This document discusses challenges with survey design, data collection, and data analysis for studies of marine wildlife related to offshore renewable energy projects. It notes issues such as insufficient survey effort within development areas, a lack of clarity around survey methods and objectives, imperfect detection of animals that is often ignored, and a need for standardized guidance on appropriate statistical analysis techniques. The document provides examples of resources on survey design and recommends a statistical analysis guidance document and software package developed to help address issues identified from offshore renewable energy monitoring projects.
3. Information available from range of sources:
Survey Design
• MMO (2014). Review of post-consent offshore wind farm monitoring data
associated with licence conditions.
• Oedekoven, et al (2013). Statistical Modelling of Seabird and Cetacean data:
Literature Review
• SNH (2011). Draft Guidance on Survey and Monitoring in Relation to Marine
Renewables Deployments in Scotland. Under revision?
• Camphuysen, et al (2004) Towards standardised seabirds at sea census
techniques in connection with environmental impact assessments for offshore wind
farms in the U.K.: a comparison of ship and aerial sampling methods for marine
birds, and their applicability to offshore wind farm assessments.
6. Offshore wind issues relevant to ‘wets’:
Survey Design
• Scale - appropriate to variability of metric
• Effort - driven by the question, variability of metric, magnitude of change of interest
• Effort - within development area often insufficient
• Monitoring- to tie responses to specific causes
• Transect spacing – default may not be appropriate
• No. surveys - unlikely to allow a change to be detected
• Control sites - unlikely to be appropriate
• Imperfect detection - often ignored
• Best practice - depends on species, site, metric, baseline variability, the question.
8. Survey Design
Sufficient effort in development site?
How much effort
is within lease
area?
Let alone the likely
development
footprint?
9. Survey Design
Is buffer relevant to lease area?
How similar are
environmental
conditions across
the survey area?
10. A B
E
D
F
C
X
Survey Design
Post-hoc subdivision of survey area
How much
effort in each
sub-division
How does
coverage
probability and
effort vary across
sub-divisions?
11. Survey Design
Also:
•VP unit of effort often unclear/ poorly defined (not snap shot so flux
measurement?)
•Detectability decreases with distance from observer but often ignored.
•For VPs, distance from shore confounds increasing distance from observer
but often (always?) ignored.
•Question being addressed and metric to be recorded often unclear.
Issues apparent from ‘wet’ renewables projects
13. Data Collection
• VP survey effort poorly/ inconsistently recorded
• Survey effort confounded?
What is true effort?
14. Data Collection
• VP survey effort poorly/ inconsistently recorded
• Survey effort confounded?
What is true effort?
15. Data Collection
• VP survey effort poorly/ inconsistently recorded
• Survey effort confounded
• Observers unclear on reasons for recording various aspects of
observations (especially effort).
18. Detection probability
What is true distribution?
Data Analysis
Confounding effect of increasing distance
from coast
• Imperfect detection
19. Data Analysis
• Imperfect detection
• Uncertainty not presented
• Unclear whether survey effort appropriate (no power analysis)
• Post-hoc subdivision of survey area/effort
• Lack of clarity over analyses methods used
• Diagnostic outputs not presented so impossible to come to view on
methods used (including Distance analysis)
20. MSS identified need for:
Data Analysis
• Review of available methods
• Guidance on most appropriate statistical analysis of bird and marine
mammal data routinely collected
• Freely available software to allow appropriate analysis
21. Clear need for guidance identified
Data Analysis
MRSea
•Contract awarded to CREEM at University of St Andrews
in 2013.
•Completed August 2013
•Workshop held September 2013
•Methods review, Guidance and software package freely
available to download:
http://www.scotland.gov.uk/Topics/marine/marineenergy/Research/SB9
22. Summary
• Range of experience to inform survey design, data collection and
analysis.
• Increasing body of guidance exists
• Wave & Tidal Stream Energy sites have distinct challenges
• Methods are evolving (and need to continue to do so)
Very brief overview of issues relating to survey design, data collection and data analysis of particular relevance to wave and tidal stream.
Some issues have been identified by experience with offshore wind projects,
Other issues identified over last few years during dealings with wave and tidal projects.
Guidance documents for offshore wind and wave & tidal available for some time.
More recently several reviews undertaken.
Whilst experience is greatest for offshore wind focus, also some valuable lessons for wave and tidal.
Line transect methodologies originated in Seabirds At Sea.
Aim was to ID seabird areas sensitive to oil spills.
However, survey design was not a dominant feature.
Vessels of opportunity, as can be seen by dominance of e.g. ferry routes or areas of greatest O&G shipping activity.
COWRIE guidance provided methodology for offshore wind transect surveys.
Relatively large sites within large areas of open water.
Guidance did highlight need for appropriate scales and survey effort.
Methods been applied over range of offshore wind projects (and to some extent wave and tidal)
Several reviews undertaken recently.
Whilst offshore wind focus, some important lessons for wave and tidal also.
“One size fits all” is not the case.
Also several issues encountered with wave and tidal projects perhaps less relevant to offshore wind
Application of ‘standard’ design may result in limited effort within the actual area of interest
For complex environments rather than large areas of open water, are buffers appropriate for providing wider context/ comparisons with lease area?
Lease area is swamped by buffer.
Wet renewables sites often selected due to very local conditions- is this reflected in the buffers?
Does this cause issues for both design and model-based density estimates?
Is comparison between lease area and buffer meaningful/ helpful?
Would it be reasonable to apply a density estimate derived from the entire survey area to the lease or development site only?
Has sufficient within lease area variability been captured to produce meaningful estimate?
Lack of suitable effort may be compounded by tidal cycle.
If you are interested in the lease area, design your survey accordingly.
Post-hoc subdivision of survey area.
Appropriate effort or coverage probability in each sub-division?
If you are likely to want to compare distributions/ abundance across the site, consider appropriate survey design OR analysis methods.
Several issues have also been encountered for wave and tidal projects that may be less relevant to offshore wind
Several issues have also been encountered for wave and tidal projects that may be less relevant to offshore wind
Movement of a vessel into the tide may result in increased encounter rates.
But effort (km of transect surveyed) does not account for this.
Movement of a vessel with the tide may result in reduced encounter rates.
But effort (km of transect surveyed) is the same as if vessel travels against the tide.
Surveys across the tide may complicate this further.
Does it matter?
It does if you are wanting to compare seasons, years, sites or pre/post construction.
It does if you want robust absolute abundance estimates to allow effect to be quantified e.g. collision risk modelling
It is difficult for surveyors/ observers to record data effectively if they do not understand the importance of what the are recording.
Make life as easy as possible for observers- think about them when designing surveys and recording protocols.
The final topic.
VP surveys often ignore the issues of declining detectability with increasing distance from observer.
For land based VPs, further complicated by compounding effect of increasing distance from coast.
If these are ignored, can you say anything meaningful about distribution and abundance at the site?
Several issues have also been encountered for wave and tidal projects that may be less relevant to offshore wind
Clear need from advisors to ensure provision of robust advice and developers/practitioners to ensure best practice is followed.