2013

Cisco System, Inc:
Implementing ERP

Submitted By
Gaurav Singh
(12120)
About CISCO
Established in 1984
Primary product was Router
In 1997 entered into elite club of fortune 500
Among top 5 companies in return on investment and in return on assets
Exceptional growth in 1998 as companies’ market capitalization passed $100 billion
mark (15 times 1997 sales)
Financial year divided into four quarters starting from 1st August

IT Department at CISCO
Pete Solvik joined as CIO in January 1993
Running a Unix based software package to support core operating and transactional
process of the company
Package was majorly supporting three functional areas
o Financials
o Manufacturing
o Order Entry
Biggest customer of the software vendor

WHY ERP
Company was able to sustain an annual growth rate of 80% and legacy system was not
able to handle such load
Frequent system outages
Due to inability of system to perform a workaround caused corruption of database which
resulted in SHUT DOWN OF COMPANY for two days
This was the defining moment for the company as after this top management decided to
implement ERP. About a month after the shutdown they created a team to do an investigation to
replace the application.

Gauarv Singh

12120

ERP 2
IMPLEMENTATION OF ERP – APPROACH
1) Selection of an ERP Product
Major decision which they took and reason behind that:
a) Whom to give responsibility from company
i.

It was critically important project

ii.

Requires heavy involvement from business community to make project successful

iii.

DECISIONCISCO management pulled out very vest people from their team to
do the work

b) How and how many partner to select from Industry
i.

There help was needed for the decision of selection and implementation of
software

ii.

Great technical skills and industry knowledge was must

iii.

DECISIONChose KPMG as integration partner. KPMG gave their best people
for this project. i.e. Program manager for this project was their director of IT.

c) Which software to select
i.

One of the most important decision

ii.

Approach 
i. Took help from large corporates
ii. Guidance of research sources like Gartner group
iii. By tapping existing user of package

iii.

Vendor selection process
i. Systematic and standard procedure
ii. RFP

iv.

DECISION Oracle was selected as vendor
i. Strong and better manufacturing capability
ii. Promise Long term sustainable relationship
iii. Flexibility as office was very near by

Gauarv Singh

12120

ERP 2
2) Approval from Board
Two key decisions need to be taken before approaching board
i.

COST of the project

ii.

Timeline / END – DATE of the project

By Systematic thinking and involvement of all partners, taking all factors into consideration they
approached board and convinced for project.
Cost: $15 million
Duration: 9 months

3) Implementation of Building team
Factors need to be considered
Size of the team
Role and responsibility of the team
Organization of team
DECISION
They picked best and brightest from the firm
FIVE Tracks
TRACK
o Cisco Information system leader
o Cisco business leader
o Business and IT consultant (Oracle / KPMG)
o Additional personnel from business as team member
o Project Manager

Gauarv Singh

12120

ERP 2
Implementation of Oracle
1. CRP0
Training on oracle to understand technical specification of project
Two week training
One small tiger team working on getting application up and running

Result at the end of phase
Some changes are required in product to fulfil the gap
Priority of changes

2. CRP1
Each track to make system work within specific area
Generate detailed documentation for each process/issue/workaround
Finding of gaps

Result at the end of phase
Identified what all modification were required
Standard document to understand the product
Feasibility of product to handle the modification

3. CRP2 and CRP3
Include major modification
Decide on after sales support package

Result at the end of phase
A centralize data warehouse to use all CISCO application
Changed company structure and process according to product
o Renumbered the product
o Changed Bill of material structure

Gauarv Singh

12120

ERP 2
o Changed most of the data according to new system
Green signal to System GO-LIVE

4. GO LIVE
Issue of hardware
Inability of software to handle volume of transaction

Workaround and solution by Team
Responsibility of vendor to solve hardware issue (Didn’t increase cost)
Stress testing was not done which resulted in data leak
All IT team worked together for next two months to solve all technical issues

Key Reason Behind success
1. No.1 agenda for the company, gave priority across all functional area
2. Company believe in standardization
3. Best people across the industry in the project
4. Team organization and culture
5. Systematic and structured approach in selection of vendor and software
6. Correct estimation and high class project management
7. Highly centralized and top to bottom approach by the company
8. Company adaptability  changed its process where it was difficult to modify the
software
9. GAP Analysis, except volume testing they did a good gap analysis

Gauarv Singh

12120

ERP 2
Gauarv Singh

12120

ERP 2

Cisco System, Inc: Implementing ERP

  • 1.
    2013 Cisco System, Inc: ImplementingERP Submitted By Gaurav Singh (12120)
  • 2.
    About CISCO Established in1984 Primary product was Router In 1997 entered into elite club of fortune 500 Among top 5 companies in return on investment and in return on assets Exceptional growth in 1998 as companies’ market capitalization passed $100 billion mark (15 times 1997 sales) Financial year divided into four quarters starting from 1st August IT Department at CISCO Pete Solvik joined as CIO in January 1993 Running a Unix based software package to support core operating and transactional process of the company Package was majorly supporting three functional areas o Financials o Manufacturing o Order Entry Biggest customer of the software vendor WHY ERP Company was able to sustain an annual growth rate of 80% and legacy system was not able to handle such load Frequent system outages Due to inability of system to perform a workaround caused corruption of database which resulted in SHUT DOWN OF COMPANY for two days This was the defining moment for the company as after this top management decided to implement ERP. About a month after the shutdown they created a team to do an investigation to replace the application. Gauarv Singh 12120 ERP 2
  • 3.
    IMPLEMENTATION OF ERP– APPROACH 1) Selection of an ERP Product Major decision which they took and reason behind that: a) Whom to give responsibility from company i. It was critically important project ii. Requires heavy involvement from business community to make project successful iii. DECISIONCISCO management pulled out very vest people from their team to do the work b) How and how many partner to select from Industry i. There help was needed for the decision of selection and implementation of software ii. Great technical skills and industry knowledge was must iii. DECISIONChose KPMG as integration partner. KPMG gave their best people for this project. i.e. Program manager for this project was their director of IT. c) Which software to select i. One of the most important decision ii. Approach  i. Took help from large corporates ii. Guidance of research sources like Gartner group iii. By tapping existing user of package iii. Vendor selection process i. Systematic and standard procedure ii. RFP iv. DECISION Oracle was selected as vendor i. Strong and better manufacturing capability ii. Promise Long term sustainable relationship iii. Flexibility as office was very near by Gauarv Singh 12120 ERP 2
  • 4.
    2) Approval fromBoard Two key decisions need to be taken before approaching board i. COST of the project ii. Timeline / END – DATE of the project By Systematic thinking and involvement of all partners, taking all factors into consideration they approached board and convinced for project. Cost: $15 million Duration: 9 months 3) Implementation of Building team Factors need to be considered Size of the team Role and responsibility of the team Organization of team DECISION They picked best and brightest from the firm FIVE Tracks TRACK o Cisco Information system leader o Cisco business leader o Business and IT consultant (Oracle / KPMG) o Additional personnel from business as team member o Project Manager Gauarv Singh 12120 ERP 2
  • 5.
    Implementation of Oracle 1.CRP0 Training on oracle to understand technical specification of project Two week training One small tiger team working on getting application up and running Result at the end of phase Some changes are required in product to fulfil the gap Priority of changes 2. CRP1 Each track to make system work within specific area Generate detailed documentation for each process/issue/workaround Finding of gaps Result at the end of phase Identified what all modification were required Standard document to understand the product Feasibility of product to handle the modification 3. CRP2 and CRP3 Include major modification Decide on after sales support package Result at the end of phase A centralize data warehouse to use all CISCO application Changed company structure and process according to product o Renumbered the product o Changed Bill of material structure Gauarv Singh 12120 ERP 2
  • 6.
    o Changed mostof the data according to new system Green signal to System GO-LIVE 4. GO LIVE Issue of hardware Inability of software to handle volume of transaction Workaround and solution by Team Responsibility of vendor to solve hardware issue (Didn’t increase cost) Stress testing was not done which resulted in data leak All IT team worked together for next two months to solve all technical issues Key Reason Behind success 1. No.1 agenda for the company, gave priority across all functional area 2. Company believe in standardization 3. Best people across the industry in the project 4. Team organization and culture 5. Systematic and structured approach in selection of vendor and software 6. Correct estimation and high class project management 7. Highly centralized and top to bottom approach by the company 8. Company adaptability  changed its process where it was difficult to modify the software 9. GAP Analysis, except volume testing they did a good gap analysis Gauarv Singh 12120 ERP 2
  • 7.