INTRODUCTION
The Escravos Gas-to-Liquids facility (EGTL) converts
natural gas feed into high quality, environmentally
superior, liquid GTL fuel, naphtha, and LPG
products. The facility feed is approximately 320
million SCFD of natural gas and the facility
produces approximately 33,000 BPD of products.
The EGTL facility will be built on the north bank of
the Escravos River tidal outlet, in the Niger Delta
about 2 kilometers north of its confluence with the
Atlantic Ocean on the Bight of Benin,
approximately 100 nautical miles south east of
Lagos, and 37 nautical miles west of Warri,
Nigeria.
PROJECT SPECIFICATION
The EGTL facilities will be built adjacent to the
existing Escravos Terminal and Gas Plant. The
building site consists of a greenfield site, with the
existing environment consisting of man-grove and
freshwater elements, typical of brackish water
sources dominated by the sea, and geotechnically
very poor soil conditions. Chevron Nigeria Limited
selected a piled raft foundation for its plant
structures, and this was used as the basis for
defining the Dredging, Reclamation and
Dewatering Works. The work consisted of
dredging 3,000,000 m3
, hydraulic sandfill of 70
ha (max. 8 m thick), the installation of closely
spaced prefabricated drains, the lowering of the
water table over an area of approximately 30 ha
A
C
Project
SHEET
Escravos Gas to Liquids Project
Dredging, Reclamation and Dewatering Works
A	 Aerial view of EGTL site with adjacent Gas Plant and 		
	 proposed reclamation area
B	 Local employees
C	 Hydraulic fill in progress
D	 Waterway pumping ashore
features
Client Chevron Nigeria Limited
Location Escravos, Delta State, Nigeria
Period 2002 - 2006
Performed by Boskalis International bv
by active pumping and the installation of the necessary monitoring
instrumentation.
DREDGING AND HYDRAULIC FILL
The sand for the hydraulic fill was dredged by a large trailing suction hopper
dredger from a borrow area located offshore the Lekki Peninsula near Lagos.
From here the sand was transported over a distance of approximately 135
kilometers and dumped in a rehandle pit dredged previously near the
entrance of the Escravos River. Two medium-size trailer dredgers were used to
redredge the sand from the rehandle pit, transport it some 30 kilometers
B
D
Theinformationcontainedinthisdatasheetisforguidancepurposesonlyandmaybesubjecttochanges.©Boskalis.Allrightsreserved.
Royal Boskalis Westminster N.V.
PO Box 43
3350 AA Papendrecht
The Netherlands
T +31 78 69 69 000
F +31 78 69 69 555
royal@boskalis.com
www.boskalis.com
01—2012
upriver and subsequently pump it ashore at the
EGTL site. The entrance channel to the Escravos
River had to be deepened first to make this
approach possible. The dredging and reclamation
works were carried out between May 2002 and
July 2003, after which the period of monitoring,
dewatering and recharge started.
PREFORMED VERTICAL DRAINS
A total of approximately 7,000 km of preformed
vertical drains were installed, some to a depth of
17.5 m and some to a depth of 40 m. This
required a total of nine installation rigs mobilized
from both Europe and Singapore. This equip-ment
included four mega-rigs, each weighing over
100 tons.
DEWATERING AND RECHARGE SYSTEM
The area was raised at the location of the
pro-posed GTL plant with 8 m of sandfill. A
dewatering system consisting of 135 deep wells
was installed around this platform. The wells were
drilled to a level of 22 m with the screen in the
sand layer being located at between 16 m and
22 m. The purpose of the wells was to lower the
water pressure in the sand layer, accelerating the
consolidation process in the cohesive layers
overlying the sand. To control the lowering of the
Escravos Gas to Liquids Project
Dredging, Reclamation and Dewatering Works
water table near the existing plant, an additional line of 100 recharge wells
was situated at the refinery site.
ENHANCED CONSOLIDATION PROGRAM
The dewatering systems went into operation in 2003 and appeared to be
effective. However, the pressure drop in the center of the sandfill was less than
expected, especially in the rainy season. Consequently, the following
additional steps were taken in early 2005.
‚‚ An LDPE rain cover (350,000 m2
) was placed over the EGTL site to stop
rainwater entering the subsoil.
‚‚ A watertight Geolock cut-off wall (11,000 m2
) was installed around the
EGTL sandfill area to prevent the ingress of groundwater from the surround-
ing areas. This cut-off wall was designed and installed by Cofra, a Boskalis
associated company.
‚‚ An additional 101 dewatering wells were placed on and around the sand-
fill to accomplish extra draw-down in the centre of the area.
These additional measures proved to be very effective and resulted in an
increase in settlement of more than 0.50 m in less than 6 months. The final
overall settlement of the EGTL site amounted to approximately 4.85 m. The
over-all contract was satisfactorily concluded on March 31, 2006.
DESIGN ENGINEERING
For the Escravos Gas to Liquid project, Hydronamic (the Boskalis in-house
engineering consultancy) performed extensive engineering in order to
optimize the overall design of the dewatering, and of the fill and drainage
operations. Hydronamic also monitored stability, settlement and environmental
impact during and after construction.
G
F
E
H
E	Installation of the vertical barrier
F	 Dewatering system
G	Installation of the vertical drains
H	EGTL site after completed ECP works

More Related Content

What's hot

LIGHT WEIGHT AND DUCTILE SLURRY FOR PRODUCTION CASING
LIGHT WEIGHT AND DUCTILE SLURRY FOR PRODUCTION CASINGLIGHT WEIGHT AND DUCTILE SLURRY FOR PRODUCTION CASING
LIGHT WEIGHT AND DUCTILE SLURRY FOR PRODUCTION CASINGManuel S. Navarro
 
ARM Casper case study-LR
ARM Casper case study-LRARM Casper case study-LR
ARM Casper case study-LRNeil McCarthy
 
Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportHonolulu Civil Beat
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606 Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606
John M Riggs
 
Company Profile Jan De Nul Group (EN) - V2015-3
Company Profile Jan De Nul Group (EN) - V2015-3Company Profile Jan De Nul Group (EN) - V2015-3
Company Profile Jan De Nul Group (EN) - V2015-3Séamus Day
 
Feb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress ReportFeb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress ReportHonolulu Civil Beat
 
The Marcellus Shale: Environmental Issues for Landowners
The Marcellus Shale: Environmental Issues for LandownersThe Marcellus Shale: Environmental Issues for Landowners
The Marcellus Shale: Environmental Issues for Landowners
Dan Arthur
 
MEG Energy - Canada
MEG Energy - CanadaMEG Energy - Canada
MEG Energy - Canada
GeoTechInsider
 
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Michael Hewitt, GISP
 
Great Resource All About Shale Oil
Great Resource All About Shale OilGreat Resource All About Shale Oil
Great Resource All About Shale OilDavid Crace
 
Formate matters-issue-7
Formate matters-issue-7Formate matters-issue-7
Formate matters-issue-7
John Downs
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
FHRahman1
 
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr DriveStorm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Fairfax County
 
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Iwl Pcu
 
Solution Bonaveture
Solution BonavetureSolution Bonaveture
Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015
Terry Aylward
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
IEI GSC
 

What's hot (20)

LIGHT WEIGHT AND DUCTILE SLURRY FOR PRODUCTION CASING
LIGHT WEIGHT AND DUCTILE SLURRY FOR PRODUCTION CASINGLIGHT WEIGHT AND DUCTILE SLURRY FOR PRODUCTION CASING
LIGHT WEIGHT AND DUCTILE SLURRY FOR PRODUCTION CASING
 
ARM Casper case study-LR
ARM Casper case study-LRARM Casper case study-LR
ARM Casper case study-LR
 
Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily Report
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606 Elgin Country Estate Project Summary as on 20160606
Elgin Country Estate Project Summary as on 20160606
 
Mc Knight Sess13 102309
Mc Knight Sess13 102309Mc Knight Sess13 102309
Mc Knight Sess13 102309
 
Company Profile Jan De Nul Group (EN) - V2015-3
Company Profile Jan De Nul Group (EN) - V2015-3Company Profile Jan De Nul Group (EN) - V2015-3
Company Profile Jan De Nul Group (EN) - V2015-3
 
Feb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress ReportFeb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress Report
 
The Marcellus Shale: Environmental Issues for Landowners
The Marcellus Shale: Environmental Issues for LandownersThe Marcellus Shale: Environmental Issues for Landowners
The Marcellus Shale: Environmental Issues for Landowners
 
MEG Energy - Canada
MEG Energy - CanadaMEG Energy - Canada
MEG Energy - Canada
 
RHowell_project summaries
RHowell_project summariesRHowell_project summaries
RHowell_project summaries
 
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
Hank Zielinski, Northhampton Generating Company, “Excellence in Surface Coal ...
 
Great Resource All About Shale Oil
Great Resource All About Shale OilGreat Resource All About Shale Oil
Great Resource All About Shale Oil
 
Formate matters-issue-7
Formate matters-issue-7Formate matters-issue-7
Formate matters-issue-7
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr DriveStorm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
 
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
 
Solution Bonaveture
Solution BonavetureSolution Bonaveture
Solution Bonaveture
 
Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 

Viewers also liked

Presentación cortezamotora
Presentación cortezamotoraPresentación cortezamotora
Presentación cortezamotora
Emma Bucio
 
Especificaciones tareas 12 14
Especificaciones tareas 12 14Especificaciones tareas 12 14
Especificaciones tareas 12 14
mikahakki44
 
Reales de plata de Juan I de Castilla
Reales de plata de Juan I de CastillaReales de plata de Juan I de Castilla
Reales de plata de Juan I de Castilla
Rafa Dzcr
 
SA Math competition.PDF
SA Math competition.PDFSA Math competition.PDF
SA Math competition.PDFWan Yee Lo
 
SunnyMinutes presentation
SunnyMinutes presentationSunnyMinutes presentation
SunnyMinutes presentation
peterkomar-hu
 
청주오피℡분당오피방[[다솜넷]]부평오피걸o선릉역안마H서초건마
청주오피℡분당오피방[[다솜넷]]부평오피걸o선릉역안마H서초건마청주오피℡분당오피방[[다솜넷]]부평오피걸o선릉역안마H서초건마
청주오피℡분당오피방[[다솜넷]]부평오피걸o선릉역안마H서초건마
dasom12net06
 
Poissons equation
Poissons equationPoissons equation
Poissons equation
Amit Kumar Mohapatra
 
Representation
RepresentationRepresentation
Representationetaylorchs
 
BI 2005 - Caso de excito COPSA y Tarjetas Sin Contacto Mifare
BI 2005 - Caso de excito COPSA y Tarjetas Sin Contacto MifareBI 2005 - Caso de excito COPSA y Tarjetas Sin Contacto Mifare
BI 2005 - Caso de excito COPSA y Tarjetas Sin Contacto Mifare
Mario Guedes de Rezende
 
Social media case study of Strepsils Campaign - Ab Montu Bolega
Social media case study of Strepsils Campaign - Ab Montu BolegaSocial media case study of Strepsils Campaign - Ab Montu Bolega
Social media case study of Strepsils Campaign - Ab Montu Bolega
Moses Gomes
 
Anthropology of the Body
Anthropology of the BodyAnthropology of the Body
Anthropology of the Body
jessievarquezjr1
 
Philippine anthropology
Philippine anthropologyPhilippine anthropology
Philippine anthropology
jessievarquezjr1
 
Resume - Sumit Jindal
Resume - Sumit JindalResume - Sumit Jindal
Resume - Sumit JindalSUMIT JINDAL
 
Online Shop SEO Audits mit Screaming Frog & URL Profiler | SEO Campixx 2016
Online Shop SEO Audits mit Screaming Frog & URL Profiler | SEO Campixx 2016Online Shop SEO Audits mit Screaming Frog & URL Profiler | SEO Campixx 2016
Online Shop SEO Audits mit Screaming Frog & URL Profiler | SEO Campixx 2016
Mario Träger
 

Viewers also liked (16)

Presentación cortezamotora
Presentación cortezamotoraPresentación cortezamotora
Presentación cortezamotora
 
Especificaciones tareas 12 14
Especificaciones tareas 12 14Especificaciones tareas 12 14
Especificaciones tareas 12 14
 
Reales de plata de Juan I de Castilla
Reales de plata de Juan I de CastillaReales de plata de Juan I de Castilla
Reales de plata de Juan I de Castilla
 
SA Math competition.PDF
SA Math competition.PDFSA Math competition.PDF
SA Math competition.PDF
 
SunnyMinutes presentation
SunnyMinutes presentationSunnyMinutes presentation
SunnyMinutes presentation
 
청주오피℡분당오피방[[다솜넷]]부평오피걸o선릉역안마H서초건마
청주오피℡분당오피방[[다솜넷]]부평오피걸o선릉역안마H서초건마청주오피℡분당오피방[[다솜넷]]부평오피걸o선릉역안마H서초건마
청주오피℡분당오피방[[다솜넷]]부평오피걸o선릉역안마H서초건마
 
presentationrentalpet
presentationrentalpetpresentationrentalpet
presentationrentalpet
 
Poissons equation
Poissons equationPoissons equation
Poissons equation
 
Representation
RepresentationRepresentation
Representation
 
Oresund
OresundOresund
Oresund
 
BI 2005 - Caso de excito COPSA y Tarjetas Sin Contacto Mifare
BI 2005 - Caso de excito COPSA y Tarjetas Sin Contacto MifareBI 2005 - Caso de excito COPSA y Tarjetas Sin Contacto Mifare
BI 2005 - Caso de excito COPSA y Tarjetas Sin Contacto Mifare
 
Social media case study of Strepsils Campaign - Ab Montu Bolega
Social media case study of Strepsils Campaign - Ab Montu BolegaSocial media case study of Strepsils Campaign - Ab Montu Bolega
Social media case study of Strepsils Campaign - Ab Montu Bolega
 
Anthropology of the Body
Anthropology of the BodyAnthropology of the Body
Anthropology of the Body
 
Philippine anthropology
Philippine anthropologyPhilippine anthropology
Philippine anthropology
 
Resume - Sumit Jindal
Resume - Sumit JindalResume - Sumit Jindal
Resume - Sumit Jindal
 
Online Shop SEO Audits mit Screaming Frog & URL Profiler | SEO Campixx 2016
Online Shop SEO Audits mit Screaming Frog & URL Profiler | SEO Campixx 2016Online Shop SEO Audits mit Screaming Frog & URL Profiler | SEO Campixx 2016
Online Shop SEO Audits mit Screaming Frog & URL Profiler | SEO Campixx 2016
 

Similar to Escravos

Abg basal drainage_and_slope_veneer_retention_pozidrain_and_erosaweb_shetland...
Abg basal drainage_and_slope_veneer_retention_pozidrain_and_erosaweb_shetland...Abg basal drainage_and_slope_veneer_retention_pozidrain_and_erosaweb_shetland...
Abg basal drainage_and_slope_veneer_retention_pozidrain_and_erosaweb_shetland...
ssuser8a213e1
 
Australia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project ManagerAustralia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project ManagerNiels Asjee
 
Australia - Ichthys GEP Project - Project Manager
Australia - Ichthys GEP Project - Project ManagerAustralia - Ichthys GEP Project - Project Manager
Australia - Ichthys GEP Project - Project ManagerNiels Asjee
 
Bro mining minerals_tcm29-33179
Bro mining minerals_tcm29-33179Bro mining minerals_tcm29-33179
Bro mining minerals_tcm29-33179pjgomezd
 
Hunda tolina irrigation problems of Tana bales irrigation project
Hunda tolina irrigation problems of Tana bales irrigation projectHunda tolina irrigation problems of Tana bales irrigation project
Hunda tolina irrigation problems of Tana bales irrigation project
Tana Bales sugar Factory
 
Melbourne Channel Deepening
Melbourne Channel DeepeningMelbourne Channel Deepening
Melbourne Channel DeepeningSikko Krol
 
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...Niels Asjee
 
Marine_Brochure_For_Web
Marine_Brochure_For_WebMarine_Brochure_For_Web
Marine_Brochure_For_WebMike Bisland
 
Abberton ICE Meeting
Abberton ICE MeetingAbberton ICE Meeting
Abberton ICE Meeting
ICEEssex
 
Exploration and production, Sigve Hamilton Aspelund
Exploration and production, Sigve Hamilton AspelundExploration and production, Sigve Hamilton Aspelund
Exploration and production, Sigve Hamilton Aspelund
Sigve Hamilton Aspelund
 
Red – dead sea conveyance
Red – dead sea conveyanceRed – dead sea conveyance
Red – dead sea conveyance
Ahmed Marei
 
Coastal regulation zone
Coastal regulation zoneCoastal regulation zone
Coastal regulation zone
Vaishnavi Bargotra
 
Revista en ingles miguel lugo
Revista en ingles miguel lugoRevista en ingles miguel lugo
Revista en ingles miguel lugo
MiguelLugo42
 
Perth Seawater Desalination Plant - serving 2 mln of people with drinking water
Perth Seawater Desalination Plant - serving 2 mln of people with drinking waterPerth Seawater Desalination Plant - serving 2 mln of people with drinking water
Perth Seawater Desalination Plant - serving 2 mln of people with drinking water
SUEZ Australia & New Zealand
 
Water management
Water managementWater management
Water management
SNC-Lavalin
 

Similar to Escravos (20)

Abg basal drainage_and_slope_veneer_retention_pozidrain_and_erosaweb_shetland...
Abg basal drainage_and_slope_veneer_retention_pozidrain_and_erosaweb_shetland...Abg basal drainage_and_slope_veneer_retention_pozidrain_and_erosaweb_shetland...
Abg basal drainage_and_slope_veneer_retention_pozidrain_and_erosaweb_shetland...
 
Australia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project ManagerAustralia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project Manager
 
Australia - Ichthys GEP Project - Project Manager
Australia - Ichthys GEP Project - Project ManagerAustralia - Ichthys GEP Project - Project Manager
Australia - Ichthys GEP Project - Project Manager
 
Bro mining minerals_tcm29-33179
Bro mining minerals_tcm29-33179Bro mining minerals_tcm29-33179
Bro mining minerals_tcm29-33179
 
SPE-132931-MS
SPE-132931-MSSPE-132931-MS
SPE-132931-MS
 
Hunda tolina irrigation problems of Tana bales irrigation project
Hunda tolina irrigation problems of Tana bales irrigation projectHunda tolina irrigation problems of Tana bales irrigation project
Hunda tolina irrigation problems of Tana bales irrigation project
 
Melbourne Channel Deepening
Melbourne Channel DeepeningMelbourne Channel Deepening
Melbourne Channel Deepening
 
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
 
Marine_Brochure_For_Web
Marine_Brochure_For_WebMarine_Brochure_For_Web
Marine_Brochure_For_Web
 
Abberton ICE Meeting
Abberton ICE MeetingAbberton ICE Meeting
Abberton ICE Meeting
 
Exploration and production, Sigve Hamilton Aspelund
Exploration and production, Sigve Hamilton AspelundExploration and production, Sigve Hamilton Aspelund
Exploration and production, Sigve Hamilton Aspelund
 
Red – dead sea conveyance
Red – dead sea conveyanceRed – dead sea conveyance
Red – dead sea conveyance
 
www homepage SBM_1
www homepage SBM_1www homepage SBM_1
www homepage SBM_1
 
WST-WSTWS-EM11803
WST-WSTWS-EM11803WST-WSTWS-EM11803
WST-WSTWS-EM11803
 
Coastal regulation zone
Coastal regulation zoneCoastal regulation zone
Coastal regulation zone
 
Revista en ingles miguel lugo
Revista en ingles miguel lugoRevista en ingles miguel lugo
Revista en ingles miguel lugo
 
Perth Seawater Desalination Plant - serving 2 mln of people with drinking water
Perth Seawater Desalination Plant - serving 2 mln of people with drinking waterPerth Seawater Desalination Plant - serving 2 mln of people with drinking water
Perth Seawater Desalination Plant - serving 2 mln of people with drinking water
 
Water management
Water managementWater management
Water management
 
Coastline2
Coastline2Coastline2
Coastline2
 
Coastline
CoastlineCoastline
Coastline
 

Escravos

  • 1. INTRODUCTION The Escravos Gas-to-Liquids facility (EGTL) converts natural gas feed into high quality, environmentally superior, liquid GTL fuel, naphtha, and LPG products. The facility feed is approximately 320 million SCFD of natural gas and the facility produces approximately 33,000 BPD of products. The EGTL facility will be built on the north bank of the Escravos River tidal outlet, in the Niger Delta about 2 kilometers north of its confluence with the Atlantic Ocean on the Bight of Benin, approximately 100 nautical miles south east of Lagos, and 37 nautical miles west of Warri, Nigeria. PROJECT SPECIFICATION The EGTL facilities will be built adjacent to the existing Escravos Terminal and Gas Plant. The building site consists of a greenfield site, with the existing environment consisting of man-grove and freshwater elements, typical of brackish water sources dominated by the sea, and geotechnically very poor soil conditions. Chevron Nigeria Limited selected a piled raft foundation for its plant structures, and this was used as the basis for defining the Dredging, Reclamation and Dewatering Works. The work consisted of dredging 3,000,000 m3 , hydraulic sandfill of 70 ha (max. 8 m thick), the installation of closely spaced prefabricated drains, the lowering of the water table over an area of approximately 30 ha A C Project SHEET Escravos Gas to Liquids Project Dredging, Reclamation and Dewatering Works A Aerial view of EGTL site with adjacent Gas Plant and proposed reclamation area B Local employees C Hydraulic fill in progress D Waterway pumping ashore features Client Chevron Nigeria Limited Location Escravos, Delta State, Nigeria Period 2002 - 2006 Performed by Boskalis International bv by active pumping and the installation of the necessary monitoring instrumentation. DREDGING AND HYDRAULIC FILL The sand for the hydraulic fill was dredged by a large trailing suction hopper dredger from a borrow area located offshore the Lekki Peninsula near Lagos. From here the sand was transported over a distance of approximately 135 kilometers and dumped in a rehandle pit dredged previously near the entrance of the Escravos River. Two medium-size trailer dredgers were used to redredge the sand from the rehandle pit, transport it some 30 kilometers B D
  • 2. Theinformationcontainedinthisdatasheetisforguidancepurposesonlyandmaybesubjecttochanges.©Boskalis.Allrightsreserved. Royal Boskalis Westminster N.V. PO Box 43 3350 AA Papendrecht The Netherlands T +31 78 69 69 000 F +31 78 69 69 555 royal@boskalis.com www.boskalis.com 01—2012 upriver and subsequently pump it ashore at the EGTL site. The entrance channel to the Escravos River had to be deepened first to make this approach possible. The dredging and reclamation works were carried out between May 2002 and July 2003, after which the period of monitoring, dewatering and recharge started. PREFORMED VERTICAL DRAINS A total of approximately 7,000 km of preformed vertical drains were installed, some to a depth of 17.5 m and some to a depth of 40 m. This required a total of nine installation rigs mobilized from both Europe and Singapore. This equip-ment included four mega-rigs, each weighing over 100 tons. DEWATERING AND RECHARGE SYSTEM The area was raised at the location of the pro-posed GTL plant with 8 m of sandfill. A dewatering system consisting of 135 deep wells was installed around this platform. The wells were drilled to a level of 22 m with the screen in the sand layer being located at between 16 m and 22 m. The purpose of the wells was to lower the water pressure in the sand layer, accelerating the consolidation process in the cohesive layers overlying the sand. To control the lowering of the Escravos Gas to Liquids Project Dredging, Reclamation and Dewatering Works water table near the existing plant, an additional line of 100 recharge wells was situated at the refinery site. ENHANCED CONSOLIDATION PROGRAM The dewatering systems went into operation in 2003 and appeared to be effective. However, the pressure drop in the center of the sandfill was less than expected, especially in the rainy season. Consequently, the following additional steps were taken in early 2005. ‚‚ An LDPE rain cover (350,000 m2 ) was placed over the EGTL site to stop rainwater entering the subsoil. ‚‚ A watertight Geolock cut-off wall (11,000 m2 ) was installed around the EGTL sandfill area to prevent the ingress of groundwater from the surround- ing areas. This cut-off wall was designed and installed by Cofra, a Boskalis associated company. ‚‚ An additional 101 dewatering wells were placed on and around the sand- fill to accomplish extra draw-down in the centre of the area. These additional measures proved to be very effective and resulted in an increase in settlement of more than 0.50 m in less than 6 months. The final overall settlement of the EGTL site amounted to approximately 4.85 m. The over-all contract was satisfactorily concluded on March 31, 2006. DESIGN ENGINEERING For the Escravos Gas to Liquid project, Hydronamic (the Boskalis in-house engineering consultancy) performed extensive engineering in order to optimize the overall design of the dewatering, and of the fill and drainage operations. Hydronamic also monitored stability, settlement and environmental impact during and after construction. G F E H E Installation of the vertical barrier F Dewatering system G Installation of the vertical drains H EGTL site after completed ECP works