Global Supplier Quality
Early Production Containment Training
Supplier Early Production Containment Process Overview
 Purpose: Protect the customer by increasing confidence that all Early Production
Containment(EPC) shipments will meet Delphi’s Technologies quality expectations and
validate the production control plan; Requirements will be define by AQE during
Advanced Product Quality Planning and includes the utilization of a Pre-Launch
Control Plan;
 Covers production runs during the start-up and acceleration of a new/changed product,
manufacturing process;
 The minimum timeframe is (30) regular production days. Actual timeframe to be
determined by Delphi and communicated to the supplier;
 It is possible for a supplier to exit some EPC activity while keeping other portions in
place as part of the production control plan;
 Any defects found at a Delphi plant or at a customer location require a 5 why analysis
and additional containment activities. Documents may need to be reviewed and updated
or additional clarification of requirements may be required.
Presentation Title | Date | Confidential
2
Supplier Early Production Containment Process Overview
Presentation Title | Date | Confidential
3
 Agreement between the AQE and supplier on early production containment
requirements and exit criteria are important. This activity should be documented
and well understood by both parties. The AQE may want to conduct an audit of this
activity as well as request and review data on a regular basis.
 Exiting will be based on the following:
• The effectiveness of the EPC to meet Delphi’s expectations of Zero Defects;
• All problem cases related to this specific product closed, or a Delphi approved plan to close;
• Production Control Plan validated. Gate charts reviewed;
• Delphi supplier quality engineer has verified all exit criteria has been met.
Supplier Early Production Containment Process Overview
Pre-Launch Control Plan
Presentation Title | Date | Confidential
4
Supplier Early Production Containment Process Overview
Presentation Title | Date | Confidential
5
 Pre-Launch Control Plan contains all the EPC strategies;
 Must contain the same controls that are documented in the regular production
control plan;
• In addition, special efforts over and above regular controls should be implemented;
 Should contain all known critical conditions/characteristics of a part, and any other
potential areas of concern;
 In general, all special characteristics should be 100% checked;
• Process parameters, which are determined to have a direct effect on special characteristics should
also be monitored and documented at an increased frequency.
Pre-Launch Control Plan Overview
Supplier Early Production Containment Process Overview
Presentation Title | Date | Confidential
6
 The control plan needs to be reviewed to ensure that it comprehends correct
inspection frequencies as well as a lot control strategy. The PFD may need to be
reviewed to comprehend setup and other hidden factory items (reject handling);
 Any defects found during pilot / prototype runs must be comprehended in the Pre-
Launch Control Plan;
• A gate chart should be kept during all runs prior to PPAP. That gate chart should determine some of
the items to be checked/controlled as additional verification during the EPC period;
• This gate chart should be updated and reviewed prior to exiting the pre-launch activity. If corrective
actions are implemented, you would expect to see no more of that type of defect if the corrective
action was adequate. All suspect parts must be analyzed .
Pre-Launch Control Plan Overview
Supplier Early Production Containment Process Overview
Presentation Title | Date | Confidential
7
 Quality control documentation should be reviewed based on data collected. The
PFMEA and control plan should be updated to comprehend and control new failure
modes as well as RPN values;
 Part variation within a product family should be comprehended (Reference slide 14
for more information);
 Labeling and incoming inspection should also be part of the control plan
verification strategy. Variation of incoming material may yield information to
internal variation. Labeling is a serious issue throughout many organizations;
 Living document, must be submitted for PPAP and each time there is a revision;
 Certain EPC controls may remain as part of the standard production flow and
should be documented in the Production Control Plan(PCP).
Pre-Launch Control Plan Overview
Supplier Early Production Containment Process Overview
Supplier - Early Production
Containment Overall Strategy
Summary
8
Supplier Early Production Containment Process Overview
9
 Identification of person responsible ;
 Development of the Pre-launch Control Plan ;
 Establishment of a reaction plan for immediate containment and notification of
Delphi;
 Identification of the measurement equipment and data collection devices/activities.
Overall Strategy Summary
Supplier Early Production Containment Process Overview
10
 Early production containment (EPC) activities (extra inspection) treated the same
as regular production activities.
• Work instructions, training, verification of gauges, data collection, reaction plans and management
layered audits need to included;
• Without a standard method for measurement the values mean nothing. (consider touch point
inspection);
• Layered audits should verify standard work, part handling, reaction to abnormal activities as well as
monitoring good quality practices;
• Audit data (product and process) must be collected, plotted, and reviewed at a regular basis. If defects
are found at the audit inspection points, the audits must remain in place;
• The supplier’s launch team should review all defects(minimum daily) and establish corrective action
plans. New (unknown) defects need special attention to determine root cause quickly.
Overall Strategy Summary
Supplier Early Production Containment Process Overview
11
 Processes should be monitored at a regular frequency based on validation and
verification of stability over time;
• If there is not sufficient data to validate the frequency established in the production control plan, the
early production containment plan should include gathering the process data at an increased frequency
(at least twice as often as recommended) and looking at stability over time to justify the monitoring
frequency on the production control plan;
 There should also be Special reaction to the produced product if the processes are
found to be unstable;
 If issues are discovered at the additional inspection area, extra inspection (reactive
containment)prior to that step may be required. The extra inspection (reactive
containment) can focus on the specific problem and not detract from the complete
inspection that is already in place.
Overall Strategy Summary
Supplier Early Production Containment Process Overview
12
 If instructed by Delphi, supplier will implement an EPC utilizing all or elements of
the formal Controlled Shipping 2 process
 If the defect rate is abnormal (FTQ), extra containment should be in place until a
root cause has been identified and corrective actions are in place. The additional
audit activity should remain until sufficient data has been gathered to justify
removal of that activity. If processes are scheduled to be added later for
improvements in quality or capacity, they should also be placed into an early
production containment process to verify their controls are adequate.
 Handling of parts should also be observed. Defects generated as a result of handling
need to be reviewed for possible changes in packaging or standard work practices.
Overall Strategy Summary
Supplier Early Production Containment Process Overview
13
 Based on historical production process indicators, additional controls may include:
• Increased frequency/sample size at value stream inspection points
• Mandated sub-supplier containment and/or supplier audits
• Addition of inspection/control items and functional testing
• Increased verification of label accuracy
• Statistical evaluations
• Enhancement of process controls
• Increased verification of error proofing
• Increased involvement and visibility of top management
• Increased audits, verifying key manufacturing quality fundamentals such as standard work, part
handling and adherence to established quality practices
Overall Strategy Summary
Supplier Early Production Containment Process Overview
14
 Families of variation must be comprehended in the control strategy. Data must be
collected and reviewed based on the variation expected. This makes setting a
required time or quantity difficult.
 In general the strategy must capture a sufficient amount of data to demonstrate
process stability throughout the known families of variation and a significant
production quantity (e.g. 10% of the first year’s volume) Some examples may
include:
• Multiple setups;
• Multiple molds or presses;
• Multiple batches;
• Multiple incoming batches;
Overall Strategy Summary
• Multiple operators;
• Multiple process settings;
• Multiple flow paths;
• Variation within a batch.
Supplier Early Production Containment Process Overview
Low volume example
For a bulk material produced in large quantities on an infrequent basis, the AQE may want to see
multiple samples from the same batch and samples from multiple batches as well as documenting
of certain process settings for each batch.
If there is some knowledge that the material is sensitive to operator setup, the AQE may request
that each batch be prepared by a separate operator.
If there is some knowledge that the material varies with temperature extremes, the AQE may
request that batches be sampled at various intervals throughout the entire year.
If the material will be produced by multiple processes each process should be validated through
the early production containment requirements.
Presentation Title | Date | Confidential
15
Early Production Containment Examples
Supplier Early Production Containment Process Overview
Presentation Title | Date | Confidential
16
High volume example
For a high volume press operation producing thousands of parts per hour the AQE may ask the
supplier to measure some quantity of parts at a set time sequence to look at wear or heat up
issues.
The AQE may ask for measurements to be taken at each tool setup to look for setup variation.
The AQE may also want additional sampling after any tool maintenance. Since so many parts are
produced so quickly it would not make sense to base exit criteria on number of pieces.
If the setup could be operator dependent then the AQE would want to ask for multiple setups by
multiple operators with multiple incoming lots to try to capture many of the known areas of
variation. Again, it may take some time to complete a run sequence to collect data from all the
areas of possible variation so a set time would probably not be applicable either.
Early Production Containment Examples
Supplier Early Production Containment Process Overview
 Supplier Containment Procedure
Presentation Title | Date | Confidential
17
Procedure Link
Thank you.

More Related Content

Similar to Early Production Containment Training.pptx

2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems (1).pdf
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems (1).pdf2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems (1).pdf
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems (1).pdf
mmmmm624454
 
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems.pptx
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems.pptx2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems.pptx
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems.pptx
ValentinoDhiyu1
 

Similar to Early Production Containment Training.pptx (20)

Process validation
Process validationProcess validation
Process validation
 
Validation master plan
Validation master planValidation master plan
Validation master plan
 
Pilot plant scaleup.pptx
Pilot plant scaleup.pptxPilot plant scaleup.pptx
Pilot plant scaleup.pptx
 
Update on-pda-tr22-revisions-for-aseptic-process-simulations
Update on-pda-tr22-revisions-for-aseptic-process-simulationsUpdate on-pda-tr22-revisions-for-aseptic-process-simulations
Update on-pda-tr22-revisions-for-aseptic-process-simulations
 
Umer al faisal
Umer al faisalUmer al faisal
Umer al faisal
 
Prospective Validation NSR.pdf
Prospective Validation NSR.pdfProspective Validation NSR.pdf
Prospective Validation NSR.pdf
 
Presentation Updating the Manufacturing Principles
Presentation Updating the Manufacturing Principles Presentation Updating the Manufacturing Principles
Presentation Updating the Manufacturing Principles
 
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems (1).pdf
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems (1).pdf2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems (1).pdf
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems (1).pdf
 
GMP- APQR training
GMP- APQR  trainingGMP- APQR  training
GMP- APQR training
 
GMP- APQR Training
GMP- APQR TrainingGMP- APQR Training
GMP- APQR Training
 
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems.pptx
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems.pptx2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems.pptx
2015_GMP_Validation_Forum_Deviation-Incident-Non-conformance-Systems.pptx
 
Change control
Change controlChange control
Change control
 
Pharmaceutical validation.pptx
Pharmaceutical validation.pptxPharmaceutical validation.pptx
Pharmaceutical validation.pptx
 
Validation
ValidationValidation
Validation
 
Notes for the subject 'Pharmaceutical Validation'
Notes for the subject 'Pharmaceutical Validation' Notes for the subject 'Pharmaceutical Validation'
Notes for the subject 'Pharmaceutical Validation'
 
VALIDATION BY DHIRAJ SHRESTHA
VALIDATION BY DHIRAJ SHRESTHAVALIDATION BY DHIRAJ SHRESTHA
VALIDATION BY DHIRAJ SHRESTHA
 
Technology transfer plan & exhibit
Technology transfer plan & exhibit Technology transfer plan & exhibit
Technology transfer plan & exhibit
 
Auditing and inspection
Auditing and inspectionAuditing and inspection
Auditing and inspection
 
validationandcalibrationmasterplan-190223191733.pptx
validationandcalibrationmasterplan-190223191733.pptxvalidationandcalibrationmasterplan-190223191733.pptx
validationandcalibrationmasterplan-190223191733.pptx
 
Basic concept of process validation
Basic concept of process validation Basic concept of process validation
Basic concept of process validation
 

Recently uploaded

一比一原版SDSU毕业证圣地亚哥州立大学毕业证成绩单如何办理
一比一原版SDSU毕业证圣地亚哥州立大学毕业证成绩单如何办理一比一原版SDSU毕业证圣地亚哥州立大学毕业证成绩单如何办理
一比一原版SDSU毕业证圣地亚哥州立大学毕业证成绩单如何办理
psavhef
 
The Future of Autonomous Vehicles | civilthings.com | Detailed information
The Future of Autonomous Vehicles | civilthings.com |  Detailed informationThe Future of Autonomous Vehicles | civilthings.com |  Detailed information
The Future of Autonomous Vehicles | civilthings.com | Detailed information
gettygaming1
 
Car Seat Covers and Seat Protection Guide
Car Seat Covers and Seat Protection GuideCar Seat Covers and Seat Protection Guide
Car Seat Covers and Seat Protection Guide
AskXX.com
 

Recently uploaded (8)

Essential Maintenance Tips For Commercial Vans.
Essential Maintenance Tips For Commercial Vans.Essential Maintenance Tips For Commercial Vans.
Essential Maintenance Tips For Commercial Vans.
 
一比一原版SDSU毕业证圣地亚哥州立大学毕业证成绩单如何办理
一比一原版SDSU毕业证圣地亚哥州立大学毕业证成绩单如何办理一比一原版SDSU毕业证圣地亚哥州立大学毕业证成绩单如何办理
一比一原版SDSU毕业证圣地亚哥州立大学毕业证成绩单如何办理
 
gtyccccccccccccccccccccccccccccccccccccccccccccccccccccccc
gtycccccccccccccccccccccccccccccccccccccccccccccccccccccccgtyccccccccccccccccccccccccccccccccccccccccccccccccccccccc
gtyccccccccccccccccccccccccccccccccccccccccccccccccccccccc
 
What Should You Do If Your Jaguar XF Bluetooth Isn't Working
What Should You Do If Your Jaguar XF Bluetooth Isn't WorkingWhat Should You Do If Your Jaguar XF Bluetooth Isn't Working
What Should You Do If Your Jaguar XF Bluetooth Isn't Working
 
The Future of Autonomous Vehicles | civilthings.com | Detailed information
The Future of Autonomous Vehicles | civilthings.com |  Detailed informationThe Future of Autonomous Vehicles | civilthings.com |  Detailed information
The Future of Autonomous Vehicles | civilthings.com | Detailed information
 
Car Seat Covers and Seat Protection Guide
Car Seat Covers and Seat Protection GuideCar Seat Covers and Seat Protection Guide
Car Seat Covers and Seat Protection Guide
 
Advanced Technology for Auto Part Industry Inventory Solutions
Advanced Technology for Auto Part Industry Inventory SolutionsAdvanced Technology for Auto Part Industry Inventory Solutions
Advanced Technology for Auto Part Industry Inventory Solutions
 
Core technology of Hyundai Motor Group's EV platform 'E-GMP'
Core technology of Hyundai Motor Group's EV platform 'E-GMP'Core technology of Hyundai Motor Group's EV platform 'E-GMP'
Core technology of Hyundai Motor Group's EV platform 'E-GMP'
 

Early Production Containment Training.pptx

  • 1. Global Supplier Quality Early Production Containment Training
  • 2. Supplier Early Production Containment Process Overview  Purpose: Protect the customer by increasing confidence that all Early Production Containment(EPC) shipments will meet Delphi’s Technologies quality expectations and validate the production control plan; Requirements will be define by AQE during Advanced Product Quality Planning and includes the utilization of a Pre-Launch Control Plan;  Covers production runs during the start-up and acceleration of a new/changed product, manufacturing process;  The minimum timeframe is (30) regular production days. Actual timeframe to be determined by Delphi and communicated to the supplier;  It is possible for a supplier to exit some EPC activity while keeping other portions in place as part of the production control plan;  Any defects found at a Delphi plant or at a customer location require a 5 why analysis and additional containment activities. Documents may need to be reviewed and updated or additional clarification of requirements may be required. Presentation Title | Date | Confidential 2
  • 3. Supplier Early Production Containment Process Overview Presentation Title | Date | Confidential 3  Agreement between the AQE and supplier on early production containment requirements and exit criteria are important. This activity should be documented and well understood by both parties. The AQE may want to conduct an audit of this activity as well as request and review data on a regular basis.  Exiting will be based on the following: • The effectiveness of the EPC to meet Delphi’s expectations of Zero Defects; • All problem cases related to this specific product closed, or a Delphi approved plan to close; • Production Control Plan validated. Gate charts reviewed; • Delphi supplier quality engineer has verified all exit criteria has been met.
  • 4. Supplier Early Production Containment Process Overview Pre-Launch Control Plan Presentation Title | Date | Confidential 4
  • 5. Supplier Early Production Containment Process Overview Presentation Title | Date | Confidential 5  Pre-Launch Control Plan contains all the EPC strategies;  Must contain the same controls that are documented in the regular production control plan; • In addition, special efforts over and above regular controls should be implemented;  Should contain all known critical conditions/characteristics of a part, and any other potential areas of concern;  In general, all special characteristics should be 100% checked; • Process parameters, which are determined to have a direct effect on special characteristics should also be monitored and documented at an increased frequency. Pre-Launch Control Plan Overview
  • 6. Supplier Early Production Containment Process Overview Presentation Title | Date | Confidential 6  The control plan needs to be reviewed to ensure that it comprehends correct inspection frequencies as well as a lot control strategy. The PFD may need to be reviewed to comprehend setup and other hidden factory items (reject handling);  Any defects found during pilot / prototype runs must be comprehended in the Pre- Launch Control Plan; • A gate chart should be kept during all runs prior to PPAP. That gate chart should determine some of the items to be checked/controlled as additional verification during the EPC period; • This gate chart should be updated and reviewed prior to exiting the pre-launch activity. If corrective actions are implemented, you would expect to see no more of that type of defect if the corrective action was adequate. All suspect parts must be analyzed . Pre-Launch Control Plan Overview
  • 7. Supplier Early Production Containment Process Overview Presentation Title | Date | Confidential 7  Quality control documentation should be reviewed based on data collected. The PFMEA and control plan should be updated to comprehend and control new failure modes as well as RPN values;  Part variation within a product family should be comprehended (Reference slide 14 for more information);  Labeling and incoming inspection should also be part of the control plan verification strategy. Variation of incoming material may yield information to internal variation. Labeling is a serious issue throughout many organizations;  Living document, must be submitted for PPAP and each time there is a revision;  Certain EPC controls may remain as part of the standard production flow and should be documented in the Production Control Plan(PCP). Pre-Launch Control Plan Overview
  • 8. Supplier Early Production Containment Process Overview Supplier - Early Production Containment Overall Strategy Summary 8
  • 9. Supplier Early Production Containment Process Overview 9  Identification of person responsible ;  Development of the Pre-launch Control Plan ;  Establishment of a reaction plan for immediate containment and notification of Delphi;  Identification of the measurement equipment and data collection devices/activities. Overall Strategy Summary
  • 10. Supplier Early Production Containment Process Overview 10  Early production containment (EPC) activities (extra inspection) treated the same as regular production activities. • Work instructions, training, verification of gauges, data collection, reaction plans and management layered audits need to included; • Without a standard method for measurement the values mean nothing. (consider touch point inspection); • Layered audits should verify standard work, part handling, reaction to abnormal activities as well as monitoring good quality practices; • Audit data (product and process) must be collected, plotted, and reviewed at a regular basis. If defects are found at the audit inspection points, the audits must remain in place; • The supplier’s launch team should review all defects(minimum daily) and establish corrective action plans. New (unknown) defects need special attention to determine root cause quickly. Overall Strategy Summary
  • 11. Supplier Early Production Containment Process Overview 11  Processes should be monitored at a regular frequency based on validation and verification of stability over time; • If there is not sufficient data to validate the frequency established in the production control plan, the early production containment plan should include gathering the process data at an increased frequency (at least twice as often as recommended) and looking at stability over time to justify the monitoring frequency on the production control plan;  There should also be Special reaction to the produced product if the processes are found to be unstable;  If issues are discovered at the additional inspection area, extra inspection (reactive containment)prior to that step may be required. The extra inspection (reactive containment) can focus on the specific problem and not detract from the complete inspection that is already in place. Overall Strategy Summary
  • 12. Supplier Early Production Containment Process Overview 12  If instructed by Delphi, supplier will implement an EPC utilizing all or elements of the formal Controlled Shipping 2 process  If the defect rate is abnormal (FTQ), extra containment should be in place until a root cause has been identified and corrective actions are in place. The additional audit activity should remain until sufficient data has been gathered to justify removal of that activity. If processes are scheduled to be added later for improvements in quality or capacity, they should also be placed into an early production containment process to verify their controls are adequate.  Handling of parts should also be observed. Defects generated as a result of handling need to be reviewed for possible changes in packaging or standard work practices. Overall Strategy Summary
  • 13. Supplier Early Production Containment Process Overview 13  Based on historical production process indicators, additional controls may include: • Increased frequency/sample size at value stream inspection points • Mandated sub-supplier containment and/or supplier audits • Addition of inspection/control items and functional testing • Increased verification of label accuracy • Statistical evaluations • Enhancement of process controls • Increased verification of error proofing • Increased involvement and visibility of top management • Increased audits, verifying key manufacturing quality fundamentals such as standard work, part handling and adherence to established quality practices Overall Strategy Summary
  • 14. Supplier Early Production Containment Process Overview 14  Families of variation must be comprehended in the control strategy. Data must be collected and reviewed based on the variation expected. This makes setting a required time or quantity difficult.  In general the strategy must capture a sufficient amount of data to demonstrate process stability throughout the known families of variation and a significant production quantity (e.g. 10% of the first year’s volume) Some examples may include: • Multiple setups; • Multiple molds or presses; • Multiple batches; • Multiple incoming batches; Overall Strategy Summary • Multiple operators; • Multiple process settings; • Multiple flow paths; • Variation within a batch.
  • 15. Supplier Early Production Containment Process Overview Low volume example For a bulk material produced in large quantities on an infrequent basis, the AQE may want to see multiple samples from the same batch and samples from multiple batches as well as documenting of certain process settings for each batch. If there is some knowledge that the material is sensitive to operator setup, the AQE may request that each batch be prepared by a separate operator. If there is some knowledge that the material varies with temperature extremes, the AQE may request that batches be sampled at various intervals throughout the entire year. If the material will be produced by multiple processes each process should be validated through the early production containment requirements. Presentation Title | Date | Confidential 15 Early Production Containment Examples
  • 16. Supplier Early Production Containment Process Overview Presentation Title | Date | Confidential 16 High volume example For a high volume press operation producing thousands of parts per hour the AQE may ask the supplier to measure some quantity of parts at a set time sequence to look at wear or heat up issues. The AQE may ask for measurements to be taken at each tool setup to look for setup variation. The AQE may also want additional sampling after any tool maintenance. Since so many parts are produced so quickly it would not make sense to base exit criteria on number of pieces. If the setup could be operator dependent then the AQE would want to ask for multiple setups by multiple operators with multiple incoming lots to try to capture many of the known areas of variation. Again, it may take some time to complete a run sequence to collect data from all the areas of possible variation so a set time would probably not be applicable either. Early Production Containment Examples
  • 17. Supplier Early Production Containment Process Overview  Supplier Containment Procedure Presentation Title | Date | Confidential 17 Procedure Link