This document summarizes the state of India's transmission and distribution (T&D) infrastructure. It notes that while transmission capacity has grown, distribution remains a concern with T&D losses as high as 23% in India compared to 5-8% in other countries. The government is taking steps like IPDS and DDUGJY schemes to strengthen the network. Private sector participation is also growing through projects using the tariff-based competitive bidding process. Overall, continued investment and upgrades are needed to support India's economic growth and achieve full electrification through initiatives like 'Power for All'.
India power transmission & distribution sector opportunity outlook 2025Rajesh Sarma
“India Power Transmission & Distribution Sector Opportunity Outlook 2025” Report Highlights
India Power Transmission & Distribution Sector Overview
India Power Transmission & Distribution Sector Dynamics
Indian Electricity Grid Overview
Existing Power Transmission & Distribution Infrastructure in India
Transmission & Distribution (T&D) Losses
India Smart Grid Adoption Initiative
India Transmission & Distribution Sector Regulatory & Policy Framework
Energy Infrastructure in India : A Reference BookInfraline Energy
India has a large energy sector which is growing rapidly and is endowed with primary and renewable energy resources. Information on data on India energy sector is widely available from large number of agencies however India does not have any one agency, like EIA USA to issue comprehensive authentic data on the sector. Energy sector professionals generally struggle to get a total picture at one place and it is a cumbersome job to get the essential and authentic information covering coal, oil and gas, power and renewable sectors. Keeping this in mind, InfralineEnergy has come up with a 'Reference Book on Energy Infrastructure in India'. For further details http://www.infraline.com/Reports.aspx?id=276&tlt=Energy-Infrastructure-in-India-A-Reference-Book-&sl=Business%20Report%20Series
PES Wind Magazine - Ingeteam Wind Energy on India's clean energy industryIngeteam Wind Energy
In February 2015, the Indian government announced its plans to almost quadruple its renewable power capacity to 175 GW by 2022 as part of the plan to supply electricity to every household in the country. This includes 60 GW from wind energy. Further, India made a commitment at COP21 to raise the share of non-fossil-fuel power capacity in the country’s power mix to 40% by 2030.
Consequently, these plans and targets make the Indian market a unique fast moving and growing market where competitive companies can have great business opportunities. But, they also come with a complex and unstable legal framework where manufacturers find many obstacles on the way.
India power transmission & distribution sector opportunity outlook 2025Rajesh Sarma
“India Power Transmission & Distribution Sector Opportunity Outlook 2025” Report Highlights
India Power Transmission & Distribution Sector Overview
India Power Transmission & Distribution Sector Dynamics
Indian Electricity Grid Overview
Existing Power Transmission & Distribution Infrastructure in India
Transmission & Distribution (T&D) Losses
India Smart Grid Adoption Initiative
India Transmission & Distribution Sector Regulatory & Policy Framework
Energy Infrastructure in India : A Reference BookInfraline Energy
India has a large energy sector which is growing rapidly and is endowed with primary and renewable energy resources. Information on data on India energy sector is widely available from large number of agencies however India does not have any one agency, like EIA USA to issue comprehensive authentic data on the sector. Energy sector professionals generally struggle to get a total picture at one place and it is a cumbersome job to get the essential and authentic information covering coal, oil and gas, power and renewable sectors. Keeping this in mind, InfralineEnergy has come up with a 'Reference Book on Energy Infrastructure in India'. For further details http://www.infraline.com/Reports.aspx?id=276&tlt=Energy-Infrastructure-in-India-A-Reference-Book-&sl=Business%20Report%20Series
PES Wind Magazine - Ingeteam Wind Energy on India's clean energy industryIngeteam Wind Energy
In February 2015, the Indian government announced its plans to almost quadruple its renewable power capacity to 175 GW by 2022 as part of the plan to supply electricity to every household in the country. This includes 60 GW from wind energy. Further, India made a commitment at COP21 to raise the share of non-fossil-fuel power capacity in the country’s power mix to 40% by 2030.
Consequently, these plans and targets make the Indian market a unique fast moving and growing market where competitive companies can have great business opportunities. But, they also come with a complex and unstable legal framework where manufacturers find many obstacles on the way.
CII has been strongly advocating for an Action Agenda towards creating an enabling and integrated policy & regulatory framework, the impact of which could facilitate considerable investments in the Infrastructure sector thus taking India’s Infrastructure story forward.
This issue of Policy Watch takes an in-depth look at the sectoral issues and has outlined some specific recommendations to reinvigorate the growth momentum in the sector.
SOLAR PV BUSINESS OPPORTUNITIES - BETWEEN INDIA AND NETHERLANDAurovilleConsulting
To explore opportunities for Dutch organizations to partner with Indian organizations in the PV value chain, requirements of the Indian PV value chain are identified and juxtaposed with the strengths of Dutch PV value chain.
A Review of Restructured Power Development and Reform Programme in Indiaijiert bestjournal
The power sector is one of the most important infrastructural aspec ts of the Indian economy. But of late,it has been facing some serious problems such as old worn-out and poor distributi on network leading to frequent outages,skewed tariff structure,huge Transmission & Distribution (T &D) losses largely due to outright theft & unmetered supply,high LT/HT line ratio,overloaded DT/ Lines,lack of accountability at feeder level and in distribution setup of State Electricity Boards (SEBs). Henc e,the Government identified Distribution Reforms as the key area to bring about the efficiency & commerc ial availability into the power sector. The Government took various initiatives in this direction;one of these is the introduction of Accelerated Power Development Programme (APDP) in February,2000. The main objective of thi s programme was to initiate a financial turnaround in the performance of the State owned power sector .
Will Demand for Power Slowdown in India? -In-depth Analysis by Mirdul AminMirdul Amin Sarkar
The Demand for Power will not slowdown in India due to increasing penetration of per capita electric consumption, increasing industrialization, growing middle class and consumer base in India.
It is expected that the Demand for electricity will increase at a CAGR of 7% to 1,894.7 TWh over FY07–22 in India.
The global power and utilities sector is undergoing significant transformation, which is challenging traditional business models, and paving way for new technologies. In all major developed economies, utility companies face a tough operating environment, and this is resulting in several new business models that are mainly based on technological advancements and customer services.
Electricity transmission grid, historically a regulated and traditionally run entity, is also moving in the same direction, and adopting several new technologies, such as Smart, energy storage, and high voltage capacity corridors. Evolution is mostly seen in developed regions with a mature power and utility sector, such as Germany, the UK and the US. However, developing economies too are looking to leapfrog to new models, and currently building plans for the future. The global smart grid market is considered as the grid of the future and is pegged at US$70 billion by 2023.
Financial & operational opportunities for disco ms under udaySakshi Saini
What erstwhile was ignored, has now gained pinnacle importance by Government as the future of power sector at large depends upon better financial health and consistent operations of DISCOMS. To ensure this objective Government did attempted FRPs for struggling Discoms in 2013 which tanked due to lack of timely implementation, forcing yet another scheme to turnaround the fate of state owned distribution utilities which has earned the nomenclature as UDAY (Ujwal DISCOM Assurance Yojana). The scheme is touted as the next paladin to bail out the struggling Discoms, potentially could see them turn green in a time horizon of 3-4 years from 2015/16.
StocksInsights Hidden Treasure November 2015 pick - Techno ElectricStocksInsights
In this package, you get high potential Multibagger Stock every month with the best possible return ratio. Our intention is to help you discover the Hidden-Treasures in the market which have the potential to generate multi-fold returns in the future without taking extra risks. Our key objective is to pick stocks which can Compound Sustainably at a healthy rate for the next 3-5 years and create enormous wealth (3-4X Returns). We like to select companies with strong Competitive Advantages and moats are quoting at a discount to their intrinsic value.
Hidden Treasures Package is suitable for whom?
– Investors looking for sustainable long term returns in good stocks.
– Has a holding period of minimum 1 Year and is willing to stomach volatility.
– Investment capital of minimum INR 2 Lakh (or) if your saving is over Rs 10K/month.
– For those who do not want to gamble in short term trade and burn their fingers.
T&D India (January 2017): INTELECT 2017 SpecialT&D India
UDAY making good progress
Inside the Magazine:
Leading Story China dominates super critical power equipment in XII Plan
Interactions: Hartek Power, mjunction, NTL Group, Siemens AG, Toshiba JSW Power Systems
Viewpoint: Clean power is the need for data centers
Special Report: FDI in Indian transformer industry
India power transmission & distribution sector opportunity outlook 2025Rajesh Sarma
“India Power Transmission & Distribution Sector Opportunity Outlook 2025” Report Highlights
India Power Transmission & Distribution Sector Overview
India Power Transmission & Distribution Sector Dynamics
Indian Electricity Grid Overview
Existing Power Transmission & Distribution Infrastructure in India
Transmission & Distribution (T&D) Losses
India Smart Grid Adoption Initiative
India Transmission & Distribution Sector Regulatory & Policy Framework
CII has been strongly advocating for an Action Agenda towards creating an enabling and integrated policy & regulatory framework, the impact of which could facilitate considerable investments in the Infrastructure sector thus taking India’s Infrastructure story forward.
This issue of Policy Watch takes an in-depth look at the sectoral issues and has outlined some specific recommendations to reinvigorate the growth momentum in the sector.
SOLAR PV BUSINESS OPPORTUNITIES - BETWEEN INDIA AND NETHERLANDAurovilleConsulting
To explore opportunities for Dutch organizations to partner with Indian organizations in the PV value chain, requirements of the Indian PV value chain are identified and juxtaposed with the strengths of Dutch PV value chain.
A Review of Restructured Power Development and Reform Programme in Indiaijiert bestjournal
The power sector is one of the most important infrastructural aspec ts of the Indian economy. But of late,it has been facing some serious problems such as old worn-out and poor distributi on network leading to frequent outages,skewed tariff structure,huge Transmission & Distribution (T &D) losses largely due to outright theft & unmetered supply,high LT/HT line ratio,overloaded DT/ Lines,lack of accountability at feeder level and in distribution setup of State Electricity Boards (SEBs). Henc e,the Government identified Distribution Reforms as the key area to bring about the efficiency & commerc ial availability into the power sector. The Government took various initiatives in this direction;one of these is the introduction of Accelerated Power Development Programme (APDP) in February,2000. The main objective of thi s programme was to initiate a financial turnaround in the performance of the State owned power sector .
Will Demand for Power Slowdown in India? -In-depth Analysis by Mirdul AminMirdul Amin Sarkar
The Demand for Power will not slowdown in India due to increasing penetration of per capita electric consumption, increasing industrialization, growing middle class and consumer base in India.
It is expected that the Demand for electricity will increase at a CAGR of 7% to 1,894.7 TWh over FY07–22 in India.
The global power and utilities sector is undergoing significant transformation, which is challenging traditional business models, and paving way for new technologies. In all major developed economies, utility companies face a tough operating environment, and this is resulting in several new business models that are mainly based on technological advancements and customer services.
Electricity transmission grid, historically a regulated and traditionally run entity, is also moving in the same direction, and adopting several new technologies, such as Smart, energy storage, and high voltage capacity corridors. Evolution is mostly seen in developed regions with a mature power and utility sector, such as Germany, the UK and the US. However, developing economies too are looking to leapfrog to new models, and currently building plans for the future. The global smart grid market is considered as the grid of the future and is pegged at US$70 billion by 2023.
Financial & operational opportunities for disco ms under udaySakshi Saini
What erstwhile was ignored, has now gained pinnacle importance by Government as the future of power sector at large depends upon better financial health and consistent operations of DISCOMS. To ensure this objective Government did attempted FRPs for struggling Discoms in 2013 which tanked due to lack of timely implementation, forcing yet another scheme to turnaround the fate of state owned distribution utilities which has earned the nomenclature as UDAY (Ujwal DISCOM Assurance Yojana). The scheme is touted as the next paladin to bail out the struggling Discoms, potentially could see them turn green in a time horizon of 3-4 years from 2015/16.
StocksInsights Hidden Treasure November 2015 pick - Techno ElectricStocksInsights
In this package, you get high potential Multibagger Stock every month with the best possible return ratio. Our intention is to help you discover the Hidden-Treasures in the market which have the potential to generate multi-fold returns in the future without taking extra risks. Our key objective is to pick stocks which can Compound Sustainably at a healthy rate for the next 3-5 years and create enormous wealth (3-4X Returns). We like to select companies with strong Competitive Advantages and moats are quoting at a discount to their intrinsic value.
Hidden Treasures Package is suitable for whom?
– Investors looking for sustainable long term returns in good stocks.
– Has a holding period of minimum 1 Year and is willing to stomach volatility.
– Investment capital of minimum INR 2 Lakh (or) if your saving is over Rs 10K/month.
– For those who do not want to gamble in short term trade and burn their fingers.
T&D India (January 2017): INTELECT 2017 SpecialT&D India
UDAY making good progress
Inside the Magazine:
Leading Story China dominates super critical power equipment in XII Plan
Interactions: Hartek Power, mjunction, NTL Group, Siemens AG, Toshiba JSW Power Systems
Viewpoint: Clean power is the need for data centers
Special Report: FDI in Indian transformer industry
India power transmission & distribution sector opportunity outlook 2025Rajesh Sarma
“India Power Transmission & Distribution Sector Opportunity Outlook 2025” Report Highlights
India Power Transmission & Distribution Sector Overview
India Power Transmission & Distribution Sector Dynamics
Indian Electricity Grid Overview
Existing Power Transmission & Distribution Infrastructure in India
Transmission & Distribution (T&D) Losses
India Smart Grid Adoption Initiative
India Transmission & Distribution Sector Regulatory & Policy Framework
T&D India (August 2017) - Power T&D Vision 2022T&D India
Power T&D Vision 2022- 1st Anniversary - This edition marks the first anniversary issue of T&D India.Completing the first year of existence is always a momentous event, and we are thrilled beyond words at crossing this milestone.
T&D India (March 2017): Privatization not a cure-all, but still worth pursuingT&D India
In the entire power value chain, it is power distribution that has most singularities. While power generation and transmission are largely institution-related businesses, it is power distribution that interfaces with the end-consumer. All the commercial losses that are talked about in the power sector originate in power distribution. Even Smart Grid architecture has a bearing on power distribution, much more than power generation or transmission.
The government’s “Power for All” programme is an ambitious plan, which depends a lot on the development of capacity expansion in power supply chain, developing coal resources and logistics and increasing technological interventions.
CII-PwC report titled Round-the-Clock Power Supply: A Key Milestone says that the Indian Power Sector depend upon the availability of power that on other hand depend on two factors—adequate electricity generated and development of supporting infrastructure for the supply of electricity.
Engineering Procurement & Construction Making India Brick by Brickelithomas202
The EPC market in India has evolved over the last few years with increased project size and complexity. This has increased private clients and entry of several foreign players.
Investment confidence in Australia’s renewable energy sector has significantly improved following the legislation of the revised Large-scale Renewable Energy Target (LRET) in mid-
2015, a new Prime Minister that is more supportive of renewable energy and a strong outcome at the Paris climate change conference. The level and pace of investment will need to increase substantially in 2016 and 2017 in order
for liable parties to deliver on the 2020 legislated target and obligation. The Clean Energy
Regulator estimates that for this to happen, around 3000 MW of new renewable capacity should
be committed in 2016.
This paper outlines the status of progress towards delivering on the 2020 target of 33,000 GWh
of new large-scale renewable energy generation. While there will be challenges, this paper finds
that there is reason to be optimistic that the required new investment will be delivered within the
required timeframe.
Govt to revisit, revise power distribution guidelines in National Electricit...Tata Power
“To succeed and survive, Indian Discoms need to quickly embrace digital technology tapping the sophisticated technologies like IoT, analytics, automation and cloud to generate higher efficiency."
- Praveer Sinha. CEO & MD, Tata Power.
Modern Energy Transport - Country Analysis IndiaAdityaDesai77
Analysis of Grid Infrastructure & Renewable Energy Potential.
Current Developments and the trends for the magnanimous growth of Electricity Demand for 1.3 Billion people.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Forklift Classes Overview by Intella PartsIntella Parts
Discover the different forklift classes and their specific applications. Learn how to choose the right forklift for your needs to ensure safety, efficiency, and compliance in your operations.
For more technical information, visit our website https://intellaparts.com
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
1. Feature - T&D Infrastructure
march 2017POWER TODAY44 www.PowerToday.in
Metamorphosis
With the Indian government looking at fortifying the T&D space and plugging the holes, the
segment may be finally receiving its long overdue attention.
W
hile India is making steady headway on
the transmission front and the sector has
witnessed commendable growth over the last
few years with substantial capacity additions,
the distribution or last mile connectivity is
still a concern in India.
At the inter-state level, though the networks are
becoming quite mature, there is significant backlog or
inadequate capacity within the state, to meet the increasing
demand and load patterns. In addition, T&D losses have
been plaguing the sector since a long time.
These losses inherent to T&D systems, include those
incurred while transmitting power from sources of supply
to points of distribution and ultimately to final consumers;
commercial losses also being accounted for in this.
Status
In India,T&D losses account for as high as 23 per cent
of the total electricity generated as compared to countries
like Singapore, Malaysia and other developed countries
wherein the losses are as low as ranging from 5-8 per cent.
These losses can be reduced by strengthening and upgrading
the T&D infrastructure combined with proper tracking
and auditing which would ensure reduced loss levels.
However, Vimal Kejriwal, MD & CEO, KEC
International Ltd is optimistic about the growth, “The
good part is that, a lot of progress is unfolding as dedicated
efforts are being undertaken by the Indian government for
improving the transmission network in India. PGCIL
which mainly owns and operates inter-state lines has
already made huge investments for the development of
inter-state networks and is managing these lines efficiently.”
On the other hand, the development of intra-state lines
is under progress with huge capex planned by many of the
SEBs. The sector is also witnessing enhanced private
participation. Further, in order to strengthen and upgrade
the transmission network numerous schemes like IPDS for
rural and semi-urban areas and DDUGJY for feeder
2. Feature - T&D Infrastructure
march 2017 POWER TODAYwww.PowerToday.in 45
“Total investment signifies an
opportunity of `97,200 crore”
Rattan Lal Labroo, Joint President - Power Group, Angelique
International Limited.
What impact will GoI’s ‘Power
for All’ initiative having on
the segment?
India, like any other developing
country,cannot overlook the pivotal
role of the power sector in fuelling
its overall development. Every
sector in an economy requires
constant and reliable supply of
electricity in order to function and
grow. With enough availability of
coal, power generation may not be a
concern today.Thus,the issue is that
all of the power generated does not
reach consumers due to the 25 per
cent leakage in Aggregate Technical
and Commercial (AT&C) losses.
GoI is focused on plugging this
leakage, which can be done by
privatising T&D to bring in
efficiency. More T&D assets are
expected to be privatised and
financiers could invest in creating
T&D platforms, expecting viable
opportunities to deploy capital.
How do you see the segment
panning out in FY17-18?
Despite enough generation,
India faces irregular power
availability across states. It all then
boils down to distribution. Thus,
while some states in the northern
and western parts of the country
have surplus power, some states in
the south face shortages.To counter
this, the NDA government, which
has made boosting power
generation a key policy priority, is
making all-out efforts to overhaul
the chain of distribution, and is
looking to supply adequate power at
affordable prices, with the aim of
doubling electricity generation to
two trillion units by 2019. The
Centre has set a target of bringing
24x7 ‘power for all’ by FY19. If the
government’s plan is to be achieved,
T&D investments have to come
through. Total T&D investment
envisioned in the 12th Five Year
Plan is Rs 4,860 billion, which
signifies an opportunity of Rs 972
billion for FY17.
(For full interview, log on to www.powertoday.in)
separation for agricultural populace have been devised.
A series of conducive policies and measures are rolled
out, as well as efforts are on towards achieving the mission
of ‘One Nation, One Grid, One Price’.
“Significant improvements are also transpiring on the
project execution front, resulting in lowering of the
execution time lines for T&D projects from the traditional
36 months to 12-18 months, which is a remarkable
achievement,” adds Kejriwal.
Financially Viability
TheviabilityofT&DinIndiaisdrivenbyaconglomerate
of factors. However one major aspect has been the drive to
sustain the annual GDP growth rate. To sustain the
envisaged annual GDP growth rate of around 8-9 per cent
over the next 20 years, it has been estimated that India will
be required to increase its electricity generation capacity
from the present ~180 GW to over 800 GW by 2032.
To this, Rattan Lal Labroo, Jt President - Power
Group, Angelique International Ltd says, “This would
require a matching upgradation and enhancement of the
electricity T&D segment, supported by a strong
manufacturing base of major equipment players, who have
catalysed the situation to a healthy financial prospective
which can offer good returns.”
On the ground level some factors still prevail, like the
pace of execution of some T&D projects which has been
impacted due to various factors such as ROW issues, end
users (like power plants) not being ready, etc., which lead to
In India, T&D losses account for as high as 23 per cent of the total
electricity generated
3. Feature - T&D Infrastructure
march 2017POWER TODAY46 www.PowerToday.in
delay in project completion schedules. This creates an
additional burden on the contractors by way of time and
cost overruns and mobilisation issues. There needs to be a
mechanism in place to resolve these ground level issues.
Kejriwal on his part feels, “GoI is conscious of the facts
and there have been changes in the approval processes for
environmental clearances, whereby the first stage approvals
have been eased. It is also imperative that we work with the
government to bring in a mechanism to fast track approvals
and easing other issues that cause delays in projects.”
Compensation levels have been enhanced for land cost
which has provided some relief on the land acquisition
issue. However, we also need to work towards improving
the credit standing of the end buyers such as SEBs, where
more thrust is required.
Kejriwal suggests warding projects by way of plug-and-
play mode where all the approvals are secured before the
project is awarded, adopting alternate and improved
technologies like gas insulated lines, etc.
The major cause for concern, which needs to be solved
on priority, is delays. Wherein adequate mechanism is
required to compensate owners and contractors for these
delays. If all these arbitrary issues are resolved, projects will
become financially viable.
Investments
Power Minister Piyush Goyal stated that PowerGrid
(PGCIL) has sought a loan assistance of $1,000 million
from ADB comprising of sovereign guaranteed loan of
$500 million and non-sovereign loan of $500 million; for
funding various transmission projects in the next three to
four years.
Meanwhile,the CEA has estimated that an expenditure
of `260,000 crore would be carried out during 2017-22 for
addition to transmission system capacity.
Inter-regional capacity addition during the 13th plan
(2017-22) is estimated at 45,700 MW, from the present
63,650 MW by the plan end, said CEA. The estimate is
that India would need 100,000 ckm of transmission lines
and 200,000 MVA transformer capacity of sub-stations at
220 kV and above voltage was expected to be added in
the 13th
Plan.
“The segment will showcase
significant growth in 2-3 years”
Vimal Kejriwal, MD & CEO, KEC International Ltd.
Kindly share your order book
and plans for FY 2017-18.
Our current order book is in
excess of `12,000 crore. Our Q3
PAT at `63 crore was up by 139 per
cent and Q3 EBITDA margin
increased to 9.26 per cent from 8
per cent, highest in the last 21
quarters. We continue to
consistently outperform on the
profitability front despite the
challenging economic scenario in
some of our markets over the last
few months, on the back of our
diversification and de-risking
strategy. Our strong order
book position and robust L1
pipeline gives us good visibility,
going ahead.
What are the projects you are
involved in?
We are involved in a significant
number of good and large value
projects in India and internationally.
We have footprint in 61+ countries
and are executing projects in 33+
countries. Major orders secured by
us this year include; `364 crore
order from KPTLC, EPC orders of
`629 crore for 765 kV and 400 kV
transmission lines from various
customers in India, `429 crore
turnkey 275 kV transmission line
order in Malaysia, `248 crore 500
kV transmission line order in
Egypt, `770 crore turnkey 220 kV
transmission line order in
Afghanistan, etc. We are also
growing rapidly in the GIS and
AIS. We have built/are building
around 70 sub-stations in both the
AIS and GIS space and have
deepened footprint in the
international sub-station market
including MENA, SAARC, Africa
and EAP as well as strengthened
our presence in the domestic
market. Some noteworthy projects,
endorsing our credentials in India
include completion of the 400 kV
transmission line for Indo-
Bangladesh cross border
interconnection five months ahead
of its scheduled completion time, in
record seven months, despite
numerous challenges including
logistics and severe monsoons.
(For full interview, log on to www.powertoday.in)
4. Feature - T&D Infrastructure
march 2017 POWER TODAYwww.PowerToday.in 47
It has suggested that investment be invited through
competitive bids. “It is expected that a total of 107,454 ckm
of transmission lines and 287,836 MVA of sub-station
transformation capacity additions are likely to be achieved
during the 12th
plan,” it has said. Various high capacity
transmissioncorridorsareinvariousstagesofimplementation
and most are likely to be commissioned by 2021.
With the new government revising the targets five
times, a secondary plan for solar parks was also drafted
along with revised transmission plan.According to industry
estimates, the cost of connecting 27 solar parks is close to
`55,000 crore. Last year, seven more parks were added,
taking the cumulative capacity to 19,900 MW, according
to MNRE.
Goyal informed parliament that under the framework
of cooperation between the Government of India and
Government of Germany, KfW, Germany is providing soft
loan to the tune of Euro 1 billion for the project.
A total sanction of $1,300 million (about `8,850 crore)
has been received from the World Bank, KFW, ADB and
NDB which will enable SBI, PNB, Canara Bank and
IREDA to fund such projects at an interest rate of less than
10 per cent.
Private Play
There is growing interest by private players too,although
PGCIL continues to be the largest player.The Tariff Based
Competitive Bidding (TBCB) route has provided a much
needed structural impetus to private players.
Adds Kejriwal, “We are witnessing some aggressive
bidding inTBCB projects and this is causing some concerns
to the banks in terms of returns on those projects, with the
project profitability always under pressure, due to the
intense competition.”
These networks are also being used by state discoms,
which is a cause for concern with regard to the credit ratings
of the end customer. However, there is clearly a lot of
interest, which is validated by way of recent investments
being made by some of the large private equity players in
some of these companies.
To this Labroo adds another dimension, as he feels that
increasingly more EPC contractors are considering PPP
projects safe because it is an annuity type product, which
has assured income streams. “Operating assets are more
lucrative because the construction risks are removed. Long-
term investors such as pension funds prefer these kinds of
annuity assets, he feels.
Techno Forward
With regard to technology,India is already migrating to
higher transmission voltages of up to 1,200 kV, working on
new technologies for bulk power transmission, has a fully
synchronised national grid, is developing high capacity
power transmission corridors (HCPTCs) and inter-
regional links for the grid, etc.
Specific to construction methodologies, modern and
highly mechanised construction techniques are gaining
traction, like the telescopic boom crane and gin poles
methodologies that are being adopted.
In addition, modern day digital disruptions are also
shaping the way projects are being executed; for example,
KEC recently used drones for stringing of power conductors
for a few projects, which resulted in a faster and safer
execution of these project.
PGCIL sought loan from ADB for the following
projects:
(i) HVDC Bipole link between western region (Raigarh,
Chhattisgarh) and southern region (Pugalur,
Tamil Nadu) - north Trichur (Kerala) - Scheme 1:
Raigarh-Pugalur 6,000 MW HVDC system.
(ii) HVDC Bipole link between western region (Raigarh,
Chhattisgarh) and southern region (Pugalur,
Tamil Nadu) - north Trichur (Kerala)- Scheme 3:
Pugalur- Trichur 2,000 MW VSC based HVDC
system.
(iii) Real time measurement/monitoring scheme.
(iv) Inter-state transmission system (ISTS) associated
with Green Energy Corridor (GEC) as under:
a) Ajmer (new) – Bikaner (new) 765 kV D/c,
b) Bikaner (new) – Moga (PG) 765 kV D/c,
c) LILO of one circuit of 400 kV Bhadla- Bikaner
(RVPN) line at Bikaner (new),
d) Establishment of 2x1,500 MVA, 765/400 kV S/s at
Bikaner (new).
Inter-regional capacity addition during the 13th plan (2017-22) is
estimated at 45,700 MW.
5. Feature - T&D Infrastructure
march 2017POWER TODAY48 www.PowerToday.in
Additionally, smart grid is like a revolution for the
electrical sector. States Amitkumar Panchal, Solution
Architect – Smart Grid, Landis + Gyr, “smart grids
can push a consumer to be more energy efficient, and help
him know how he can do more by using less of the
planet´s resources.”
As part of a smarter grid, the grids will be self-healing
grids, which will enable more reliable power distribution.
Utilities will be able to detect outages before the user
notices an outage and will be able heal the same faster.
This will benefit the common population of India, as with
more reliable distribution, the common public will get
better power.
Some older equipment that cannot be retrofitted to be
compatible with smart grid technologies will have to be
replaced. This may present a problem for utilities and
regulators since keeping equipment beyond its depreciated
life minimises the capital cost to consumers.
Inversely, the early retirement of equipment may be an
issue. Cost of implementing smart grids runs in crore
of rupees. It is very difficult to analyse the performance
and benefits of smart grids without actually
implementing them.
Overall, the major elements of any such projects should
include developing a smart grid vision, conducting
appropriate awareness to educate and develop a consensus,
identifying viable funding options and implementing
appropriate policy and regulatory actions to set common
standards and encourage innovation. These steps are
in development and the figures will be out once studies
are completed.
Impact of Renewables
To address the fluctuations in the renewable power
supply, GoI in 2013 announced a National Green Corridor
Programme (NGCP) worth `43,000 crore to enable the
flow of renewable energy into the national grid network.
Two green corridor transmission networks are proposed
Exhibit 01: Region Wise Split of Year Wise Capacity Addition of Transmission Lines at 400 kV Voltage in c.km
2412
1452
1979
2667
1898
1357
2789
2000
2500
3000
C.km
1051
1779
1401
787
235
647 640
1137
1290
16
1698
2437
2538
2077
251
0
500
1000
1500
2000
2500
3000
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
4239
3390
1760
1557
515654
903
1215 1273
218
4893
4293
2975 2840
733
0
1000
2000
3000
4000
5000
6000
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
1525
1651
1531
2733
2286
1386
2000
2500
3000
C.km
Northern Region Southern Region
Eastern Region
Western Region
Exhibit 01: Region Wise Split of Year Wise Capacity Addition of Transmission Lines at 400 kV Voltage in c.km
2412
1452
1266
1979
1238
255
446
91
810
4
2667
1898
1357
2789
1242
0
500
1000
1500
2000
2500
3000
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
1051
1779
1401
787
235
647 640
1137
1290
16
1698
2437
2538
2077
251
0
500
1000
1500
2000
2500
3000
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
4239
3390
1760
1557
515654
903
1215 1273
218
4893
4293
2975 2840
733
0
1000
2000
3000
4000
5000
6000
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
1202 1208
447
636 681
329
1525
460
1651
705
1531
2733
907
2286
1386
0
500
1000
1500
2000
2500
3000
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
Cental State Total
Source: Ministry of Power, PGCIL
Northern Region Southern Region
Eastern Region
Western Region
Region Wise Split of Year Wise Capacity Addition of Transmission Lines at 400 kV Voltage in c.km
Tecnology wise India is migrating to higher transmission voltages, working on bulk transmission and has a fully synchronised national grid.
6. Feature - T&D Infrastructure
march 2017POWER TODAY50 www.PowerToday.in
— JOCELYN FERNANDES
under the project - Firstly, construction of the inter-state
transmission network for connecting renewable energy-
rich states under Green Corridor-I will be completed.
Besides, Green Corridor-II for solar parks is also started
which is connecting solar parks in different states including
Andhra Pradesh, Madhya Pradesh, Karnataka, Rajasthan
and Gujarat.
MNRE sanctioned 34 solar parks of capacity 20,000
MW in 21 states are under various stages of execution.The
intra-state grid upgradation would be taken up by PGCIL,
while the inter-state network would be developed by the
state utilities.
Sector Outlook
India, like any other developing country, cannot
overlook the pivotal role of the power sector in fuelling its
overall development. Every sector in an economy requires
constant and reliable supply of electricity in order to
function and grow.
With enough availability of coal, power generation may
Green Corridor Transmission Network Plan
(i) HVDC Bipole link between Western Region (Raigarh,
Chhattisgarh) and Southern Region (Pugalur,
Tamil Nadu) - North Trichur (Kerala)- Scheme 1:
Raigarh-Pugalur 6000 MW HVDC System.
(ii) HVDC Bipole link between Western Region
(Raigarh, Chhattisgarh) and Southern Region
(Pugalur, Tamil Nadu) - North Trichur (Kerala)-
Scheme 3: Pugalur- Trichur 2000 MW VSC based
HVDC System.
not be a concern today. Thus, the issue is that all of the
power generated does not reach consumers due to the
25 per cent leakage in AggregateTechnical and Commercial
(AT&C) losses.
Adds Kejriwal, ‘Power for all’ and complete village
electrification by May 2018 would necessitate augmenting
T&D infrastructure. With dedicated efforts aimed towards
creating proper systems and structures, the T&D
architecture seems to be evolving and marching in the
right direction.”
GoI is also focused on plugging this leakage, which can
be done by privatising T&D to bring in efficiency. More
T&D assets are expected to be privatised and financiers
could invest in creating T&D platforms, expecting viable
opportunities to deploy capital.
Observes Labroo, “The Centre has set a target of
bringing 24x7 ‘power for all’ by fiscal 2019. If the
government’s power for all by FY19 is to be achieved,T&D
investments have to come through. Total T&D investment
envisioned in the 12th Five Year Plan is `4,860 billion,
which signifies an opportunity of `972 billion for FY17.”
Huge investments have been planned and massive
network interconnectivity is envisaged with focus on
affordability and reliability including substantial
expenditures being incurred by states for expanding the
intra-state transmission infrastructure in addition to
PGCIL having enhanced its Annual Capital Outlay to
`25,000 crore.These developments combined with reforms
like UDAY, which is expected to improve the liquidity
position of the discoms, augur well for the sector.
On the backdrop of these,the outlook is quite optimistic
and the segment is well poised to showcase significant
growth levels, two-three years down the line.
2412
1452
1266
1979
1238
255
446
91
810
4
2667
1898
1357
2789
1242
0
500
1000
1500
2000
2500
3000
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
1051
1779
1401
787
235
647 640
1137
1290
16
1698
2437
2538
2077
251
0
500
1000
1500
2000
2500
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
4239
3390
1760
1557
515654
903
1215 1273
218
4893
4293
2975 2840
733
0
1000
2000
3000
4000
5000
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
1202 1208
447
636 681
329
1525
460
1651
705
1531
2733
907
2286
1386
0
500
1000
1500
2000
2500
3000
FY'11 FY'12 FY'13 FY'14 FY'15
LengthinC.km
Cental State Total
Source: Ministry of Power, PGCIL
Eastern Region
Western Region
Region Wise Split of Year Wise Capacity Addition of Transmission Lines at 400 kV Voltage in c.km