SlideShare a Scribd company logo
1 of 10
CONSTRUCTION & 
ENGINEERING 
SEMINAR 
Jason Smit
THE INTERPRETATION AND 
APPLICATION OF DEMAND 
GUARANTEES 
> 2 recent SCA cases: 
> Coface South Africa Insurance Co v East London Own Haven 
> Guardrisk Insurance Company Ltd v Kentz 
> Both establish the basic premise that “on-demand” 
guarantees are enforceable and payable on their terms alone 
> Absent fraud, issues arising as between the holder of a 
guarantee and the other party to an underlying contract are 
irrelevant and will not be considered by the courts 
2
GUARDRISK – BASIC FACTS 
> Kentz was involved as a contractor for the Medupi project 
> Contracted, in turn, with Brokrew Industrial for the supply of 
ducting 
> An advance payment was made by Ketz to Brokrew and 
Brokrew was required to obtain an advance payment guarantee, 
issued in favour of Kentz, as well as a performance guarantee 
> Guadrisk issued the guarantees 
> Brokrew subsequently ran into difficulties and could not perform 
in terms of the contract with Kentz 
> Kentz ultimate cancelled the contract and called the guarantees 
> Guardrisk resisted on the basis that Kentz’s claim was 
fraudulent 
3
GUARDRISK – ISSUES CONSIDERED 
> What was the nature of the guarantees? 
> Were they “conditional” or “on demand”? 
> The guarantees were held to be “on demand” instruments 
> The guarantees recorded that they held the guaranteed sums, as the 
disposal of the Employer, as security for Brokrew’s obligations 
> The guarantees bound the issuer as principal and not surety 
> Importantly, the guarantees stated that a dispute beween Employer 
and Contractor would not prevent payment 
> What is required to sustain a “fraud” allegation on the part of 
the issuing institution? 
> Where the party calling the guarantee does so in the knowledge 
that it is not entitled payment 
> The party alleging the fraud must prove it 
4
GUARDRISK – ISSUES CONSIDERED 
> Did the manner in which Kentz engaged with the contractor 
matter in relation to the enforcement of the guarantees? 
> Kentz issued two notices to the Contractor. 
> The first stated that Kentz was entitled to cancel the contract, 
reserved Kentz’s rights to do so and then demanded the remedying of 
certain defects 
> The second cancelled the contract 
> The court had no difficulty with this approach 
> Does the court have any reference to the underlying agreement? 
> No – this is not permissible 
> At the stage where demand is made in terms of a guarantee, all other 
disputes between Employer and Contractor are irrelevant 
> Payment in terms of a performance / demand guarantee are 
independent of the underlying contract 
5
COFACE – BASIC FACTS 
> Coface issued a performance guarantee in favour of ELOH 
> It undertook to pay in terms of the guarantee, on receipt of a 
demand stating that the underlying contract between ELOH 
and its contractor had been cancelled due to the contractor’s 
default 
> Coface contended that ELOH was not entitled to have 
cancelled the underlying contract and that it (Coface) 
therefore did not have to pay out under the guarantee 
> Coface attempted to introduce issues relevant to the underlying 
contract in order to avoid liability (design and errors in certification) 
6
COFACE – ISSUES CONSIDERED 
> In what circumstances can “extraneous” issues be considered 
when dealing with demand guarantees 
> Fraud 
> The introduction of underlying contractual disputes and the 
joining of other parties (contractors) etc should be avoided 
> As in the Guardrisk case, guarantees are enforceable on their 
terms 
> The previous SCA decision in the Dormell case was clearly 
incorrect 
7
> Both judgments confirm that a demand / call bond 
must be honoured on its terms 
> If those terms are met, no other issues are relevant 
for consideration by our courts 
> Underlying disputes between Employer and 
Contractor will not be considered 
> The fraud defence will not be lightly inferred 
> “Our courts, in a long line of cases and also relying on 
English authorities, have strictly applied the principle 
that a bank faced with a valid demand in respect of a 
performance guarantee, is obliged to pay the 
beneficiary without investigation of the contractual 
position between the beneficiary and the principal 
debtor” (Guardrisk) 
8 
GENERAL OBSERVATIONS FROM 
GUARDRISK AND COFACE
STANDARD CONDITIONS DEALING 
WITH INSOLVENCY / BUSINESS 
RESCUE AND RESULTANT RIGHTS 
> FIDIC Silver Book 
> 15.2(e) – Employer is entitled to terminate if Contractor “becomes bankrupt 
or insolvent, goes into liquidation, has a receiving or administration order 
made against him, compounds with his creditors, carries on business under a 
receiver” 
> 16.2(f) – similar right for the Contractor 
> NEC PSC 
> 90.1 – “if the other Party has a winding up order made against it, has a 
provisional liquidator appointed, has an administration order made against it, 
has a receiver appointed, makes an arrangement with its creditors 
> JBCC Series 2000 
> 36.1 – cancellation by Employer where Contractor fails to comply with 15.1 
(BoQ, security etc) or 15.3 (progress with skill diligence, regularity) 
9
THINGS TO CONSIDER 
> Does the wording of security issued entitle the holder to 
claim without reference to the underlying contract? 
> Does the wording of the security issued entitle the holder to 
claim if its co-contracting party goes into business rescue, as 
opposed to being wound up? 
> Can the underlying contract be cancelled if the co-contracting 
party goes into business rescue? 
10

More Related Content

What's hot

Can a work in a contract be omitted
Can a work in a contract be omittedCan a work in a contract be omitted
Can a work in a contract be omitted
AMILA GAYAN
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
AMILA GAYAN
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Francis Ho
 
Z Subcontracting and Flow Down Clauses What's In Your Contract
Z Subcontracting and Flow Down Clauses What's In Your ContractZ Subcontracting and Flow Down Clauses What's In Your Contract
Z Subcontracting and Flow Down Clauses What's In Your Contract
jpeabody
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram
 

What's hot (20)

SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTSSWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct payments
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 
Can a work in a contract be omitted
Can a work in a contract be omittedCan a work in a contract be omitted
Can a work in a contract be omitted
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
RWY CIPAA 2012 - Scope and Applicability
RWY CIPAA 2012 - Scope and ApplicabilityRWY CIPAA 2012 - Scope and Applicability
RWY CIPAA 2012 - Scope and Applicability
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract Administrators
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentation
 
Z Subcontracting and Flow Down Clauses What's In Your Contract
Z Subcontracting and Flow Down Clauses What's In Your ContractZ Subcontracting and Flow Down Clauses What's In Your Contract
Z Subcontracting and Flow Down Clauses What's In Your Contract
 
CIArb Promotional Talk
CIArb Promotional TalkCIArb Promotional Talk
CIArb Promotional Talk
 
Your Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter MostYour Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter Most
 
When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?
 
Werksmans Construction & Engineering Seminar - Deon Griessel presentation
Werksmans Construction & Engineering Seminar - Deon Griessel presentationWerksmans Construction & Engineering Seminar - Deon Griessel presentation
Werksmans Construction & Engineering Seminar - Deon Griessel presentation
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
 

Similar to CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAND GUARANTEES

13 AND 14 SME FINANCE.pptx
13 AND 14 SME FINANCE.pptx13 AND 14 SME FINANCE.pptx
13 AND 14 SME FINANCE.pptx
VbsReddy2
 
C ps, css, rep & warranties
C ps, css, rep & warrantiesC ps, css, rep & warranties
C ps, css, rep & warranties
IrinaTyan
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
Ryan Hatton
 

Similar to CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAND GUARANTEES (20)

TYPES OF CONSTRUCTION AND ENGINEERING GUARANTEES:
TYPES OF CONSTRUCTION AND ENGINEERING GUARANTEES:TYPES OF CONSTRUCTION AND ENGINEERING GUARANTEES:
TYPES OF CONSTRUCTION AND ENGINEERING GUARANTEES:
 
CLI ARTICLE ON SUBCONTRACTING
CLI ARTICLE ON SUBCONTRACTINGCLI ARTICLE ON SUBCONTRACTING
CLI ARTICLE ON SUBCONTRACTING
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
13 AND 14 SME FINANCE.pptx
13 AND 14 SME FINANCE.pptx13 AND 14 SME FINANCE.pptx
13 AND 14 SME FINANCE.pptx
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract Drafting
 
Calling of a demand guarantee
Calling of a demand guaranteeCalling of a demand guarantee
Calling of a demand guarantee
 
Contract of guarantee
Contract of guaranteeContract of guarantee
Contract of guarantee
 
C ps, css, rep & warranties
C ps, css, rep & warrantiesC ps, css, rep & warranties
C ps, css, rep & warranties
 
Non Fund Based Credit Facilities (BG & LC)
Non Fund Based Credit Facilities (BG & LC)Non Fund Based Credit Facilities (BG & LC)
Non Fund Based Credit Facilities (BG & LC)
 
dischargeofcontract-170721054842 (1).pdf
dischargeofcontract-170721054842 (1).pdfdischargeofcontract-170721054842 (1).pdf
dischargeofcontract-170721054842 (1).pdf
 
Discharge of contract (Business Law)
Discharge of contract (Business Law)Discharge of contract (Business Law)
Discharge of contract (Business Law)
 
Contract of guarantee
Contract of guaranteeContract of guarantee
Contract of guarantee
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
 
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsLetters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
 
BUSINESS LAWS( CONTRACT OF GUARANTEE)SUDHARSHAN.pptx
BUSINESS LAWS( CONTRACT OF GUARANTEE)SUDHARSHAN.pptxBUSINESS LAWS( CONTRACT OF GUARANTEE)SUDHARSHAN.pptx
BUSINESS LAWS( CONTRACT OF GUARANTEE)SUDHARSHAN.pptx
 
Insolvency Resolution Process of Guarantors under IBC
Insolvency Resolution Process of Guarantors under IBCInsolvency Resolution Process of Guarantors under IBC
Insolvency Resolution Process of Guarantors under IBC
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
 

More from Werksmans Attorneys

More from Werksmans Attorneys (20)

Labour employment seminar 2016
Labour  employment seminar 2016Labour  employment seminar 2016
Labour employment seminar 2016
 
Reaching the summit - addressing the land question seminar
Reaching the summit - addressing the land question seminar Reaching the summit - addressing the land question seminar
Reaching the summit - addressing the land question seminar
 
Collusive tendering
Collusive tenderingCollusive tendering
Collusive tendering
 
Developing sexuality and sexual health policies in the disability sector
Developing sexuality and sexual health policies in the disability sector Developing sexuality and sexual health policies in the disability sector
Developing sexuality and sexual health policies in the disability sector
 
Recent developments in mining legislation and case law: Director Chris Stevens
Recent developments in mining legislation and case law: Director Chris StevensRecent developments in mining legislation and case law: Director Chris Stevens
Recent developments in mining legislation and case law: Director Chris Stevens
 
Business rescue: Saving distressed companies (Director Eric Levenstein and Se...
Business rescue: Saving distressed companies (Director Eric Levenstein and Se...Business rescue: Saving distressed companies (Director Eric Levenstein and Se...
Business rescue: Saving distressed companies (Director Eric Levenstein and Se...
 
Business rescue in mining: Peter van den Steen (VSquared)
Business rescue in mining: Peter van den Steen (VSquared)Business rescue in mining: Peter van den Steen (VSquared)
Business rescue in mining: Peter van den Steen (VSquared)
 
Environmental regulation of prospecting, exploration, mining and production: ...
Environmental regulation of prospecting, exploration, mining and production: ...Environmental regulation of prospecting, exploration, mining and production: ...
Environmental regulation of prospecting, exploration, mining and production: ...
 
WHEN GOOD CONSTRUCTION CONTRACTS GO BAD
WHEN GOOD CONSTRUCTION CONTRACTS GO BAD WHEN GOOD CONSTRUCTION CONTRACTS GO BAD
WHEN GOOD CONSTRUCTION CONTRACTS GO BAD
 
The Future of Section 197 in South Africa: Bradley Workman-Davies
The Future of Section 197 in South Africa: Bradley Workman-DaviesThe Future of Section 197 in South Africa: Bradley Workman-Davies
The Future of Section 197 in South Africa: Bradley Workman-Davies
 
The Employment Equity Amendment Act: Anastasia Vatalidis
The Employment Equity Amendment Act: Anastasia VatalidisThe Employment Equity Amendment Act: Anastasia Vatalidis
The Employment Equity Amendment Act: Anastasia Vatalidis
 
Controlling Strike Violence: Advocate Anton Myburgh SC
Controlling Strike Violence: Advocate Anton Myburgh SCControlling Strike Violence: Advocate Anton Myburgh SC
Controlling Strike Violence: Advocate Anton Myburgh SC
 
BBBEE Presentation Cape Town Seminar 29 August 2014
BBBEE Presentation Cape Town Seminar 29 August 2014BBBEE Presentation Cape Town Seminar 29 August 2014
BBBEE Presentation Cape Town Seminar 29 August 2014
 
VSquXred Business Rescue presentation
VSquXred Business Rescue presentation VSquXred Business Rescue presentation
VSquXred Business Rescue presentation
 
Foreign & local investment opportunities in South Africa offered by the busin...
Foreign & local investment opportunities in South Africa offered by the busin...Foreign & local investment opportunities in South Africa offered by the busin...
Foreign & local investment opportunities in South Africa offered by the busin...
 
Foreign & local investment opportunities in South Africa offered by the busin...
Foreign & local investment opportunities in South Africa offered by the busin...Foreign & local investment opportunities in South Africa offered by the busin...
Foreign & local investment opportunities in South Africa offered by the busin...
 
Healthcare and the Consumer Protection Act 68 of 2008 - Ahmore Burger-Smidt
Healthcare and the Consumer Protection Act 68 of 2008 - Ahmore Burger-SmidtHealthcare and the Consumer Protection Act 68 of 2008 - Ahmore Burger-Smidt
Healthcare and the Consumer Protection Act 68 of 2008 - Ahmore Burger-Smidt
 
The Competition Amendment Act No. 1 of 2009 - by director Dominique Arteiro
The Competition Amendment Act No. 1 of 2009 - by director Dominique ArteiroThe Competition Amendment Act No. 1 of 2009 - by director Dominique Arteiro
The Competition Amendment Act No. 1 of 2009 - by director Dominique Arteiro
 
Corporate social responsibility - by director Ina Meiring
 Corporate social responsibility - by director Ina Meiring Corporate social responsibility - by director Ina Meiring
Corporate social responsibility - by director Ina Meiring
 
The current status of the South African healthcare law programme - by Anele K...
The current status of the South African healthcare law programme - by Anele K...The current status of the South African healthcare law programme - by Anele K...
The current status of the South African healthcare law programme - by Anele K...
 

Recently uploaded

一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
Airst S
 
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
ShashankKumar441258
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
MollyBrown86
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
Airst S
 
PowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptxPowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptx
ca2or2tx
 
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
Airst S
 

Recently uploaded (20)

Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptx
 
The doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statuteThe doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statute
 
Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.
 
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxKEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
 
Hely-Hutchinson v. Brayhead Ltd .pdf
Hely-Hutchinson v. Brayhead Ltd         .pdfHely-Hutchinson v. Brayhead Ltd         .pdf
Hely-Hutchinson v. Brayhead Ltd .pdf
 
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdfNavigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
 
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
PPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxPPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptx
 
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 
CAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction FailsCAFC Chronicles: Costly Tales of Claim Construction Fails
CAFC Chronicles: Costly Tales of Claim Construction Fails
 
Police Misconduct Lawyers - Law Office of Jerry L. Steering
Police Misconduct Lawyers - Law Office of Jerry L. SteeringPolice Misconduct Lawyers - Law Office of Jerry L. Steering
Police Misconduct Lawyers - Law Office of Jerry L. Steering
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
 
PowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptxPowerPoint - Legal Citation Form 1 - Case Law.pptx
PowerPoint - Legal Citation Form 1 - Case Law.pptx
 
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
一比一原版(ECU毕业证书)埃迪斯科文大学毕业证如何办理
 
The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...
 

CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAND GUARANTEES

  • 1. CONSTRUCTION & ENGINEERING SEMINAR Jason Smit
  • 2. THE INTERPRETATION AND APPLICATION OF DEMAND GUARANTEES > 2 recent SCA cases: > Coface South Africa Insurance Co v East London Own Haven > Guardrisk Insurance Company Ltd v Kentz > Both establish the basic premise that “on-demand” guarantees are enforceable and payable on their terms alone > Absent fraud, issues arising as between the holder of a guarantee and the other party to an underlying contract are irrelevant and will not be considered by the courts 2
  • 3. GUARDRISK – BASIC FACTS > Kentz was involved as a contractor for the Medupi project > Contracted, in turn, with Brokrew Industrial for the supply of ducting > An advance payment was made by Ketz to Brokrew and Brokrew was required to obtain an advance payment guarantee, issued in favour of Kentz, as well as a performance guarantee > Guadrisk issued the guarantees > Brokrew subsequently ran into difficulties and could not perform in terms of the contract with Kentz > Kentz ultimate cancelled the contract and called the guarantees > Guardrisk resisted on the basis that Kentz’s claim was fraudulent 3
  • 4. GUARDRISK – ISSUES CONSIDERED > What was the nature of the guarantees? > Were they “conditional” or “on demand”? > The guarantees were held to be “on demand” instruments > The guarantees recorded that they held the guaranteed sums, as the disposal of the Employer, as security for Brokrew’s obligations > The guarantees bound the issuer as principal and not surety > Importantly, the guarantees stated that a dispute beween Employer and Contractor would not prevent payment > What is required to sustain a “fraud” allegation on the part of the issuing institution? > Where the party calling the guarantee does so in the knowledge that it is not entitled payment > The party alleging the fraud must prove it 4
  • 5. GUARDRISK – ISSUES CONSIDERED > Did the manner in which Kentz engaged with the contractor matter in relation to the enforcement of the guarantees? > Kentz issued two notices to the Contractor. > The first stated that Kentz was entitled to cancel the contract, reserved Kentz’s rights to do so and then demanded the remedying of certain defects > The second cancelled the contract > The court had no difficulty with this approach > Does the court have any reference to the underlying agreement? > No – this is not permissible > At the stage where demand is made in terms of a guarantee, all other disputes between Employer and Contractor are irrelevant > Payment in terms of a performance / demand guarantee are independent of the underlying contract 5
  • 6. COFACE – BASIC FACTS > Coface issued a performance guarantee in favour of ELOH > It undertook to pay in terms of the guarantee, on receipt of a demand stating that the underlying contract between ELOH and its contractor had been cancelled due to the contractor’s default > Coface contended that ELOH was not entitled to have cancelled the underlying contract and that it (Coface) therefore did not have to pay out under the guarantee > Coface attempted to introduce issues relevant to the underlying contract in order to avoid liability (design and errors in certification) 6
  • 7. COFACE – ISSUES CONSIDERED > In what circumstances can “extraneous” issues be considered when dealing with demand guarantees > Fraud > The introduction of underlying contractual disputes and the joining of other parties (contractors) etc should be avoided > As in the Guardrisk case, guarantees are enforceable on their terms > The previous SCA decision in the Dormell case was clearly incorrect 7
  • 8. > Both judgments confirm that a demand / call bond must be honoured on its terms > If those terms are met, no other issues are relevant for consideration by our courts > Underlying disputes between Employer and Contractor will not be considered > The fraud defence will not be lightly inferred > “Our courts, in a long line of cases and also relying on English authorities, have strictly applied the principle that a bank faced with a valid demand in respect of a performance guarantee, is obliged to pay the beneficiary without investigation of the contractual position between the beneficiary and the principal debtor” (Guardrisk) 8 GENERAL OBSERVATIONS FROM GUARDRISK AND COFACE
  • 9. STANDARD CONDITIONS DEALING WITH INSOLVENCY / BUSINESS RESCUE AND RESULTANT RIGHTS > FIDIC Silver Book > 15.2(e) – Employer is entitled to terminate if Contractor “becomes bankrupt or insolvent, goes into liquidation, has a receiving or administration order made against him, compounds with his creditors, carries on business under a receiver” > 16.2(f) – similar right for the Contractor > NEC PSC > 90.1 – “if the other Party has a winding up order made against it, has a provisional liquidator appointed, has an administration order made against it, has a receiver appointed, makes an arrangement with its creditors > JBCC Series 2000 > 36.1 – cancellation by Employer where Contractor fails to comply with 15.1 (BoQ, security etc) or 15.3 (progress with skill diligence, regularity) 9
  • 10. THINGS TO CONSIDER > Does the wording of security issued entitle the holder to claim without reference to the underlying contract? > Does the wording of the security issued entitle the holder to claim if its co-contracting party goes into business rescue, as opposed to being wound up? > Can the underlying contract be cancelled if the co-contracting party goes into business rescue? 10