SlideShare a Scribd company logo
1 of 1
Download to read offline
Copyright © 2015 CH2M. george.dounis@ch2m.com
www.ch2m.com
Follow us @ch2mhill
Shallow Tunelling in an Urban Environment
Geotechnical Modelling and Risk Assessment
G. Dounis, and G.D. Barton
The biggest upgrade of Glasgow's wastewater network since Victorian
times includes construction of a new £100m sewer tunnel (see Fig. 1).
A total length of 5.4km is proposed with internal diameter of tunnel
ranging from 4.65m to 2.10m and three permanent shafts of 15m
diameter. The tunnel will pass at shallow depth (4m min.) under three
railway lines, a heavily trafficked motorway and residential areas.
The ground investigation process
was challenging considering the
project’s complexity and the
urban environment which
includes extensive historic mining
and industrial activity.
A detailed £1.5m ground
investigation programme was
implemented comprising:
• Cable percussion boreholes with rotary core follow on and rotary
open hole boreholes (179 boreholes, 5,035m drilling)
• In situ testing (SPTs, permeability, high pressure dilatometer) and
laboratory testing (geotechnical, environmental, chemical)
• Installation and monitoring of gas and water monitoring standpipes
(133 single and dual installations)
• Down-hole geophysics including optical/ acoustic televiewer logging
(see Fig. 2), natural gamma, density and calliper measurements, and
fluid temperature, conductivity and flowmeter recordings
• Surface geophysics surveys i.e. magnetic, microgravity, ground
penetration radar, resistivity and seismic techniques (see Fig. 3) and
• Specialised laboratory testing to define the Drilling Rate Index™,
Bit Wear Index™ and Cutter Life Index™ of the rock samples.
No mine shafts were encountered, however, during the execution of the
site works two significant incidents had to be dealt with in relation to
historic mine workings; the first one being a 0.5m deep depression of
2.0m in diameter (see Fig. 4) and the second one being a blow-out of
soil and water approximately 120m away from the drilling operation,
which covered an area of roughly 5m² (see Fig. 5). Grouting works
were implemented to treat and stabilise the affected areas.
A complex geotechnical model was established (see Fig. 6).
The geotechnical risks were quantified through contractual statements,
referred to as Baseline Statements, in the Geotechnical Baseline Report
for Bidding (GBR-B) and the following procedure was followed:
The Geotechnical Baseline Report for Construction (GBR-C) consists
the basis of the Contractor’s price and will be the most significant
criterion to determine future compensation event.
ACKNOWLEDGEMENT
The authors would like to thank Scottish Water for their permission to
publish this poster. The authors also appreciate the kind support and
valuable comments of Mark Welsh (CH2M, Project Manager), Colin
Warren (CH2M, Geotechnical/ Tunnelling Consultant) and Vik Adam
(JWH Ross, Project Mining Engineer).
REFERENCES
Bruland, A. 1998. Project report 13A-98 – Hard rock tunnel boring:
Drillability Test Methods, Department of Civil and Transport
Engineering at the Norwegian University of Science and Technology,
Trondheim.
Stone, K. Murray, A. Cooke, S. Foran, J. Gooderham, L. 2009.
Unexploded Ordnance (UXO) – A guide for the construction industry,
CIRIA, London.
GBR-B GBR-C
4
Tenderers
Preferred
Tenderer
Negotiation
Fig. 1. Project route.
Fig. 5. Washed-out material during
drilling operation 120m away.
Fig. 2. Optical televiewer
logging – dark zone (right)
corresponds to collapsed
mine working (left).
Fig. 4. Investigation of mine shaft
– resistivity, magnetic and microgravity survey.
The following geotechnical risks were identified:
Hazard
Unexploded Ordnance in shafts
Boulders in Glacial Till
Alluvium soft and highly compressible
below shallow cover
Extensive mining (shafts, packed
waste, collapsed material and voids)
Bedrock with varying characteristics,
structural folding, faults
Layers of running sand at tunnel crown
level
Existence of hazardous gases and
water bearing strata with varying
connectivity
Superficial natural deposits in a highly
variable interface with underlying
rockhead
Shallow rock cover with collapse
potential
Delays to the construction programme
Delays due to required interventions
Face instability and increased surface
settlement
Subsidence due to potential collapse of
the abandoned working
Problems at the tunnel face and
decreased TBM's penetrability rates
Increased volume loss at the tunnel
face and surface settlement
Delays to TBM's operation, influence
on the selection and design of the TBM
Difficulties in TBM’s drive at
transition zones, increased no of
interventions
Influx of the overlying superficial
deposits, increased surface settlement
under low pressure operation
Risk
Fig. 6. Sample of the geotechnical and mining model.
(coloured dotted lines represent coal seams and their likelihood of being worked)
Fig. 4. Ground depression during
drilling of nearby borehole.

More Related Content

What's hot

Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)sou_suk_sou
 
Modern mining
Modern miningModern mining
Modern miningarabnubia
 
Geomodelling, resource & reserve estimation using mining software
Geomodelling, resource & reserve estimation using mining softwareGeomodelling, resource & reserve estimation using mining software
Geomodelling, resource & reserve estimation using mining softwareChandra Bose
 
SAIMM paper - slope steepening
SAIMM paper - slope steepeningSAIMM paper - slope steepening
SAIMM paper - slope steepeningAlfred Madowe
 
Effect of CO2 sequestration on soil liquefaction in geological pits
Effect of CO2 sequestration on soil liquefaction in geological pitsEffect of CO2 sequestration on soil liquefaction in geological pits
Effect of CO2 sequestration on soil liquefaction in geological pitsijiert bestjournal
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET Journal
 
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...Michal Krzeminski
 
2 surface mine planning
2 surface mine planning2 surface mine planning
2 surface mine planningUET Peshawar
 
Hydrocarbon Trapping mechanism and petrophysical analysis of Afam field, offs...
Hydrocarbon Trapping mechanism and petrophysical analysis of Afam field, offs...Hydrocarbon Trapping mechanism and petrophysical analysis of Afam field, offs...
Hydrocarbon Trapping mechanism and petrophysical analysis of Afam field, offs...David Oyeyemi
 
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground MinesPERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground MinesPERUMIN - Convención Minera
 
Introduction to underground mine planning
Introduction to underground mine planningIntroduction to underground mine planning
Introduction to underground mine planningIndranathSinha3
 
Mapping of Aquifer Contamination Using Geoelectric Methods at a Municipal Sol...
Mapping of Aquifer Contamination Using Geoelectric Methods at a Municipal Sol...Mapping of Aquifer Contamination Using Geoelectric Methods at a Municipal Sol...
Mapping of Aquifer Contamination Using Geoelectric Methods at a Municipal Sol...iosrjce
 
Numerical Modelling of Waterlogging Problem in New Urbanized Communities in A...
Numerical Modelling of Waterlogging Problem in New Urbanized Communities in A...Numerical Modelling of Waterlogging Problem in New Urbanized Communities in A...
Numerical Modelling of Waterlogging Problem in New Urbanized Communities in A...IJERA Editor
 
2015 CDA-Frederickhouse Erosion Control
2015 CDA-Frederickhouse Erosion Control2015 CDA-Frederickhouse Erosion Control
2015 CDA-Frederickhouse Erosion Controlshiqiang Ye
 
The Quality of Ground Water for Selected Area in South of Babylon Governorate...
The Quality of Ground Water for Selected Area in South of Babylon Governorate...The Quality of Ground Water for Selected Area in South of Babylon Governorate...
The Quality of Ground Water for Selected Area in South of Babylon Governorate...iosrjce
 
The CarboZALF-D manipulation experiment – experimental design and SOC patterns
The CarboZALF-D manipulation experiment – experimental design and SOC patternsThe CarboZALF-D manipulation experiment – experimental design and SOC patterns
The CarboZALF-D manipulation experiment – experimental design and SOC patternsAgriculture Journal IJOEAR
 
Tunnel Stability Factor Michalis_Konstantis
Tunnel Stability Factor Michalis_KonstantisTunnel Stability Factor Michalis_Konstantis
Tunnel Stability Factor Michalis_KonstantisILIAS MICHALIS
 

What's hot (20)

Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)
 
Modern mining
Modern miningModern mining
Modern mining
 
Geomodelling, resource & reserve estimation using mining software
Geomodelling, resource & reserve estimation using mining softwareGeomodelling, resource & reserve estimation using mining software
Geomodelling, resource & reserve estimation using mining software
 
Pecker aci2003
Pecker aci2003Pecker aci2003
Pecker aci2003
 
Stages of mining Development and Exploitation
Stages of mining Development and ExploitationStages of mining Development and Exploitation
Stages of mining Development and Exploitation
 
SAIMM paper - slope steepening
SAIMM paper - slope steepeningSAIMM paper - slope steepening
SAIMM paper - slope steepening
 
Effect of CO2 sequestration on soil liquefaction in geological pits
Effect of CO2 sequestration on soil liquefaction in geological pitsEffect of CO2 sequestration on soil liquefaction in geological pits
Effect of CO2 sequestration on soil liquefaction in geological pits
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil Erosion
 
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
 
2 surface mine planning
2 surface mine planning2 surface mine planning
2 surface mine planning
 
Hydrocarbon Trapping mechanism and petrophysical analysis of Afam field, offs...
Hydrocarbon Trapping mechanism and petrophysical analysis of Afam field, offs...Hydrocarbon Trapping mechanism and petrophysical analysis of Afam field, offs...
Hydrocarbon Trapping mechanism and petrophysical analysis of Afam field, offs...
 
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground MinesPERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
 
Introduction to underground mine planning
Introduction to underground mine planningIntroduction to underground mine planning
Introduction to underground mine planning
 
Mapping of Aquifer Contamination Using Geoelectric Methods at a Municipal Sol...
Mapping of Aquifer Contamination Using Geoelectric Methods at a Municipal Sol...Mapping of Aquifer Contamination Using Geoelectric Methods at a Municipal Sol...
Mapping of Aquifer Contamination Using Geoelectric Methods at a Municipal Sol...
 
Numerical Modelling of Waterlogging Problem in New Urbanized Communities in A...
Numerical Modelling of Waterlogging Problem in New Urbanized Communities in A...Numerical Modelling of Waterlogging Problem in New Urbanized Communities in A...
Numerical Modelling of Waterlogging Problem in New Urbanized Communities in A...
 
Geotechnics report
Geotechnics report Geotechnics report
Geotechnics report
 
2015 CDA-Frederickhouse Erosion Control
2015 CDA-Frederickhouse Erosion Control2015 CDA-Frederickhouse Erosion Control
2015 CDA-Frederickhouse Erosion Control
 
The Quality of Ground Water for Selected Area in South of Babylon Governorate...
The Quality of Ground Water for Selected Area in South of Babylon Governorate...The Quality of Ground Water for Selected Area in South of Babylon Governorate...
The Quality of Ground Water for Selected Area in South of Babylon Governorate...
 
The CarboZALF-D manipulation experiment – experimental design and SOC patterns
The CarboZALF-D manipulation experiment – experimental design and SOC patternsThe CarboZALF-D manipulation experiment – experimental design and SOC patterns
The CarboZALF-D manipulation experiment – experimental design and SOC patterns
 
Tunnel Stability Factor Michalis_Konstantis
Tunnel Stability Factor Michalis_KonstantisTunnel Stability Factor Michalis_Konstantis
Tunnel Stability Factor Michalis_Konstantis
 

Similar to George Dounis_PID_509

The role of site investigation
The role of site investigationThe role of site investigation
The role of site investigationAngelo Indelicato
 
Athens pecker 2005
Athens pecker 2005Athens pecker 2005
Athens pecker 2005gefyra-rion
 
Geo trans2004 pecker
Geo trans2004 peckerGeo trans2004 pecker
Geo trans2004 peckergefyra-rion
 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis Smith
 
Mokpo symposium pecker 2006
Mokpo symposium pecker 2006Mokpo symposium pecker 2006
Mokpo symposium pecker 2006gefyra-rion
 
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...Christian Olele
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptxSubratDash37
 
Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...Hsuain
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel ProjectsKeith Kong
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINALBenjamin Kramka
 
IRJET - Shrinkage Crack Study due to Lead Contamination in Bentonite Clay
IRJET - Shrinkage Crack Study due to Lead Contamination in Bentonite ClayIRJET - Shrinkage Crack Study due to Lead Contamination in Bentonite Clay
IRJET - Shrinkage Crack Study due to Lead Contamination in Bentonite ClayIRJET Journal
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsIRJET Journal
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsIRJET Journal
 
Evaluating Interface Properties of Geomembrane and Compacted Clay Liners for ...
Evaluating Interface Properties of Geomembrane and Compacted Clay Liners for ...Evaluating Interface Properties of Geomembrane and Compacted Clay Liners for ...
Evaluating Interface Properties of Geomembrane and Compacted Clay Liners for ...MrEddyAsyrafSyed
 
Geo-Tech Studies for Longwall
Geo-Tech Studies for LongwallGeo-Tech Studies for Longwall
Geo-Tech Studies for LongwallVR M
 

Similar to George Dounis_PID_509 (20)

The role of site investigation
The role of site investigationThe role of site investigation
The role of site investigation
 
Athens pecker 2005
Athens pecker 2005Athens pecker 2005
Athens pecker 2005
 
Geo trans2004 pecker
Geo trans2004 peckerGeo trans2004 pecker
Geo trans2004 pecker
 
Dfi2005 pecker
Dfi2005 peckerDfi2005 pecker
Dfi2005 pecker
 
Lecture 6 p
Lecture 6 pLecture 6 p
Lecture 6 p
 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016
 
Mokpo symposium pecker 2006
Mokpo symposium pecker 2006Mokpo symposium pecker 2006
Mokpo symposium pecker 2006
 
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...
 
Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...
Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...
Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
 
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
 
Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel Projects
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINAL
 
IRJET - Shrinkage Crack Study due to Lead Contamination in Bentonite Clay
IRJET - Shrinkage Crack Study due to Lead Contamination in Bentonite ClayIRJET - Shrinkage Crack Study due to Lead Contamination in Bentonite Clay
IRJET - Shrinkage Crack Study due to Lead Contamination in Bentonite Clay
 
Aoc sediment update_part2
Aoc sediment update_part2Aoc sediment update_part2
Aoc sediment update_part2
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
 
Evaluating Interface Properties of Geomembrane and Compacted Clay Liners for ...
Evaluating Interface Properties of Geomembrane and Compacted Clay Liners for ...Evaluating Interface Properties of Geomembrane and Compacted Clay Liners for ...
Evaluating Interface Properties of Geomembrane and Compacted Clay Liners for ...
 
Geo-Tech Studies for Longwall
Geo-Tech Studies for LongwallGeo-Tech Studies for Longwall
Geo-Tech Studies for Longwall
 

George Dounis_PID_509

  • 1. Copyright © 2015 CH2M. george.dounis@ch2m.com www.ch2m.com Follow us @ch2mhill Shallow Tunelling in an Urban Environment Geotechnical Modelling and Risk Assessment G. Dounis, and G.D. Barton The biggest upgrade of Glasgow's wastewater network since Victorian times includes construction of a new £100m sewer tunnel (see Fig. 1). A total length of 5.4km is proposed with internal diameter of tunnel ranging from 4.65m to 2.10m and three permanent shafts of 15m diameter. The tunnel will pass at shallow depth (4m min.) under three railway lines, a heavily trafficked motorway and residential areas. The ground investigation process was challenging considering the project’s complexity and the urban environment which includes extensive historic mining and industrial activity. A detailed £1.5m ground investigation programme was implemented comprising: • Cable percussion boreholes with rotary core follow on and rotary open hole boreholes (179 boreholes, 5,035m drilling) • In situ testing (SPTs, permeability, high pressure dilatometer) and laboratory testing (geotechnical, environmental, chemical) • Installation and monitoring of gas and water monitoring standpipes (133 single and dual installations) • Down-hole geophysics including optical/ acoustic televiewer logging (see Fig. 2), natural gamma, density and calliper measurements, and fluid temperature, conductivity and flowmeter recordings • Surface geophysics surveys i.e. magnetic, microgravity, ground penetration radar, resistivity and seismic techniques (see Fig. 3) and • Specialised laboratory testing to define the Drilling Rate Index™, Bit Wear Index™ and Cutter Life Index™ of the rock samples. No mine shafts were encountered, however, during the execution of the site works two significant incidents had to be dealt with in relation to historic mine workings; the first one being a 0.5m deep depression of 2.0m in diameter (see Fig. 4) and the second one being a blow-out of soil and water approximately 120m away from the drilling operation, which covered an area of roughly 5m² (see Fig. 5). Grouting works were implemented to treat and stabilise the affected areas. A complex geotechnical model was established (see Fig. 6). The geotechnical risks were quantified through contractual statements, referred to as Baseline Statements, in the Geotechnical Baseline Report for Bidding (GBR-B) and the following procedure was followed: The Geotechnical Baseline Report for Construction (GBR-C) consists the basis of the Contractor’s price and will be the most significant criterion to determine future compensation event. ACKNOWLEDGEMENT The authors would like to thank Scottish Water for their permission to publish this poster. The authors also appreciate the kind support and valuable comments of Mark Welsh (CH2M, Project Manager), Colin Warren (CH2M, Geotechnical/ Tunnelling Consultant) and Vik Adam (JWH Ross, Project Mining Engineer). REFERENCES Bruland, A. 1998. Project report 13A-98 – Hard rock tunnel boring: Drillability Test Methods, Department of Civil and Transport Engineering at the Norwegian University of Science and Technology, Trondheim. Stone, K. Murray, A. Cooke, S. Foran, J. Gooderham, L. 2009. Unexploded Ordnance (UXO) – A guide for the construction industry, CIRIA, London. GBR-B GBR-C 4 Tenderers Preferred Tenderer Negotiation Fig. 1. Project route. Fig. 5. Washed-out material during drilling operation 120m away. Fig. 2. Optical televiewer logging – dark zone (right) corresponds to collapsed mine working (left). Fig. 4. Investigation of mine shaft – resistivity, magnetic and microgravity survey. The following geotechnical risks were identified: Hazard Unexploded Ordnance in shafts Boulders in Glacial Till Alluvium soft and highly compressible below shallow cover Extensive mining (shafts, packed waste, collapsed material and voids) Bedrock with varying characteristics, structural folding, faults Layers of running sand at tunnel crown level Existence of hazardous gases and water bearing strata with varying connectivity Superficial natural deposits in a highly variable interface with underlying rockhead Shallow rock cover with collapse potential Delays to the construction programme Delays due to required interventions Face instability and increased surface settlement Subsidence due to potential collapse of the abandoned working Problems at the tunnel face and decreased TBM's penetrability rates Increased volume loss at the tunnel face and surface settlement Delays to TBM's operation, influence on the selection and design of the TBM Difficulties in TBM’s drive at transition zones, increased no of interventions Influx of the overlying superficial deposits, increased surface settlement under low pressure operation Risk Fig. 6. Sample of the geotechnical and mining model. (coloured dotted lines represent coal seams and their likelihood of being worked) Fig. 4. Ground depression during drilling of nearby borehole.