1. 1. General
Position Title and No. SITE INCHARGE
Name of Key Expert SHIW DAYAL SINGH
Name of the Firm proposing the Non Key
Expert
M/S CHETAN ENGINEERS
Date of Birth [06/01/1976]
Nationality Indian
Country of Citizenship/Residence SRI RAMSEWASADAN
GOVINDPUR(MAHARANICHOWK)
FATUHA,PATNA (BIHAR) PIN-803201
07874006329
2. Education:
EXAMINATION YEAR OF PASSING BOARD/UNIVERSITY PERCENTAGE OBTAINED
S.S.C 1991 BSEB (PATNA) 59.77
I.SC. 1993 BIEC (PATNA) 62.33
DIPLOMA
IN SURVEY
2000 D.G.M.S. ( DHANBAD ) PASS
B.TECH(CIVIL) 2005 U.P.T.U. (LUCKNOW) 71.92
3. Employment record relevant to the assignment: TOTAL-12YEARS-1MONTHS.
Period Employingorganization and your
title/position.
Contact information for references*
Country Summary of activities
performedrelevantto
the Assignment
[ Feb
2006 -
present]
Organisation:
M/S CHETAN ENGINEERS
PositionHeld: SITE INCHARGE
KAMLESH PATEL (OWNER)
NIKUNJPATEL (PROJECT MANAGER)
India
All type of civil works.
[ July
2004 -
May
2005]
Organisation: IJM.
PositionHeld:Surveyor.
RAJU BHAI (PROJECTMANAGER)
RAJESH SHARMA (SITE INCHARGE)
SURVEY WORKS.
2. 4. Language Skills (indicate only languages in which you can work):
Languages Read Write Spoken
English Excellent Excellent
Hindi Excellent Excellent Excellent
5. Adequacy for the Assignment:
Reference to Prior Work/Assignments that Best Illustrates Capability to Handle the Assigned Tasks
1.Project Name: : INR 49 CRORES CONSTRUCTION OF 4 LANE ROB ON CT-3/LNG ACCESS ROAD AT MUNDRA (SEZ).
Year: Nov-2014 to present
Location: MUNDRA (SEZ).Gujrat india.
Client: Adani
Main Project Features: in 1.1 KM. Rob.,pile , pile-cap , pier , pier-cap , psc – girder , rcc- girder,ms-girder ,
solid-slab , box-slab, re-panal.
Position Held: site incharge.
Activity Performed: (1) EXECUTION & SUPERVISION OF CONSTRUCTION WORKS (2) ORGANISING
MATERIALS ANDEQUIPEMENTS (3)LAYOUT OF COORDINATE,LEVEL AND CHECKING OF DIMENSION AS PER
DRAWINGS.(4) COORDINATION WITH CLIENT AND ASSOCIATED SUB-CONTRACTORS FOR TIMELY
COMPLETION OF WORKS (5) PREPARING BAR BENDING SCHEDULE (B.B.S) & QTY
2.Project Name: INR 30 CRORES WATER LILY PROJECT CONSISTING BUILDINGS.
Year: May-2012 to oct-2014
Location: Adani santigram ahmedabad gujrat.
Client: Adani
Main ProjectFeatures: GROUND TO BASMENT,LAKE, WALKWAYBRIDGE, PARKING SLAB, RETINGING WALL.
Position Held: SR. ENGINEER
Activity Performed: same to 1.
3.Project Name: INR 18 CRORES SURAT – DAHISAR BOT PROJECTS.
Year: Feb-2010 to April-2012
Location: vapi to valsad.
Client: IRB.
Main Project Features: MAJOR BRIDGE, FLY OVER, PEDESTRIAN UNDER PASS, VEHICLE UNDERPASS .
Position Held: SR. ENGINEER
3. Activity Performed: (1) EXECUTION & SUPERVISION OF CONSTRUCTION WORKS (2) ORGANISING
MATERIALS ANDEQUIPEMENTS (3)LAYOUT OF COORDINATE,LEVEL AND CHECKING OF DIMENSION AS PER
DRAWINGS.(4) PREPARING BAR BENDING SCHEDULE (B.B.S) & QTY
4.Project Name: INR 22 CRORES CONSTRUCTION OF 5 LANE ROB MUNDRA (SEZ).
Year: Aug-2008 to Jan-2010.
Location: MUNDRA (SEZ).Gujrat india.
Client: Adani
Main Project Features: in 1.02 KM. Rob.,pile , pile-cap , pier , pier-cap , psc – girder , solid-slab , box-slab,
re-panal.
Position Held: SR. ENGINEER
Activity Performed: (1) LAYOUT OF COORDINATE, LEVEL, DIMENSION AND BBS AS PER DRAWINGS
AND CHECKING TO CLINT.
5.Project Name: INR 6 CRORES SBC PUMPING SCHEME PROJECT .
Year: Feb-2006 to July-2008
Location: SURENDAR NAGER (GUJRAT).
Client: Kilosker-Brother ltd.
Main Project Features: PUMPING STATION NO-5 TO LIFT WATER 21 M WITHIN RANGE OF 54 M. IN CROSS
GATED, FOREBAY, VERTICAL TURBINE,CIRCULAR TURBINE, CONVERGENCE BAY & RCC SLAB.
Position Held: ENGINEER
Activity Performed: (1) EXECUTION & SUPERVISION OF WORKS .
6.Project Name: DELHI METRO CONNAUGHT PLACE-DWARKA SECTION LANE:-3
Year: July-2004 to may-2005
Location: motipur to pussa road.
Client: DMRC.
Main Project Features: pile , pile-cap , pier ,Pier-head, pier-cap , precast slab.
Position Held: SURVEYOR.
Activity Performed: (1) PRE-CAST SLAB LAUNCHING WITH COORDINATE, LEVEL AND DIMENSION AS
PER DRAWINGS AND CHECKING TO CLINT.