SlideShare a Scribd company logo
(a) Variable cost in total changes in relation to changes in volume, e.g. direct material and commission.
(b) Fixed cost in total remains constant when volume changes within the relevant range, e.g. rent,
depreciation.
(c) Different costs react differently when volume or activity changes.
(d) High-low method, scatter graph and the least squares method.
(e) This is the activity range wherein the assumption regarding cost behaviour is valid.
Question 2.1
Q2.1 Page 1 of 15
(a) MONTH UNITS COST
August 1,025 R1,050
June 750 R775
Difference 275 R275
Variable cost per unit R1.000
August:
Total cost R1,050
Total variable cost R1,025
Total fixed cost R25
June:
Total cost R775
Total variable cost R750
Total fixed cost R25
Units produced: 600
Total variable cost R600
Total fixed cost R25
Total cost R625
(b) Units produced: 1,000
Total variable cost R1,000
Total fixed cost R25
Total cost R1,025
Question 2.2
Q2.2 Page 2 of 15
a. C
b. B
c. B
d. A
e. B
Explanations:
a. Answers A and B describe the cost of specific cost units, and answer D describes a specific cost
unit. They are not general definitions of a cost unit.
b. Answer A describes total production cost. Answer C is only a part of prime cost. Answer D is an
overhead cost.
c. The total amount of fixed costs remains unchanged when production volume changes, therefore the
unit rate fluctuates.
d. OBSERVATIONS CONSULTATIONS COST
High 5,750 R289,125
Low 4,500 R269,750
Difference 1,250 R19,375
Variable cost per unit R15.500
With the same amount of fixed overheads at both activity levels, the change in overheads must be
due to extra variable cost.
e. The graph shows a variable cost which starts to be incurred only beyond a certain volume of output.
Only B fits this description of cost behaviour.
Question 2.3
Q2.3 Page 3 of 15
a. A and D
b. See below
c. See below
d. See below
e. See below
Explanations:
a. Machine rental cost is a stepped fixed cost. For one machine the total rental cost stays constant until
the machine is working at full capacity. Then two machines will be needed and the rental cost goes up
a step to a new higher level. When the two machines are at full capacity there will be a need to rent
three machines, and so on.
Depreciation on delivery vehicles is a stepped fixed cost. Depreciation is calculated on an annual basis
and is unlikely to be affected by the level of activity in the short term. For one vehicle the annual
depreciation is a constant amount. If two vehicles are required the depreciation cost goes up a step,
and so on.
Royalty costs and direct material costs are variable costs.
b. As activity increases within the relevant range, the total variable costs will increase. The variable cost
per unit will remain the same and the fixed cost per unit will decrease.
Question 2.4
Q2.4 Page 4 of 15
c. Variable cost per unit R2.000
Units produced 3,000
Total variable cost R6,000
Total fixed cost R4,000
Total cost R10,000
d. Suitable as cost centre Suitable as cost unit
Restaurant X
Guest night X
Meal served X
Fitness suite X
Bar X
e. The period fixed cost is approximately R150. Variable cost per unit is:
Total cost R500
Fixed cost R150
Difference R350
Units produced 200
Variable cost per unit R1.750
Q2.4 Page 5 of 15
When you are trying to determine whether a cost is direct or indirect, think about
whether the cost would need to be shared over several cost units or whether it can be
attributed directly to a particular unit. A cost that needs to be shared must be an
indirect cost.
ITEM CLASSIFICATION
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20 (v)
(iv)
(iv)
(vi)
(ii)
(vii)
(vii)
(vi)
(vi)
(vi)
(iii)
(i)
(iv)
(vi)
(iv)
(viii)
Question 2.5
(vii)
(vii)
(vii)
(iv)
Q2.5 Page 6 of 15
Cost of direct material
+ Cost of direct labour
+ Factory overheads
Direct material opening inventory
+ purchases
+ Import duties or any other cost to deliver material in storeroom
– direct material closing inventory
Wages paid
– wages owing at beginning of period
+ wages owing at end of period
Question 2.6
Question 2.7
Question 2.8
Q2.6 - 2.8 Page 7 of 15
(a) - ©
Indirect labour costs
Y
R4 000
B
R3 000 D
R2 000
Variable cost
R1 000
A
E
Fixed cost
0
Production units
Line AB is the line of best fit (total cost line)
Line AC is the fixed cost line (R800 per month).
600 800 1 000 1 200 1 400
Question 2.9
C
X
200 400
Q2.9 Page 8 of 15
The amount of the fixed cost is the distance between line OX and line AC = R800
The variable cost is the distance between line AC and line AB.
The variable cost rate (variable cost per unit) is the gradient (slope) of line AB.
The gradient of line AB is calculated as follows:
Choose any point on the diagram (for example, point E). From this point draw a vertical line to AB.
The gradient can now be computed as follows:
Vertical distance (change in cost)
Horizontal distance (change in production)
DE (R2 500 - R800)
AE (1 000 -0)
= R1.700 (variable cost per unit)
(d) Variable cost R3,400
Fixed cost R800
Total cost R4,200
Units produced 2,000
=
Q2.9 Page 9 of 15
(a) and (b)
Y
220
200 D B
180
160
140
120
100
80 A
60 E
40
20
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Production units
Line AB is the line of best fit (total cost line)
Line AC is the fixed cost line
Question 2.10
C
X
Semi-VariableCosts(R)
Q2.10 Page 10 of 15
(c) The amount of the fixed cost is the distance between line OX and line AC = R60
The variable cost is the distance between line AC and line AB.
The variable cost rate (variable cost per unit) is the gradient (slope) of line AB.
The gradient of line AB is calculated as follows:
Choose any point on the diagram (for example, point E). From this point draw a vertical line to AB.
The gradient can now be computed as follows:
Vertical distance (change in cost)
Horizontal distance (change in production)
DE (R190 - R60)
AE (25 -0)
= R5,20 (variable cost per unit)
=
Q2.10 Page 11 of 15
OBSERVATIONS UNITS COST
High 1,310 R4,995
Low 900 R3,560
Difference 410 R1,435
Variable cost per unit R3.500
June:
Total cost R4,995
Total variable cost R4,585
Total fixed cost R410
March:
Total cost R3,560
Total variable cost R3,150
Total fixed cost R410
Question 2.11
Q2.11 Page 12 of 15
2.12.1 C
2.12.2 B
2.12.3 D
2.12.4 D
2.12.5 A
2.12.6 C
2.12.7 B
2.12.8 A
2.12.9 B
2.12.10 D
2.12.11 A
2.12.12 D
2.12.13 B
Calculations:
2.12.6 Variable cost per unit R3.500
Units produced 17,000
Total cost @ 17 000 units R246,500
Total variable cost R59,500
Total fixed cost R187,000
Question 2.12
Q2.12 Page 13 of 15
2.12.8 OBSERVATION SQ METRES COST
High 15,100 R83,585
Low 12,750 R73,950
Difference 2,350 R9,635
Variable cost per unit R4.100
High:
Total cost R83,585
Total variable cost R61,910
Total fixed cost R21,675
Low:
Total cost R73,950
Total variable cost R52,275
Total fixed cost R21,675
Square metres: 16,200
Total variable cost R66,420
Total fixed cost R21,675
Total cost R88,095
Q2.12 Page 14 of 15
Question 2.

More Related Content

What's hot

COBB DOUGLAS PRODUCTION FUNCTION THEORY
COBB DOUGLAS PRODUCTION FUNCTION THEORYCOBB DOUGLAS PRODUCTION FUNCTION THEORY
COBB DOUGLAS PRODUCTION FUNCTION THEORY
Gourav Dholwal
 

What's hot (16)

8 c 2
8 c 28 c 2
8 c 2
 
Earned value
Earned value Earned value
Earned value
 
Example 2
Example 2Example 2
Example 2
 
Production and cost
Production and costProduction and cost
Production and cost
 
Accountancy
AccountancyAccountancy
Accountancy
 
simba nyakdee nyakudanga presentation on isoquants
simba nyakdee nyakudanga presentation on isoquantssimba nyakdee nyakudanga presentation on isoquants
simba nyakdee nyakudanga presentation on isoquants
 
COBB DOUGLAS PRODUCTION FUNCTION THEORY
COBB DOUGLAS PRODUCTION FUNCTION THEORYCOBB DOUGLAS PRODUCTION FUNCTION THEORY
COBB DOUGLAS PRODUCTION FUNCTION THEORY
 
ISOCOST & LEAST COST COMBINATION-CS.FINAL YEAR
ISOCOST & LEAST COST COMBINATION-CS.FINAL YEARISOCOST & LEAST COST COMBINATION-CS.FINAL YEAR
ISOCOST & LEAST COST COMBINATION-CS.FINAL YEAR
 
Absorption costing
Absorption costingAbsorption costing
Absorption costing
 
Copy of Financial report
Copy of Financial reportCopy of Financial report
Copy of Financial report
 
Cost of Production
Cost of ProductionCost of Production
Cost of Production
 
Isocost
IsocostIsocost
Isocost
 
firm cost of production
firm cost of productionfirm cost of production
firm cost of production
 
Production 2
Production 2Production 2
Production 2
 
MANAGEMENT ACCOUNTING
MANAGEMENT ACCOUNTING MANAGEMENT ACCOUNTING
MANAGEMENT ACCOUNTING
 
Purchase a new machine / Faten Al Joaid - Certified Auditor LACPA
Purchase a new machine / Faten Al Joaid - Certified Auditor LACPAPurchase a new machine / Faten Al Joaid - Certified Auditor LACPA
Purchase a new machine / Faten Al Joaid - Certified Auditor LACPA
 

Similar to Cost & man chapter 2 solutions 2008

EGT267 Programming for Engineering Applications Spring 2020 .docx
EGT267 Programming for Engineering Applications Spring 2020 .docxEGT267 Programming for Engineering Applications Spring 2020 .docx
EGT267 Programming for Engineering Applications Spring 2020 .docx
gidmanmary
 
Cost sheet with inventory
Cost sheet with inventoryCost sheet with inventory
Cost sheet with inventory
Prof_Ramana
 

Similar to Cost & man chapter 2 solutions 2008 (20)

Bsr3 a unit 1 2016
Bsr3 a unit 1   2016Bsr3 a unit 1   2016
Bsr3 a unit 1 2016
 
Pyndick chapter 7-production cost
Pyndick chapter 7-production costPyndick chapter 7-production cost
Pyndick chapter 7-production cost
 
Acct303 chapter2
Acct303 chapter2Acct303 chapter2
Acct303 chapter2
 
EGT267 Programming for Engineering Applications Spring 2020 .docx
EGT267 Programming for Engineering Applications Spring 2020 .docxEGT267 Programming for Engineering Applications Spring 2020 .docx
EGT267 Programming for Engineering Applications Spring 2020 .docx
 
Cost sheet1
Cost sheet1Cost sheet1
Cost sheet1
 
Replacement Theory. by Dr. Babasaheb. J. Mohite
Replacement Theory. by  Dr. Babasaheb. J. MohiteReplacement Theory. by  Dr. Babasaheb. J. Mohite
Replacement Theory. by Dr. Babasaheb. J. Mohite
 
Group ii-rtp-dec-2012
Group ii-rtp-dec-2012Group ii-rtp-dec-2012
Group ii-rtp-dec-2012
 
Chapter 08costos
Chapter 08costosChapter 08costos
Chapter 08costos
 
Chapter 7 cost of production
Chapter 7 cost of productionChapter 7 cost of production
Chapter 7 cost of production
 
Chapter10 noha2012
Chapter10 noha2012Chapter10 noha2012
Chapter10 noha2012
 
Job costing slides
Job costing slidesJob costing slides
Job costing slides
 
Economics of Power Generation(4) h.pdf
Economics of Power Generation(4)       h.pdfEconomics of Power Generation(4)       h.pdf
Economics of Power Generation(4) h.pdf
 
CA Unit-4 (Overhead) Problems and Solutions
CA Unit-4 (Overhead) Problems and SolutionsCA Unit-4 (Overhead) Problems and Solutions
CA Unit-4 (Overhead) Problems and Solutions
 
Cost sheet with inventory
Cost sheet with inventoryCost sheet with inventory
Cost sheet with inventory
 
Accounting
AccountingAccounting
Accounting
 
Economics 4
Economics 4Economics 4
Economics 4
 
economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami
 
Accounting problems 2
Accounting problems 2Accounting problems 2
Accounting problems 2
 
Management and Cost Accounting 7th Edition Drury Solutions Manual
Management and Cost Accounting 7th Edition Drury Solutions ManualManagement and Cost Accounting 7th Edition Drury Solutions Manual
Management and Cost Accounting 7th Edition Drury Solutions Manual
 
Production
ProductionProduction
Production
 

Recently uploaded

Digital Commerce Lecture for Advanced Digital & Social Media Strategy at UCLA...
Digital Commerce Lecture for Advanced Digital & Social Media Strategy at UCLA...Digital Commerce Lecture for Advanced Digital & Social Media Strategy at UCLA...
Digital Commerce Lecture for Advanced Digital & Social Media Strategy at UCLA...
Valters Lauzums
 
Liquid Staking: An Overview for Beginners in 2024
Liquid Staking: An Overview for Beginners in 2024Liquid Staking: An Overview for Beginners in 2024
Liquid Staking: An Overview for Beginners in 2024
nehapardhi711
 
Relatório da OMS / Unicef / IBFAN sobre a situação do Código Internacional de...
Relatório da OMS / Unicef / IBFAN sobre a situação do Código Internacional de...Relatório da OMS / Unicef / IBFAN sobre a situação do Código Internacional de...
Relatório da OMS / Unicef / IBFAN sobre a situação do Código Internacional de...
Prof. Marcus Renato de Carvalho
 
Unlocking Success: The Leading SEO Reseller Services in India
Unlocking Success: The Leading SEO Reseller Services in IndiaUnlocking Success: The Leading SEO Reseller Services in India
Unlocking Success: The Leading SEO Reseller Services in India
PitchPineMedia1
 

Recently uploaded (20)

The_Canvas_of_Creative_Mastery_Newsletter_May_2024_Version
The_Canvas_of_Creative_Mastery_Newsletter_May_2024_VersionThe_Canvas_of_Creative_Mastery_Newsletter_May_2024_Version
The_Canvas_of_Creative_Mastery_Newsletter_May_2024_Version
 
Kế hoạch Digital Marketing cho bánh Cosy
Kế hoạch Digital Marketing cho bánh CosyKế hoạch Digital Marketing cho bánh Cosy
Kế hoạch Digital Marketing cho bánh Cosy
 
Digital Commerce Lecture for Advanced Digital & Social Media Strategy at UCLA...
Digital Commerce Lecture for Advanced Digital & Social Media Strategy at UCLA...Digital Commerce Lecture for Advanced Digital & Social Media Strategy at UCLA...
Digital Commerce Lecture for Advanced Digital & Social Media Strategy at UCLA...
 
Liquid Staking: An Overview for Beginners in 2024
Liquid Staking: An Overview for Beginners in 2024Liquid Staking: An Overview for Beginners in 2024
Liquid Staking: An Overview for Beginners in 2024
 
Core Web Vitals SEO Workshop - improve your performance [pdf]
Core Web Vitals SEO Workshop - improve your performance [pdf]Core Web Vitals SEO Workshop - improve your performance [pdf]
Core Web Vitals SEO Workshop - improve your performance [pdf]
 
The What, Why & How of 3D and AR in Digital Commerce
The What, Why & How of 3D and AR in Digital CommerceThe What, Why & How of 3D and AR in Digital Commerce
The What, Why & How of 3D and AR in Digital Commerce
 
34-Rahul-Mande.pdf PROJECT REPORT MBA 4TH SEMESTER
34-Rahul-Mande.pdf PROJECT REPORT MBA 4TH SEMESTER34-Rahul-Mande.pdf PROJECT REPORT MBA 4TH SEMESTER
34-Rahul-Mande.pdf PROJECT REPORT MBA 4TH SEMESTER
 
Top 3 Ways to Align Sales and Marketing Teams for Rapid Growth
Top 3 Ways to Align Sales and Marketing Teams for Rapid GrowthTop 3 Ways to Align Sales and Marketing Teams for Rapid Growth
Top 3 Ways to Align Sales and Marketing Teams for Rapid Growth
 
Digital Marketing Training In Bangalore
Digital Marketing Training In BangaloreDigital Marketing Training In Bangalore
Digital Marketing Training In Bangalore
 
Awesome Free Global Opportunity Online Mining Crypto Currency On Your Mobile...
Awesome Free Global  Opportunity Online Mining Crypto Currency On Your Mobile...Awesome Free Global  Opportunity Online Mining Crypto Currency On Your Mobile...
Awesome Free Global Opportunity Online Mining Crypto Currency On Your Mobile...
 
How to Run Landing Page Tests On and Off Paid Social Platforms
How to Run Landing Page Tests On and Off Paid Social PlatformsHow to Run Landing Page Tests On and Off Paid Social Platforms
How to Run Landing Page Tests On and Off Paid Social Platforms
 
What is Digital Marketing? Advantages and Disadvantages
What is Digital Marketing? Advantages and DisadvantagesWhat is Digital Marketing? Advantages and Disadvantages
What is Digital Marketing? Advantages and Disadvantages
 
Relatório da OMS / Unicef / IBFAN sobre a situação do Código Internacional de...
Relatório da OMS / Unicef / IBFAN sobre a situação do Código Internacional de...Relatório da OMS / Unicef / IBFAN sobre a situação do Código Internacional de...
Relatório da OMS / Unicef / IBFAN sobre a situação do Código Internacional de...
 
Digital Money Maker Club – von Gunnar Kessler digital.
Digital Money Maker Club – von Gunnar Kessler digital.Digital Money Maker Club – von Gunnar Kessler digital.
Digital Money Maker Club – von Gunnar Kessler digital.
 
A Guide to UK Top Search Engine Optimization
A Guide to UK Top Search Engine OptimizationA Guide to UK Top Search Engine Optimization
A Guide to UK Top Search Engine Optimization
 
Unlocking Success: The Leading SEO Reseller Services in India
Unlocking Success: The Leading SEO Reseller Services in IndiaUnlocking Success: The Leading SEO Reseller Services in India
Unlocking Success: The Leading SEO Reseller Services in India
 
The Wealth of a Homeonwers association is analogous to the wealth of a Nation
The Wealth of a Homeonwers association is analogous to the wealth of a NationThe Wealth of a Homeonwers association is analogous to the wealth of a Nation
The Wealth of a Homeonwers association is analogous to the wealth of a Nation
 
15 ideas and frameworks on the art of storytelling
15 ideas and frameworks on the art of storytelling15 ideas and frameworks on the art of storytelling
15 ideas and frameworks on the art of storytelling
 
AI-Powered Personalization: Principles, Use Cases, and Its Impact on CRO
AI-Powered Personalization: Principles, Use Cases, and Its Impact on CROAI-Powered Personalization: Principles, Use Cases, and Its Impact on CRO
AI-Powered Personalization: Principles, Use Cases, and Its Impact on CRO
 
SMM Cheap - No. 1 SMM panel in the world
SMM Cheap - No. 1 SMM panel in the worldSMM Cheap - No. 1 SMM panel in the world
SMM Cheap - No. 1 SMM panel in the world
 

Cost & man chapter 2 solutions 2008

  • 1. (a) Variable cost in total changes in relation to changes in volume, e.g. direct material and commission. (b) Fixed cost in total remains constant when volume changes within the relevant range, e.g. rent, depreciation. (c) Different costs react differently when volume or activity changes. (d) High-low method, scatter graph and the least squares method. (e) This is the activity range wherein the assumption regarding cost behaviour is valid. Question 2.1 Q2.1 Page 1 of 15
  • 2. (a) MONTH UNITS COST August 1,025 R1,050 June 750 R775 Difference 275 R275 Variable cost per unit R1.000 August: Total cost R1,050 Total variable cost R1,025 Total fixed cost R25 June: Total cost R775 Total variable cost R750 Total fixed cost R25 Units produced: 600 Total variable cost R600 Total fixed cost R25 Total cost R625 (b) Units produced: 1,000 Total variable cost R1,000 Total fixed cost R25 Total cost R1,025 Question 2.2 Q2.2 Page 2 of 15
  • 3. a. C b. B c. B d. A e. B Explanations: a. Answers A and B describe the cost of specific cost units, and answer D describes a specific cost unit. They are not general definitions of a cost unit. b. Answer A describes total production cost. Answer C is only a part of prime cost. Answer D is an overhead cost. c. The total amount of fixed costs remains unchanged when production volume changes, therefore the unit rate fluctuates. d. OBSERVATIONS CONSULTATIONS COST High 5,750 R289,125 Low 4,500 R269,750 Difference 1,250 R19,375 Variable cost per unit R15.500 With the same amount of fixed overheads at both activity levels, the change in overheads must be due to extra variable cost. e. The graph shows a variable cost which starts to be incurred only beyond a certain volume of output. Only B fits this description of cost behaviour. Question 2.3 Q2.3 Page 3 of 15
  • 4. a. A and D b. See below c. See below d. See below e. See below Explanations: a. Machine rental cost is a stepped fixed cost. For one machine the total rental cost stays constant until the machine is working at full capacity. Then two machines will be needed and the rental cost goes up a step to a new higher level. When the two machines are at full capacity there will be a need to rent three machines, and so on. Depreciation on delivery vehicles is a stepped fixed cost. Depreciation is calculated on an annual basis and is unlikely to be affected by the level of activity in the short term. For one vehicle the annual depreciation is a constant amount. If two vehicles are required the depreciation cost goes up a step, and so on. Royalty costs and direct material costs are variable costs. b. As activity increases within the relevant range, the total variable costs will increase. The variable cost per unit will remain the same and the fixed cost per unit will decrease. Question 2.4 Q2.4 Page 4 of 15
  • 5. c. Variable cost per unit R2.000 Units produced 3,000 Total variable cost R6,000 Total fixed cost R4,000 Total cost R10,000 d. Suitable as cost centre Suitable as cost unit Restaurant X Guest night X Meal served X Fitness suite X Bar X e. The period fixed cost is approximately R150. Variable cost per unit is: Total cost R500 Fixed cost R150 Difference R350 Units produced 200 Variable cost per unit R1.750 Q2.4 Page 5 of 15
  • 6. When you are trying to determine whether a cost is direct or indirect, think about whether the cost would need to be shared over several cost units or whether it can be attributed directly to a particular unit. A cost that needs to be shared must be an indirect cost. ITEM CLASSIFICATION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 (v) (iv) (iv) (vi) (ii) (vii) (vii) (vi) (vi) (vi) (iii) (i) (iv) (vi) (iv) (viii) Question 2.5 (vii) (vii) (vii) (iv) Q2.5 Page 6 of 15
  • 7. Cost of direct material + Cost of direct labour + Factory overheads Direct material opening inventory + purchases + Import duties or any other cost to deliver material in storeroom – direct material closing inventory Wages paid – wages owing at beginning of period + wages owing at end of period Question 2.6 Question 2.7 Question 2.8 Q2.6 - 2.8 Page 7 of 15
  • 8. (a) - © Indirect labour costs Y R4 000 B R3 000 D R2 000 Variable cost R1 000 A E Fixed cost 0 Production units Line AB is the line of best fit (total cost line) Line AC is the fixed cost line (R800 per month). 600 800 1 000 1 200 1 400 Question 2.9 C X 200 400 Q2.9 Page 8 of 15
  • 9. The amount of the fixed cost is the distance between line OX and line AC = R800 The variable cost is the distance between line AC and line AB. The variable cost rate (variable cost per unit) is the gradient (slope) of line AB. The gradient of line AB is calculated as follows: Choose any point on the diagram (for example, point E). From this point draw a vertical line to AB. The gradient can now be computed as follows: Vertical distance (change in cost) Horizontal distance (change in production) DE (R2 500 - R800) AE (1 000 -0) = R1.700 (variable cost per unit) (d) Variable cost R3,400 Fixed cost R800 Total cost R4,200 Units produced 2,000 = Q2.9 Page 9 of 15
  • 10. (a) and (b) Y 220 200 D B 180 160 140 120 100 80 A 60 E 40 20 0 2 4 6 8 10 12 14 16 18 20 22 24 26 Production units Line AB is the line of best fit (total cost line) Line AC is the fixed cost line Question 2.10 C X Semi-VariableCosts(R) Q2.10 Page 10 of 15
  • 11. (c) The amount of the fixed cost is the distance between line OX and line AC = R60 The variable cost is the distance between line AC and line AB. The variable cost rate (variable cost per unit) is the gradient (slope) of line AB. The gradient of line AB is calculated as follows: Choose any point on the diagram (for example, point E). From this point draw a vertical line to AB. The gradient can now be computed as follows: Vertical distance (change in cost) Horizontal distance (change in production) DE (R190 - R60) AE (25 -0) = R5,20 (variable cost per unit) = Q2.10 Page 11 of 15
  • 12. OBSERVATIONS UNITS COST High 1,310 R4,995 Low 900 R3,560 Difference 410 R1,435 Variable cost per unit R3.500 June: Total cost R4,995 Total variable cost R4,585 Total fixed cost R410 March: Total cost R3,560 Total variable cost R3,150 Total fixed cost R410 Question 2.11 Q2.11 Page 12 of 15
  • 13. 2.12.1 C 2.12.2 B 2.12.3 D 2.12.4 D 2.12.5 A 2.12.6 C 2.12.7 B 2.12.8 A 2.12.9 B 2.12.10 D 2.12.11 A 2.12.12 D 2.12.13 B Calculations: 2.12.6 Variable cost per unit R3.500 Units produced 17,000 Total cost @ 17 000 units R246,500 Total variable cost R59,500 Total fixed cost R187,000 Question 2.12 Q2.12 Page 13 of 15
  • 14. 2.12.8 OBSERVATION SQ METRES COST High 15,100 R83,585 Low 12,750 R73,950 Difference 2,350 R9,635 Variable cost per unit R4.100 High: Total cost R83,585 Total variable cost R61,910 Total fixed cost R21,675 Low: Total cost R73,950 Total variable cost R52,275 Total fixed cost R21,675 Square metres: 16,200 Total variable cost R66,420 Total fixed cost R21,675 Total cost R88,095 Q2.12 Page 14 of 15