The document discusses a pre-feasibility study for the Romero Project in the Dominican Republic. It notes the study found an internal rate of return of 28% and all-in sustaining costs of $595 per ounce of gold equivalent. It also mentions plans to submit permit applications and continue exploration in the area. Statements in the document regarding the pre-feasibility study, project economics, and development plans are considered forward-looking information that involves risks and uncertainties.
The document discusses the Romero Project pre-feasibility study results and Goldquest Corp's exploration efforts. Key points:
- The pre-feasibility study published in November 2016 showed a 28% internal rate of return and $595/oz all-in sustaining costs for the Romero Project.
- Goldquest is exploring the 50-km long Tireo Formation surrounding the Romero deposit and has made new discoveries, including the high-grade Cachimbo polymetallic discovery.
- The company is well financed with over $25 million cash and is accelerating news flow through feasibility studies, permitting, and exploration programs.
The document summarizes a presentation about the Romero Gold Project in the Dominican Republic. Key points include:
- A pre-feasibility study showed a 28% after-tax IRR, $203 million after-tax NPV, and all-in sustaining costs of $595/oz for the proposed starter mine.
- Proven and probable reserves total over 7 million tonnes at 3.72 g/t gold for 840,000 ounces of gold.
- The mine plan outlines a 2,800 tpd underground operation producing on average 109,500 ounces of gold equivalent annually over a 7 year mine life.
- Exploration continues to show promise with a new high-grade
The document summarizes a presentation on the Romero Project pre-feasibility study. Some key points:
- The pre-feasibility study showed a 28% internal rate of return and $595/oz all-in sustaining costs.
- Mineral reserves are estimated at 7 million tonnes grading 3.72 g/t gold for 840,000 ounces of gold.
- Measured and indicated resources are estimated at 20.2 million tonnes grading 2.67 g/t gold for 1.7 million ounces of gold.
- Inferred resources are estimated at 3 million tonnes grading 2.03 g/t gold for 197,000 ounces of gold.
The document discusses Goldquest Corporation's Romero gold-copper project in the Dominican Republic. Key points include:
- A pre-feasibility study shows the project has an after-tax NPV of $203 million and IRR of 28% at $1,300/oz gold.
- Proven and probable reserves total over 7 million tonnes grading 3.72 g/t gold and 0.88% copper for 980,000 ounces of gold.
- Exploration is targeting additional deposits along the 50 km Tireo Formation, with a 10,000 meter drill program underway.
- Goldquest Corp released a pre-feasibility study for its Romero gold-copper project in the Dominican Republic in September 2016.
- The study outlined a 7.3 year mine plan producing an average of 109,000 ounces of gold equivalent per year at all-in sustaining costs of $595 per ounce and an after-tax IRR of 28%.
- Proven and probable reserves are estimated at over 7 million tonnes grading 3.72 g/t gold and 0.88% copper, containing over 840,000 ounces of gold and 136 million pounds of copper.
The document discusses a pre-feasibility study for the Romero Gold/Copper mining project in the Dominican Republic. Key highlights from the study include an after-tax NPV of $203 million and an IRR of 28% at gold and copper prices of $1,300/oz and $2.50/lb respectively. The study outlines a 7.3 year mine life with average annual production of 109,000 ounces of gold equivalent and all-in sustaining costs of $595/oz. Exploration is also ongoing across the company's land package with several high-grade drill intercepts outlined.
The document summarizes the results of a pre-feasibility study for the Romero Gold/Copper mine in the Dominican Republic. Key highlights include an after-tax NPV of $203 million and IRR of 28% at metal prices of $1,300/oz for gold and $2.50/lb for copper. The study outlines a 7-year mine life with average annual production of 109,000 ounces of gold equivalent and all-in sustaining costs of $595/oz. Upcoming work will include feasibility studies, permitting, and ongoing exploration to expand resources.
IMPACT Silver is a Canadian silver mining company with operations focused on exploration and development of silver projects in Mexico. The company operates two production centers, processing ore from four mines located in two districts. IMPACT aims to increase production through continued exploration, targeting new resources to expand mill throughput and generate cash flow. Key goals include advancing exploration prospects, increasing mill feed grades and throughput, and ultimately upgrading to the TSX to support future growth objectives of becoming a mid-tier silver producer.
The document discusses the Romero Project pre-feasibility study results and Goldquest Corp's exploration efforts. Key points:
- The pre-feasibility study published in November 2016 showed a 28% internal rate of return and $595/oz all-in sustaining costs for the Romero Project.
- Goldquest is exploring the 50-km long Tireo Formation surrounding the Romero deposit and has made new discoveries, including the high-grade Cachimbo polymetallic discovery.
- The company is well financed with over $25 million cash and is accelerating news flow through feasibility studies, permitting, and exploration programs.
The document summarizes a presentation about the Romero Gold Project in the Dominican Republic. Key points include:
- A pre-feasibility study showed a 28% after-tax IRR, $203 million after-tax NPV, and all-in sustaining costs of $595/oz for the proposed starter mine.
- Proven and probable reserves total over 7 million tonnes at 3.72 g/t gold for 840,000 ounces of gold.
- The mine plan outlines a 2,800 tpd underground operation producing on average 109,500 ounces of gold equivalent annually over a 7 year mine life.
- Exploration continues to show promise with a new high-grade
The document summarizes a presentation on the Romero Project pre-feasibility study. Some key points:
- The pre-feasibility study showed a 28% internal rate of return and $595/oz all-in sustaining costs.
- Mineral reserves are estimated at 7 million tonnes grading 3.72 g/t gold for 840,000 ounces of gold.
- Measured and indicated resources are estimated at 20.2 million tonnes grading 2.67 g/t gold for 1.7 million ounces of gold.
- Inferred resources are estimated at 3 million tonnes grading 2.03 g/t gold for 197,000 ounces of gold.
The document discusses Goldquest Corporation's Romero gold-copper project in the Dominican Republic. Key points include:
- A pre-feasibility study shows the project has an after-tax NPV of $203 million and IRR of 28% at $1,300/oz gold.
- Proven and probable reserves total over 7 million tonnes grading 3.72 g/t gold and 0.88% copper for 980,000 ounces of gold.
- Exploration is targeting additional deposits along the 50 km Tireo Formation, with a 10,000 meter drill program underway.
- Goldquest Corp released a pre-feasibility study for its Romero gold-copper project in the Dominican Republic in September 2016.
- The study outlined a 7.3 year mine plan producing an average of 109,000 ounces of gold equivalent per year at all-in sustaining costs of $595 per ounce and an after-tax IRR of 28%.
- Proven and probable reserves are estimated at over 7 million tonnes grading 3.72 g/t gold and 0.88% copper, containing over 840,000 ounces of gold and 136 million pounds of copper.
The document discusses a pre-feasibility study for the Romero Gold/Copper mining project in the Dominican Republic. Key highlights from the study include an after-tax NPV of $203 million and an IRR of 28% at gold and copper prices of $1,300/oz and $2.50/lb respectively. The study outlines a 7.3 year mine life with average annual production of 109,000 ounces of gold equivalent and all-in sustaining costs of $595/oz. Exploration is also ongoing across the company's land package with several high-grade drill intercepts outlined.
The document summarizes the results of a pre-feasibility study for the Romero Gold/Copper mine in the Dominican Republic. Key highlights include an after-tax NPV of $203 million and IRR of 28% at metal prices of $1,300/oz for gold and $2.50/lb for copper. The study outlines a 7-year mine life with average annual production of 109,000 ounces of gold equivalent and all-in sustaining costs of $595/oz. Upcoming work will include feasibility studies, permitting, and ongoing exploration to expand resources.
IMPACT Silver is a Canadian silver mining company with operations focused on exploration and development of silver projects in Mexico. The company operates two production centers, processing ore from four mines located in two districts. IMPACT aims to increase production through continued exploration, targeting new resources to expand mill throughput and generate cash flow. Key goals include advancing exploration prospects, increasing mill feed grades and throughput, and ultimately upgrading to the TSX to support future growth objectives of becoming a mid-tier silver producer.
Outback Goldfields is exploring for high-grade gold at its Fosterville property in Victoria, Australia. It has entered into an agreement to acquire gold assets from Petratherm. Completing the acquisition is subject to regulatory approvals. The company has a large land package in a prolific gold district near Kirkland Lake Gold's Fosterville mine. It has an experienced management team and board. Near-term catalysts include an upcoming work program focused on high-grade, low-cost targets.
The Company is focused on the advanced stage Blue Moon Zinc project with significant values for copper, gold and silver. The project is subject to a NI 43-101 report filed on SEDAR and available here. The Company plans to advance Blue Moon to a feasibility study and permitting.
IMPACT Silver provides concise summaries of documents in 3 sentences or less. Here is a 3 sentence summary of the provided document:
The document discusses IMPACT Silver's operations, which include two production centers and four producing silver mines in Mexico. It notes the risks associated with forward-looking statements and outlines IMPACT's management team, properties, exploration targets, and future plans to increase production and expand processing capacity through continued exploration and development. The appendix provides resource estimates for the Capire mine and highlights from drilling at the Capire and Mirasol properties.
This presentation is updated to reflect our Quarter 2 results for Fiscal 2018. Please do not hesitate to contact Evan Eadie in investor relations with your questions.
E-mail: investor@starcore.com
Phone: 1-604-602-4935 x230
Tamino Minerals Inc. is a junior mining exploration company focused on gold projects in Mexico. It owns the El Volcan gold project, which has potential for gold and silver mineralization. The company plans to conduct mapping, sampling, trenching, geophysics and a 2500 meter drill program at El Volcan in 2020. Tamino Minerals' management team has extensive experience operating mining projects and exploration companies in Mexico. The company aims to become a leading gold project developer and miner in Mexico by acquiring and developing early stage properties.
Goldquest Mining Corp is an emerging developer unlocking value at its Romero gold discovery in the Dominican Republic. A 2015 preliminary economic assessment showed the Romero Project has a $219 million after-tax NPV at a 6% discount rate and 34% IRR, with a 2.7 year payback period and $572 per ounce all-in sustaining costs. The PEA outlined a 2,500 tonne per day underground mine with average resource grades of 4 grams per tonne gold, 0.8% copper, and 4.3 grams per tonne silver over a 7.7 million tonne mine plan targeting the high grade core of the 19.4 million tonne indicated resource. Goldquest
- The corporate presentation discusses Great Panther Silver's plans for production at its Guanajuato and Topia mines in Mexico, as well as exploring other properties. It provides financial results for Q2 2016 and the outlook for 2016. Production is expected to be between 4-4.2 million silver equivalent ounces at a cash cost per ounce of $3.8-3.9. The presentation highlights Great Panther's low costs of production and strong financial position as it works to increase production organically and through potential acquisitions.
The document provides an overview of GoldQuest Mining Inc. and its projects in the Dominican Republic. It summarizes the Romero project's mineral resource estimate of 2.4 million ounces of gold equivalent in the indicated category and 0.8 million ounces in the inferred category. A preliminary economic assessment for Romero completed in May 2014 outlined a 15-year mine life with average annual gold production of 90,000 ounces at an all-in sustaining cost of $353 per ounce and estimated post-tax NPV of $294 million. GoldQuest plans further exploration in 2014 to expand resources and advance Romero towards production while also exploring other prospects in its land package.
- The document discusses GoldQuest Mining Inc.'s Romero Project in the Dominican Republic. It provides details on the project's mineral resources, including an indicated resource of 2.4 million ounces of gold equivalent and inferred resource of 0.8 million ounces.
- A preliminary economic assessment completed in May 2014 found the Romero Project could produce 90,000 ounces of gold per year at an all-in sustaining cost of $353 per ounce, with an after-tax NPV of $294 million and 15.1% IRR over a 15-year mine life.
- GoldQuest aims to fast-track the Romero Project towards production while also conducting exploration at its other Tireo properties in
F.D.G. Mining Inc. owns gold mining concessions in Nicaragua that show potential for development. The company's key asset is the Topacio Gold Project, which has an inferred resource of 340,345 ounces of gold based on a 2012 estimate. F.D.G. plans to have JDS Energy and Mining Inc. complete an evaluation of Topacio to develop an execution plan. Additionally, F.D.G. holds the San Pedro and El Santo concessions near producing mines owned by B2Gold, suggesting further exploration potential. The company aims to advance its Nicaraguan assets and generate shareholder value from gold production.
SilverCrest Mines | Corporate Presentation | July 2014Silvercrestmines
SilverCrest Mines Inc. (NYSE MKT: SVLC; TSX: SVL) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest´s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal silver and gold producer, with an estimated life of mine of 8 years and average operating cash costs of $11 per ounce of silver equivalent (55:1 Ag:Au). SilverCrest anticipates that the new 3,000 tonnes per day conventional mill facility at the Santa Elena Mine should recover an average annual rate of 1.5 million ounces of silver and 32,800 ounces of gold over the current reserve. Major expansion and commissioning of the 3,000 tonnes per day conventional mill facility is nearing completion and is expected to significantly increase metals production at the Santa Elena Mine in 2014 and beyond. Exploration programs continue to make new discoveries at Santa Elena and also have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State, Mexico.
The document provides an overview of the Castelo de Sonhos gold project in Brazil being developed by TriStar Gold Inc. Key highlights from a preliminary feasibility study include projected gold production of 1.3 million ounces over 11 years at an average rate of 121,000 ounces per year. The study estimates an after-tax NPV of $321 million using a gold price of $1,550 per ounce and an internal rate of return of 28%. Initial capital costs are estimated at $261 million and operating costs are estimated at $900 per ounce on an all-in sustaining basis. Mining will use conventional open pit methods to extract ore from three deposits - Esperança South, East and Center - over two phases.
IMPACT Silver provides forward-looking statements about its operations that are based on assumptions and could change materially due to risks and uncertainties. The company operates two production centers in Mexico - Guadalupe processing ore from three mines, and a pilot plant at Capire processing from its mine. IMPACT explores across its land holdings for new deposits to develop organically and increase production over time through prudent management and continuous exploration.
SilverCrest Mines | Corporate Presentation | January 2014Silvercrestmines
SilverCrest Mines Inc. (TSX‐V: SVL; NYSE MKT: SVLC) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest’s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal gold and silver producer, with an estimated life of mine cash cost of US$8 per ounce of silver equivalent (55:1 Ag: Au). SilverCrest anticipates that the 2,500 tonnes per day open pit heap leach facility at the Santa Elena mine should recover approximately 625,000 ounces of silver and 33,000 ounces of gold in 2013. An expansion plan is well underway to nearly double the annual metals production in 2014 at the Santa Elena Mine (open pit and underground). Exploration programs have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State with stated resources nearing 200 million ounces of Ag equivalent.
Granada Gold Mine - Corporate Presentation - August 2020MomentumPR
Granada Gold Mine Inc. is a Canadian junior mining and exploration company with Gold and Silver properties in Quebec and Ontario. The Company's current focus is directed towards the development and continued exploration of the Granada Property situated in the heart of the famous Abitibi Greenstone Belt and along the prolific "Cadillac Trend". This potential high-tonnage, near-surface deposit is located 15 minutes from Rouyn-Noranda Quebec. The Rouyn-Noranda airport offers easy access into the area and on to paved roads to the mine site. The area offers excellent infrastructure and good supply of skilled labour throughout the region.
IMPACT Silver provides forward-looking statements about its exploration and development plans that are based on assumptions and could change materially due to risks and uncertainties. The company operates two production centers in Mexico and has four producing silver mines. It aims to grow through continued exploration, mine development, and potential expansions to increase production and cash flow.
Starcore International Mines Ltd is a Canadian mining company focused on precious metals production in Mexico through its San Martin Gold Mine in Queretaro, Mexico. It also owns a precious metals processing facility in Matehuala, Mexico called Altiplano, which processes gold and silver concentrates from small miners. Starcore owns the advanced stage Toiyabe Gold Project in Nevada, USA and the El Creston molybdenum deposit in Mexico which presents optionality. The company has a proven management team focused on growth through its production assets and exploration projects.
The document discusses Goldquest Corporation's Romero gold-copper project in the Dominican Republic. Key points include:
- A pre-feasibility study shows the project has a 28% IRR, $203M after-tax NPV, and AISC of $595/oz.
- Proven and probable reserves total 7 million tonnes grading 3.72 g/t gold and 0.88% copper for 980,000 oz gold and 136 million lbs copper.
- Exploration is targeting additional deposits along the 50km long Tireo Formation, which hosts Romero and multiple other targets.
The document discusses the results of a pre-feasibility study for the Romero Gold/Copper mine in the Dominican Republic. Key highlights from the study include an after-tax net present value of $203 million, an internal rate of return of 28%, and average annual production of 109,000 ounces of gold equivalent at all-in sustaining costs of $595 per ounce. The study outlines an underground mining operation with a 7.3 year mine life and total capital costs of $158 million for initial project development. The mineral resource estimate for the Romero deposit indicates total indicated resources of over 2 million ounces of gold equivalent and inferred resources of over 240,000 ounces.
The document discusses Goldquest Corp's Romero gold-copper project in the Dominican Republic. It highlights results from a 2016 pre-feasibility study that showed the project has an after-tax NPV of $203 million and IRR of 28% at $1,300/oz gold price. The study outlined probable mineral reserves of 7 million tonnes grading 3.72 g/t gold and 0.88% copper containing 1.12 million ounces of gold equivalent. The project is planned as an underground mine producing over 100,000 ounces of gold equivalent annually at average all-in sustaining costs of $595/oz over a 7 year mine life. Goldquest also discusses exploration potential from the surrounding 50km
GoldQuest Mining Corp presents information on its Romero discovery project in the Dominican Republic. Key points include:
- A preliminary economic assessment shows an after-tax NPV of $219 million, IRR of 34%, payback of 2.7 years, and AISC of $572/oz for the Romero project.
- The project envisions a 2,500 tpd operation with bulk long-hole and cut-and-fill mining of a high-grade copper-gold deposit.
- Pre-production capital is estimated at $143.1 million. The management team has experience developing mines in the Dominican Republic.
Outback Goldfields is exploring for high-grade gold at its Fosterville property in Victoria, Australia. It has entered into an agreement to acquire gold assets from Petratherm. Completing the acquisition is subject to regulatory approvals. The company has a large land package in a prolific gold district near Kirkland Lake Gold's Fosterville mine. It has an experienced management team and board. Near-term catalysts include an upcoming work program focused on high-grade, low-cost targets.
The Company is focused on the advanced stage Blue Moon Zinc project with significant values for copper, gold and silver. The project is subject to a NI 43-101 report filed on SEDAR and available here. The Company plans to advance Blue Moon to a feasibility study and permitting.
IMPACT Silver provides concise summaries of documents in 3 sentences or less. Here is a 3 sentence summary of the provided document:
The document discusses IMPACT Silver's operations, which include two production centers and four producing silver mines in Mexico. It notes the risks associated with forward-looking statements and outlines IMPACT's management team, properties, exploration targets, and future plans to increase production and expand processing capacity through continued exploration and development. The appendix provides resource estimates for the Capire mine and highlights from drilling at the Capire and Mirasol properties.
This presentation is updated to reflect our Quarter 2 results for Fiscal 2018. Please do not hesitate to contact Evan Eadie in investor relations with your questions.
E-mail: investor@starcore.com
Phone: 1-604-602-4935 x230
Tamino Minerals Inc. is a junior mining exploration company focused on gold projects in Mexico. It owns the El Volcan gold project, which has potential for gold and silver mineralization. The company plans to conduct mapping, sampling, trenching, geophysics and a 2500 meter drill program at El Volcan in 2020. Tamino Minerals' management team has extensive experience operating mining projects and exploration companies in Mexico. The company aims to become a leading gold project developer and miner in Mexico by acquiring and developing early stage properties.
Goldquest Mining Corp is an emerging developer unlocking value at its Romero gold discovery in the Dominican Republic. A 2015 preliminary economic assessment showed the Romero Project has a $219 million after-tax NPV at a 6% discount rate and 34% IRR, with a 2.7 year payback period and $572 per ounce all-in sustaining costs. The PEA outlined a 2,500 tonne per day underground mine with average resource grades of 4 grams per tonne gold, 0.8% copper, and 4.3 grams per tonne silver over a 7.7 million tonne mine plan targeting the high grade core of the 19.4 million tonne indicated resource. Goldquest
- The corporate presentation discusses Great Panther Silver's plans for production at its Guanajuato and Topia mines in Mexico, as well as exploring other properties. It provides financial results for Q2 2016 and the outlook for 2016. Production is expected to be between 4-4.2 million silver equivalent ounces at a cash cost per ounce of $3.8-3.9. The presentation highlights Great Panther's low costs of production and strong financial position as it works to increase production organically and through potential acquisitions.
The document provides an overview of GoldQuest Mining Inc. and its projects in the Dominican Republic. It summarizes the Romero project's mineral resource estimate of 2.4 million ounces of gold equivalent in the indicated category and 0.8 million ounces in the inferred category. A preliminary economic assessment for Romero completed in May 2014 outlined a 15-year mine life with average annual gold production of 90,000 ounces at an all-in sustaining cost of $353 per ounce and estimated post-tax NPV of $294 million. GoldQuest plans further exploration in 2014 to expand resources and advance Romero towards production while also exploring other prospects in its land package.
- The document discusses GoldQuest Mining Inc.'s Romero Project in the Dominican Republic. It provides details on the project's mineral resources, including an indicated resource of 2.4 million ounces of gold equivalent and inferred resource of 0.8 million ounces.
- A preliminary economic assessment completed in May 2014 found the Romero Project could produce 90,000 ounces of gold per year at an all-in sustaining cost of $353 per ounce, with an after-tax NPV of $294 million and 15.1% IRR over a 15-year mine life.
- GoldQuest aims to fast-track the Romero Project towards production while also conducting exploration at its other Tireo properties in
F.D.G. Mining Inc. owns gold mining concessions in Nicaragua that show potential for development. The company's key asset is the Topacio Gold Project, which has an inferred resource of 340,345 ounces of gold based on a 2012 estimate. F.D.G. plans to have JDS Energy and Mining Inc. complete an evaluation of Topacio to develop an execution plan. Additionally, F.D.G. holds the San Pedro and El Santo concessions near producing mines owned by B2Gold, suggesting further exploration potential. The company aims to advance its Nicaraguan assets and generate shareholder value from gold production.
SilverCrest Mines | Corporate Presentation | July 2014Silvercrestmines
SilverCrest Mines Inc. (NYSE MKT: SVLC; TSX: SVL) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest´s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal silver and gold producer, with an estimated life of mine of 8 years and average operating cash costs of $11 per ounce of silver equivalent (55:1 Ag:Au). SilverCrest anticipates that the new 3,000 tonnes per day conventional mill facility at the Santa Elena Mine should recover an average annual rate of 1.5 million ounces of silver and 32,800 ounces of gold over the current reserve. Major expansion and commissioning of the 3,000 tonnes per day conventional mill facility is nearing completion and is expected to significantly increase metals production at the Santa Elena Mine in 2014 and beyond. Exploration programs continue to make new discoveries at Santa Elena and also have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State, Mexico.
The document provides an overview of the Castelo de Sonhos gold project in Brazil being developed by TriStar Gold Inc. Key highlights from a preliminary feasibility study include projected gold production of 1.3 million ounces over 11 years at an average rate of 121,000 ounces per year. The study estimates an after-tax NPV of $321 million using a gold price of $1,550 per ounce and an internal rate of return of 28%. Initial capital costs are estimated at $261 million and operating costs are estimated at $900 per ounce on an all-in sustaining basis. Mining will use conventional open pit methods to extract ore from three deposits - Esperança South, East and Center - over two phases.
IMPACT Silver provides forward-looking statements about its operations that are based on assumptions and could change materially due to risks and uncertainties. The company operates two production centers in Mexico - Guadalupe processing ore from three mines, and a pilot plant at Capire processing from its mine. IMPACT explores across its land holdings for new deposits to develop organically and increase production over time through prudent management and continuous exploration.
SilverCrest Mines | Corporate Presentation | January 2014Silvercrestmines
SilverCrest Mines Inc. (TSX‐V: SVL; NYSE MKT: SVLC) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest’s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal gold and silver producer, with an estimated life of mine cash cost of US$8 per ounce of silver equivalent (55:1 Ag: Au). SilverCrest anticipates that the 2,500 tonnes per day open pit heap leach facility at the Santa Elena mine should recover approximately 625,000 ounces of silver and 33,000 ounces of gold in 2013. An expansion plan is well underway to nearly double the annual metals production in 2014 at the Santa Elena Mine (open pit and underground). Exploration programs have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State with stated resources nearing 200 million ounces of Ag equivalent.
Granada Gold Mine - Corporate Presentation - August 2020MomentumPR
Granada Gold Mine Inc. is a Canadian junior mining and exploration company with Gold and Silver properties in Quebec and Ontario. The Company's current focus is directed towards the development and continued exploration of the Granada Property situated in the heart of the famous Abitibi Greenstone Belt and along the prolific "Cadillac Trend". This potential high-tonnage, near-surface deposit is located 15 minutes from Rouyn-Noranda Quebec. The Rouyn-Noranda airport offers easy access into the area and on to paved roads to the mine site. The area offers excellent infrastructure and good supply of skilled labour throughout the region.
IMPACT Silver provides forward-looking statements about its exploration and development plans that are based on assumptions and could change materially due to risks and uncertainties. The company operates two production centers in Mexico and has four producing silver mines. It aims to grow through continued exploration, mine development, and potential expansions to increase production and cash flow.
Starcore International Mines Ltd is a Canadian mining company focused on precious metals production in Mexico through its San Martin Gold Mine in Queretaro, Mexico. It also owns a precious metals processing facility in Matehuala, Mexico called Altiplano, which processes gold and silver concentrates from small miners. Starcore owns the advanced stage Toiyabe Gold Project in Nevada, USA and the El Creston molybdenum deposit in Mexico which presents optionality. The company has a proven management team focused on growth through its production assets and exploration projects.
The document discusses Goldquest Corporation's Romero gold-copper project in the Dominican Republic. Key points include:
- A pre-feasibility study shows the project has a 28% IRR, $203M after-tax NPV, and AISC of $595/oz.
- Proven and probable reserves total 7 million tonnes grading 3.72 g/t gold and 0.88% copper for 980,000 oz gold and 136 million lbs copper.
- Exploration is targeting additional deposits along the 50km long Tireo Formation, which hosts Romero and multiple other targets.
The document discusses the results of a pre-feasibility study for the Romero Gold/Copper mine in the Dominican Republic. Key highlights from the study include an after-tax net present value of $203 million, an internal rate of return of 28%, and average annual production of 109,000 ounces of gold equivalent at all-in sustaining costs of $595 per ounce. The study outlines an underground mining operation with a 7.3 year mine life and total capital costs of $158 million for initial project development. The mineral resource estimate for the Romero deposit indicates total indicated resources of over 2 million ounces of gold equivalent and inferred resources of over 240,000 ounces.
The document discusses Goldquest Corp's Romero gold-copper project in the Dominican Republic. It highlights results from a 2016 pre-feasibility study that showed the project has an after-tax NPV of $203 million and IRR of 28% at $1,300/oz gold price. The study outlined probable mineral reserves of 7 million tonnes grading 3.72 g/t gold and 0.88% copper containing 1.12 million ounces of gold equivalent. The project is planned as an underground mine producing over 100,000 ounces of gold equivalent annually at average all-in sustaining costs of $595/oz over a 7 year mine life. Goldquest also discusses exploration potential from the surrounding 50km
GoldQuest Mining Corp presents information on its Romero discovery project in the Dominican Republic. Key points include:
- A preliminary economic assessment shows an after-tax NPV of $219 million, IRR of 34%, payback of 2.7 years, and AISC of $572/oz for the Romero project.
- The project envisions a 2,500 tpd operation with bulk long-hole and cut-and-fill mining of a high-grade copper-gold deposit.
- Pre-production capital is estimated at $143.1 million. The management team has experience developing mines in the Dominican Republic.
- GoldQuest is an emerging developer that has discovered a compelling copper and gold deposit in the Dominican Republic called the Romero Project.
- A preliminary economic assessment shows the Romero Project has strong economics including a $219 million after-tax NPV at a 34% IRR and a short 2.7 year payback.
- The project is expected to produce over 150,000 ounces of gold equivalent per year at low costs of $572 per ounce on average over its mine life.
SilverCrest Mines | Corporate Presentation | March 2014Silvercrestmines
SilverCrest Mines Inc. (TSX: SVL; NYSE MKT: SVLC) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest’s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal silver and gold producer, with an estimated life of mine of 8 years and cash costs of $11 per ounce of silver equivalent (55:1 Ag:Au) for the open pit heap leach and underground mine. SilverCrest anticipates that the new 3,000 tonnes per day conventional mill facility at the Santa Elena Mine should recover an average annual rate of 1.5 million ounces of silver and 32,800 ounces of gold over the current reserve. Major expansion and construction of the 3,000 tonnes per day conventional mill facility is nearing completion and is expected to significantly increase metals production at the Santa Elena Mine (open pit and underground) in 2014 and beyond. Exploration programs continue to make new discoveries at Santa Elena and also have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State with stated resources nearing 200 million ounces of Ag equivalent.
SilverCrest Mines | Corporate Presentation | April 2014Silvercrestmines
SilverCrest Mines Inc. (TSX: SVL; NYSE MKT: SVLC) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest’s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal silver and gold producer, with an estimated life of mine of 8 years and cash costs of $11 per ounce of silver equivalent (55:1 Ag:Au) for the open pit heap leach and underground mine. SilverCrest anticipates that the new 3,000 tonnes per day conventional mill facility at the Santa Elena Mine should recover an average annual rate of 1.5 million ounces of silver and 32,800 ounces of gold over the current reserve. Major expansion and construction of the 3,000 tonnes per day conventional mill facility is nearing completion and is expected to significantly increase metals production at the Santa Elena Mine (open pit and underground) in 2014 and beyond. Exploration programs continue to make new discoveries at Santa Elena and also have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State with stated resources nearing 200 million ounces of Ag equivalent.
SilverCrest Mines | Corporate Presentation | July 2014Silvercrestmines
SilverCrest Mines Inc. (NYSE MKT: SVLC; TSX: SVL) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest´s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal silver and gold producer, with an estimated life of mine of 8 years and average operating cash costs of $11 per ounce of silver equivalent (55:1 Ag:Au). SilverCrest anticipates that the new 3,000 tonnes per day conventional mill facility at the Santa Elena Mine should recover an average annual rate of 1.5 million ounces of silver and 32,800 ounces of gold over the current reserve. Major expansion and commissioning of the 3,000 tonnes per day conventional mill facility is nearing completion and is expected to significantly increase metals production at the Santa Elena Mine in 2014 and beyond. Exploration programs continue to make new discoveries at Santa Elena and also have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State, Mexico.
SilverCrest Mines | Corporate Presentation | September 2014Silvercrestmines
SilverCrest Mines Inc. (NYSE MKT: SVLC; TSX: SVL) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest’s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal silver and gold producer, with an estimated life of mine of 8 years and average operating cash costs of $11 per ounce of silver equivalent (55:1 Ag:Au). SilverCrest anticipates that the new 3,000 tonnes per day conventional mill facility at the Santa Elena Mine should recover an average annual rate of 1.5 million ounces of silver and 32,800 ounces of gold over the current reserve. Major expansion and commissioning of the 3,000 tonnes per day conventional mill facility has been completed and is expected to significantly increase metals production at the Santa Elena Mine in 2014 and beyond. Exploration programs continue to make new discoveries at Santa Elena and also have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State, Mexico.
SilverCrest Mines | Corporate Presentation | December 2013Silvercrestmines
SilverCrest Mines Inc. (TSX‐V: SVL; NYSE MKT: SVLC) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest’s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal gold and silver producer, with an estimated life of mine cash cost of US$8 per ounce of silver equivalent (55:1 Ag: Au). SilverCrest anticipates that the 2,500 tonnes per day open pit heap leach facility at the Santa Elena mine should recover approximately 725,000 ounces of silver and 30,000 ounces of gold in 2013. An expansion plan is well underway to significantly increase the annual metals production in 2014 at the Santa Elena Mine (open pit and underground). Exploration programs have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State with stated resources nearing 200 million ounces of Ag equivalent.
SilverCrest Mines | Corporate Presentation | November 2013 Silvercrestmines
SilverCrest Mines Inc. (TSX‐V: SVL; NYSE MKT: SVLC) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest’s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal gold and silver producer, with an estimated life of mine cash cost of US$8 per ounce of silver equivalent (55:1 Ag: Au). SilverCrest anticipates that the 2,500 tonnes per day open pit heap leach facility at the Santa Elena mine should recover approximately 625,000 ounces of silver and 33,000 ounces of gold in 2013. An expansion plan is well underway to nearly double the annual metals production in 2014 at the Santa Elena Mine (open pit and underground). Exploration programs have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State with stated resources nearing 200 million ounces of Ag equivalent.
SilverCrest Mines | Corporate Presentation | October 2014Silvercrestmines
SilverCrest Mines Inc. (NYSE MKT: SVLC; TSX: SVL) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest’s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal silver and gold producer, with an estimated life of mine of 8 years and average operating cash costs of $11 per ounce of silver equivalent (55:1 Ag:Au). SilverCrest anticipates that the new 3,000 tonnes per day conventional mill facility at the Santa Elena Mine should recover an average annual rate of 1.5 million ounces of silver and 32,800 ounces of gold over the current reserve. Major expansion and commissioning of the 3,000 tonnes per day conventional mill facility has been completed and is expected to significantly increase metals production at the Santa Elena Mine in 2014 and beyond. Exploration programs continue to make new discoveries at Santa Elena and also have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State, Mexico.
SilverCrest Mines | Corporate Presentation | May 2014Silvercrestmines
SilverCrest Mines Inc. (TSX: SVL; NYSE MKT: SVLC) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest’s flagship property is the 100%‐owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high‐grade, epithermal silver and gold producer, with an estimated life of mine of 8 years and cash costs of $11 per ounce of silver equivalent (55:1 Ag:Au) for the open pit heap leach and underground mine. SilverCrest anticipates that the new 3,000 tonnes per day conventional mill facility at the Santa Elena Mine should recover an average annual rate of 1.5 million ounces of silver and 32,800 ounces of gold over the current reserve. Major expansion and construction of the 3,000 tonnes per day conventional mill facility is nearing completion and is expected to significantly increase metals production at the Santa Elena Mine (open pit and underground) in 2014 and beyond. Exploration programs continue to make new discoveries at Santa Elena and also have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State with stated resources nearing 200 million ounces of Ag equivalent.
SilverCrest Mines | Corporate Presentation | October 2013Silvercrestmines
- The corporate presentation outlines SilverCrest's plan to expand production at its Santa Elena mine in Mexico. Production is expected to increase from 2.49 million silver equivalent ounces in 2013 to 3.5 million ounces in 2014 through developing an underground mine and increasing mill throughput.
- A pre-feasibility study showed strong economics for the expansion, with an IRR of 88% and 5-year NPV of $223 million at base case metal prices. The expansion capital costs are estimated at $82 million over 2013-2014.
- The underground mine will be developed using long-hole stoping, with production coming from the open pit, underground mine and leach pads starting in 2014. Production is expected to
This corporate presentation provides an overview of the company's operations in Mexico and Peru. It highlights production increases at its Guanajuato Mine Complex in Mexico through higher grades and operational efficiencies, which have significantly lowered costs per ounce. The company has maintained a strong balance sheet with no debt and cash of C$17 million. It is focused on further growing production at its existing mines through continued exploration and development of new projects in its portfolio.
- The presentation provides an overview of Great Panther Silver, a primary silver producer with two mining operations in Mexico. It discusses the company's growth strategy, recent financial performance, and low cost profile compared to peers. Great Panther is focusing on organic growth from its Guanajuato Mine Complex in Mexico, one of the country's most historic silver districts, with potential to develop satellite mines in the region.
This corporate presentation discusses the company's two producing silver mines in Mexico, the Guanajuato Mine and the San Ignacio Mine. It provides production results for Q2 2016, noting increasing production and declining costs. The presentation also profiles the experienced management team and discusses the company's focus on growth through production increases and acquisitions while maintaining a strong balance sheet with no debt.
This corporate presentation summarizes Great Panther Silver's operations and outlook:
- They operate two silver-gold mines in Mexico and expect to produce between 4-4.2 million silver equivalent ounces in 2016 at a cash cost of $5-7 per ounce and all-in sustaining costs of $13-15 per ounce.
- Their largest mine is the Guanajuato Mine Complex in Mexico, which accounted for 75% of production in Q2 2016. Production is growing through expansions and resource increases.
- They maintain a strong balance sheet with $17 million in cash and no debt to support growth from organic expansion and potential acquisitions.
This corporate presentation summarizes Great Panther Silver's operations and outlook:
- They operate two silver-gold mines in Mexico and expect to produce between 4-4.2 million silver equivalent ounces in 2016 at a cash cost of $5-7 per ounce and all-in sustaining costs of $13-15 per ounce.
- Their Guanajuato Mine Complex in Mexico, which produces around 75% of their metal, had cash costs of $0.61 per ounce and all-in sustaining costs of $2.72 per ounce in Q2 2016.
- Their Topia Mine in Mexico, which produces around 25% of their metal, had higher cash costs of $12.32
Similar to Gold Quest Corporate Presentation - September 2017 (20)
Goldquest Corp is a mining exploration company exploring for gold and copper in the Dominican Republic. They discovered a multi-million ounce gold deposit called Romero in 2012. A pre-feasibility study is due in Q3 2016 and permitting is in progress. Goldquest is also exploring a 50km long belt surrounding Romero that shows potential for additional discoveries. They have $9 million in cash to fund both development and exploration programs.
- The document discusses GoldQuest Mining Corp.'s Romero Project and Tireo Project in the Dominican Republic.
- For the Romero Project, it summarizes the May 2014 Preliminary Economic Assessment that outlined a 15-year mine life producing 90,000 ounces of gold per year at an AISC of $353/oz and an unoptimized post-tax NPV of $294 million.
- For the Tireo Project, it outlines GoldQuest's 2014-2015 exploration program including ZTEM and magnetic surveys, mapping, sampling, IP surveys, and over 4,200 meters of drilling to define new targets near their discovery at Romero.
This document provides a summary and forward-looking statements for a mining company. It discusses:
1) The company has mineral properties in the Dominican Republic and plans to continue exploration programs and studies to estimate their mineral resources.
2) Forward-looking statements are subject to risks and uncertainties that could cause actual results to differ from expectations.
3) The company's Qualified Person supervised preparation of the exploration technical data in the presentation.
GoldQuest Corporate Presentation - Cambridge House September 25, 2014GoldQuest Mining Corp.
- The document discusses GoldQuest Mining Inc., a mining company focused on its Romero gold project and Tireo exploration project in the Dominican Republic.
- It provides an overview of GoldQuest's projects, including a preliminary economic assessment for the Romero project indicating a 15-year mine life and low all-in sustaining costs of $353 per ounce.
- The document also summarizes GoldQuest's 2014 exploration program at Tireo, which includes airborne surveys, mapping, sampling, IP surveys, and a 10,000 meter drill program aimed at generating new targets using geophysical data.
- GoldQuest is a mining exploration company focused on its Romero and Tireo projects in the Dominican Republic.
- At Romero, a preliminary economic assessment outlined a 15-year mine life producing 90,000 ounces of gold per year at an all-in sustaining cost of $353/ounce.
- Exploration at the larger Tireo project is ongoing, with an initial 10,000 meter drill program targeting areas with similarities to the Romero deposit.
- GoldQuest has $8.2 million in cash and is trading at a valuation of only $7/ounce for its indicated resources, representing potential for significant share price growth as exploration succeeds.
The document discusses GoldQuest Mining's Romero Project in the Dominican Republic. It provides details on the project's mineral resource estimates, including an indicated resource of 2.4 million ounces of gold equivalent and an inferred resource of 0.8 million ounces. It also summarizes the results of a preliminary economic assessment completed in May 2014 that found the Romero Project could produce 90,000 ounces of gold per year at an all-in sustaining cost of $353 per ounce with an after-tax IRR of 15.1%. The document outlines GoldQuest's exploration strategy for its Tireo Project to identify additional gold deposits using geological, geophysical and geochemical methods informed by its understanding of the Romero deposit.
1) The document discusses the Romero Project, owned by GoldQuest Mining Inc.
2) GoldQuest discovered Romero in May 2012 and has since delineated a National Instrument 43-101 compliant mineral resource at Romero.
3) The indicated resource at Romero is 19.42 million tonnes at 2.63 g/t gold equivalent for 2.38 million ounces of gold equivalent. The inferred resource is 10.02 million tonnes at 2.45 g/t gold equivalent for 0.79 million ounces of gold equivalent.
The document discusses GoldQuest Mining Inc., a mining exploration and development company operating in the Dominican Republic. It highlights GoldQuest's experienced management team which has a track record of successful mining development in the Dominican Republic. It also summarizes GoldQuest's key projects - the Romero Project, which has NI 43-101 indicated and inferred gold equivalent resource estimates, and the Tireo Project, where a new ZTEM airborne survey is underway to identify additional exploration targets. GoldQuest is well positioned for further discovery and development with an experienced team and $11 million in treasury funds as of December 2013.
This presentation by Thibault Schrepel, Associate Professor of Law at Vrije Universiteit Amsterdam University, was made during the discussion “Artificial Intelligence, Data and Competition” held at the 143rd meeting of the OECD Competition Committee on 12 June 2024. More papers and presentations on the topic can be found at oe.cd/aicomp.
This presentation was uploaded with the author’s consent.
Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...Suzanne Lagerweij
This is a workshop about communication and collaboration. We will experience how we can analyze the reasons for resistance to change (exercise 1) and practice how to improve our conversation style and be more in control and effective in the way we communicate (exercise 2).
This session will use Dave Gray’s Empathy Mapping, Argyris’ Ladder of Inference and The Four Rs from Agile Conversations (Squirrel and Fredrick).
Abstract:
Let’s talk about powerful conversations! We all know how to lead a constructive conversation, right? Then why is it so difficult to have those conversations with people at work, especially those in powerful positions that show resistance to change?
Learning to control and direct conversations takes understanding and practice.
We can combine our innate empathy with our analytical skills to gain a deeper understanding of complex situations at work. Join this session to learn how to prepare for difficult conversations and how to improve our agile conversations in order to be more influential without power. We will use Dave Gray’s Empathy Mapping, Argyris’ Ladder of Inference and The Four Rs from Agile Conversations (Squirrel and Fredrick).
In the session you will experience how preparing and reflecting on your conversation can help you be more influential at work. You will learn how to communicate more effectively with the people needed to achieve positive change. You will leave with a self-revised version of a difficult conversation and a practical model to use when you get back to work.
Come learn more on how to become a real influencer!
This presentation by OECD, OECD Secretariat, was made during the discussion “Competition and Regulation in Professions and Occupations” held at the 77th meeting of the OECD Working Party No. 2 on Competition and Regulation on 10 June 2024. More papers and presentations on the topic can be found at oe.cd/crps.
This presentation was uploaded with the author’s consent.
This presentation by Juraj Čorba, Chair of OECD Working Party on Artificial Intelligence Governance (AIGO), was made during the discussion “Artificial Intelligence, Data and Competition” held at the 143rd meeting of the OECD Competition Committee on 12 June 2024. More papers and presentations on the topic can be found at oe.cd/aicomp.
This presentation was uploaded with the author’s consent.
Carrer goals.pptx and their importance in real lifeartemacademy2
Career goals serve as a roadmap for individuals, guiding them toward achieving long-term professional aspirations and personal fulfillment. Establishing clear career goals enables professionals to focus their efforts on developing specific skills, gaining relevant experience, and making strategic decisions that align with their desired career trajectory. By setting both short-term and long-term objectives, individuals can systematically track their progress, make necessary adjustments, and stay motivated. Short-term goals often include acquiring new qualifications, mastering particular competencies, or securing a specific role, while long-term goals might encompass reaching executive positions, becoming industry experts, or launching entrepreneurial ventures.
Moreover, having well-defined career goals fosters a sense of purpose and direction, enhancing job satisfaction and overall productivity. It encourages continuous learning and adaptation, as professionals remain attuned to industry trends and evolving job market demands. Career goals also facilitate better time management and resource allocation, as individuals prioritize tasks and opportunities that advance their professional growth. In addition, articulating career goals can aid in networking and mentorship, as it allows individuals to communicate their aspirations clearly to potential mentors, colleagues, and employers, thereby opening doors to valuable guidance and support. Ultimately, career goals are integral to personal and professional development, driving individuals toward sustained success and fulfillment in their chosen fields.
XP 2024 presentation: A New Look to Leadershipsamililja
Presentation slides from XP2024 conference, Bolzano IT. The slides describe a new view to leadership and combines it with anthro-complexity (aka cynefin).
This presentation by Nathaniel Lane, Associate Professor in Economics at Oxford University, was made during the discussion “Pro-competitive Industrial Policy” held at the 143rd meeting of the OECD Competition Committee on 12 June 2024. More papers and presentations on the topic can be found at oe.cd/pcip.
This presentation was uploaded with the author’s consent.
This presentation by Yong Lim, Professor of Economic Law at Seoul National University School of Law, was made during the discussion “Artificial Intelligence, Data and Competition” held at the 143rd meeting of the OECD Competition Committee on 12 June 2024. More papers and presentations on the topic can be found at oe.cd/aicomp.
This presentation was uploaded with the author’s consent.
This presentation by Professor Alex Robson, Deputy Chair of Australia’s Productivity Commission, was made during the discussion “Competition and Regulation in Professions and Occupations” held at the 77th meeting of the OECD Working Party No. 2 on Competition and Regulation on 10 June 2024. More papers and presentations on the topic can be found at oe.cd/crps.
This presentation was uploaded with the author’s consent.
This presentation by OECD, OECD Secretariat, was made during the discussion “Pro-competitive Industrial Policy” held at the 143rd meeting of the OECD Competition Committee on 12 June 2024. More papers and presentations on the topic can be found at oe.cd/pcip.
This presentation was uploaded with the author’s consent.
Mastering the Concepts Tested in the Databricks Certified Data Engineer Assoc...SkillCertProExams
• For a full set of 760+ questions. Go to
https://skillcertpro.com/product/databricks-certified-data-engineer-associate-exam-questions/
• SkillCertPro offers detailed explanations to each question which helps to understand the concepts better.
• It is recommended to score above 85% in SkillCertPro exams before attempting a real exam.
• SkillCertPro updates exam questions every 2 weeks.
• You will get life time access and life time free updates
• SkillCertPro assures 100% pass guarantee in first attempt.
2. Statements contained in this presentation that are not historical facts are forward-looking information that involves known and unknown risks and uncertainties. Forward-
looking statements in this presentation include, but are not limited to, statements with respect to the pre-feasibility study for the Romero Project (the “PFS”), the results of the
PFS, including the mine plan, the production schedule, infrastructure, capital and operating costs and financial analysis, opportunities to enhance the project economics, the
advancement of Romero, the potential of the remaining resources and surrounding area, opportunities for growth beyond the mine plan, plans for Romero South, interpretation
of the results of the PFS, the merits of the Company's mineral properties, mineral reserve and resource estimates, the Dominican Republic and the Company's plans,
exploration programs and studies for its mineral properties, including the timing of such plans, programs and studies. In certain cases, forward-looking statements can be
identified by the use of words such as "plans", “proposed”, "has proven", "expects" or "does not expect", "is expected", “upside”, "potential", "appears", "budget", "scheduled",
"estimates", "forecasts", “goal”, "at least", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions,
events or results "may", "could", "would", "should", "might" or "will be taken", "occur" or "be achieved".
Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the
Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such risks and other factors
include, among others, the assumptions and risks associated with the results of the PFS; commodity prices; changes in general economic conditions; market sentiment;
currency exchange rates; the Company's ability to continue as a going concern; the Company's ability to raise funds through equity financings; risks inherent in mineral
exploration; risks related to operations in foreign countries; future prices of metals; failure of equipment or processes to operate as anticipated; accidents, labor disputes and
other risks of the mining industry; delays in obtaining governmental approvals; government regulation of mining operations; environmental risks; title disputes or claims;
limitations on insurance coverage and the timing and possible outcome of litigation. Although the Company has attempted to identify important factors that could affect the
Company and may cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause
actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual
results and future events could differ materially from those anticipated in such statements. Accordingly, do not place undue reliance on forward-looking statements. All
statements are made as of the date of this presentation and the Company is under no obligation to update or alter any forward-looking statements.
Forward-looking statements are based on assumptions that the Company believes to be reasonable, including expectations regarding mineral exploration and development
costs; expected trends in mineral prices and currency exchange rates; the accuracy of the Company's current mineral resource estimates; that the Company's activities will be
in accordance with the Company's public statements and stated goals; that there will be no material adverse change affecting the Company or its properties; that all required
approvals will be obtained and that there will be no significant disruptions affecting the Company or its properties.
Certain technical information in this presentation was taken from the press released dated September 27, 2016 announcing the results of the Romero Project PFS.
The technical information in this presentation related to the PFS is based on information prepared by Mr. Makarenko, P.Eng. and Ms. McLeod, P.Eng. of JDS Energy & Mining
Inc. (“JDS”), who are each a Qualified Person and independent of the Company as defined by NI 43-101.
Jeremy K. Niemi, P.Geo., VP Exploration of the Company, is the Qualified Person who supervised the preparation of the technical information related to exploration in this
presentation.
Please refer to the Company's most recent Management's Discussion & Analysis (available at www.sedar.com) for further information regarding the Company and its mineral
properties.
All values are in U.S. Dollars unless otherwise stated.
www.goldquestcorp.com | 2
3. A Growth Company
Exploring
The 50-km long Tireo Formation surrounding Romero
2/3 complete our 10,000 m exploration drill program
New discovery at 3 of 20 target
Cachimbo: Gold-Rich Polymetallic Discovery
14 g/t gold, 74 g/t silver, 12% zinc, 1 % copper over 5 m
Well Financed & Careful with Funds
Major shareholder: AGNICO EAGLE
+C25 M cash in hand
Careful with funds
Accelerating Newsflow
Feasibility studies, permitting and already delivering exciting
exploration results
The Romero Gold/Copper mine, Dominican Republic
GQC discovered the multi-million ounce gold deposit in 2012
Pre-feasibility study (PFS) published Nov. 11th, 2016 @ 28% IRR
and $595/oz All in Sustaining Costs (AISC)
Permitting in progress
Developing
4. The Dominican Republic
www.goldquestcorp.com | 4
Canada
USA
Romero Project
Santo Domingo
San Juan
Puerto Plata
Falcondo
Mine
Pueblo Viejo Mine
Cerro de Maimon Mine
Tireo
Concessions
Strong relationship with the
government and community
No Government Royalties
Reasonable Taxes (32%)
One of the fastest growing
economies in the Americas
(World Bank)
Dominican
Republic
source www.barrack.com
source www.perilya.com/au
5. Experienced Corporate Management Team
www.goldquestcorp.com | 5
Bill Fisher, P.Geo
• Former CEO Globestar
• Chairman Aurelian
• VP Exploration of Boliden
Executive Chairman, CEO
Paul Robertson, CA,CPA
CFO
• Former CFO Grayd
Resources (acquired by
Agnico Eagle)
Dave Massola
VP Corp. Development
• Former construction
manager for GlobeStar’s
Cerro de Maimon
C$0.90
Felix Mercedes, MBA
Country Manager
• Director of Mining &
Petroleum Chamber in the
DR
Jeremy Niemi, P.Geo
VP Exploration
• Former VP Exploration
Noront; Former Kinross
JP LeBlanc
Engineering Manager
• Former construction
manager for GlobeStar’s
Cerro de Maimon
Highly Qualified Team
with proven experience in
the Dominican Republic
6. www.goldquestcorp.com | 6
Technical & Financial Expertise
Bill Fisher, P.Geo
• Former CEO Globestar
• Chairman Aurelian
• VP Exploration of Boliden
Executive Chairman, CEO
Florian Siegfried, MBA
Director
• Finance executive and fund
manager >15 years mining
experience
Frank Balint
Director
• Mining executive >35
years including INMET
• Retired as full-time CEO Q3 ‘17
• Former Country Manager
Globestar
Patrick Michaels
Director
• Finance executive with
extensive experience in mining
finance
Julio Espaillat, M.Eng
Director
Diverse
A combination of expertise with member from the Canada,
Dominican Republic, and Switzerland
7. Prefeasibility Study Highlights
www.goldquestcorp.com | 7
* Net Present Value (“NPV”), Internal Rate of Return (“IRR”), All-In
Sustaining Costs (“AISC”)
** Gold Equivalent (“AuEq.”) ounces are calculated as follows: Au oz.
payable + ((Cu lbs. payable * $2.50/lb.) + (Ag oz. payable *
$20/oz.))/$1,300 oz.)
$203M
NPV*5% IRR*
28%
AFTER TAX
PAYBACK
2.5YRS
AISC*
$595/OZ.
AuEq.**
LTP-94
158.6m to 160.0m
288.6 g/t Gold 5.6%
Copper
Currently in the permitting phase
Preliminary Feasibility Study (PFS) published
November 11th, 2016
8. Return Wasterock Underground
Wasterock will be returned underground as backfill
A gold/copper concentrate product will be shipped to international
smelters
No use of Cyanide or other Contaminates
No use of Water from the San Juan River
Run-off water recirculated to supply mine’s needs
Small surface footprint over underground mine, thus minimal
affect on landscape
Minimal Surface Impact
Compact & Inert Dry Stack Tailings
No use of tailing ponds or dam structures
Will be filtered, dried & placed in a dry stack storage facility
designed with to be seismic & hurricane resistant
And more…
Ventilation fans will be located underground to reduce noise
No relocation of local Hondo Valle Village, or any settlements
For more detail see GQC’s PFS (November, 2016)
PFS: Responsible Mine Design
9. 0%
5%
10%
15%
20%
25%
30%
35%
$0
$50
$100
$150
$200
$250
$300
$350
$1,000 $1,100 $1,200 $1,300 $1,400 $1,500
AfterTaxIRR
AfterTaxNPV5%(US$M)
Gold Price (US$/oz)
After Tax NPV5%
After Tax IRR
2016 PFS Highlights
www.goldquestcorp.com | 9
PFS Summary Results
At US$1300 Au / US$2.50.lb Cu
Start-Up CAPEX $158M
Sustaining CAPEX $92M
Throughput 2800 tpd
Mining Method
Underground LHOS &
Cut and Fill
Life of Mine 7.3 Years
Head Grade AuEq 5 g/t AuEq
Annual Production 109Koz AuEq
Recoveries
Gold - 78%
Copper - 95%
All in Sustaining
Cash Costs
US$595/oz
After Tax NPV* $203M
After Tax IRR * 28%
Robust at Significantly Lower Metal Prices
and Excellent Leverage to Higher Prices
Low Capex, High IRR, Scalable Deposit
* Pre-feasibility Study (“PFS”), Net Present Value (“NPV”), Internal Rate of Return (“IRR”), All-In Sustaining Costs (“AISC”)
** Gold Equivalent (“AuEq.”) ounces are calculated as follows: Au oz. payable + ((Cu lbs. payable * $2.50/lb.) + (Ag oz. payable * $20/oz.))/$1,300 oz.)
After-Tax NPV & IRR Sensitivity to Gold Price
10. Surface Infrastructure
Underground Mine = Minimal Surface
Disturbance
Mine Portal: No shaft required
Single Copper Concentrate Facility
~90,000 tonne per year of Copper
concentrate shipped to international smelters
Minimal Environmental Impact
Benign dry stack tailings system
Low water-use process
Romero Reserve
Mine
Portal
Processing
Plant
Dry stack Tailings
500 m
Romero South
Resource
www.goldquestcorp.com | 10
11. Gold-Copper Starter Mine
www.goldquestcorp.com | 11
Surface Portal
Access Ramp
Ventilation
Production
Ramp
Remaining
Mineral Resources
2800 tpd – 75% Longhole
Large Stopes (up to 20m x 20m x
50m)
Options to expand mine as metal
prices rise
View Looking North
only considers 35% of current M&I Resource
16. www.goldquestcorp.com | 16
Romero South: 10.75 g/t - 28.5 m
10 km
* Gold Equivalent (“AuEq.”) ounces are
calculated as follows:
Au oz. payable +( ((Cu lbs. payable *
$2.50/lb.) + (Ag oz. payable * $20/oz) +
(Zn oz payable * $1.2/lb)) .)/$1,300 oz )
Cachimbo: 9.1 g/t - 15.2 m
Jengibre: 1.5 g/t – 40 m
Ginger Ridge (PRG) 4.5 g/t – 18 m
Tireo Land Package Perimeter
Hydrothermal Alteration
Grab Samples Gold (g/t)
2.0 – 167.5 (201)
BDL – 2.0 (3272)
Romero: 10.4 g/t - 234.8m
Las Tomates: 4.7 g/t - 6.8 m
Imperial: 8.5 g/t - 2.4 m
Drilling Highlights in AuEq*
Mineros Ridge: 0.8 g/t - 15.3 m
Vaca Valley: 0.4 g/t - 56.8 m
Ongoing Ex;loration Program
Previously Reported Drilling
2017 Reported Drilling
2017 Cachimbo Discovery
17. Exploring the Tireo Belt Romero Deposit
Romero South Deposit
IP Chargeability (mV/V)
Romero
Project
Exploration
Program
Ongoing Exploration Program
Recently completed ~ 100 line km of gradient
induced polarization (IP) geophysics, identifying 6
new targets (see figure) SE of Cachimbo
Targets occur along the mineralization trend hosting
the Cachimbo Discovery, and the Romero Deposits
Refining drill targets by
Deep IP sections
Detailed mapping
Large scale soil sampling
Continuing to explore extent of Cachimbo
10 km
Cachimbo Discovery
www.goldquestcorp.com | 17
64 5
2
3
1
18. Delineating our 2017 Gold-Rich Polymetallic Discovery
www.goldquestcorp.com | 18
*http://goldquestcorp.com/index.php/news/2016-news/336-
Gold – VMS Setting: 2 Zones
TIR-
16-09
Length
(m)
Au
(g/t)
Ag
(g/t)
Cu
(%)
Zn
(%)
Zone
1
4.6 4.5 72.6 0.5 3.5
Zone
2
15.2 5.3 30.6 0.4 4.2
Inc. 4.9 13.8 73.7 1.1 11.8
Highlights of the Cachimbo Discovery
Cachimbo Discovery Hole: TIR-16-09
Discovery on our 3rd of 20 targets*
Adjacent to 167.5 g/t Au grab sample
First high zinc in the Tireo Belt
AssaysPending 1000 m
N
Gold ValuesGold values are a downhole
Composite Cut-Off
grade 0.1 g/t Au.
2.0-5.0 gpt
>/= 0.50 gpt
19. Permitting a Mine in the Dominican Republic
www.goldquestcorp.com | 19
DEVELOPMENT
Exploration
Concession
Application Process
Pre-Economic
Assessment (PEA)
Detailed Engineering studies
Mineral Exploration &
Ore Deposit Discovery
Sequential and time
intensive process of
gathering and testing data to
find economic ore deposit
Exploitation
License
Application Process
Social,
Environmental &
Economic
Assessment
Detailed Engineering studies
Environmental
License
Application Process
Mine
Construction
& Operation
Mine Closure
& Rehabilitation
Pre-Feasibility
Study (PFS)
Detailed Engineering Studies
Permitting Process
After the Exploitation License is
granted, the Environmental License
must be granted before the mine is
constructed and put into operation
2005 –
2012
2013;
2015
2015-
2016
2015-
Present
20. One of few recent significant discoveries globally
Continuing to de-risk our high return project
PFS (Nov 11th, 2016) @ 28% IRR and $595/oz AISC
Permitting underway
Developing
Summary
www.goldquestcorp.com | 20
Exploring
10,000 m drilling in progress
20 new targets in 100% owned, 50 km Tireo Belt
Cachimbo discovery – 3rd of 20 targets
14 g/t Au, 74 g/t Ag, 12% Zn, 1% Cu over 5 m
Accelerating Newsflow
Ongoing exploration results
Expecting exploitation concession
Feasibility EIA
Project debt financing
Well Financed & Careful with Funds
Major shareholder: AGNICO EAGLE
~C25 M cash in hand
Always careful with funds
21. Stock Price Performance and Price Targets
www.goldquestcorp.com | 21
Tyron Breytenbach
C$1.00
C$1.40
Michael Curran
C$0.90
Jamie Spratt
C$0.90
(Ron Stewart)
*Analyst Price Targets as of March 6th, 2017
**Analyst Price Targets as of Dec. 31st, 2016
***Stock Chart: September 13th, 2017 close
C$1.25
Stuart McDougall
Analyst Target Prices
*
*
*
**
**
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
$0.00
$0.10
$0.20
$0.30
$0.40
$0.50
$0.60
$0.70
15-10-29
15-11-29
15-12-29
16-01-29
16-02-29
16-03-31
16-04-30
16-05-31
16-06-30
16-07-31
16-08-31
16-09-30
16-10-31
16-11-30
16-12-31
17-01-31
17-02-28
17-03-31
17-04-30
17-05-31
17-06-30
17-07-31
17-08-31
Volume(M)
SharePrice(C$/share)
GoldQuest Stock Chart ***
Agnico Eagle Private
Placement @ C$0.60 per
common share
22. 0.00x
0.10x
0.20x
0.30x
0.40x
0.50x
0.60x
0.70x
0.80x
0.90x
Integra Gold
Corp
Sabina Gold
& Silver Corp
Dalradian
Resources
Inc
Victoria Gold
Corp
Belo Sun
Mining Corp
Continental
Gold Inc
IDM Mining
Inc
Goldquest
Mining Corp
Falco
Resources
Ltd
Golden Reign
Resources
Ltd
P/NAV
P/NAV Comparison of Development Stage Gold Companies
Low Price to Net Asset Value (P/NAV)
www.goldquestcorp.com | 22
Consensus NAVPS estimates and pricing as of March 30th, 2017; Source: Red Cloud Klondike Strike Inc., Thomson Eikon, S&P Capital IQ
FS
PFS
PEA
24. Management
Bill Fisher CEO
Paul Robertson CFO
Jeremy Niemi VP Exploration
David Massola VP Development
Felix Mercedes Country Manager
JP Le Blanc Engineering Manager
Directors
Bill Fisher Executive Chairman
Julio Espaillat
Florian Siegfried
Patrick Michaels
Frank Balint
Contact Info:
Bill Fisher
1 (416) 583-5797
bfisher@goldquestcorp.com
Sebastian de Kloet
1 (877) 919-5979
sdekloet@redcloudks.com
* Cash (Actual) as of June 30st, 2017
**As of September 15th, 2017 close
www.goldquestcorp.com | 24
Share Information
For up to date share
information,
please visit our website at
www.goldquestcorp.com
Market Capitalization* ~C$124M
Shares Outstanding
Basic
254,007,384
Shares Outstanding
Fully Diluted
291,057,724
Cash* 25.8M
Stock Price** C$0.38
25. Mineral Reserve & Resource Estimate for Romero Project
www.goldquestcorp.com | 25
(1) Effective data for the Mineral Resource is September 27, 2016
(2) Mineral Resources which are not mineral reserves do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by
environmental, permitting, legal, title, taxation, sociopolitical, marketing or other relevant issues.
(3) The quantity and grade of reported Inferred Resources in the estimation are uncertain in nature and there has been insufficient exploration to define these Inferred
Resources as an Indicated or Measured Mineral Resource and it is uncertain if further exploration will result in upgrading them to an Indicated or Measured Mineral
Resource category.
(4) Gold Equivalent Metal prices used were $1,400/oz Au, $20.00/oz Ag and $2.50/lb Cu and recoveries of 78.1% for gold, 94.6% for copper and 58.6% for silver.
(5) Columns may not calculate precisely due to rounding errors.
Category Zone Tonnes Au (g/t) Cu (%) Zn (%)
Ag
(g/t)
AuEq
(g/t)
Au Ounces AuEq Ounces
Indicated Romero 18,390,000 2.57 0.65 0.31 4.2 3.43 1,520,000 2,028,000
Romero
South 1,840,000 3.69 0.25 0.18 1.6 4.01 218,000 237,000
Total Indicated Mineral Resources 20,230,000 2.67 0.61 0.30 4.0 3.48 1,738,000 2,265,000
Inferred Romero 2,120,000 1.80 0.39 0.36 3.2 2.32 123,000 158,000
Romero
South 900,000 2.57 0.20 0.21 2.1 2.84 74,000 82,000
Total Inferred Mineral Resources 3,020,000 2.03 0.33 0.32 2.9 2.47 197,000 240,000
Mine Reserves Tonnes Au Ag Cu Au Eq(1)
(Cutoff $70
NSR)(2) (g/t) (oz) (g/t) (oz) (%) (M lb) (g/t) (oz)
Total Probable 7,031,000 3.72 840,000 4.33 980,000 0.88 136 4.9 1,117,000
(1) Au equivalent metal prices: Au $1,300/oz Cu $2.50/lb Ag $20.00/oz
(2) Cutoff NSR metal prices: Cu Au $1,250/oz $2.50/lb Ag $17.00/oz; Recovery: Au-71.7 Cu-96.8 Ag-54.4,
Payable: Au-90.0 Cu-96.5 Ag-95.0, TCRC: $257.83/dmt, Cu concentrate 20%
Romero Mineral Reserve Estimate
Romero Mineral Resource Estimate
26. Pre-Production Capital Costs IRR
28%
After taxes
NPV5%
$203M
PAYBACK
2.5
YEARS
AISC
$595/OZ
AuEq.
$158.6
CAPITAL
Contingency
$21.3M
Owner’s Cost
$10.2M
EPCM
$23.2M
Indirect Costs
$11.8M
Underground Mining
$15.7M
Off-Site Infrastructure
$21.5M
Site Development and Road Blocks
$13.5M
Processing Facilities
$32.4M
DIRECT COSTS
INDIRECT COSTSOn-site Mining
$8.8M
www.goldquestcorp.com | 26
27. The inclusion of communities in our
activities
Implementation of sustainable
environmental practices
Active participation in the sustainable
economic development of the area
Commitment to the safety and health of
employees and communities
Operate in a transparent manner and
with the central government and local
government
Social Welfare
GoldQuest’s CSR Commitment
The Planet
• Environmental
Stewardship
Community
• Social
Welfare
Company
• Reputation
• Profitability
CSR
www.goldquestcorp.com | 27
28. Gold-Rich VMS Clan
www.goldquestcorp.com | 28
Image modified from Dubé, B; Gosselin, P; Mercier-Langevin, P; Hannington, M; Galley, 2007. Mineral deposits of Canada: a synthesis of major deposit-types, district
metallogeny, the evolution of geological provinces, and exploration methods; by Goodfellow, W D (ed.); Geological Association of Canada, Mineral Deposits Division, Special
Publication no. 5, 2007; p. 75-94
Au
Au Zn-Au
Cu-Au
Cu-Au
Cu-Au
Au
Romero
Project
Cachimbo
Discovery
167.5 g/t Au
at surface
Zn-Au