SlideShare a Scribd company logo
1 of 56
Concrete and Masonry in
Construction
 Subpart Q
Objectives
In this course, we will discuss the following:
 OSHA’s minimum requirements for concrete and
masonry work in construction
 General requirements, equipment, tools, formwork,
shoring, precast concrete, and lift-slab operations
 Hazards associated with concrete and masonry
construction operations
 Abatement methods
Subpart Q – Concrete and Masonry
Construction
 1926.700 – Scope, application, and definitions
 1926.701 – General requirements
 1926.702 – Requirements for equipment and tools
 1926.703 – Requirements for cast-in-place concrete
 1926.704 – Requirements for precast concrete
 1926.705 – Requirements for lift-slab operations
 1926.706 – Requirements for masonry construction
Definitions
 Bull float
 A tool used to spread out and smooth concrete.
 Formwork
 The total system of support for freshly placed or
partially cured concrete.
 Lift slab
 A method of concrete construction in which floor
and roof slabs are cast on or at ground level and,
using jacks, lifted into position.
1926.700(b)
 Limited access zone
 An area alongside a masonry wall, which is under
construction, and is clearly demarcated to limit access
by employees.
 Precast concrete
 Concrete members which have been formed, cast, and
cured prior to final placement in a structure.
 Reshoring
 The construction operation in which shoring equipment
is placed, as original forms and shores are removed, to
support partially cured concrete and construction loads.
Definitions 1926.700(b)
 Shore
 A supporting member that resists a compressive force
imposed by a load.
 Vertical slipforms
 These forms are jacked vertically during placement of
concrete.
 Jacking operation
 The task of lifting a slab during the construction of a
building where the lift-slab process is being used.
Definitions 1926.700(b)
Does Subpart Q Apply?
Construction Loads
 Structures must be capable of supporting
loads.
1926.701(a)
Reinforcing Steel
 Guard protruding, reinforcing steel
 Letter of interpretation: 05/29/1997
» [Addresses use of small plastic rebar caps]
 Letter of interpretation: 03/10/2006
» [Horizontal protection
from impalement]
1926.701(b)
Rebar Protection
 The following images are from video shot
during an investigation of an actual rebar
accident.
Courtesy of Utah Occupational Safety and Health Division
Post-Tensioning Operations
 Method of reinforcing concrete, masonry, and other
structural elements
 Strands ½″ diameter are stressed to a force of 33,000
lbs. using a hydraulic jack
1926.701(c)
Post-Tensioning Operations
 No non-essential employees allowed in hazard
zone.
 Use signs and barriers to limit employees
access to work zone.
1926.701(c)(1)-(2)
Jack
Riding Concrete Buckets 1926.701(d)
No riders
 Employees must not be permitted under
concrete buckets while they are being elevated
or lowered into position.
1926.701(e)(1)
Working Under Loads
Working Under Loads
 Elevated concrete bucket routes
1926.701(e)(2)
Personal Protective Equipment
 Employees must wear protective head and face
equipment when applying cement, sand, and water
mixture through a pneumatic hose.
1926.701(f)
Bulk Cement Storage
 Bins, containers, and silos
must be equipped with:
 Conical or tapered bottoms
 Mechanical or pneumatic means
to start flow of material.
 Ejection system must be shut
down, locked and tagged out
prior to entry.
1926.702(a)(1)-(2)
Concrete Mixers
 Concrete mixers with one cubic yard or larger
loading skips must be equipped with:
 Mechanical device to clear skip of materials
 Guardrails installed on each side of the skip
1926.702(b)(1)-(2)
Power Concrete Trowels
 Manually guided concrete troweling machine
must be equipped with:
 Automatic control switches shut off power when
hands are removed.
1926.702(c)
Power Concrete Trowels
Concrete Buggies
 Concrete buggy handles must not extend
beyond the wheels on either side of the
buggy.
1926.702(d)
 Discharge pipes must be provided with pipe supports
designed for 100 percent overload.
 Compressed air hoses must be provided with positive
fail-safe joint connectors.
1926.702(e)(1)-(2)
Concrete Pumping System
Concrete Buckets
 Concrete buckets equipped with hydraulic or
pneumatic gates:
 Must have positive safety latches or similar devices
to prevent accidental dumping
 Designed to prevent concrete from hanging up on
top and sides
1926.702(f)(1)-(2)
Tremie Sections
 Sections of tremie and
similar concrete
conveyances must be
secured with wire rope
(or equivalent materials)
in addition to the regular
couplings or
connections.
1926.702(g)
Bull Floats
 Bull float handles must
be constructed of
nonconductive material
or insulated.
 When used where they
may contact energized
electrical conductors
1926.702(h)
Masonry Saws
 Masonry saws must be
guarded with a
semicircular enclosure
over the blade.
 Method for retaining
blade fragments must be
incorporated in the
design of the enclosure.
1926.702(i)(1)-(2)
Lockout/Tagout Procedures
 Employees must not be allowed to perform
maintenance or repair activity on equipment.
 Unless hazardous energy sources have locked out or
tagged out.
1926.702(j)(1)
General Requirements
 Formwork must be
designed, fabricated,
erected, supported,
braced, and maintained.
 Must support without failure
all vertical and lateral loads
applied to it
1926.703(a)(1)
General Requirements
 Drawings or plans for the jack layout, formwork,
working decks, and scaffolds must be available
at the jobsite.
1926.703(a)(2)
 Inspected prior to erection.
 Damaged equipment shall not be used.
 Inspected immediately
prior to, during, and
immediately after concrete
placement.
Shoring and Reshoring 1926.703(b)(1)-(3)
 Equipment found to be damaged or weakened
must be immediately reinforced.
 Sills must be sound,
rigid, and capable of
carrying maximum
intended load.
1926.703(b)(4)-(5)
Shoring and Reshoring
Shoring and Reshoring
 All base plates, shore heads, extension
devices, and adjustment screws must be in
firm contact, and secured when necessary,
with the foundation and form.
1926.703(b)(6)
 Adjustment of single
post shores to raise
formwork must not be
made after the
placement of concrete.
Shoring and Reshoring 1926.703(b)(9)
 Reshoring must be
erected:
 As the original forms
and shores are
removed.
 Whenever the concrete
is required to support
loads in excess of its
capacity.
1926.703(b)(10)
Shoring and Reshoring
 Form steel rods or pipes
on which jacks climb
must be:
 Designed for that purpose
and adequately braced
when not encased in
concrete.
 Provided with scaffolds or
work platform where
employees required to
pass.
1926.703(c)(1)-(3)
Vertical Slipforms
Vertical Slipforms
 Jacks and lifting devices must be provided with
mechanical dogs or other automatic holding
devices.
1926.703(c)(5)
Vertical Slipforms
Forms and shores
must not be removed
until employer
determines concrete
has gained sufficient
strength.
1926.703(e)(1)
Removal of Formwork
 Wall units, structural
framing, and tilt-up
wall panels must be
adequately supported
to prevent
overturning.
1926.704(a)
Precast Concrete
Precast Concrete
 Tilt-up precast concrete members
 Lifting inserts embedded or otherwise attached must
be capable of supporting at least two times the
maximum intended load.
1926.704(b)
Precast Concrete 1926.704(c)
 Precast concrete
members
 Other than tilt-up
members.
» Lifting inserts
capable of
supporting at least
four times maximum
intended load.
Precast Concrete 1926.704(d)
 Lifting hardware must be capable of supporting
at least five times maximum intended load.
Precast Concrete
 No employees permitted under precast
concrete members being lifted or tilted into
position.
 Except employees
required for the
erection of those
members.
1926.704(e)
Fall Protection
 Each employee engaged in the erection of
precast concrete members and related
operations who is 6 feet or more above lower
levels shall be protected from falling.
1926.501(b)(12)
Precast Concrete
 Precast walls can be installed quickly.
 Foundations can be backfilled as soon as the
slab is in placed, enhancing jobsite safety.
 Designed by a registered professional engineer
 Plans and designs implemented by employer must
include:
 Detailed instructions
 Sketches indicating method of erection
1926.705(a)
Lift-Slab Operations
 Marked to indicate rated
capacity
 Not loaded beyond capacity
 Synchronized lifting to ensure
uniform lifting
 Manual controls located in
central location—attended by
competent person (must be
experienced)
1926.705(b), (c), (g), (i)
Jack/Lifting Unit
 No employees permitted in the building or
structure while any jacking operation is taking
place.
 Except essential personnel
1926.705(k)(1)
Lift-Slab Operations
L’Ambiance Plaza, Bridgeport, Conn.
 Lift slab construction project
 28 workers killed
 Multiple failures in design system and
construction practices
 Established prior to the start of construction
 Equal to the height of the wall plus four feet
 Unscaffolded side of wall
 Restricted to entry by employees constructing the wall
 Remain until adequately supported
1926.706(a)(1)-(5)
Limited Access Zone
 Masonry walls over 8 feet in
height must be adequately
braced.
 Bracing must remain in place
until permanent supporting
elements of the structure are in
place.
1926.706(b)
Limited Access Zone
Limited Access Zone
Limited Access Zone
Limited Access Zone
Summary
We covered the following information during this
presentation:
 OSHA’s minimum requirements for concrete and
masonry work in construction
 General requirements for equipment, tools,
formwork, shoring, precast concrete, and lift-slab
operations
 Hazards associated with concrete
and masonry construction
operations
 Abatement methods
Thank You For Attending!
Final Questions?

More Related Content

Similar to ConcreteMasonry.ppt

Fall Protection OSHA NEW General Industry 2017 standard
Fall Protection OSHA NEW General Industry 2017 standardFall Protection OSHA NEW General Industry 2017 standard
Fall Protection OSHA NEW General Industry 2017 standardJohn Newquist
 
Excavation and Trenching Onsite Wastewater Systems by L&I
Excavation and Trenching Onsite Wastewater Systems by L&IExcavation and Trenching Onsite Wastewater Systems by L&I
Excavation and Trenching Onsite Wastewater Systems by L&IAtlantic Training, LLC.
 
Analysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyAnalysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyIRJET Journal
 
Precast Concrete Specifications.doc
Precast Concrete Specifications.docPrecast Concrete Specifications.doc
Precast Concrete Specifications.docAbdallah437436
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptxAnanthakumar75
 
Escalator replacement specifications rev 2 consolidated comments
Escalator replacement specifications   rev 2 consolidated commentsEscalator replacement specifications   rev 2 consolidated comments
Escalator replacement specifications rev 2 consolidated commentsgulilero
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017John Newquist
 
Materials Handling, Storage, Use and Disposal by NMED
Materials Handling, Storage, Use and Disposal by NMEDMaterials Handling, Storage, Use and Disposal by NMED
Materials Handling, Storage, Use and Disposal by NMEDAtlantic Training, LLC.
 
Scaffold 5
Scaffold 5Scaffold 5
Scaffold 5FFSafety
 
hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxZakaria156221
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxZakaria156221
 
Suportes E Catwalks
Suportes E CatwalksSuportes E Catwalks
Suportes E Catwalksguest91efda
 
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...Patrice Adjei
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication constructionDivya Vishnoi
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfssuseref23d3
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015John Newquist
 
Ch 5 demolition of structures
Ch 5 demolition of structuresCh 5 demolition of structures
Ch 5 demolition of structuresAnkit Patel
 

Similar to ConcreteMasonry.ppt (20)

Fall Protection OSHA NEW General Industry 2017 standard
Fall Protection OSHA NEW General Industry 2017 standardFall Protection OSHA NEW General Industry 2017 standard
Fall Protection OSHA NEW General Industry 2017 standard
 
Excavation and Trenching Onsite Wastewater Systems by L&I
Excavation and Trenching Onsite Wastewater Systems by L&IExcavation and Trenching Onsite Wastewater Systems by L&I
Excavation and Trenching Onsite Wastewater Systems by L&I
 
Analysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyAnalysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case study
 
Micropiles
Micropiles Micropiles
Micropiles
 
Precast Concrete Specifications.doc
Precast Concrete Specifications.docPrecast Concrete Specifications.doc
Precast Concrete Specifications.doc
 
Metroppt
MetropptMetroppt
Metroppt
 
Sub Structure Construction.pptx
Sub Structure Construction.pptxSub Structure Construction.pptx
Sub Structure Construction.pptx
 
Escalator replacement specifications rev 2 consolidated comments
Escalator replacement specifications   rev 2 consolidated commentsEscalator replacement specifications   rev 2 consolidated comments
Escalator replacement specifications rev 2 consolidated comments
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017
 
Materials Handling, Storage, Use and Disposal by NMED
Materials Handling, Storage, Use and Disposal by NMEDMaterials Handling, Storage, Use and Disposal by NMED
Materials Handling, Storage, Use and Disposal by NMED
 
Scaffold 5
Scaffold 5Scaffold 5
Scaffold 5
 
Highway Construction
Highway ConstructionHighway Construction
Highway Construction
 
hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptx
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptx
 
Suportes E Catwalks
Suportes E CatwalksSuportes E Catwalks
Suportes E Catwalks
 
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015
 
Ch 5 demolition of structures
Ch 5 demolition of structuresCh 5 demolition of structures
Ch 5 demolition of structures
 

Recently uploaded

UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

ConcreteMasonry.ppt

  • 1. Concrete and Masonry in Construction  Subpart Q
  • 2. Objectives In this course, we will discuss the following:  OSHA’s minimum requirements for concrete and masonry work in construction  General requirements, equipment, tools, formwork, shoring, precast concrete, and lift-slab operations  Hazards associated with concrete and masonry construction operations  Abatement methods
  • 3. Subpart Q – Concrete and Masonry Construction  1926.700 – Scope, application, and definitions  1926.701 – General requirements  1926.702 – Requirements for equipment and tools  1926.703 – Requirements for cast-in-place concrete  1926.704 – Requirements for precast concrete  1926.705 – Requirements for lift-slab operations  1926.706 – Requirements for masonry construction
  • 4. Definitions  Bull float  A tool used to spread out and smooth concrete.  Formwork  The total system of support for freshly placed or partially cured concrete.  Lift slab  A method of concrete construction in which floor and roof slabs are cast on or at ground level and, using jacks, lifted into position. 1926.700(b)
  • 5.  Limited access zone  An area alongside a masonry wall, which is under construction, and is clearly demarcated to limit access by employees.  Precast concrete  Concrete members which have been formed, cast, and cured prior to final placement in a structure.  Reshoring  The construction operation in which shoring equipment is placed, as original forms and shores are removed, to support partially cured concrete and construction loads. Definitions 1926.700(b)
  • 6.  Shore  A supporting member that resists a compressive force imposed by a load.  Vertical slipforms  These forms are jacked vertically during placement of concrete.  Jacking operation  The task of lifting a slab during the construction of a building where the lift-slab process is being used. Definitions 1926.700(b)
  • 7. Does Subpart Q Apply?
  • 8. Construction Loads  Structures must be capable of supporting loads. 1926.701(a)
  • 9. Reinforcing Steel  Guard protruding, reinforcing steel  Letter of interpretation: 05/29/1997 » [Addresses use of small plastic rebar caps]  Letter of interpretation: 03/10/2006 » [Horizontal protection from impalement] 1926.701(b)
  • 10. Rebar Protection  The following images are from video shot during an investigation of an actual rebar accident. Courtesy of Utah Occupational Safety and Health Division
  • 11. Post-Tensioning Operations  Method of reinforcing concrete, masonry, and other structural elements  Strands ½″ diameter are stressed to a force of 33,000 lbs. using a hydraulic jack 1926.701(c)
  • 12. Post-Tensioning Operations  No non-essential employees allowed in hazard zone.  Use signs and barriers to limit employees access to work zone. 1926.701(c)(1)-(2) Jack
  • 13. Riding Concrete Buckets 1926.701(d) No riders
  • 14.  Employees must not be permitted under concrete buckets while they are being elevated or lowered into position. 1926.701(e)(1) Working Under Loads
  • 15. Working Under Loads  Elevated concrete bucket routes 1926.701(e)(2)
  • 16. Personal Protective Equipment  Employees must wear protective head and face equipment when applying cement, sand, and water mixture through a pneumatic hose. 1926.701(f)
  • 17. Bulk Cement Storage  Bins, containers, and silos must be equipped with:  Conical or tapered bottoms  Mechanical or pneumatic means to start flow of material.  Ejection system must be shut down, locked and tagged out prior to entry. 1926.702(a)(1)-(2)
  • 18. Concrete Mixers  Concrete mixers with one cubic yard or larger loading skips must be equipped with:  Mechanical device to clear skip of materials  Guardrails installed on each side of the skip 1926.702(b)(1)-(2)
  • 19. Power Concrete Trowels  Manually guided concrete troweling machine must be equipped with:  Automatic control switches shut off power when hands are removed. 1926.702(c)
  • 21. Concrete Buggies  Concrete buggy handles must not extend beyond the wheels on either side of the buggy. 1926.702(d)
  • 22.  Discharge pipes must be provided with pipe supports designed for 100 percent overload.  Compressed air hoses must be provided with positive fail-safe joint connectors. 1926.702(e)(1)-(2) Concrete Pumping System
  • 23. Concrete Buckets  Concrete buckets equipped with hydraulic or pneumatic gates:  Must have positive safety latches or similar devices to prevent accidental dumping  Designed to prevent concrete from hanging up on top and sides 1926.702(f)(1)-(2)
  • 24. Tremie Sections  Sections of tremie and similar concrete conveyances must be secured with wire rope (or equivalent materials) in addition to the regular couplings or connections. 1926.702(g)
  • 25. Bull Floats  Bull float handles must be constructed of nonconductive material or insulated.  When used where they may contact energized electrical conductors 1926.702(h)
  • 26. Masonry Saws  Masonry saws must be guarded with a semicircular enclosure over the blade.  Method for retaining blade fragments must be incorporated in the design of the enclosure. 1926.702(i)(1)-(2)
  • 27. Lockout/Tagout Procedures  Employees must not be allowed to perform maintenance or repair activity on equipment.  Unless hazardous energy sources have locked out or tagged out. 1926.702(j)(1)
  • 28. General Requirements  Formwork must be designed, fabricated, erected, supported, braced, and maintained.  Must support without failure all vertical and lateral loads applied to it 1926.703(a)(1)
  • 29. General Requirements  Drawings or plans for the jack layout, formwork, working decks, and scaffolds must be available at the jobsite. 1926.703(a)(2)
  • 30.  Inspected prior to erection.  Damaged equipment shall not be used.  Inspected immediately prior to, during, and immediately after concrete placement. Shoring and Reshoring 1926.703(b)(1)-(3)
  • 31.  Equipment found to be damaged or weakened must be immediately reinforced.  Sills must be sound, rigid, and capable of carrying maximum intended load. 1926.703(b)(4)-(5) Shoring and Reshoring
  • 32. Shoring and Reshoring  All base plates, shore heads, extension devices, and adjustment screws must be in firm contact, and secured when necessary, with the foundation and form. 1926.703(b)(6)
  • 33.  Adjustment of single post shores to raise formwork must not be made after the placement of concrete. Shoring and Reshoring 1926.703(b)(9)
  • 34.  Reshoring must be erected:  As the original forms and shores are removed.  Whenever the concrete is required to support loads in excess of its capacity. 1926.703(b)(10) Shoring and Reshoring
  • 35.  Form steel rods or pipes on which jacks climb must be:  Designed for that purpose and adequately braced when not encased in concrete.  Provided with scaffolds or work platform where employees required to pass. 1926.703(c)(1)-(3) Vertical Slipforms
  • 36. Vertical Slipforms  Jacks and lifting devices must be provided with mechanical dogs or other automatic holding devices. 1926.703(c)(5)
  • 38. Forms and shores must not be removed until employer determines concrete has gained sufficient strength. 1926.703(e)(1) Removal of Formwork
  • 39.  Wall units, structural framing, and tilt-up wall panels must be adequately supported to prevent overturning. 1926.704(a) Precast Concrete
  • 40. Precast Concrete  Tilt-up precast concrete members  Lifting inserts embedded or otherwise attached must be capable of supporting at least two times the maximum intended load. 1926.704(b)
  • 41. Precast Concrete 1926.704(c)  Precast concrete members  Other than tilt-up members. » Lifting inserts capable of supporting at least four times maximum intended load.
  • 42. Precast Concrete 1926.704(d)  Lifting hardware must be capable of supporting at least five times maximum intended load.
  • 43. Precast Concrete  No employees permitted under precast concrete members being lifted or tilted into position.  Except employees required for the erection of those members. 1926.704(e)
  • 44. Fall Protection  Each employee engaged in the erection of precast concrete members and related operations who is 6 feet or more above lower levels shall be protected from falling. 1926.501(b)(12)
  • 45. Precast Concrete  Precast walls can be installed quickly.  Foundations can be backfilled as soon as the slab is in placed, enhancing jobsite safety.
  • 46.  Designed by a registered professional engineer  Plans and designs implemented by employer must include:  Detailed instructions  Sketches indicating method of erection 1926.705(a) Lift-Slab Operations
  • 47.  Marked to indicate rated capacity  Not loaded beyond capacity  Synchronized lifting to ensure uniform lifting  Manual controls located in central location—attended by competent person (must be experienced) 1926.705(b), (c), (g), (i) Jack/Lifting Unit
  • 48.  No employees permitted in the building or structure while any jacking operation is taking place.  Except essential personnel 1926.705(k)(1) Lift-Slab Operations
  • 49. L’Ambiance Plaza, Bridgeport, Conn.  Lift slab construction project  28 workers killed  Multiple failures in design system and construction practices
  • 50.  Established prior to the start of construction  Equal to the height of the wall plus four feet  Unscaffolded side of wall  Restricted to entry by employees constructing the wall  Remain until adequately supported 1926.706(a)(1)-(5) Limited Access Zone
  • 51.  Masonry walls over 8 feet in height must be adequately braced.  Bracing must remain in place until permanent supporting elements of the structure are in place. 1926.706(b) Limited Access Zone
  • 55. Summary We covered the following information during this presentation:  OSHA’s minimum requirements for concrete and masonry work in construction  General requirements for equipment, tools, formwork, shoring, precast concrete, and lift-slab operations  Hazards associated with concrete and masonry construction operations  Abatement methods
  • 56. Thank You For Attending! Final Questions?