right Choice for Your Garden
 
一比一原版美国俄亥俄大学毕业证(OU学位证)如何办理
一比一原版美国俄亥俄大学毕业证(OU学位证)如何办理一比一原版美国俄亥俄大学毕业证(OU学位证)如何办理
一比一原版美国俄亥俄大学毕业证(OU学位证)如何办理
 
Stag Elevators | Leading Home Elevator Company in India
Stag Elevators | Leading Home Elevator Company in IndiaStag Elevators | Leading Home Elevator Company in India
Stag Elevators | Leading Home Elevator Company in India
 
The Uttoxeter and Cheadle Voice Issue 123
The Uttoxeter and Cheadle Voice Issue 123The Uttoxeter and Cheadle Voice Issue 123
The Uttoxeter and Cheadle Voice Issue 123
 
快速办理(加拿大CBU毕业证书)卡普顿大学毕业证毕业完成信一模一样
快速办理(加拿大CBU毕业证书)卡普顿大学毕业证毕业完成信一模一样快速办理(加拿大CBU毕业证书)卡普顿大学毕业证毕业完成信一模一样
快速办理(加拿大CBU毕业证书)卡普顿大学毕业证毕业完成信一模一样
 
一比一原版(UoL毕业证)伦敦大学毕业证如何办理
一比一原版(UoL毕业证)伦敦大学毕业证如何办理一比一原版(UoL毕业证)伦敦大学毕业证如何办理
一比一原版(UoL毕业证)伦敦大学毕业证如何办理
 
欧洲杯下注-欧洲杯下注买球网-欧洲杯下注买球网站|【​网址​🎉ac10.net🎉​】
欧洲杯下注-欧洲杯下注买球网-欧洲杯下注买球网站|【​网址​🎉ac10.net🎉​】欧洲杯下注-欧洲杯下注买球网-欧洲杯下注买球网站|【​网址​🎉ac10.net🎉​】
欧洲杯下注-欧洲杯下注买球网-欧洲杯下注买球网站|【​网址​🎉ac10.net🎉​】
 
一比一原版塔夫斯大学毕业证Tufts成绩单一模一样
一比一原版塔夫斯大学毕业证Tufts成绩单一模一样一比一原版塔夫斯大学毕业证Tufts成绩单一模一样
一比一原版塔夫斯大学毕业证Tufts成绩单一模一样
 
MISS RAIPUR 2024 - WINNER POONAM BHARTI.
MISS RAIPUR 2024 - WINNER POONAM BHARTI.MISS RAIPUR 2024 - WINNER POONAM BHARTI.
MISS RAIPUR 2024 - WINNER POONAM BHARTI.
 
美洲杯投注冠军赔率揭晓!谁将问鼎南美之王?|【​网址​🎉ac22.net🎉​】
美洲杯投注冠军赔率揭晓!谁将问鼎南美之王?|【​网址​🎉ac22.net🎉​】美洲杯投注冠军赔率揭晓!谁将问鼎南美之王?|【​网址​🎉ac22.net🎉​】
美洲杯投注冠军赔率揭晓!谁将问鼎南美之王?|【​网址​🎉ac22.net🎉​】
 

Hills Road Cycle Lanes revisited

  • 1. Hills Road cycle lanes – revisited A survey carried out during December 2016 on behalf of the Hills Road Area Residents Association James Berry 29th December 2016
  • 2. On 21st August 2016, immediately after the cycle lanes were completed on the section of Hills Road from Long Road to Cherry Hinton Road, my wife and I carried out a detailed survey. This identified a number of issues, including:  Obsolete dual-use signage on the western side of Hills Road  Unidentified bus stops on the eastern side of Hills Road  Extended verges on the western side of Hills Road  Unfinished pavements  Confusing signs  Abandoned equipment I updated our survey in December, and was pleased that considerable progress had been made. However, there is still work to do, which is outlined in this report. This survey incorporates observations by members of the Hills Road Area Residents Association. Photographs overleaf: Abandoned equipment illustrated in the survey on 21st August 2016
  • 3.
  • 4. Action taken since survey on 21st August 2016  The pavement on the western side of Hills Road has been resurfaced.  On the western side of Hills Road, from Luard Road to Long Road, the dual-use signposts and the white line, separating pedestrians and cyclists, have been removed.  Almost all of the abandoned equipment and confusing signs have been removed.  Planting has taken place along most of the Homerton College frontage and on the two bus stops on the eastern side of Hills Road.  The bus stops outside 267 Hills Road and the EF Language School now display illuminated online signs with bus times, and the EF Language School has a bus stop sign.  The troughs on the eastern side of Hills Road have been filled with gravel, ready for planting.  Plastic white posts have been installed in the troughs on the western side of Hills Road, from numbers 256 to 282, to help the sedum grow and discourage vehicles from mounting the pavement. Photographs overleaf: top left – resurfaced pavement; top right – plastic white posts; bottom left – Homerton College planting; bottom right – troughs ready for planting.
  • 5.
  • 6. Summary of action remaining Cycle signage on western side of Hills Road Install a sign at the junction of Luard Road and Hills Road to make it clear that the pavement from Luard Road to Long Road is for pedestrian use only. Bus stops on eastern side of Hills Road Install a bus stop sign outside 269 Hills Road. Extended verges on western side of Hills Road Landscape the verges. Abandoned equipment and signs Remove the two concrete sections near the junction of Hills Road and Cavendish Avenue. Incomplete sedum planting (1) Plant sedum on the eastern side. (2) Dig out the troughs on the western side, and prepare with soil and gravel, before relaying the sedum strips. Incomplete pavements Resurface the pavements outside 256, 258, 260 and 285 Hills Road.
  • 7. Cycle signage on western side of Hills Road Before the construction of the cycle lanes, the pavement on the western side of Hills Road was dual-use, shared by cyclists and pedestrians. Since our last report, the pavement has been resurfaced and the dual-use white line, separating pedestrians and cyclists, has been removed from Long Road to Luard Road. The blue dual-use signposts near the entrance to The Perse School and outside 288 Hills Road have also been taken away. However, the white line remains from Luard Road to Homerton College, and there is nothing to indicate to cyclists travelling south from Luard Road that the pavement is for pedestrians only. As a result, many cyclists continue to cycle on the pavement. Action: Install a sign at the junction of Luard Road and Hills Road to make it clear that the pavement is for pedestrian use only. Photographs overleaf: left - sign required at Luard Road junction to signify end of dual-use; right– dual-use white line from Luard Road to Homerton College.
  • 8.
  • 9. Bus stops on eastern side of Hills Road There are two bus stops on the eastern side of Hills Road – one next to the EF Language School and one outside 269 Hills Road. When we carried out our survey in August, there was nothing to identify these as bus stops, which must have been confusing for both passengers and bus drivers. Now both bus stops have been planted and have Real Time Passenger Information displays. However, while the stop next to the EF Language School has a bus stop sign, the one outside 269 Hills Road doesn’t. Action: Install a bus stop sign outside 269 Hills Road. Photographs overleaf: top left – Real Time Passenger Information display; top right – bus stop sign next to EF Language School; bottom left – planting; bottom right- missing bus stop sign outside 269 Hills Road
  • 10.
  • 11. Extended verges on western side of Hills Road The extended verges on the western side of Hills Road were not laid properly. Concrete, rubble and stones were left from the installation of new street lights. The soil was simply tipped in and wasn’t pressed down. Seeds were scattered without watering. Then the contractors dumped equipment on the verges and in some cases ploughed them up with their vehicles. Generally, the verges are below pavement level, which will make mowing difficult. It is not surprising that the verges are generally a mixture of bare earth and weeds. Grant Weller (Project Manager – Cycling Infrastructure Team) confirmed on 6 September that: “With regards the extended verges, they are due to be landscaped at the start of the planting season which will be towards the end of September/early October. They will be planted with a variety of low maintenance, drought resistance scrubs and plants. Not wishing to leave these excavations open for any period of time they were immediately filled with the topsoil originally specified, a British Standard grade topsoil. Inevitably, areas like this will attract weeds if left unattended but prior to planting they will be removed and a layer of bark nuggets placed amongst the new plants to act as a future weed suppressant.” Action: Landscape the extended verges. Photographs overleaf: examples of poor quality verges
  • 12.
  • 13. Abandoned equipment Barriers, traffic cones, road signs, sandbags and planks have now been taken away from both sides of Hills Road. The large pile of soil at the Hills Avenue junction has gone and the compound for cabins and equipment at the entrance to Luard Road has been removed. However, there are still two concrete sections near the junction of Hills Road and Cavendish Avenue. Action: Remove the two concrete sections Photograph overleaf: Concrete sections near Cavendish Avenue junction.
  • 14.
  • 15. Incomplete sedum planting The sedum troughs on the eastern side of Hills Road were properly prepared by professional landscape gardeners, with layers of soil and gravel. The sedum has yet to be planted. On the western side of Hills Road, soil was tipped into the troughs and the sedum strips were simply thrown down. In many places, the sedum has failed to grow. Action: (1) Plant sedum on the eastern side. (2) Dig out the troughs on the western side, and prepare properly, with soil and gravel, before relaying the sedum strips. Photographs overleaf: top left – sedum has taken root in places; top right – poorly laid sedum; bottom left – gravel laid on top of sedum; gravel laid properly on eastern side
  • 16.
  • 17. Incomplete pavements The pavements on both sides of Hills Rod have been resurfaced (in technical terms “overlaid with slurry seal”). However, the section outside 285 Hills Road was missed. And the section outside 256, 258 and 260 Hills Road was not completed satisfactorily, leaving a number of depressions which fill with water and soggy leaves. We observed that the puddles remained for 6 days in December, and froze over on cold nights, presenting a safety hazard. Action: Resurface the pavement outside 256, 258, 260 and 285 Hills Road. Photographs overleaf: top left – two puddles outside 258 Hills Road; top right – pavement not resurfaced outside 285 Hills Road; bottom left – puddle outside 256 Hills Road; bottom right - puddle outside 260 Hills Road