This document contains a schedule for a proposed hotel project in Dehradun, India with a total duration of 1538 days from September 16, 2016 to December 1, 2020. It lists 35 tasks related to activities like obtaining building plans, site preparation, construction of floors and installation of services like HVAC, electrical, and plumbing. Key milestones include completion of the basement by September 2017, all construction works by October 2018, furnishing by June 2020, and project inauguration on December 1, 2020.