This document discusses renewable energy opportunities available through infrastructure projects using ground source heat pump technology. It provides an overview of GI Energy's experience with ground source heat pumps and energy foundations. Specifically, it details a case study of their work installing geothermal loops into the foundations of the Crossrail project in London. The loops capture renewable geothermal energy that can be used for heating and cooling the new train stations. The document outlines the technical design and installation process for the foundation loops at various Crossrail station sites.
The document discusses the integration of geothermal loops into the diaphragm walls of the Knightsbridge Palace Hotel project in London. Speakers discuss the structural design challenges, integrating the geothermal system, and lessons learned from installing the geothermal loops in the diaphragm walls during construction. Research is being conducted to study the effects of heating and cooling the walls on thermal properties and structural stresses.
The document summarizes the construction of the Big Water Visitor Center Project at the Escalante Grand Staircase National Monument from 2001 to 2002. It provides an overview of the project manager and superintendent, and documents the complex construction process through photos showing the excavation, footings, foundation walls, structural steelwork, stone masonry, electrical and mechanical work, and final completion of the building and landscaping. The curved, unconventional design of the building required precision at every stage to complete the complex structure.
ICRI - Modern Trends - FRCM Strengthening TechnologyLorella Angelini
The document summarizes a presentation on Fiber Reinforced Cement Matrix (FRCM) strengthening systems. FRCM is a composite material made of a high strength fiber mesh embedded in a cementitious matrix. It is used to strengthen structures by increasing flexural, shear, and compressive capacity. The presentation discusses the benefits of FRCM such as compatibility with concrete, ease of application, safety, and durability. Case studies are provided that demonstrate how FRCM has been used to strengthen various structures like buildings, bridges, and towers.
Attleboro Luther's Reservoir Dam & Pump Station RehabilitationThomasSexton8
The document summarizes improvements made to Luther's Reservoir Dam, dike, and pumping station in Attleboro, MA. The original structures from the 1950s/60s were deteriorating and needed upgrades. The project involved replacing the bascule gate, repairing the earthen dike, upgrading the pumping equipment and electrical systems, and waterproofing the station building. Construction started in 2017 and included installing a new automated crest gate, slide gates, pumps, and remote monitoring equipment to modernize the flood control and drinking water infrastructure.
This document describes a new tower design for wind turbines using precast concrete elements. The tower uses precast concrete columns, cross beams, and diagonals arranged in a space truss configuration for strength and stability. Compared to steel towers, this design offers lower transportation costs since elements can be larger. Assembly is also faster using long precast elements and quick connections. The design allows controlling the tower's natural vibration frequency. The inventors have a patent pending and won an innovation award for this new wind turbine tower concept.
The Wellesley High School project update provides details on construction progress from Summer 2009 through March 2010. Key milestones include expanding parking lots, demolishing part of the lecture hall to build 5 new classrooms, installing piles and pouring concrete foundations, erecting over 2000 tons of structural steel, and making progress on the building's frame with a goal of being weather tight by early 2011. The project remains on time and within budget according to the Massachusetts School Building Authority which is closely monitoring progress.
ABC in Nebraska: Belden to Laurel BridgeJill Reeves
This document summarizes the replacement of the Belden-Laurel Bridge in Nebraska using accelerated bridge construction (ABC) techniques. The old 3-span steel girder bridge from 1938 was deteriorating and in need of replacement. The new single-span bridge features precast concrete girders, deck panels, abutment caps, wing walls, and approach slabs that were assembled on site to replace the bridge over a weekend, minimizing road closure time. The precast elements were connected using self-consolidating concrete, ultra-high performance concrete, and high-early strength concrete to accelerate construction.
After more than 40 years, the California home of post-tensioning pioneer Edward K. Rice, PE, FACI, stands as a testament to the durability of post-tensioning used with shrinkage-compensating Type K cement.
The document discusses the integration of geothermal loops into the diaphragm walls of the Knightsbridge Palace Hotel project in London. Speakers discuss the structural design challenges, integrating the geothermal system, and lessons learned from installing the geothermal loops in the diaphragm walls during construction. Research is being conducted to study the effects of heating and cooling the walls on thermal properties and structural stresses.
The document summarizes the construction of the Big Water Visitor Center Project at the Escalante Grand Staircase National Monument from 2001 to 2002. It provides an overview of the project manager and superintendent, and documents the complex construction process through photos showing the excavation, footings, foundation walls, structural steelwork, stone masonry, electrical and mechanical work, and final completion of the building and landscaping. The curved, unconventional design of the building required precision at every stage to complete the complex structure.
ICRI - Modern Trends - FRCM Strengthening TechnologyLorella Angelini
The document summarizes a presentation on Fiber Reinforced Cement Matrix (FRCM) strengthening systems. FRCM is a composite material made of a high strength fiber mesh embedded in a cementitious matrix. It is used to strengthen structures by increasing flexural, shear, and compressive capacity. The presentation discusses the benefits of FRCM such as compatibility with concrete, ease of application, safety, and durability. Case studies are provided that demonstrate how FRCM has been used to strengthen various structures like buildings, bridges, and towers.
Attleboro Luther's Reservoir Dam & Pump Station RehabilitationThomasSexton8
The document summarizes improvements made to Luther's Reservoir Dam, dike, and pumping station in Attleboro, MA. The original structures from the 1950s/60s were deteriorating and needed upgrades. The project involved replacing the bascule gate, repairing the earthen dike, upgrading the pumping equipment and electrical systems, and waterproofing the station building. Construction started in 2017 and included installing a new automated crest gate, slide gates, pumps, and remote monitoring equipment to modernize the flood control and drinking water infrastructure.
This document describes a new tower design for wind turbines using precast concrete elements. The tower uses precast concrete columns, cross beams, and diagonals arranged in a space truss configuration for strength and stability. Compared to steel towers, this design offers lower transportation costs since elements can be larger. Assembly is also faster using long precast elements and quick connections. The design allows controlling the tower's natural vibration frequency. The inventors have a patent pending and won an innovation award for this new wind turbine tower concept.
The Wellesley High School project update provides details on construction progress from Summer 2009 through March 2010. Key milestones include expanding parking lots, demolishing part of the lecture hall to build 5 new classrooms, installing piles and pouring concrete foundations, erecting over 2000 tons of structural steel, and making progress on the building's frame with a goal of being weather tight by early 2011. The project remains on time and within budget according to the Massachusetts School Building Authority which is closely monitoring progress.
ABC in Nebraska: Belden to Laurel BridgeJill Reeves
This document summarizes the replacement of the Belden-Laurel Bridge in Nebraska using accelerated bridge construction (ABC) techniques. The old 3-span steel girder bridge from 1938 was deteriorating and in need of replacement. The new single-span bridge features precast concrete girders, deck panels, abutment caps, wing walls, and approach slabs that were assembled on site to replace the bridge over a weekend, minimizing road closure time. The precast elements were connected using self-consolidating concrete, ultra-high performance concrete, and high-early strength concrete to accelerate construction.
After more than 40 years, the California home of post-tensioning pioneer Edward K. Rice, PE, FACI, stands as a testament to the durability of post-tensioning used with shrinkage-compensating Type K cement.
Discover how you can use concrete lego blocks to solve many civil engineering problems. Learn how to value engineer your next project with concrete lego blocks. They are excellent for the construction of a number of retaining walls including, gravity retaining walls, reinforced block retaining walls and inclined retaining walls
Built in 1937, the Fallingwater Residence stands to this day as one of the greatest architectural achievements of Frank Lloyd Wright. Over time, the structure has endured a number of structural issues, which included cracking and deflection at the cantilever terraces. To ensure its historic value, contractors used post-tensioning systems to rehab a portion of the deteriorating elements. Post-tensioning allowed for hidden repairs in the floor cavity between the girders, making rehabilitation virtually invisible from many viewpoints. With repairs completed in 2002, the post-tensioned systems used proved to be a durable solution for the Fallingwater residence.
The magazine discusses various construction projects that utilized Leca products:
- A residential development project in Finland that used Leca aggregate for the roof provided easy installation of technical systems and moisture management.
- A bridge project in Poland that used Leca aggregate in matresses below the road structure halved construction costs by reducing soil tension.
- A tram stop project in Scotland used over 14,000 cubic meters of Leca aggregate to raise the structure seven meters and avoid excessive burden on the existing ground.
Nilex provided multiple geosynthetic solutions for the construction of the 40 km South Fraser Perimeter Road in British Columbia. This included geogrids, geotextiles, and mechanically stabilized earth walls and slopes to address challenges from poor soils and proximity to the Fraser River. Nilex's solutions saved $810,000 and reduced CO2 emissions by 605 tons compared to conventional construction methods. The road was completed ahead of schedule and was the first major project outside the US to receive Greenroads certification.
UKWP Case study - Mauchline Final copy 23 06 15ADAM DUKE
The Mauchline STW project involved upgrading the inlet works using a Design for Manufacture and Assembly (DfMA) approach to address issues identified by the Scottish Environment Protection Agency. This included constructing a new inlet storm screen chamber, flume channel, grit removal plant, and other components using precast concrete sections for increased efficiency. The DfMA approach reduced construction time and costs by designing elements off-site and assembling them with minimal additional work. The completed upgrades helped ensure the treatment works complied with its discharge consent.
The document provides an overview of projects and initiatives at Richland College from 2011-2012 and plans for the future. It discusses renovations to parking lots, elevators, restrooms, and other buildings. It also outlines plans to increase sustainability through more efficient lighting, HVAC systems, and waste reduction. The goal is to reduce energy and water usage while saving costs.
The document discusses several infrastructure projects in the UK involving bridge and retaining wall design. It provides details on the structural elements designed, software used, design codes followed, and roles and responsibilities on each project. The projects included bridge assessments, refurbishments, and new designs incorporating concrete, steel, timber and prestressed structures. Design activities involved load calculations, 3D modeling, temporary works planning and site supervision.
The document discusses concepts of mobility in architecture and housing. It describes how mobility has allowed architecture to become more dynamic and adaptable over time, enabled by developments in mechanics. Examples are given of early mobile structures like drawbridges, as well as modern kinetic buildings that move parts of their structures. The document also discusses the history of mobile homes and houses, which first emerged in the 19th century and allowed for portable living. Various mobile housing designs and technologies are presented, like prefabricated homes, container homes, and structures on wheels that can be transported to new locations.
The document summarizes the renovation of a 2,200 square foot duplex penthouse in Tribeca, Manhattan. The renovation transformed the space into a modern two bedroom, two bathroom loft apartment while maintaining historic details. Major renovations included encasing structural columns in steel, adding a fireplace, creating an 18-foot ceiling with a mezzanine level, and installing a new balcony and MEP systems. The general contractor, X-ACT Contracting Corporation, completed the 12-month gut renovation in 2014.
Carbon fiber wraps can be used for strengthening concrete and steel structures by increasing strength and corrosion resistance, with advantages of high strength, low weight, and speed of installation. Applications include strengthening pipes, columns, beams, and walls for seismic activity, added loads, corrosion, fatigue, and repairs from cutting or drilling. Engineering support is available and examples provided strengthening infrastructure for water, sewer, power plants, and other industrial facilities.
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
Construction of the Crosstown LRT is progressing at Leaside and Laird stations:
1) At Leaside station, deep excavation under Eglinton Avenue will occur from January to March 2019, requiring the closure of some pedestrian routes and TTC stops to be determined.
2) At Laird station, 24-hour mining excavation is underway from the main and secondary entrances and will continue until late 2019 to create the underground cavern for the station.
3) The mining process at Laird involves installing pipe roof supports, excavating materials below the roof, spraying concrete to support underground surfaces, and completing final lining works as sections are excavated.
The Kimbell Art Museum in Fort Worth commissioned renowned Italian architect Renzo Piano to design an expansion underground and connected to the original landmark building by Louis Kahn. Piano's design was greatly influenced by Kahn's structure while having its own identity, and was carefully engineered to protect artworks from moisture through extensive waterproofing and a specially designed glass roof bringing in natural light. The expansion has been praised for successfully adding to the museum without detracting from Kahn's original work.
Waterbury VT Downtown Planning Study Presentation 2009-10-29.
Please note: This is a work in progress, posted for discussion purposes only. There is discussion in this presentation of how VT's tax increment finance and local option tax work that was included at the request of the committee, and no proposal or recommendation has been made - just a starting point for an important discussion of how these tools could work.
The 2201 Westlake/Enso building in Seattle combines residential condominiums, retail space, and office space into one building through an innovative structural design. The building uses a combination of post-tensioned slabs, high-strength concrete and reinforcement, and minimal interior columns to accommodate four different uses stacked vertically. This structural solution allowed for open floor plans while keeping construction costs within budget.
This document provides details for a final design review of a proposed residential development project at 220 Grove Place. The existing single-family home on the property would be demolished and replaced with 4 attached single-family homes. The development plans meet the zoning and design standards for density, height, setbacks and parking. The Architectural Review Board recommended approval with conditions regarding fence height, landscaping details, and tree placement.
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...McKenney's Inc
Starting in April 2009, McKenney’s, Inc performed HVAC, sheet metal and piping installation on multiple energy-efficient barracks, which included a total of 125 dorm-style rooms with kitchenettes at Fort Benning, a US Army Base in Georgia.
Western Works CLC - Construction Update: January 18, 2022Crosstown TO
The document provides updates on construction progress for various stations and sections of the Eglinton Crosstown LRT project. Caledonia, Keelesdale, and Mount Dennis stations are undergoing finishing work like tiling, signage installation, and landscaping through 2022. Rail corridor construction between stations includes concrete pours, utility work, and track installation. LRVs are being tested and commissioned in single and coupled configurations between Mount Dennis and Caledonia stations to ensure safety and reliability before revenue service begins.
The document summarizes damage from an earthquake that occurred on May 12, 2072 at the Mailun Power Plant project site in Nepal. Key points of damage included debris filling the desander basin and blocking the intake area, penstock pipes being damaged along the transmission line from IP3 to IP5, an anchor block and manhole being damaged, and debris covering the penstock alignment from IP14 to IP17. Significant damage also occurred at the Korean bridge, which was overtopped after the river bed rose 3-4 meters, and at the power house back wall due to rockfall.
Richard Barker has 29 years of experience in civil engineering projects, mainly in the water industry. He has experience managing projects valued up to £6.5 million, including water and sewage treatment works. His most recent role is as Senior Site Manager at MWH/Biwater Treatment Ltd, where he has managed several projects involving upgrades and installations at water and sewage treatment works.
The document describes the design process of a 1:5 scale model of a bamboo bus shelter. It discusses the design concepts, material selection, structural analysis, construction progress, and joinery techniques. Bamboo and thatched roof materials were chosen for their sustainability and ability to withstand tropical weather conditions. Various prototypes were tested before finalizing a design with diagonal bracing for the roof and inverted V bracing on the sides to reinforce the structure and distribute loads from the roof to the ground.
Gi energy renewable energy opportunities with infrastructure projects june ...GI Energy
Installing renewable energy technologies into major infrastructure projects can provide opportunities for providing reduced CO2 savings and life cycle run costs adding a significant green element to a project..
This document summarizes the work of the SERVE project in Tipperary, Ireland. The SERVE project retrofitted existing homes and buildings, constructed new buildings, installed renewable energy systems, collected energy usage data, and researched socioeconomic impacts. Key results included 400 retrofits, 50 new builds, renewable energy installations, over 40 million pieces of energy data collected, and €4.1 million in grant aid secured. Energy usage decreased and biomass use increased post-retrofit. The document discusses how the SERVE project informed current national retrofit programs and energy policies in Ireland.
Discover how you can use concrete lego blocks to solve many civil engineering problems. Learn how to value engineer your next project with concrete lego blocks. They are excellent for the construction of a number of retaining walls including, gravity retaining walls, reinforced block retaining walls and inclined retaining walls
Built in 1937, the Fallingwater Residence stands to this day as one of the greatest architectural achievements of Frank Lloyd Wright. Over time, the structure has endured a number of structural issues, which included cracking and deflection at the cantilever terraces. To ensure its historic value, contractors used post-tensioning systems to rehab a portion of the deteriorating elements. Post-tensioning allowed for hidden repairs in the floor cavity between the girders, making rehabilitation virtually invisible from many viewpoints. With repairs completed in 2002, the post-tensioned systems used proved to be a durable solution for the Fallingwater residence.
The magazine discusses various construction projects that utilized Leca products:
- A residential development project in Finland that used Leca aggregate for the roof provided easy installation of technical systems and moisture management.
- A bridge project in Poland that used Leca aggregate in matresses below the road structure halved construction costs by reducing soil tension.
- A tram stop project in Scotland used over 14,000 cubic meters of Leca aggregate to raise the structure seven meters and avoid excessive burden on the existing ground.
Nilex provided multiple geosynthetic solutions for the construction of the 40 km South Fraser Perimeter Road in British Columbia. This included geogrids, geotextiles, and mechanically stabilized earth walls and slopes to address challenges from poor soils and proximity to the Fraser River. Nilex's solutions saved $810,000 and reduced CO2 emissions by 605 tons compared to conventional construction methods. The road was completed ahead of schedule and was the first major project outside the US to receive Greenroads certification.
UKWP Case study - Mauchline Final copy 23 06 15ADAM DUKE
The Mauchline STW project involved upgrading the inlet works using a Design for Manufacture and Assembly (DfMA) approach to address issues identified by the Scottish Environment Protection Agency. This included constructing a new inlet storm screen chamber, flume channel, grit removal plant, and other components using precast concrete sections for increased efficiency. The DfMA approach reduced construction time and costs by designing elements off-site and assembling them with minimal additional work. The completed upgrades helped ensure the treatment works complied with its discharge consent.
The document provides an overview of projects and initiatives at Richland College from 2011-2012 and plans for the future. It discusses renovations to parking lots, elevators, restrooms, and other buildings. It also outlines plans to increase sustainability through more efficient lighting, HVAC systems, and waste reduction. The goal is to reduce energy and water usage while saving costs.
The document discusses several infrastructure projects in the UK involving bridge and retaining wall design. It provides details on the structural elements designed, software used, design codes followed, and roles and responsibilities on each project. The projects included bridge assessments, refurbishments, and new designs incorporating concrete, steel, timber and prestressed structures. Design activities involved load calculations, 3D modeling, temporary works planning and site supervision.
The document discusses concepts of mobility in architecture and housing. It describes how mobility has allowed architecture to become more dynamic and adaptable over time, enabled by developments in mechanics. Examples are given of early mobile structures like drawbridges, as well as modern kinetic buildings that move parts of their structures. The document also discusses the history of mobile homes and houses, which first emerged in the 19th century and allowed for portable living. Various mobile housing designs and technologies are presented, like prefabricated homes, container homes, and structures on wheels that can be transported to new locations.
The document summarizes the renovation of a 2,200 square foot duplex penthouse in Tribeca, Manhattan. The renovation transformed the space into a modern two bedroom, two bathroom loft apartment while maintaining historic details. Major renovations included encasing structural columns in steel, adding a fireplace, creating an 18-foot ceiling with a mezzanine level, and installing a new balcony and MEP systems. The general contractor, X-ACT Contracting Corporation, completed the 12-month gut renovation in 2014.
Carbon fiber wraps can be used for strengthening concrete and steel structures by increasing strength and corrosion resistance, with advantages of high strength, low weight, and speed of installation. Applications include strengthening pipes, columns, beams, and walls for seismic activity, added loads, corrosion, fatigue, and repairs from cutting or drilling. Engineering support is available and examples provided strengthening infrastructure for water, sewer, power plants, and other industrial facilities.
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
Construction of the Crosstown LRT is progressing at Leaside and Laird stations:
1) At Leaside station, deep excavation under Eglinton Avenue will occur from January to March 2019, requiring the closure of some pedestrian routes and TTC stops to be determined.
2) At Laird station, 24-hour mining excavation is underway from the main and secondary entrances and will continue until late 2019 to create the underground cavern for the station.
3) The mining process at Laird involves installing pipe roof supports, excavating materials below the roof, spraying concrete to support underground surfaces, and completing final lining works as sections are excavated.
The Kimbell Art Museum in Fort Worth commissioned renowned Italian architect Renzo Piano to design an expansion underground and connected to the original landmark building by Louis Kahn. Piano's design was greatly influenced by Kahn's structure while having its own identity, and was carefully engineered to protect artworks from moisture through extensive waterproofing and a specially designed glass roof bringing in natural light. The expansion has been praised for successfully adding to the museum without detracting from Kahn's original work.
Waterbury VT Downtown Planning Study Presentation 2009-10-29.
Please note: This is a work in progress, posted for discussion purposes only. There is discussion in this presentation of how VT's tax increment finance and local option tax work that was included at the request of the committee, and no proposal or recommendation has been made - just a starting point for an important discussion of how these tools could work.
The 2201 Westlake/Enso building in Seattle combines residential condominiums, retail space, and office space into one building through an innovative structural design. The building uses a combination of post-tensioned slabs, high-strength concrete and reinforcement, and minimal interior columns to accommodate four different uses stacked vertically. This structural solution allowed for open floor plans while keeping construction costs within budget.
This document provides details for a final design review of a proposed residential development project at 220 Grove Place. The existing single-family home on the property would be demolished and replaced with 4 attached single-family homes. The development plans meet the zoning and design standards for density, height, setbacks and parking. The Architectural Review Board recommended approval with conditions regarding fence height, landscaping details, and tree placement.
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...McKenney's Inc
Starting in April 2009, McKenney’s, Inc performed HVAC, sheet metal and piping installation on multiple energy-efficient barracks, which included a total of 125 dorm-style rooms with kitchenettes at Fort Benning, a US Army Base in Georgia.
Western Works CLC - Construction Update: January 18, 2022Crosstown TO
The document provides updates on construction progress for various stations and sections of the Eglinton Crosstown LRT project. Caledonia, Keelesdale, and Mount Dennis stations are undergoing finishing work like tiling, signage installation, and landscaping through 2022. Rail corridor construction between stations includes concrete pours, utility work, and track installation. LRVs are being tested and commissioned in single and coupled configurations between Mount Dennis and Caledonia stations to ensure safety and reliability before revenue service begins.
The document summarizes damage from an earthquake that occurred on May 12, 2072 at the Mailun Power Plant project site in Nepal. Key points of damage included debris filling the desander basin and blocking the intake area, penstock pipes being damaged along the transmission line from IP3 to IP5, an anchor block and manhole being damaged, and debris covering the penstock alignment from IP14 to IP17. Significant damage also occurred at the Korean bridge, which was overtopped after the river bed rose 3-4 meters, and at the power house back wall due to rockfall.
Richard Barker has 29 years of experience in civil engineering projects, mainly in the water industry. He has experience managing projects valued up to £6.5 million, including water and sewage treatment works. His most recent role is as Senior Site Manager at MWH/Biwater Treatment Ltd, where he has managed several projects involving upgrades and installations at water and sewage treatment works.
The document describes the design process of a 1:5 scale model of a bamboo bus shelter. It discusses the design concepts, material selection, structural analysis, construction progress, and joinery techniques. Bamboo and thatched roof materials were chosen for their sustainability and ability to withstand tropical weather conditions. Various prototypes were tested before finalizing a design with diagonal bracing for the roof and inverted V bracing on the sides to reinforce the structure and distribute loads from the roof to the ground.
Gi energy renewable energy opportunities with infrastructure projects june ...GI Energy
Installing renewable energy technologies into major infrastructure projects can provide opportunities for providing reduced CO2 savings and life cycle run costs adding a significant green element to a project..
This document summarizes the work of the SERVE project in Tipperary, Ireland. The SERVE project retrofitted existing homes and buildings, constructed new buildings, installed renewable energy systems, collected energy usage data, and researched socioeconomic impacts. Key results included 400 retrofits, 50 new builds, renewable energy installations, over 40 million pieces of energy data collected, and €4.1 million in grant aid secured. Energy usage decreased and biomass use increased post-retrofit. The document discusses how the SERVE project informed current national retrofit programs and energy policies in Ireland.
14OTC 25107-Active Heating for Life of Field Flow AssurancePaul McDermott
This document discusses active heating technologies for subsea pipelines to manage hydrate formation and wax deposition over the life of oil and gas fields. It describes how active heating systems provide greater operational flexibility than traditional passive thermal controls. The main active heating methods are hot fluid circulation systems and electrical heating systems, with direct electrical heating and electrically heat traced pipe-in-pipe systems highlighted as promising technologies. Recent projects demonstrate active heating can support tiebacks over 50km and water depths over 1000m. Future trends indicate these technologies will play a crucial role in enabling production from more remote and challenging reservoirs.
The document summarizes information presented at a seminar on heat pumps and renewable energy technologies. It discusses sustainable development and various forms of renewable energy like heat pumps, solar, and wind. It then focuses on heat pumps, explaining how they work, their advantages over gas boilers in terms of cost and carbon emissions, and different types of ground source heat pumps. Micro district heating solutions are also introduced. The document concludes by covering incentives for renewable technologies like the Renewable Heat Incentive and loans available for businesses and organizations.
GSHP Training for Plumbcenter - Delivered by Kensa Heat Pumps - November 2011kensaheatpumps
The document provides an introduction to Kensa, a UK manufacturer of heat pumps. It discusses Kensa's products, including ground source heat pumps and accessories. It covers topics like how heat pumps work, product qualification, installation costs, government incentives like the Renewable Heat Incentive, and examples of heat pump sizing and costs for residential projects using ground arrays or boreholes.
- The document discusses the HeatPod project, a whole-house retrofit by Penwith Housing Association to dramatically reduce the carbon emissions and energy use of an existing home.
- The retrofit included external wall insulation, triple glazed windows, an energy efficient heat recovery ventilation system and a ground-source heat pump installed in a conservatory addition called a "HeatPod".
- Initial results showed the home's carbon emissions reduced to around 17kg CO2/m2/year and space heating has not been needed so far, with the internal temperature maintained at 18 degrees Celsius using just the heat pump system.
This workshop aims to educate homeowners in the Kingston region about renewable energy technologies and the process for implementing them. The workshop will provide practical knowledge about different renewable technologies, how they fit into a total home system, and resources to support homeowners' projects. The goals are to demystify the technologies, illustrate the process for projects, support economic activity, and leverage regional knowledge to accelerate renewable energy adoption. This will help reduce the community's carbon footprint and advance Kingston's status as a green community.
This document provides an overview of concentrating solar power technologies. It discusses the principles of concentrating sunlight to generate heat and electricity. It compares existing CSP technologies like parabolic troughs, central receivers, and dish Stirling systems. It also outlines the solar power potential in India and commercially deployed CSP projects like the Andasol plant in Spain. Key challenges and development measures to advance CSP are summarized.
This document summarizes a geothermal energy project in Puerto Rico using Single-Well Engineered Geothermal Systems (SWEGS). It outlines the team developing the GTherm Green Boiler, including engineering, drilling, and research partners. It then describes how the SWEGS works by drilling a central well with lateral holes to harvest heat via heat pipes. The document discusses the flexibility and environmental benefits of the closed-loop system. It analyzes Puerto Rico's energy profile and compares the levelized costs of GTherm to other power sources. Finally, it presents the future considerations and applications of GTherm systems.
L'intervento di Markus Gründler (SOLID) in occasione dell'evento "Solare termodinamico di piccola taglia: impianti dimostrativi in Sardegna e calore di processo industriale" che si è tenuto a Pula (CA) il 25 settembre 2015.
High Concentration Photovoltaic (HCPV) TechnologyACX
This document discusses using high concentration photovoltaic (HCPV) technology in Kenya. It describes a case study of an HCPV project currently providing electricity to a customer in Kenya. The project uses linear fresnel solar collectors to concentrate sunlight onto absorber tubes to generate thermal energy. This technology provides attractive returns on investment for the customer and helps reduce their power bills in a financially viable way while also allowing them to claim carbon credits.
LNG Basics for Petroleum Engineers provides an overview of liquefied natural gas (LNG) plants and processes. It discusses (1) why LNG is used to transport stranded natural gas long distances, (2) the pre-treatment and liquefaction processes required, and (3) the main equipment used, including heat exchangers, storage tanks, and loading systems. The document also reviews the main commercial liquefaction processes, including cascade, mixed refrigerant, and AP-X, and notes advances in near-shore and offshore floating LNG plant concepts.
The workshop provided information on home heating technologies including solar thermal and geothermal systems. For solar thermal, it discussed the differences between flat plate and evacuated tube collectors and provided case studies showing returns on investment of 16.7-23.7% for domestic hot water and pool heating systems. For geothermal, it outlined the types of systems and discussed installation considerations and costs, noting that while upfront costs are higher, operating costs are reduced by 66% compared to gas systems. A case study compared typical system costs to a geothermal heat pump system.
Process heat requirement constitutes a large part of global energy demand. Solar thermal harnesses heat from the sun that can be effectively used for process heat requirements, and save upto 30% cost when compared to conventional energy sources like gas, diesel, electricity etc.
HMX offers solar thermal solutions for steam generation and high-temperature hot water for a range of applications such as process heating, CIP (clean in place), pasteurization, distillation, cooking, air heating, etc., across industries and commercial establishments.
The document summarizes a project exploring hydrogen barrier coatings for gas network assets to enable the repurposing of existing gas infrastructure for hydrogen transport. Key findings include identifying high priority assets for coating, screening potential barrier coating materials with the most permeation-resistant being metals, and evaluating coating deposition technologies. The next steps proposed are to develop and validate complete coating systems and deposition processes through further testing and trials.
The document discusses energy conservation through waste heat recovery and combined heat and power generation. It provides two case studies as examples. The first case study examines using waste heat from a diesel engine exhaust to generate steam and distilled water. The second case study compares the environmental and economic benefits of a combined heat and power system versus separate heat and power generation. Key topics covered include definitions of waste heat recovery and combined heat and power, types and sources of waste heat, and the environmental and financial benefits of combined heat and power systems.
“Towards net zero: extracting energy from flooded coal mines for heating and ...Kyungeun Sung
“Towards net zero: extracting energy from flooded coal mines for heating and cooling applications” – Prof Amin Al-Habaibeh, Nottingham Trent University, presenting at the Net Zero Conference 2022, ‘Research Journeys in/to Net Zero: Current and Future Research Leaders in the Midlands, UK’ (on Friday 24th June 2022 at De Montfort University)
This document discusses the potential applications of geothermal energy systems in mining. It describes how geothermal systems work by exchanging heat with the ground through open or closed loop systems. Several existing examples of geothermal systems at mines are provided, using mine water, flooded workings, or dewatering pumping to heat and cool nearby buildings. Potential applications on mining projects are identified during exploration, operation, closure and post-closure phases. Challenges to greater adoption include high costs and lack of focus on energy issues by mining companies, but opportunities exist to promote geothermal's benefits to both communities near legacy mines and active mining companies.
Similar to GI Energy - Rehau PowerPoint June 2015 (20)
7. Primary circuit options for GSHP systems
Systems can be combined to give optimal solution
Open Loop System
Closed Loop Systems
8. Ground Sourced Heat Pump (GSHP) Principle
TrinityHaus colloquium
Geothermal heat
flow
(0.06 W/m2)
Solar /atmospheric energy
(10’s -100’s W/m2)
Ground Temperature 10o -12o
Pass a fluid through a constant 12o
temperature ground:
− A cooler fluid will increase in
temperature, (used for heating)
− A warmer fluid will decrease in
temperature (used for cooling)
The magnitude of this temperature
differential is around 3o-5o
Need to maintain this differential for
gshp system viability
Designed to be maintained with
seasonal heating and cooling cycles
9. TrinityHaus colloquium
Ground sourced heat pump system
HEAT
PUMP
Compressor
Expansion valve
Pump
Pump
SOURCE CIRCUIT
(Geothermal piles)
SECONDARY CIRCUIT
(Building)
Cool
Warm
Hot
Warm
Cool
Warm
System is reversible allowing for both heating and cooling
OOC Heating load 965,841kWhth 42% of Building Requirement
OOC Cooling Load 557,536kWhtc 100% of Building Requirement
Hot
6o
30o
50o
10o
Heat
Exchange
r
Heat
Exchange
r
15. Slide 15
Benefits of using EnergyPiles ® / Energy Walls®
Piles have dual functionality – structural and as energy
source
One of the cheapest sources of ground energy
Relatively low extra over cost to use the piles (depends
on technique)
Minimal impact on piling program
Provides a Stable & Sustainable renewable energy
• Advantage for BREEAM / LEED buildings
• Reduces CO2 emissions to the atmosphere.
• UK Energy foundations saving circa 7,000T /annum
17. Geothermal Loops Have Now Been Installed Successfully In
All Foundation Types
Small / large diameter bored piles –
Westminster Academy / One New Change/ US Embassy
Piles under bentonite or dry bore – Bankside London
CFA piles - Canterbury University/ Belfast Police station
Driven Cast In-situ piles. North Kent Police Station
Driven Precast Piles – Balmore Glasgow & Bristol
Diaphragm walls - Bulgari Hotel Knightsbridge / Crossrail Stations
19. CFA Piles, Hauser Forum Cambridge
• Pile design – Mott MacDonald
• Pile Contractor – Bachy
• Loop design / build – GIL
• CFA piles (600mm dia) 149 No up to
25m depth
• Loops - 4 pipes x 40mm dia
• Pushed with 1 x 40mm bar
• Heating - 188kW
• Cooling - 117kW
Plunging used 40mm bar + 4 pipes (2 loops)
Trimming Cage and header pipes
32. Bulgari Hotel - First Energy Diaphragm Wall Project in UK
• System:
– Diaphragm Wall & Energy
Piles®
• Size:
– 150kW Heating
– 150kW Cooling
• Collector type:
– 50 Energy Piles
– 150m Energy D. Wall
• On Site:
– Commissioned 2012
34. Crossrail Stations London
• System:
– Diaphragm Wall & Energy
Piles®
• Size:
– 150kW-300kW Heating
– 150kW-300kW Cooling
• Collector type:
– Energy Piles
– Energy D. Wall
• On Site:
– Farringdon Street
– Tottenham Court Road
– Bond street
– Fisher Street
– Paddington
35. Anticipated CO2 Savings at Crossrail
Contract
Heating
peak power
Cooling
peak power
CO2
Savings
(T/Annum)
(kW) (kW)
Paddington Integrated 420 240 200
Bond St WTH 186 186 28
Bond St ETH 340 340 49
TCR West 160 160 21
TCR East 75 75 9
Fisher St 60 60 10
Liverpool St – Blomfield 150 80 11
Liverpool St – Moorgate 70 25 14
Farringdon West 120 120 16
Farringdon East 90 90 12
Totals 1,671 1,376 370
66. Slide 66
Benefits of using EnergyPiles ® / Energy Walls®
Piles have dual functionality – structural and as energy
source
One of the cheapest sources of ground energy
Relatively low extra over cost to use the piles (depends
on technique)
Minimal impact on piling program
Provides a Stable & Sustainable renewable energy
• Advantage for BREEAM / LEED buildings
• Reduces CO2 emissions to the atmosphere.
• UK Energy foundations saving circa 7,000T /annum
68. GI Energy UK Headquarters
Contact - Tony Amis
tony.amis@gienergy.co.uk
Shillingwood House
Westwood Way
Westwood Business Park
Coventry
West midlands
CV4 8JZ
Mobile: +44 (0)7595 278 428
Phone: +44 (0)2476 850 403
www.gienergy.net
contact
70. All contents of this presentation are copyright Geothermal International Limited. Reproduction is forbidden without specific permission of Geothermal International Limited.