Presented by George Holder (Costain) at the COMIT 2015 winter Community Day. This describes a drilling machine developed for creating bold fitting holes in the concrete linings used in the Crossrail tunnels.
3. 3
Tunnels – What Are They Made of?
Key
Counter Key
Standard
SegmentFeatures
Bolt Pocket
Grout Hole
Circumferential
Dowels
4. 4
Tunnels – How to Build a Ring
Crown
Axis
Right AxisLeft AxisInvert Axis Invert
Axis
Invert Axis
Right AxisLeft Axis
Crown
Axis
Key Segment
Counter Key Segment
Standard Segment
Question?
Why are the keys so random?
5. 5
Tunnels – Why so random?
Key Segment
Counter Key Segment
Standard Segment
Straight Tunnel
Keys on opposite
sides
Curved Tunnel
Keys on same sides
Examples in 2D
Space
Answer
Because Tunnels Aren’t Straight!
Rings are tapered
6. 6
Tunnels – 3D Space
3D Space becomes much more
complex
Tunnels no longer curve only left or
right they also change level vertically
There is 22 different positions a key
can be relative to the previous
segment
Key could be anywhere at any
given point
Question?
WHAT HAS ALL THIS GOT TO DO WITH
DRILLING?
9. 9
What do we Install?
Overhead Line Equipment (OHLE)
(3 Holes every 9.6m plus additional supports on curves)
Walkway and Fire Main Bracket
(4 Holes every 3.2m)
Cable Management System
(3 Holes every 3.2m)
Earth Return Wire
(1 Hole every 600mm)
Cable Management System
(3 Holes every 3.2m)
10. 10
Relationship to the Trains
Straight
Track
Left Curve Right Curve
Location of brackets is fixed by Track Cant at any given
11. 11
Walkway Bracket Example
Top of
Bracket
Bottom of Bracket
3.2m from previous bracket
Fixing requirements established
4 holes required
Preferred hole positions identified
Hole positions tested against
segment arrangements
Alternative hole positions required?
Designer continues until satisfied
that optimal solution is found
For the walkway:
8 Holes Positions
4 fixings required
Gives ~20 suitable fixing
combinations
12. 12
Summary so far…….
Tunnels
Construction method
Key segment location
No-drill zones
Services
Which services required
Fixed relationship to track
Fixed position relative to
previous bracket
Alternative hole positionsSo how do we undertaking Drilling
Activities?
13. 13
3 Stages for Drilling
3D Scan
Processing of Data
Machine Operations
14. 14
3D Laser Scan
3D Laser Scanner takes
measurements
Processed to provide key
locations (i.e. Segment
Corners)
Data is provided in
coordinate form
x
y
z (chainage)
15. 15
Data Processing
Computer Programme developed to set out holes
Interprets data from scan to identify no-drill zones
Drilling Rule Books (Spacing / Relationship to Track / Allowable Variations)
Basically:
Tests coordinates of each hole position against no drill zones
Identifies most preferred hole combination
Allows for clashes to be resolved before arriving on site
16. 16
Where are we now?...
Tunnels
Precise details of geometry
known
No-drill zones identified
Mis-alignment accounted for
Brackets
Required bracket positions
known
Hole combinations and
positions known
All works now complete off-site “virtually”
All that’s left to do is input to machine to do physical work
Finally…. How the machine works
19. 19
Operation –Working Configuration
Machine lifts onto upper
wagon
All walkways and working
platforms erected
Machine ready for drilling
operations
20. 20
Guidance – Z-Axis - Chainage
x
y
z (chainage)
Laser Measurement
Required distance to
target known
Operator moves machine
Machine positioned to
drill
21. 21
Guidance – X-Axis & Y-Axis
x
y
z (chainage)
Guide Rollers ensure roughly
central
Laser measurement to check
central
Fine adjustment of position
through hydraulic system
24. 24
Safety, Health, Environmental & Quality Benefits
Safety Health Environmental
Elimination of Hand Arm Vibration
Minimisation of Working at Height
Elimination of 99% of Dust
Quality
Pre-planning of hole positions and clash elimination
Reduction of On-Site technical decision making required
Operations
Surpasses tender production rates
Reduction in Man Hours
25. 25
Summary
Identified significant challenge in drilling for brackets
Holistic approach by team towards solution
Early adaption to change, factory thinking approach
De-risking
Enables manufacturing approach to delivering the construction work
Innovative approach, commercially viable