Mr. Mike D'Alessandro provides an overview of the timeline and requirements for proposal submission on Omnibus IV the DoD's first $1B medical research and development support vehicle.
2. Agenda
Omnibus III Snapshot
Omnibus IV Milestone Schedule
Contract Overview
Instructions to Offerors (Section L)
Evaluation Factors for Award (Section M)
Task Order Procedures
UNCLASSIFIED 2
UNCLASSIFIED
2
3. Omnibus III Snapshot
Multiple Award IDIQ Contract
$497M Maximum Contract Value
~$400M Dollars Obligated to Date
UNCLASSIFIED 3
UNCLASSIFIED
3
52%
48%
Large Business Small Business
Omnibus III Task Order Awards
4. Omnibus IV Milestone Schedule
Omnibus IV Industry Day July 2016
Release Draft Solicitation for Industry Comment Sept 2016
Issue Solicitation Nov 2016
Proposal Due Date Dec 2016
Evaluate Proposals Jan-Feb 2017
Final Proposal Evaluations Mar 2017
Business Clearance Reviews Apr 2017
Contract Awards May 2017
UNCLASSIFIED 4
UNCLASSIFIED
4
5. Contract Overview
Multiple-Award Task-Order (MATO), Indefinite-Delivery
Indefinite-Quantity (ID/IQ) contract
66 month ordering period
36 month base ordering period, 24 month optional ordering
period, and a 6 month optional ordering period
On-ramping/off-ramping
Program ceiling of $999M for OBIV
1 Lot of Contracts
UNCLASSIFIED 5
UNCLASSIFIED
5
6. Contract Overview cont.
• Contract Types
Firm Fixed Price and Cost Plus Fixed Fee
• Need adequate accounting system for CPFF eligibility
• Omnibus III Task Order Statistics
45% FFP
55% CPFF
UNCLASSIFIED 6
UNCLASSIFIED
6
7. Instructions to Offerors (Section L)
• Proposal Volumes
Administrative
Technical
Management
Cost/Price
Past Performance
Small Business Participation
UNCLASSIFIED 7
UNCLASSIFIED
7
8. Evaluation Factors for Award (Section M)
Source Selection Methodology
• Tradeoff – An award may be made to other than the lowest priced
proposal if the Government determines that paying a price premium
for the higher rated proposal is warranted. The Government may
also award to other than the highest rated proposal, if the
Government determines that paying a price premium is not
warranted.
UNCLASSIFIED 8
UNCLASSIFIED
8
9. Task Order Procedures
• Small Business Set Aside Determination Process
Seeking Industry Input
• Task Order Competition Evaluations
Technical
Cost/Price
Past Performance (only from Omnibus IV)
UNCLASSIFIED 9
UNCLASSIFIED
9