Preservation guidelines
• Maintaining the traditional character of the block;
• Maintaining the informal nature of the streets, lanes,
  and gardens where they exist;
• Maintaining the soft edges found along neighborhood
  streets; and
• Encouraging informal gardens throughout the
  neighborhood.
Neighborhood Strategic Plan
• Encouraging the use of rain barrels and greywater
  recycling;
• Supporting community gardens; and
• Identifying future pocket park locations.
Beaufort’s Block by Block Green Infrastructure
Northwest Quadrant Conceptual Design

What is Green Infrastructure?
Stormwater management strategy that uses natural hydrologic
features to manage water and provide environmental and
community benefits.


    How do we make this…         function more like this?
Green Infrastructure

          Under Natural
        Conditions Runoff is   ....But increases After
            Limited....             Development




                                                  5
Beaufort’s Block by Block Green Infrastructure
Northwest Quadrant Conceptual Design

What is Green Infrastructure?
Stormwater management strategy that uses natural hydrologic
features to manage water and provide environmental and
community benefits.


    How do we make this…         function more like this?
Green Infrastructure - Multiple Benefits


                      Water quality           Cost savings
                      Flood and               Community identity
                       hydromodification       Recreational
                       control                  greenspace
                      Rainwater capture and  Reduced urban heat
                       use                     island effect
                      Increased groundwater  Wildlife habitat
                       recharge and baseflow  Enhanced property
                      Improved air quality      values
                      Reduced energy          Carbon sequestering
                       consumption             Aesthetic benefits
Multiple Benefits

                Category                    Indicator
                           Reduced Stormwater Volume
Environmental              Reduced Peak Flow Rate
                           Reduced Pollutant Loading
                           Increased Groundwater Recharge
                           Reduced Energy Use and Heat Island Effect
                           Reduced Particulate Matter
                           Increased Carbon Sequestration
                           Improved Quality of Life and Aesthetics
Social
                           Increased Recreational Opportunities
                           Job Creation
                           Reduced Infrastructure Costs
Economic
                           Reduced Pumping Costs
                           Increased or Stabilized Property Values
Economic Benefits
Economic Benefits
Effects of Water Pollution




                             Photo courtesy of NRCS
BMP Functions


                                         Hydrologic
                                          controls                                                       Removal processes




                                                                    Evapotranspiration
                               or flow attenuation




                                                                                                                                              Biotransformation/
                               Storage/detention




                                                                                                                                              phytoremediation
                                                                                                                            Bioaccumulation




                                                                                                                                                                   volatilization)
                                                                                                                                                                   photolysis;
                                                                                                                                                                   Other (e.g.,
                                                     Infiltration




                                                                                                    Filtration

                                                                                                                 Sorption
                                                                                         Settling
 Structural BMPs
 Bioretention                       +                (+)             o                   o          +            o          +                      +                   (o)
 Permeable pavement                 +                (+)             –                   –          +            –          –                      –                    –
 Infiltration basin                 +                 +             (o)                  o          +            o          +                      +                   (o)
 Cisterns/rain barrels              +                 –              –                   –          –            –          –                      –                    –
 Note: ( ) optional function; + major function; o secondary function; – insignificant function
BMP Design

  Bioretention
     Bioswales
     Planter Boxes
  Permeable Pavement
  Green Roofs
  Water Harvesting
     Cisterns
     Rain Barrels
  Sand Filters
  Vegetated Swales
  Vegetated Filter Strips
Bioretention Areas
Bioretention Schematic
                               Runoff
       Vegetation on Surface


                Media




Underdrain System
Bioretention Areas

   Pollutant removal functions
    Sedimentation (temporary)
       Trash, TSS, Phosphorus
    Microbial Processes
       Nitrogen, Pathogens
    Chemical Processes
       Metals, Phosphorus
    Exposure to Sunlight & Dryness
       Pathogens, Oil & Grease
Bioretention Areas
• Soil Media Depth
Where are pollutants removed?   TSS
                                TP
                                Temp
                                TN
                                Pathogens
                                Metals
                                Oil & Grease
Bioretention Areas




            www.bae.ncsu.edu/stormwater
Integrating into Landscape




                    www.bae.ncsu.edu/stormwater
Integrating into Landscape
Parking Lots




                                         Port City
                                         Java, Market
               www.bae.ncsu.edu/stormwater
Parking Lots




               www.bae.ncsu.edu/stormwater
www.bae.ncsu.edu/stormwater
www.bae.ncsu.edu/stormwater
Bioretention Areas
                     + 4 Hours
                                 +14 Hours
Bioretention Areas

 Mulch and Vegetation
    Drought tolerant vegetation
    Periodic inundation
    Native species
 Consider size and appearance at maturity
Bioretention Variations

 Bioswales
Bioretention Variations

 Transportation Corridor
    Right-of-way
Permeable Pavement

  Allows for rainfall
   infiltration
  Low traffic surfaces
   (driveways, parking
   lots, walk ways)
  Provides peak flow
   mitigation, volume
   storage, and some water
   quality improvement
Permeable Pavements

   Permeable Interlocking
    Concrete Pavers (PICP)

   Concrete Grid Pavers (CGP)

   Pervious (Porous)
    Pavements (PC & PA)

   Plastic Reinforcing Grids
    (PG)
Permeable Pavement
Permeable Pavement
Store/Treat the design storm volume
   within base and sub-base reservoirs
       • d=V/A×n
          –   d = Gravel Layer Depth (ft)
          –   V = Water Quality Volume
          –   A = Surface Area (square ft)
          –   n = Porosity (0.3 to 0.4)
 Structural Design
  
  •   Total traffic Guide for Design of Pavement Structures
        AASHTO
     In situ soil strength
        (1993)
  •
     Environmental elements to the Guide for Design of
        AASHTO Supplement
     Bedding and Structures (1998)
        Pavement reservoir layer design
  •    AASHTO Flexible Pavement Method
Permeable Pavement


 These systems should be installed by a qualified
  professional
      • The only exception is very small backyard patios where BMP
        failure will not be hazardous to human health
      • A list of professionals qualified in permeable paver installation is
        available through the Interlocking Concrete Pavement Institute
        (ICPI) – www.icpi.org
      • More information on pervious concrete is available through the
        Carolina Ready Mixed Concrete Association (CRMCA) –
        www.crmca.com
Permeable Pavement
Permeable Pavement




                     6 inches pervious concrete



                     Washed no 57 stone (Min 6”)
Permeable Pavement




 6 in

  6-9 in

12-18 in
Permeable Pavement


                          Grid Pavers
                     Sand
                               PICP with gravel fill
   Washed No. 57 Stone



Interlocking Concrete Pavers
            Pea Gravel
    Washed No. 57 Stone
Permeable Pavement
Permeable Pavement




   6 in

   6-9 in

 12-18 in
Permeable Pavement
Permeable Pavement
Permeable Pavement
Permeable Pavement
Permeable Pavement
Permeable Pavement
Permeable Pavement
Vegetated Infiltration Basin
Vegetated Infiltration Basin
Vegetated Infiltration Basin
Photo credit: Jill Bicknell, Santa Clara Valley Urban Runoff Program.
Stormwater Wetlands

 Reduce  Nutrients
 Slow Flow of Water
Stormwater Wetlands
Stormwater Wetlands
Stormwater Wetlands
Stormwater Wetlands
Stormwater Wetlands


A Diverse System of
  Herbaceous Plants tends
  to limit mosquito
  population
Human Introduction of
  Gambousia affinis NOT
  recommended



                      www.bae.ncsu.edu/stormwater
Multi-Benefit Use
Beaufort’s Block by Block Green Infrastructure
Northwest Quadrant Conceptual Design
Beaufort’s Block by Block Green Infrastructure
Northwest Quadrant Conceptual Design

                                                                                US Marine Corps Air Station                                           Golf Professionals Club
                    Laurel Bay

                                        116

                                                                                      Beaufort Northwest Quadrant                                              802

                                                                                            Project Location



                                                          Burton
                                                                                                                    Beaufort
                                                                     Beaufort
                                                                           280

                                                                                                                                                                21
                                                                                                                                      281

                                              170




                                                         802




                                                                                                               Port Royal
       Legend
                                                                                                                          Par is
          Project Location                          Shell Point
                                                                                                    M ale co




          Northwest Quadrant Boundary
                                                                                                        n




          City of Beaufort Limits
          Highway
                                                                                                               Marine Corps Recruit Depot
          Major Road
                                                                                                         Parris Island
          Railroads (Local)
          Lake/Pond/Stream/River
                                                                                                                                   City of Beaufort
          Swamp/Marsh                                0         0.5     1                 2
                                                                                          Miles                                    South Carolina
          Cities
                                                                                                                                   Project Location
Beaufort’s Block by Block Green Infrastructure                                                                                                                                                                            BOUNDARY ST



Northwest Quadrant Conceptual Design




                                                                                                                                                                                         WILMINGTO N ST
                                                                            UNION ST
                                                                                                                     BA
                                                                                                                       GG
                                                                                                                              ET                                                        CONGRES S ST
                                                                                                                                 T            ST




                                                                                                                                                        BLADEN ST




                                                                                                                                                                                                                                        CHURCH ST
                                                                                                                                                                                                                           GREENE ST
                                                    RIBAU T RD




                                                                                                    Northwest




                                                                                                                                                                          MONSON ST




                                                                                                                                                                                                                                                    NEWCASTLE ST
                      D




                                                                                                                                                       WASHINGTON ST
             MARS H R




                                                                                                                   HAMAR ST
                                                                                                    Quadrant




                                                                                                                                                                                                          HARRINGTON ST
                                                                                                     Beaufort                                                         DUKE ST




                                                                                                                               ADVENTURE ST
                                                                                                                                                                                      BLADEN LN


                                                                                                                                                                                                                           PRINCE ST

                                                                                                                                                                                      ELTON LN
                                                                                         PILOT ST




                                                     KING ST
                                                                                                                                                                                                                                                    KING ST
                                                                 EUHAW ST



                                                                              GLEBE ST
                          HEYWARD ST
 WAIGHT ST




                                                                                                        NORTH ST                                                                                                            NORTH ST




                                                                                                        T
                                                                                                      YS                                                                                                                                                           CRAVEN ST
                                                                                                    BA

                                                                                                                                                                                                                                                                    Historic
                                               ST
                                                                                                                                                                                                                                                                   Downtown
                                       SIM
                                          MS                                                                                                       Beaufort River                                                                                                   Beaufort
                                               T        RD
                                            PO
                                          DE



 Legend
                                                                                                                                                                      City of Beaufort
                     Streets                                                              0           200    400              800
                                                                                                                                Feet                                  South Carolina
                     Northwest Quadrant Boundary
                                                                                                                                                                    Northwest Quadrant
Charrette Process


   Work session with director and staff
   Site selection and preliminary concept plans
   Presentations to staff and officials
   Final concept plans and report
   Final presentation
Implementation


 Regulating Plan
    T3 Neighborhood General
    T4 Urban Neighborhood and Neighborhood Center
    T5 Urban Center/Corridor
 Localized Improvements
 Public Right of Way and Block Level Solutions
Transects


 Integration of Green Infrastructure techniques into
  the planning and development process
 Consistent, predictable costs and performance, and
  replicable results
 Adaptable to local conditions
 Ancillary benefits and values
    Aesthetics, identity, energy…..
Localized Improvements


   Correct drainage issues
   Improve streetscape and reduce maintenance
   Create community value
   Demonstrate progress
   Planned and Constructed incrementally
Project Criteria




                                                                                                                  s
                                                                          ment




                                                                                                             nsect




                                                                                                                                                             t
                                                                                                                                                        enefi
                                                                    prove




                                                                                                                      Techn ration of
                                                                                                      of T ra




                                                                                                                                                                           ts
                                                                                                                                                  ood B



                                                                                                                                                                           fi
                                                                                                                                                                       Bene
                                                                                        lity
                                                             age Im




                                                                                                                           ology
                                                                                                          n
                                                                                  r Q ua




                                                                                                                                             bor h
                                                                                                    ra tio



                                                                                                                           nst




                                                                                                                                                                       la ry
                                                                                                                      Demo



                                                                                                                                        Neigh
                                                       Dr ain




                                                                                 Wate



                                                                                               Integ




                                                                                                                                                                 Ancil
Candidate Project/Transects
Section 8 Housing Church and Washington Streets                    ○                                  ○                    ○                                           
Private Lot between Prince and Hamar                               ●                    ●              ○                                        ●                        ●
Glebe Street Extension                                             ●                    ●                                                      ●                       
Stormwater Dry Pond Hamar and Washington                           ○                                  ○                                        ●                        ●
Green Street along Pilot from Prince to North Street
Connection of Duke and Princeton                                   ○                                                                          ●                        ●
Duke Street from Bladen to Pilot Street                            ●                    ●              ●                                                                ●
Candidate Improvements
Bump Outs for Tree Space                                           ●                    ●                                                      ●                        ●
Vegetated Curb Extensions                                          ●                    ●                                                      ●                        ●
Residential on-lot Permeable Pavement                              ●                    ●              ●                                        ●                        ●
T3 – Neighborhood
T3 – Neighborhood
T4 – Neighborhood Center
T4 – Neighborhood Center
T5 – Urban Corridor/Center
T5 – Urban Corridor/Center
20
                      15
                                           BAGGETT ST




                                                                                     HAMAR ST
UNION ST




                                                                                                20
                                                          GREENE ST




                                      20
                           20




                                                                                                                                                          25
     20


                                                                                                                                         WASHINGTON ST



                                                     20




                                                                                                                     20
                                                                                DUKE ST




                                                                                                     ADVENTURE ST
                           15




             Legend
                                Storm Sewers
                                                                                                                                           PRINCE ST
                                Streets




                                                                                                                                              BLADEN ST
                                Duke Street Catchment
                                                                                                                    Proposed Vegetated
                                15




                                Basin Catchment                                                            20
                                                                            Beaufort
                                Parcels                                                                             Infiltration Basin
                                                                           Elementary
                                               PILOT ST




             Elevation, ft
                                5   KING ST                                  School                                            KING ST

                                10
           GLEBE ST




                                15
                                                                                                                                   25
                                20
                                                                                     25




                                                                                                                          25
                                                                                                25




                                25                                                                                        25
                                                                      25




                                                                            City of Beaufort
                                             0 50 100     200
                                                            Feet            South Carolina
                                                                       Project Contributing Areas
Prince Street and Hamar Street

• Vegetated Infiltration Basin
• Open Community Park Space
• Large watershed
Prince Street and Hamar Street

• Water Volume and Quality
  Treatment
• Community Park Space
• Aesthetic Improvement
23




         Prince Street and Hamar Street
                                                                                                                                        22




                                                                          16
                                                                17
                                                                                     PRINCE ST




                                          Diversion Structure                  Inlet & Monitoring Point




                                                                                                                                                       Water




                                                                                                                           19
                                                                                                           16


Green                       Green                                               18

                                                                                                                20    21
                                                                                                                                Ponding Surface       Storage
                                                                                                                     22
Infrastructure         Infrastructure   Width                                                             Length                 Depth    Area        Volume
                 HAMAR ST




                                                                                           23


Practice              Practice Location  (ft)                                                               (ft)                  (ft)   (sq ft)       (cu ft)
Vegetated                   Legend
                               Catch Basins
infiltration                Open Space
                               Diversion Structure
                               Inlet & Monitoring Point
Basin                         Parcel
                               Streets
                               Storm Sewers
                                                                                     125                   125                    2.0        15,700   20,880
                               Proposed Inlet Line
                               Parcels
                               Top Footprint
                                     24




                               Banks - 2:1 Sideslope
                               Banks - Steps
                               Bottom Footprint

                                                                                          City of Beaufort
                                          0    15    30              60
                                                                       Feet               South Carolina
                                                                                       Implementation Areas
Duke Street From Bladen To Hamar



• Permeable Pavement and
  Bioretention
• Streetscape Enhancement
• Aesthetic Improvement
Duke Street From Bladen To Hamar



• Permeable Pavement and
  Bioretention
• Streetscape Enhancement
• Aesthetic Improvement
20
                      15
                                           BAGGETT ST




                                                                                     HAMAR ST
UNION ST




                                                                                                20
                                                          GREENE ST




                                      20
                           20




                                                                                                                                                          25
     20


                                                                                                                                         WASHINGTON ST



                                                     20




                                                                                                                     20
                                                                                DUKE ST




                                                                                                     ADVENTURE ST
                           15




             Legend
                                Storm Sewers
                                                                                                                                           PRINCE ST
                                Streets




                                                                                                                                              BLADEN ST
                                Duke Street Catchment
                                                                                                                    Proposed Vegetated
                                15




                                Basin Catchment                                                            20
                                                                            Beaufort
                                Parcels                                                                             Infiltration Basin
                                                                           Elementary
                                               PILOT ST




             Elevation, ft
                                5   KING ST                                  School                                            KING ST

                                10
           GLEBE ST




                                15
                                                                                                                                   25
                                20
                                                                                     25




                                                                                                                          25
                                                                                                25




                                25                                                                                        25
                                                                      25




                                                                            City of Beaufort
                                             0 50 100     200
                                                            Feet            South Carolina
                                                                       Project Contributing Areas
Duke Street From Bladen To Hamar



• Water Volume and Quality
  Treatment
• Enhanced Parking Areas
• Reduce Localized
  Flooding
Duke Street From Bladen To Hamar       WAS HING TON ST




                          HAMAR ST




                                                  ADVENTURE ST
                                                                           DUKE ST




                                                                                     BLADEN ST
                             Green
                         Infrastructure                                     PRINCE ST
  Legend
Green Infrastructure
      Catch Basins
                            Practice     Width Length Surface Area Water Storage
Practice Sewers
      Storm                 Location      (ft)        (ft)         (sq ft)       Volume (cu ft)
      Streets
Bioretention
      Bioretention
                          Right-of-way 200 8
                          0  50  100
                                                      840          6,717
                                                     City of Beaufort                 9,404
                                                      South Carolina
PermeablePavement
      Permeable Pavement  Right-of-way Feet 8 Available Implementation Area
                                                     1680          13,434             4,030
Duke Street From Bladen To Hamar                                                            WASHINGTON ST




                         HAMAR ST




                                                                ADVENTURE ST
                                                                                                    DUKE ST




                                                                                                           BLADEN ST
                                   Green
                               Infrastructure
Green Infrastructure
  Legend
                                  Practice    Width Length Surface Area Water Storage
                                                                      PRINCE ST
Practice Basins
      Catch                       Location     (ft)   (ft)    (sq ft)       Volume (cu ft)
     Storm Sewers
Bioretention                        Right-of-way            8                  182of Beaufort
                                                                                           1,453                       2,034
                         ±
     Streets
                                                                               City
     Bioretention                   0   45   90    180
                                                                               South Carolina
Permeable Pavement
    Permeable Pavement              Right-of-way     Feet
                                                            8                  363         2,906                       872
Duke Street From Bladen To Hamar                                                            WASHINGTON ST




                         HAMAR ST




                                                                ADVENTURE ST
                                                                                                    DUKE ST




                                                                                                           BLADEN ST
                                   Green
                               Infrastructure
Green Infrastructure
  Legend
                                  Practice    Width Length Surface Area Water Storage
                                                                      PRINCE ST
Practice Basins
      Catch                       Location     (ft)   (ft)    (sq ft)       Volume (cu ft)
     Storm Sewers
Bioretention                        Right-of-way            8                  182of Beaufort
                                                                                           1,453                       2,034
                         ±
     Streets
                                                                               City
     Bioretention                   0   45   90    180
                                                                               South Carolina
Permeable Pavement
    Permeable Pavement              Right-of-way     Feet
                                                            8                  363         2,906                       872
Operations and Maintenance
Task                                              Frequency                                           Maintenance notes
Monitor infiltration and drainage   1 time/year                            Inspect drainage time (12–24 hours). Might have to determine
                                                                           infiltration rate (every 2–3 years). Turning over or replacing the media
                                                                           (top 2–3 inches) might be necessary to improve infiltration (at least
                                                                           0.5 in/hr).
Pruning                             1–2 times/year                         Nutrients in runoff often cause bioretention vegetation to flourish.
Mowing                              2–12 times/year                        Frequency depends on the location, plant selection and desired
                                                                           aesthetic appeal.
Mulching                            1–2 times/ year                        Recommend maintaining 1”–3” uniform mulch layer.
Mulch removal                       1 time/2–3 years                       Mulch accumulation reduces available water storage volume.
                                                                           Removal of mulch also increases surface infiltration rate of fill soil.
Watering                            1 time/2–3 days for first 1–2          If drought conditions exist, watering after the initial year might be
                                    months; sporadically after             required.
                                    establishment
Fertilization                       1 time initially                       One-time spot fertilization for first year vegetation.
Remove and replace dead plants      1 time/year                            Within the first year, 10% of plants can die. Survival rates increase
                                                                           with time.
Inlet inspection                    Once after first rain of the season,   Check for sediment accumulation to ensure that flow into the
                                    then monthly during the rainy          retention area is as designed. Remove any accumulated sediment.
                                    season
Outlet inspection                   Once after first rain of the season,   Check for erosion at the outlet and remove any accumulated mulch or
                                    then monthly during the rainy          sediment.
                                    season
Miscellaneous upkeep                12 times/year                          Tasks include trash collection, plant health, spot weeding, and
                                                                           removing mulch from the overflow device.
Operations and Maintenance
Permeable pavement operations and maintenance considerations
Task                           Frequency                             Maintenance notes
Forebay cleanout        As needed, typical 5 – 10    Check for sediment accumulation to ensure that
                        years                        flow into the retention area is as designed.
                                                     Remove any accumulated sediment.
Invasive species/tree   Semi-annual                  Within the first year, 10% of plants can die.
control                                              Survival rates increase with time.
Bank mowing and         Monthly or as needed         Frequency depends on the location, plant
stabilization                                        selection and desired aesthetic appeal.
Outlet inspection and   Monthly and after storms     Check for erosion at the outlet and remove any
cleanout                greater than 2 inches        accumulated mulch or sediment.
Trash removal           As needed                    Remove accumulated debris throughout the
                                                     area.
Rodent & mosquito       As needed                    Inspect for signs of vector control issues. Proper
management                                           eradication measures should be used.


                                                    Stormwater wetland operations and maintenance considerations
                                                Task                                 Frequency                            Maintenance notes
                                                Impervious to Pervious       Once after first rain of     Check for sediment and debris accumulation to
                                                interface                    the season, then monthly     ensure that flow onto the permeable pavement
                                                                             during the rainy season      is not restricted. Remove any accumulated
                                                                                                          sediment, vegetative debris, or trash. Stabilize
                                                                                                          any exposed soil.
                                                Vacuum street sweeper        Twice per year as needed     Portions of pavement should be swept with a
                                                                                                          vacuum street sweeper at least twice per year or
                                                                                                          as needed to maintain infiltration rates.
                                                Replace fill materials       1-2 times per year (and      Fill materials will need to be replaced after each
                                                (applies to pervious         after any vac truck          sweeping and as needed to keep voids with the
                                                pavers only)                 sweeping)                    paver surface.
                                                Miscellaneous upkeep         4 times per year or as       Tasks include trash collection, sweeping, and
                                                                             needed for aesthetics        spot weeding.
Cost Estimate
Item
 No                     Description                   Quantity Unit   Unit Cost    Total
       Preparation
 1     Traffic Control                                     15 Day     $1,000.00    $15,000
 2     Temporary Construction Fence                       500 LF          $2.50     $1,250
 3     Silt Fence                                         500 LF          $3.00     $1,500
       Site Preparation
 4     Excavation and Removal                              775   CY      $45.00    $34,875
 5     Clearing and Grubbing                            15,700   SF       $0.75    $11,775
       Vegetated Infiltration Basin
 6     Fine Grading                                     15,700   SF      $0.72     $11,304
 7     Inlet Diversion Structure                             1   LS    $15,000     $15,000
 8     Vegetation                                       15,700   SF      $4.00     $62,800
                              Construction Subtotal                               $153,504
9      Bond (5% of subtotal)                                                        $7,675
10     Mobilization (10% of subtotal)                                              $15,350
11     Construction contingency (20% of subtotal)                                  $30,701
                                Construction Total                                $207,230
12     Design (40% of Construction Total)                                          $82,892
                                    Total Cost                                    $290,123
Cost Estimate
Item No                       Description                    Quantity       Unit   Unit Cost     Total
          Preparation
  1       Traffic Control                                           15      day      $1,000.00    $15,000
  2       Temporary Construction Fence                             545       LF          $2.50     $1,363
  3       Silt Fence                                               545       LF          $3.00     $1,635
          Site Preparation
  4       Curb and Gutter Removal                                  545      LF           $3.30     $1,799
  5       Excavation and Removal                                   296      CY          $45.00    $13,320
          Traditional Bioretention
  7       Fine Grading                                           1,453      SF           $0.72     $1,046
  8       Soil Media                                               162      CY          $40.00     $6,480
  9       Filter Layer (sand and No. 8 stone)                       18      CY          $45.00      $810
  10      Vegetation                                             1,453      SF           $4.00     $5,812
  11      Mulch                                                     14      CY          $55.00      $770
  12      Curb and Gutter                                          278      LF          $22.00     $6,116
          Permeable Pavement
  13      Curb and Gutter                                          363      LF          $22.00     $7,986
  14      Permeable Pavement                                      2906      SF          $12.00    $34,872
  15      Structural Layer (washed no 57 or no 2 stone)             54      CY          $50.00     $2,700
  16      Concrete Transition Strip                                363      LF           $4.00     $1,452
  17      Utility Conflicts                                             1    LS     $10,000.00    $10,000
                                     Construction Subtotal                                       $111,160
  21      Bond (5% of subtotal)                                                                    $5,558
  22      Mobilization (10% of subtotal)                                                          $11,116
  23      Construction contingency (20% of subtotal)                                              $22,232
                                    Construction Total                                           $150,066
  24      Design (40% of Construction Total)                                                      $60,026
                                         Total Cost                                              $210,093
Annual Maintenance Costs




                                                      Routine
   Green Infrastructure        Area    Unit Cost    Maintenance
          Practice             (ft2)   (per ft2) (monthly to 2 years)
Bioretention                 1,453         $2.28            $3,312.84
Permeable pavement           2,906         $0.67            $1,947.02
Vegetated Infiltration Basin 15,700        $1.91          $29,987.00
Typical Maintenance
Typical Maintenance
Questions?

More Related Content

Similar to EPA Technical Assistance Grant - Beaufort SC Northwest Quadrant

STP designs - Dr. Ananth Kodavasal
STP designs - Dr. Ananth KodavasalSTP designs - Dr. Ananth Kodavasal
STP designs - Dr. Ananth KodavasalADDA
 
Sewage Treatment Plant Design Project
Sewage  Treatment  Plant  Design  ProjectSewage  Treatment  Plant  Design  Project
Sewage Treatment Plant Design ProjectAnoop Shrestha
 
Stormwater GreenHomeNYC August 2008
Stormwater GreenHomeNYC August 2008Stormwater GreenHomeNYC August 2008
Stormwater GreenHomeNYC August 2008GreenHomeNYC
 
Biofilter presentation (2)
Biofilter presentation (2)Biofilter presentation (2)
Biofilter presentation (2)Rajendra Shah
 
Enzotech presentation july12
Enzotech presentation july12Enzotech presentation july12
Enzotech presentation july12enzotechslides
 
Ohio Awwa 2008 Ozone Drinking Water Treatment
Ohio Awwa 2008 Ozone Drinking Water TreatmentOhio Awwa 2008 Ozone Drinking Water Treatment
Ohio Awwa 2008 Ozone Drinking Water TreatmentARSacco
 
Biological methods of waste disposal
Biological methods of waste disposalBiological methods of waste disposal
Biological methods of waste disposalKRATIKA SINGHAM
 
"Managing a Terraformed Planet: Earth Systems Engineering
"Managing a Terraformed Planet: Earth Systems Engineering"Managing a Terraformed Planet: Earth Systems Engineering
"Managing a Terraformed Planet: Earth Systems EngineeringLincolnCenterASU
 
Sustainable Principles for Land Development
Sustainable Principles for Land DevelopmentSustainable Principles for Land Development
Sustainable Principles for Land DevelopmentMaria Cahill
 
Industrial waster water management and its application
Industrial waster water management and its applicationIndustrial waster water management and its application
Industrial waster water management and its applicationARUNKUMARC39
 
Anaerobic Process For Cdm Project
Anaerobic Process For Cdm ProjectAnaerobic Process For Cdm Project
Anaerobic Process For Cdm Projectsakti_siregar
 
DECENTRALIZED TREATMENT SYSTEM
DECENTRALIZED TREATMENT SYSTEMDECENTRALIZED TREATMENT SYSTEM
DECENTRALIZED TREATMENT SYSTEMSHUBHAM BHAGAT
 
Water Quality, Quantity, and Management: Lessons from the Marcellus Shale Reg...
Water Quality, Quantity, and Management: Lessons from the Marcellus Shale Reg...Water Quality, Quantity, and Management: Lessons from the Marcellus Shale Reg...
Water Quality, Quantity, and Management: Lessons from the Marcellus Shale Reg...Cary Institute of Ecosystem Studies
 
BIOTECHNOLOGICAL APPROACHES TOWARDS WATER WASTE MANAGEMENT
BIOTECHNOLOGICAL APPROACHES TOWARDS WATER       WASTE MANAGEMENT BIOTECHNOLOGICAL APPROACHES TOWARDS WATER       WASTE MANAGEMENT
BIOTECHNOLOGICAL APPROACHES TOWARDS WATER WASTE MANAGEMENT saadmughal1271
 

Similar to EPA Technical Assistance Grant - Beaufort SC Northwest Quadrant (20)

STP designs - Dr. Ananth Kodavasal
STP designs - Dr. Ananth KodavasalSTP designs - Dr. Ananth Kodavasal
STP designs - Dr. Ananth Kodavasal
 
Sewage Treatment Plant Design Project
Sewage  Treatment  Plant  Design  ProjectSewage  Treatment  Plant  Design  Project
Sewage Treatment Plant Design Project
 
Stormwater GreenHomeNYC August 2008
Stormwater GreenHomeNYC August 2008Stormwater GreenHomeNYC August 2008
Stormwater GreenHomeNYC August 2008
 
Biofilter presentation (2)
Biofilter presentation (2)Biofilter presentation (2)
Biofilter presentation (2)
 
Wastewater presentation indon.ppt
Wastewater presentation indon.pptWastewater presentation indon.ppt
Wastewater presentation indon.ppt
 
Enzotech presentation july12
Enzotech presentation july12Enzotech presentation july12
Enzotech presentation july12
 
Ohio Awwa 2008 Ozone Drinking Water Treatment
Ohio Awwa 2008 Ozone Drinking Water TreatmentOhio Awwa 2008 Ozone Drinking Water Treatment
Ohio Awwa 2008 Ozone Drinking Water Treatment
 
Etp 2011 -slide share
Etp 2011 -slide shareEtp 2011 -slide share
Etp 2011 -slide share
 
L 18 trickling filter
L 18 trickling filterL 18 trickling filter
L 18 trickling filter
 
Soil bio technology
Soil bio technologySoil bio technology
Soil bio technology
 
Biological methods of waste disposal
Biological methods of waste disposalBiological methods of waste disposal
Biological methods of waste disposal
 
"Managing a Terraformed Planet: Earth Systems Engineering
"Managing a Terraformed Planet: Earth Systems Engineering"Managing a Terraformed Planet: Earth Systems Engineering
"Managing a Terraformed Planet: Earth Systems Engineering
 
Sustainable Principles for Land Development
Sustainable Principles for Land DevelopmentSustainable Principles for Land Development
Sustainable Principles for Land Development
 
TEEB biodiversity and Water Patrick ten Brink of IEEP presentation at water d...
TEEB biodiversity and Water Patrick ten Brink of IEEP presentation at water d...TEEB biodiversity and Water Patrick ten Brink of IEEP presentation at water d...
TEEB biodiversity and Water Patrick ten Brink of IEEP presentation at water d...
 
Greenhouse gas accounting for the land-based sector - Annette Cowie
Greenhouse gas accounting for the land-based sector - Annette CowieGreenhouse gas accounting for the land-based sector - Annette Cowie
Greenhouse gas accounting for the land-based sector - Annette Cowie
 
Industrial waster water management and its application
Industrial waster water management and its applicationIndustrial waster water management and its application
Industrial waster water management and its application
 
Anaerobic Process For Cdm Project
Anaerobic Process For Cdm ProjectAnaerobic Process For Cdm Project
Anaerobic Process For Cdm Project
 
DECENTRALIZED TREATMENT SYSTEM
DECENTRALIZED TREATMENT SYSTEMDECENTRALIZED TREATMENT SYSTEM
DECENTRALIZED TREATMENT SYSTEM
 
Water Quality, Quantity, and Management: Lessons from the Marcellus Shale Reg...
Water Quality, Quantity, and Management: Lessons from the Marcellus Shale Reg...Water Quality, Quantity, and Management: Lessons from the Marcellus Shale Reg...
Water Quality, Quantity, and Management: Lessons from the Marcellus Shale Reg...
 
BIOTECHNOLOGICAL APPROACHES TOWARDS WATER WASTE MANAGEMENT
BIOTECHNOLOGICAL APPROACHES TOWARDS WATER       WASTE MANAGEMENT BIOTECHNOLOGICAL APPROACHES TOWARDS WATER       WASTE MANAGEMENT
BIOTECHNOLOGICAL APPROACHES TOWARDS WATER WASTE MANAGEMENT
 

More from City of Beaufort Planning Department

More from City of Beaufort Planning Department (20)

City of Beaufort Civic Master Plan - Adopted
City of Beaufort Civic Master Plan - AdoptedCity of Beaufort Civic Master Plan - Adopted
City of Beaufort Civic Master Plan - Adopted
 
Civic Master Plan - Nov. 4, 2013 Version
Civic Master Plan - Nov. 4, 2013 VersionCivic Master Plan - Nov. 4, 2013 Version
Civic Master Plan - Nov. 4, 2013 Version
 
APA Great Neighborhood Award - Slide Show Presentation
APA Great Neighborhood Award - Slide Show PresentationAPA Great Neighborhood Award - Slide Show Presentation
APA Great Neighborhood Award - Slide Show Presentation
 
Civic Master Plan - October 18, 2013 Draft
Civic Master Plan - October 18, 2013 DraftCivic Master Plan - October 18, 2013 Draft
Civic Master Plan - October 18, 2013 Draft
 
Civic Master Plan - Oct. 3, 2013 Draft
Civic Master Plan - Oct. 3, 2013 DraftCivic Master Plan - Oct. 3, 2013 Draft
Civic Master Plan - Oct. 3, 2013 Draft
 
Civic Master Plan Draft - August 5, 2013
Civic Master Plan Draft - August 5, 2013Civic Master Plan Draft - August 5, 2013
Civic Master Plan Draft - August 5, 2013
 
Civic master plan overview presentation - March 20, 2013
Civic master plan overview presentation - March 20, 2013Civic master plan overview presentation - March 20, 2013
Civic master plan overview presentation - March 20, 2013
 
Civic Master Plan - March 18, 2013 DRAFT
Civic Master Plan - March 18, 2013 DRAFTCivic Master Plan - March 18, 2013 DRAFT
Civic Master Plan - March 18, 2013 DRAFT
 
Districts and maps presentation 01.09.2013
Districts and maps presentation 01.09.2013Districts and maps presentation 01.09.2013
Districts and maps presentation 01.09.2013
 
FBC Advisory Committee Kickoff Meeting 091912
FBC Advisory Committee Kickoff Meeting 091912FBC Advisory Committee Kickoff Meeting 091912
FBC Advisory Committee Kickoff Meeting 091912
 
Boundary Street Presentation Sept 20, 2012
Boundary Street Presentation Sept 20, 2012Boundary Street Presentation Sept 20, 2012
Boundary Street Presentation Sept 20, 2012
 
2009 Comprehensive Plan
2009 Comprehensive Plan2009 Comprehensive Plan
2009 Comprehensive Plan
 
Boundary Street - June 11, 2012 Tiger III Grant Presentation
Boundary Street - June 11, 2012 Tiger III Grant PresentationBoundary Street - June 11, 2012 Tiger III Grant Presentation
Boundary Street - June 11, 2012 Tiger III Grant Presentation
 
Sectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing PresentationSectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing Presentation
 
Redevelopment commission pp 9.01.11
Redevelopment commission pp 9.01.11Redevelopment commission pp 9.01.11
Redevelopment commission pp 9.01.11
 
Lowcountry housingtrustlocalbankersmeetingpresentation
Lowcountry housingtrustlocalbankersmeetingpresentationLowcountry housingtrustlocalbankersmeetingpresentation
Lowcountry housingtrustlocalbankersmeetingpresentation
 
Civic masterplan sector1-appendixc
Civic masterplan sector1-appendixcCivic masterplan sector1-appendixc
Civic masterplan sector1-appendixc
 
Civic masterplan sector1-appendixb
Civic masterplan sector1-appendixbCivic masterplan sector1-appendixb
Civic masterplan sector1-appendixb
 
Civic masterplan sector1-appendixa
Civic masterplan sector1-appendixaCivic masterplan sector1-appendixa
Civic masterplan sector1-appendixa
 
Civic masterplan sector1-appendixd
Civic masterplan sector1-appendixdCivic masterplan sector1-appendixd
Civic masterplan sector1-appendixd
 

Recently uploaded

Fashion trends before and after covid.pptx
Fashion trends before and after covid.pptxFashion trends before and after covid.pptx
Fashion trends before and after covid.pptxVanshNarang19
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonDelhi Call girls
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsCharles Obaleagbon
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...Amil baba
 
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...Call Girls in Nagpur High Profile
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Sitegalleryaagency
 
MASONRY -Building Technology and Construction
MASONRY -Building Technology and ConstructionMASONRY -Building Technology and Construction
MASONRY -Building Technology and Constructionmbermudez3
 
DragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxDragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxmirandajeremy200221
 
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai DouxDubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Douxkojalkojal131
 
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...Suhani Kapoor
 
Raj Nagar Extension Call Girls 9711199012 WhatsApp No, Delhi Escorts in Raj N...
Raj Nagar Extension Call Girls 9711199012 WhatsApp No, Delhi Escorts in Raj N...Raj Nagar Extension Call Girls 9711199012 WhatsApp No, Delhi Escorts in Raj N...
Raj Nagar Extension Call Girls 9711199012 WhatsApp No, Delhi Escorts in Raj N...ankitnayak356677
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfParomita Roy
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfAmirYakdi
 
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Delhi Call girls
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...home
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CANestorGamez6
 
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service BhiwandiVIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service BhiwandiSuhani Kapoor
 

Recently uploaded (20)

Fashion trends before and after covid.pptx
Fashion trends before and after covid.pptxFashion trends before and after covid.pptx
Fashion trends before and after covid.pptx
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past Questions
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
 
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
 
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
 
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Site
 
MASONRY -Building Technology and Construction
MASONRY -Building Technology and ConstructionMASONRY -Building Technology and Construction
MASONRY -Building Technology and Construction
 
DragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxDragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptx
 
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai DouxDubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
 
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
 
Raj Nagar Extension Call Girls 9711199012 WhatsApp No, Delhi Escorts in Raj N...
Raj Nagar Extension Call Girls 9711199012 WhatsApp No, Delhi Escorts in Raj N...Raj Nagar Extension Call Girls 9711199012 WhatsApp No, Delhi Escorts in Raj N...
Raj Nagar Extension Call Girls 9711199012 WhatsApp No, Delhi Escorts in Raj N...
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
 
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
 
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service BhiwandiVIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
 

EPA Technical Assistance Grant - Beaufort SC Northwest Quadrant

  • 1. Block by Block Green Infrastructure Northwest Quadrant Conceptual Design City of Beaufort
  • 2. Beaufort’s Block by Block Green Infrastructure Northwest Quadrant Conceptual Design
  • 3. Beaufort’s Block by Block Green Infrastructure Northwest Quadrant Conceptual Design Preservation guidelines • Maintaining the traditional character of the block; • Maintaining the informal nature of the streets, lanes, and gardens where they exist; • Maintaining the soft edges found along neighborhood streets; and • Encouraging informal gardens throughout the neighborhood. Neighborhood Strategic Plan • Encouraging the use of rain barrels and greywater recycling; • Supporting community gardens; and • Identifying future pocket park locations.
  • 4. Beaufort’s Block by Block Green Infrastructure Northwest Quadrant Conceptual Design What is Green Infrastructure? Stormwater management strategy that uses natural hydrologic features to manage water and provide environmental and community benefits. How do we make this… function more like this?
  • 5. Green Infrastructure Under Natural Conditions Runoff is ....But increases After Limited.... Development 5
  • 6. Beaufort’s Block by Block Green Infrastructure Northwest Quadrant Conceptual Design What is Green Infrastructure? Stormwater management strategy that uses natural hydrologic features to manage water and provide environmental and community benefits. How do we make this… function more like this?
  • 7. Green Infrastructure - Multiple Benefits  Water quality  Cost savings  Flood and  Community identity hydromodification  Recreational control greenspace  Rainwater capture and  Reduced urban heat use island effect  Increased groundwater  Wildlife habitat recharge and baseflow  Enhanced property  Improved air quality values  Reduced energy  Carbon sequestering consumption  Aesthetic benefits
  • 8. Multiple Benefits Category Indicator Reduced Stormwater Volume Environmental Reduced Peak Flow Rate Reduced Pollutant Loading Increased Groundwater Recharge Reduced Energy Use and Heat Island Effect Reduced Particulate Matter Increased Carbon Sequestration Improved Quality of Life and Aesthetics Social Increased Recreational Opportunities Job Creation Reduced Infrastructure Costs Economic Reduced Pumping Costs Increased or Stabilized Property Values
  • 11. Effects of Water Pollution Photo courtesy of NRCS
  • 12.
  • 13. BMP Functions Hydrologic controls Removal processes Evapotranspiration or flow attenuation Biotransformation/ Storage/detention phytoremediation Bioaccumulation volatilization) photolysis; Other (e.g., Infiltration Filtration Sorption Settling Structural BMPs Bioretention + (+) o o + o + + (o) Permeable pavement + (+) – – + – – – – Infiltration basin + + (o) o + o + + (o) Cisterns/rain barrels + – – – – – – – – Note: ( ) optional function; + major function; o secondary function; – insignificant function
  • 14. BMP Design  Bioretention  Bioswales  Planter Boxes  Permeable Pavement  Green Roofs  Water Harvesting  Cisterns  Rain Barrels  Sand Filters  Vegetated Swales  Vegetated Filter Strips
  • 16. Bioretention Schematic Runoff Vegetation on Surface Media Underdrain System
  • 17. Bioretention Areas Pollutant removal functions  Sedimentation (temporary)  Trash, TSS, Phosphorus  Microbial Processes  Nitrogen, Pathogens  Chemical Processes  Metals, Phosphorus  Exposure to Sunlight & Dryness  Pathogens, Oil & Grease
  • 18. Bioretention Areas • Soil Media Depth Where are pollutants removed? TSS TP Temp TN Pathogens Metals Oil & Grease
  • 19. Bioretention Areas www.bae.ncsu.edu/stormwater
  • 20. Integrating into Landscape www.bae.ncsu.edu/stormwater
  • 22. Parking Lots Port City Java, Market www.bae.ncsu.edu/stormwater
  • 23. Parking Lots www.bae.ncsu.edu/stormwater
  • 26. Bioretention Areas + 4 Hours +14 Hours
  • 27. Bioretention Areas  Mulch and Vegetation  Drought tolerant vegetation  Periodic inundation  Native species  Consider size and appearance at maturity
  • 29. Bioretention Variations  Transportation Corridor  Right-of-way
  • 30. Permeable Pavement  Allows for rainfall infiltration  Low traffic surfaces (driveways, parking lots, walk ways)  Provides peak flow mitigation, volume storage, and some water quality improvement
  • 31. Permeable Pavements  Permeable Interlocking Concrete Pavers (PICP)  Concrete Grid Pavers (CGP)  Pervious (Porous) Pavements (PC & PA)  Plastic Reinforcing Grids (PG)
  • 33. Permeable Pavement Store/Treat the design storm volume  within base and sub-base reservoirs • d=V/A×n – d = Gravel Layer Depth (ft) – V = Water Quality Volume – A = Surface Area (square ft) – n = Porosity (0.3 to 0.4)  Structural Design  • Total traffic Guide for Design of Pavement Structures AASHTO  In situ soil strength (1993) •  Environmental elements to the Guide for Design of AASHTO Supplement  Bedding and Structures (1998) Pavement reservoir layer design • AASHTO Flexible Pavement Method
  • 34. Permeable Pavement  These systems should be installed by a qualified professional • The only exception is very small backyard patios where BMP failure will not be hazardous to human health • A list of professionals qualified in permeable paver installation is available through the Interlocking Concrete Pavement Institute (ICPI) – www.icpi.org • More information on pervious concrete is available through the Carolina Ready Mixed Concrete Association (CRMCA) – www.crmca.com
  • 36. Permeable Pavement 6 inches pervious concrete Washed no 57 stone (Min 6”)
  • 37. Permeable Pavement 6 in 6-9 in 12-18 in
  • 38. Permeable Pavement Grid Pavers Sand PICP with gravel fill Washed No. 57 Stone Interlocking Concrete Pavers Pea Gravel Washed No. 57 Stone
  • 40. Permeable Pavement 6 in 6-9 in 12-18 in
  • 51. Photo credit: Jill Bicknell, Santa Clara Valley Urban Runoff Program.
  • 52. Stormwater Wetlands  Reduce Nutrients  Slow Flow of Water
  • 57. Stormwater Wetlands A Diverse System of Herbaceous Plants tends to limit mosquito population Human Introduction of Gambousia affinis NOT recommended www.bae.ncsu.edu/stormwater
  • 59. Beaufort’s Block by Block Green Infrastructure Northwest Quadrant Conceptual Design
  • 60. Beaufort’s Block by Block Green Infrastructure Northwest Quadrant Conceptual Design US Marine Corps Air Station Golf Professionals Club Laurel Bay 116 Beaufort Northwest Quadrant 802 Project Location Burton Beaufort Beaufort 280 21 281 170 802 Port Royal Legend Par is Project Location Shell Point M ale co Northwest Quadrant Boundary n City of Beaufort Limits Highway Marine Corps Recruit Depot Major Road Parris Island Railroads (Local) Lake/Pond/Stream/River City of Beaufort Swamp/Marsh 0 0.5 1 2 Miles South Carolina Cities Project Location
  • 61. Beaufort’s Block by Block Green Infrastructure BOUNDARY ST Northwest Quadrant Conceptual Design WILMINGTO N ST UNION ST BA GG ET CONGRES S ST T ST BLADEN ST CHURCH ST GREENE ST RIBAU T RD Northwest MONSON ST NEWCASTLE ST D WASHINGTON ST MARS H R HAMAR ST Quadrant HARRINGTON ST Beaufort DUKE ST ADVENTURE ST BLADEN LN PRINCE ST ELTON LN PILOT ST KING ST KING ST EUHAW ST GLEBE ST HEYWARD ST WAIGHT ST NORTH ST NORTH ST T YS CRAVEN ST BA Historic ST Downtown SIM MS Beaufort River Beaufort T RD PO DE Legend City of Beaufort Streets 0 200 400 800 Feet South Carolina Northwest Quadrant Boundary Northwest Quadrant
  • 62. Charrette Process  Work session with director and staff  Site selection and preliminary concept plans  Presentations to staff and officials  Final concept plans and report  Final presentation
  • 63. Implementation  Regulating Plan  T3 Neighborhood General  T4 Urban Neighborhood and Neighborhood Center  T5 Urban Center/Corridor  Localized Improvements  Public Right of Way and Block Level Solutions
  • 64. Transects  Integration of Green Infrastructure techniques into the planning and development process  Consistent, predictable costs and performance, and replicable results  Adaptable to local conditions  Ancillary benefits and values  Aesthetics, identity, energy…..
  • 65. Localized Improvements  Correct drainage issues  Improve streetscape and reduce maintenance  Create community value  Demonstrate progress  Planned and Constructed incrementally
  • 66.
  • 67. Project Criteria s ment nsect t enefi prove Techn ration of of T ra ts ood B fi Bene lity age Im ology n r Q ua bor h ra tio nst la ry Demo Neigh Dr ain Wate Integ Ancil Candidate Project/Transects Section 8 Housing Church and Washington Streets ○  ○ ○   Private Lot between Prince and Hamar ● ● ○  ● ● Glebe Street Extension ● ●   ●  Stormwater Dry Pond Hamar and Washington ○  ○  ● ● Green Street along Pilot from Prince to North Street Connection of Duke and Princeton ○    ● ● Duke Street from Bladen to Pilot Street ● ● ●   ● Candidate Improvements Bump Outs for Tree Space ● ●   ● ● Vegetated Curb Extensions ● ●   ● ● Residential on-lot Permeable Pavement ● ● ●  ● ●
  • 72. T5 – Urban Corridor/Center
  • 73. T5 – Urban Corridor/Center
  • 74.
  • 75. 20 15 BAGGETT ST HAMAR ST UNION ST 20 GREENE ST 20 20 25 20 WASHINGTON ST 20 20 DUKE ST ADVENTURE ST 15 Legend Storm Sewers PRINCE ST Streets BLADEN ST Duke Street Catchment Proposed Vegetated 15 Basin Catchment 20 Beaufort Parcels Infiltration Basin Elementary PILOT ST Elevation, ft 5 KING ST School KING ST 10 GLEBE ST 15 25 20 25 25 25 25 25 25 City of Beaufort 0 50 100 200 Feet South Carolina Project Contributing Areas
  • 76. Prince Street and Hamar Street • Vegetated Infiltration Basin • Open Community Park Space • Large watershed
  • 77. Prince Street and Hamar Street • Water Volume and Quality Treatment • Community Park Space • Aesthetic Improvement
  • 78. 23 Prince Street and Hamar Street 22 16 17 PRINCE ST Diversion Structure Inlet & Monitoring Point Water 19 16 Green Green 18 20 21 Ponding Surface Storage 22 Infrastructure Infrastructure Width Length Depth Area Volume HAMAR ST 23 Practice Practice Location (ft) (ft) (ft) (sq ft) (cu ft) Vegetated Legend Catch Basins infiltration Open Space Diversion Structure Inlet & Monitoring Point Basin Parcel Streets Storm Sewers 125 125 2.0 15,700 20,880 Proposed Inlet Line Parcels Top Footprint 24 Banks - 2:1 Sideslope Banks - Steps Bottom Footprint City of Beaufort 0 15 30 60 Feet South Carolina Implementation Areas
  • 79. Duke Street From Bladen To Hamar • Permeable Pavement and Bioretention • Streetscape Enhancement • Aesthetic Improvement
  • 80. Duke Street From Bladen To Hamar • Permeable Pavement and Bioretention • Streetscape Enhancement • Aesthetic Improvement
  • 81. 20 15 BAGGETT ST HAMAR ST UNION ST 20 GREENE ST 20 20 25 20 WASHINGTON ST 20 20 DUKE ST ADVENTURE ST 15 Legend Storm Sewers PRINCE ST Streets BLADEN ST Duke Street Catchment Proposed Vegetated 15 Basin Catchment 20 Beaufort Parcels Infiltration Basin Elementary PILOT ST Elevation, ft 5 KING ST School KING ST 10 GLEBE ST 15 25 20 25 25 25 25 25 25 City of Beaufort 0 50 100 200 Feet South Carolina Project Contributing Areas
  • 82. Duke Street From Bladen To Hamar • Water Volume and Quality Treatment • Enhanced Parking Areas • Reduce Localized Flooding
  • 83. Duke Street From Bladen To Hamar WAS HING TON ST HAMAR ST ADVENTURE ST DUKE ST BLADEN ST Green Infrastructure PRINCE ST Legend Green Infrastructure Catch Basins Practice Width Length Surface Area Water Storage Practice Sewers Storm Location (ft) (ft) (sq ft) Volume (cu ft) Streets Bioretention Bioretention Right-of-way 200 8 0 50 100 840 6,717 City of Beaufort 9,404 South Carolina PermeablePavement Permeable Pavement Right-of-way Feet 8 Available Implementation Area 1680 13,434 4,030
  • 84. Duke Street From Bladen To Hamar WASHINGTON ST HAMAR ST ADVENTURE ST DUKE ST BLADEN ST Green Infrastructure Green Infrastructure Legend Practice Width Length Surface Area Water Storage PRINCE ST Practice Basins Catch Location (ft) (ft) (sq ft) Volume (cu ft) Storm Sewers Bioretention Right-of-way 8 182of Beaufort 1,453 2,034 ± Streets City Bioretention 0 45 90 180 South Carolina Permeable Pavement Permeable Pavement Right-of-way Feet 8 363 2,906 872
  • 85. Duke Street From Bladen To Hamar WASHINGTON ST HAMAR ST ADVENTURE ST DUKE ST BLADEN ST Green Infrastructure Green Infrastructure Legend Practice Width Length Surface Area Water Storage PRINCE ST Practice Basins Catch Location (ft) (ft) (sq ft) Volume (cu ft) Storm Sewers Bioretention Right-of-way 8 182of Beaufort 1,453 2,034 ± Streets City Bioretention 0 45 90 180 South Carolina Permeable Pavement Permeable Pavement Right-of-way Feet 8 363 2,906 872
  • 86. Operations and Maintenance Task Frequency Maintenance notes Monitor infiltration and drainage 1 time/year Inspect drainage time (12–24 hours). Might have to determine infiltration rate (every 2–3 years). Turning over or replacing the media (top 2–3 inches) might be necessary to improve infiltration (at least 0.5 in/hr). Pruning 1–2 times/year Nutrients in runoff often cause bioretention vegetation to flourish. Mowing 2–12 times/year Frequency depends on the location, plant selection and desired aesthetic appeal. Mulching 1–2 times/ year Recommend maintaining 1”–3” uniform mulch layer. Mulch removal 1 time/2–3 years Mulch accumulation reduces available water storage volume. Removal of mulch also increases surface infiltration rate of fill soil. Watering 1 time/2–3 days for first 1–2 If drought conditions exist, watering after the initial year might be months; sporadically after required. establishment Fertilization 1 time initially One-time spot fertilization for first year vegetation. Remove and replace dead plants 1 time/year Within the first year, 10% of plants can die. Survival rates increase with time. Inlet inspection Once after first rain of the season, Check for sediment accumulation to ensure that flow into the then monthly during the rainy retention area is as designed. Remove any accumulated sediment. season Outlet inspection Once after first rain of the season, Check for erosion at the outlet and remove any accumulated mulch or then monthly during the rainy sediment. season Miscellaneous upkeep 12 times/year Tasks include trash collection, plant health, spot weeding, and removing mulch from the overflow device.
  • 87. Operations and Maintenance Permeable pavement operations and maintenance considerations Task Frequency Maintenance notes Forebay cleanout As needed, typical 5 – 10 Check for sediment accumulation to ensure that years flow into the retention area is as designed. Remove any accumulated sediment. Invasive species/tree Semi-annual Within the first year, 10% of plants can die. control Survival rates increase with time. Bank mowing and Monthly or as needed Frequency depends on the location, plant stabilization selection and desired aesthetic appeal. Outlet inspection and Monthly and after storms Check for erosion at the outlet and remove any cleanout greater than 2 inches accumulated mulch or sediment. Trash removal As needed Remove accumulated debris throughout the area. Rodent & mosquito As needed Inspect for signs of vector control issues. Proper management eradication measures should be used. Stormwater wetland operations and maintenance considerations Task Frequency Maintenance notes Impervious to Pervious Once after first rain of Check for sediment and debris accumulation to interface the season, then monthly ensure that flow onto the permeable pavement during the rainy season is not restricted. Remove any accumulated sediment, vegetative debris, or trash. Stabilize any exposed soil. Vacuum street sweeper Twice per year as needed Portions of pavement should be swept with a vacuum street sweeper at least twice per year or as needed to maintain infiltration rates. Replace fill materials 1-2 times per year (and Fill materials will need to be replaced after each (applies to pervious after any vac truck sweeping and as needed to keep voids with the pavers only) sweeping) paver surface. Miscellaneous upkeep 4 times per year or as Tasks include trash collection, sweeping, and needed for aesthetics spot weeding.
  • 88. Cost Estimate Item No Description Quantity Unit Unit Cost Total Preparation 1 Traffic Control 15 Day $1,000.00 $15,000 2 Temporary Construction Fence 500 LF $2.50 $1,250 3 Silt Fence 500 LF $3.00 $1,500 Site Preparation 4 Excavation and Removal 775 CY $45.00 $34,875 5 Clearing and Grubbing 15,700 SF $0.75 $11,775 Vegetated Infiltration Basin 6 Fine Grading 15,700 SF $0.72 $11,304 7 Inlet Diversion Structure 1 LS $15,000 $15,000 8 Vegetation 15,700 SF $4.00 $62,800 Construction Subtotal $153,504 9 Bond (5% of subtotal) $7,675 10 Mobilization (10% of subtotal) $15,350 11 Construction contingency (20% of subtotal) $30,701 Construction Total $207,230 12 Design (40% of Construction Total) $82,892 Total Cost $290,123
  • 89. Cost Estimate Item No Description Quantity Unit Unit Cost Total Preparation 1 Traffic Control 15 day $1,000.00 $15,000 2 Temporary Construction Fence 545 LF $2.50 $1,363 3 Silt Fence 545 LF $3.00 $1,635 Site Preparation 4 Curb and Gutter Removal 545 LF $3.30 $1,799 5 Excavation and Removal 296 CY $45.00 $13,320 Traditional Bioretention 7 Fine Grading 1,453 SF $0.72 $1,046 8 Soil Media 162 CY $40.00 $6,480 9 Filter Layer (sand and No. 8 stone) 18 CY $45.00 $810 10 Vegetation 1,453 SF $4.00 $5,812 11 Mulch 14 CY $55.00 $770 12 Curb and Gutter 278 LF $22.00 $6,116 Permeable Pavement 13 Curb and Gutter 363 LF $22.00 $7,986 14 Permeable Pavement 2906 SF $12.00 $34,872 15 Structural Layer (washed no 57 or no 2 stone) 54 CY $50.00 $2,700 16 Concrete Transition Strip 363 LF $4.00 $1,452 17 Utility Conflicts 1 LS $10,000.00 $10,000 Construction Subtotal $111,160 21 Bond (5% of subtotal) $5,558 22 Mobilization (10% of subtotal) $11,116 23 Construction contingency (20% of subtotal) $22,232 Construction Total $150,066 24 Design (40% of Construction Total) $60,026 Total Cost $210,093
  • 90. Annual Maintenance Costs Routine Green Infrastructure Area Unit Cost Maintenance Practice (ft2) (per ft2) (monthly to 2 years) Bioretention 1,453 $2.28 $3,312.84 Permeable pavement 2,906 $0.67 $1,947.02 Vegetated Infiltration Basin 15,700 $1.91 $29,987.00

Editor's Notes

  1. Beaufort River impaired for fecal coliform and dissolved oxygen (eutrophication from nutrients)Impaired for aquatic life, good for recreation (for now)
  2. Beaufort River impaired for fecal coliform and dissolved oxygen (eutrophication from nutrients)Impaired for aquatic life, good for recreation (for now)
  3. Bioretention BMPs are small-scale, shallow, vegetated, depressed areas with a soil (often engineered soil)media and plant-based filtration device that removes pollutants through a variety of physical, biological,and chemical treatment processes
  4. 36 acres. Does not include the drainage area for the Department of Social Services.
  5. Provide treatment for the runoff generated by the 1.22 inch event
  6. 1.5 acres.
  7. Utilizing all of the area available for implementation (6,717 square feet of bioretention and 13,434 square feet of permeable pavement) will provide treatment for the runoff generated by the 5.97 inch event (approximately a 5 year event), substantially more than is required by the current design storm.