Case study : Dell Inc. Improving the Flexibility
of the Desktop PC Supply Chain
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 2/26
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 3/26




DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 4/26




DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 5/26




DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 6/26
MOTHERBOARD
Nervous System of a computer
that contains the circuity of the
central processing system
CHASSIS
Enclosure of framework case
that contains and protects all
the vital internal components
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 7/26



DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 8/26

DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 9/26


DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 10/26


•
•
•
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 11/26
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 12/26








DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 13/26




DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 14/26
91% 94% 96%
90% 85%
73%
9% 6% 4%
10% 15%
27%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
January 05 February 05 March 05 April 05 May 05 June 05
L6 L5
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 15/26





DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 16/26




DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 17/26
Option 1 Option 2 Option 2* Option 3A Option 3B Option 4 Option 5
Worlwide procurement 10 1 1 1 1 5 10
Regional procurement 8 5 5 5 5 5 10
Master scheduler 5 5 5 5 5 5 5
Production control 5 10 10 7 7 7 5
Operations 1 10 10 5 5 1 1
DAO Quality 5 10 10 5 5 1 1
Processing engineering 1 10 10 5 5 1 1
Supplier quality
engineering (regional)
10 1 1 1 1 5 7
Supplier quality
engineering (global)
1 1 1 1 1 1 10
Cost accounting 5 1 1 10 10 10 1
Inventory control 1 5 5 5 7 10 1
Logistics 5 1 1 5 5 5 10
TOTAL (complexity level) 57 60 60 55 57 56 62
COST PER BOX $10,07 $7,00 $7,90 $7,54 $7,70 $7,61 $7,00
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 18/26
 
 
 
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 19/26
•

•
•

•

•
•
Option 1 Option 3A
Worlwide procurement 10 1
Regional procurement 8 5
Master scheduler 5 5
Production control 5 7
Operations 1 5
DAO Quality 5 5
Processing engineering 1 5
Supplier quality
engineering (regional)
10 1
Supplier quality
engineering (global)
1 1
Cost accounting 5 10
Inventory control 1 5
Logistics 5 5
TOTAL (complexity
level)
57 55
COST PER BOX $10,07 $7,54
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 20/26


DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 21/26
•
•
•
 

•
Option 1 Option 2
Worlwide procurement 10 1
Regional procurement 8 5
Master scheduler 5 5
Production control 5 10
Operations 1 10
DAO Quality 5 10
Processing engineering 1 10
Supplier quality
engineering (regional)
10 1
Supplier quality
engineering (global)
1 1
Cost accounting 5 1
Inventory control 1 5
Logistics 5 1
TOTAL (complexity level) 57 60
COST PER BOX $10,07 $7,00
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 22/26
•
•
•
•
•
•
•
•
•
•
3A
2
DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 23/26




DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 24/26




DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes 25/26
26/26DELL Case Study | Coordination in the Supply Chain Management | Group 1 | ESC Rennes
Dell Corporation - Case Study

Dell Corporation - Case Study

  • 1.
    Case study :Dell Inc. Improving the Flexibility of the Desktop PC Supply Chain
  • 2.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 2/26
  • 3.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 3/26    
  • 4.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 4/26    
  • 5.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 5/26    
  • 6.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 6/26 MOTHERBOARD Nervous System of a computer that contains the circuity of the central processing system CHASSIS Enclosure of framework case that contains and protects all the vital internal components
  • 7.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 7/26   
  • 8.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 8/26 
  • 9.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 9/26  
  • 10.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 10/26   • • •
  • 11.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 11/26
  • 12.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 12/26        
  • 13.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 13/26    
  • 14.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 14/26 91% 94% 96% 90% 85% 73% 9% 6% 4% 10% 15% 27% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% January 05 February 05 March 05 April 05 May 05 June 05 L6 L5
  • 15.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 15/26     
  • 16.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 16/26    
  • 17.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 17/26 Option 1 Option 2 Option 2* Option 3A Option 3B Option 4 Option 5 Worlwide procurement 10 1 1 1 1 5 10 Regional procurement 8 5 5 5 5 5 10 Master scheduler 5 5 5 5 5 5 5 Production control 5 10 10 7 7 7 5 Operations 1 10 10 5 5 1 1 DAO Quality 5 10 10 5 5 1 1 Processing engineering 1 10 10 5 5 1 1 Supplier quality engineering (regional) 10 1 1 1 1 5 7 Supplier quality engineering (global) 1 1 1 1 1 1 10 Cost accounting 5 1 1 10 10 10 1 Inventory control 1 5 5 5 7 10 1 Logistics 5 1 1 5 5 5 10 TOTAL (complexity level) 57 60 60 55 57 56 62 COST PER BOX $10,07 $7,00 $7,90 $7,54 $7,70 $7,61 $7,00
  • 18.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 18/26      
  • 19.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 19/26 •  • •  •  • • Option 1 Option 3A Worlwide procurement 10 1 Regional procurement 8 5 Master scheduler 5 5 Production control 5 7 Operations 1 5 DAO Quality 5 5 Processing engineering 1 5 Supplier quality engineering (regional) 10 1 Supplier quality engineering (global) 1 1 Cost accounting 5 10 Inventory control 1 5 Logistics 5 5 TOTAL (complexity level) 57 55 COST PER BOX $10,07 $7,54
  • 20.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 20/26  
  • 21.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 21/26 • • •    • Option 1 Option 2 Worlwide procurement 10 1 Regional procurement 8 5 Master scheduler 5 5 Production control 5 10 Operations 1 10 DAO Quality 5 10 Processing engineering 1 10 Supplier quality engineering (regional) 10 1 Supplier quality engineering (global) 1 1 Cost accounting 5 1 Inventory control 1 5 Logistics 5 1 TOTAL (complexity level) 57 60 COST PER BOX $10,07 $7,00
  • 22.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 22/26 • • • • • • • • • • 3A 2
  • 23.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 23/26    
  • 24.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 24/26    
  • 25.
    DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes 25/26
  • 26.
    26/26DELL Case Study| Coordination in the Supply Chain Management | Group 1 | ESC Rennes