The document provides disassembly instructions for a power shift transmission used in 924G and 924Gz wheel loaders. It lists 37 steps to fully disassemble the transmission, removing components like gears, shafts, seals, bearings, and clutch groups. Special tools are required for tasks like compressing springs and removing press-fit components. Cleanliness is emphasized throughout to prevent dirt from entering the mechanism during reassembly.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix AAB) Service Repair Manua...9fiisekodkdmd
This document provides disassembly instructions for the power shift transmission on 924G and 924Gz wheel loaders. It outlines 71 steps to fully disassemble the transmission, including removing individual components like gears, shafts, seals, bearings, and clutch groups. Precision tools are required and notes emphasize cleanliness during disassembly to prevent dirt from entering internal mechanisms.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix AAB) Service Repair Manua...9fikslkddmd8u
The document provides disassembly instructions for the power shift transmission of 924G and 924Gz wheel loaders. It lists 57 steps to fully disassemble the transmission along with required tools. Key components that are disassembled include the torque converter, gear assemblies, clutch groups, seals, bearings, and other internal transmission parts. Detailed illustrations accompany each step to show how to remove individual parts in the proper sequence. Cleanliness is emphasized during the disassembly process to prevent dirt from entering the transmission.
The document provides disassembly instructions for the power shift transmission of 924G and 924Gz wheel loaders. It lists 57 steps to fully disassemble the transmission along with required tools. Key components that are disassembled include the torque converter, gear assemblies, clutch groups, seals, bearings, and plates/discs. Detailed illustrations accompany each step to show how to remove individual parts in the proper sequence. Cleanliness is emphasized throughout the disassembly process.
This service repair manual provides instructions for disassembling the power shift transmission of 924G and 924Gz wheel loaders. The disassembly procedure involves 71 steps to remove components like the torque converter, clutch groups, gears, shafts, seals, and bearings. Various tools are required, and cleanliness is important to prevent dirt from entering during reassembly. Detailed illustrations accompany each step to show how to properly disassemble the transmission.
The document provides disassembly instructions for the power shift transmission of 924G and 924Gz wheel loaders. It lists 57 steps to fully disassemble the transmission along with required tools. Key components that are disassembled include the torque converter, gear assemblies, clutch groups, seals, bearings, and plates/discs. Detailed illustrations accompany each step to show how to remove individual parts in the proper sequence. Cleanliness is emphasized throughout to prevent dirt from entering internal mechanisms during disassembly.
This service repair manual provides instructions for disassembling the power shift transmission of 924G and 924Gz wheel loaders. The disassembly procedure involves 71 steps to remove components like the torque converter, clutch groups, gears, shafts, seals, and bearings. Various tools are required, and cleanliness is important to prevent dirt from entering during reassembly. Detailed illustrations accompany each step to show how components connect and disassemble.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix 3DZ) Service Repair Manua...9fiisekodkdmd
This document provides disassembly instructions for the power shift transmission of a 924G and 924Gz wheel loader. It lists 70 steps to fully disassemble the transmission, removing components like gears, clutches, seals, bearings and shafts. Special tools are required for tasks like compressing springs and pulling components. Cleanliness is emphasized throughout to prevent dirt from entering the transmission during disassembly.
This service repair manual provides instructions for disassembling the power shift transmission of a 924G or 924Gz wheel loader. It lists 70 steps to fully disassemble the transmission, removing components like gears, clutches, seals, bearings and shafts. Pictures and exploded diagrams accompany each step to illustrate the proper procedure. Cleaning is important during disassembly to prevent dirt from entering internal mechanisms.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix AAB) Service Repair Manua...9fiisekodkdmd
This document provides disassembly instructions for the power shift transmission on 924G and 924Gz wheel loaders. It outlines 71 steps to fully disassemble the transmission, including removing individual components like gears, shafts, seals, bearings, and clutch groups. Precision tools are required and notes emphasize cleanliness during disassembly to prevent dirt from entering internal mechanisms.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix AAB) Service Repair Manua...9fikslkddmd8u
The document provides disassembly instructions for the power shift transmission of 924G and 924Gz wheel loaders. It lists 57 steps to fully disassemble the transmission along with required tools. Key components that are disassembled include the torque converter, gear assemblies, clutch groups, seals, bearings, and other internal transmission parts. Detailed illustrations accompany each step to show how to remove individual parts in the proper sequence. Cleanliness is emphasized during the disassembly process to prevent dirt from entering the transmission.
The document provides disassembly instructions for the power shift transmission of 924G and 924Gz wheel loaders. It lists 57 steps to fully disassemble the transmission along with required tools. Key components that are disassembled include the torque converter, gear assemblies, clutch groups, seals, bearings, and plates/discs. Detailed illustrations accompany each step to show how to remove individual parts in the proper sequence. Cleanliness is emphasized throughout the disassembly process.
This service repair manual provides instructions for disassembling the power shift transmission of 924G and 924Gz wheel loaders. The disassembly procedure involves 71 steps to remove components like the torque converter, clutch groups, gears, shafts, seals, and bearings. Various tools are required, and cleanliness is important to prevent dirt from entering during reassembly. Detailed illustrations accompany each step to show how to properly disassemble the transmission.
The document provides disassembly instructions for the power shift transmission of 924G and 924Gz wheel loaders. It lists 57 steps to fully disassemble the transmission along with required tools. Key components that are disassembled include the torque converter, gear assemblies, clutch groups, seals, bearings, and plates/discs. Detailed illustrations accompany each step to show how to remove individual parts in the proper sequence. Cleanliness is emphasized throughout to prevent dirt from entering internal mechanisms during disassembly.
This service repair manual provides instructions for disassembling the power shift transmission of 924G and 924Gz wheel loaders. The disassembly procedure involves 71 steps to remove components like the torque converter, clutch groups, gears, shafts, seals, and bearings. Various tools are required, and cleanliness is important to prevent dirt from entering during reassembly. Detailed illustrations accompany each step to show how components connect and disassemble.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix 3DZ) Service Repair Manua...9fiisekodkdmd
This document provides disassembly instructions for the power shift transmission of a 924G and 924Gz wheel loader. It lists 70 steps to fully disassemble the transmission, removing components like gears, clutches, seals, bearings and shafts. Special tools are required for tasks like compressing springs and pulling components. Cleanliness is emphasized throughout to prevent dirt from entering the transmission during disassembly.
This service repair manual provides instructions for disassembling the power shift transmission of a 924G or 924Gz wheel loader. It lists 70 steps to fully disassemble the transmission, removing components like gears, clutches, seals, bearings and shafts. Pictures and exploded diagrams accompany each step to illustrate the proper procedure. Cleaning is important during disassembly to prevent dirt from entering internal mechanisms.
This service repair manual provides instructions for disassembling the power shift transmission on Caterpillar 924G and 924Gz wheel loaders. It outlines 59 steps to fully disassemble the transmission, including removing individual gears, clutches, seals, and other components. Required tools are listed. Detailed illustrations accompany each step to show how to remove specific parts in the correct order. Cleanliness is emphasized during disassembly to prevent dirt from entering internal mechanisms.
This document provides disassembly instructions for the power shift transmission of a 924G and 924Gz wheel loader. It lists 70 steps to fully disassemble the transmission, removing components like gears, clutches, seals, bearings and shafts. Special tools are required for tasks like compressing springs and pulling components. Cleanliness is emphasized throughout to prevent dirt from entering the transmission during disassembly.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix 3DZ) Service Repair Manua...9fikslkddmd8u
This document provides instructions for disassembling the power shift transmission on Caterpillar 924G and 924Gz wheel loaders. The summary is as follows:
1) Place the transmission on a repair stand and remove components like the torque converter, top case, selector valve, and flex plate.
2) Remove gears, bearings, seals, and clutch groups including the forward low and high, reverse second, and first third gear clutches.
3) Clean parts and inspect them for wear during disassembly. Take note of order and numbers of plates and discs for reassembly.
This document provides disassembly instructions for the power shift transmission of Caterpillar 924G and 924Gz wheel loaders. It describes 59 steps to fully disassemble the transmission, including removing the top case, torque converter, gears, bearings, seals, and individual clutch groups like the forward low and high clutches, reverse second gear clutch, and first third gear clutch. Precautions are given to clean components thoroughly and note part orders for reassembly. Required specialty tools are listed.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, plates, discs, retainers, springs and other internal components. Cleanliness is emphasized throughout the process to prevent dirt from entering the mechanisms.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, plates, discs, retainers, springs and other internal components. Cleanliness is emphasized throughout the process to prevent dirt from entering the mechanisms.
This document provides disassembly instructions for the transmission and torque converter of a 924G or 924Gz wheel loader. It lists over 60 detailed steps for disassembling components like gears, plates, seals, bearings, and clutches. Special tools are required and safety precautions mentioned. The transmission must first be removed and cleaned before beginning disassembly.
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents over 60 steps for disassembling components such as gears, plates, seals, bearings, hubs and clutches. Cleanliness is emphasized throughout the process to prevent dirt entry into internal mechanisms.
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents 53 steps for disassembling the various components. These include removing plates, discs, gears, seals, bearings, and other parts of the transmission and torque converter. Cleanliness is emphasized throughout the process.
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents 53 detailed steps for disassembling the various transmission components. These include removing gears, plates, seals, bearings, springs, and other parts. Cleanliness is emphasized throughout the process.
This document provides disassembly instructions for the transmission and torque converter of a 924G or 924Gz wheel loader. It lists over 60 detailed steps for disassembling components like gears, plates, seals, bearings, and clutches. Special tools are required and safety precautions mentioned. The transmission must first be removed and cleaned before beginning disassembly.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, plates, discs, retainers, springs and other internal components. Cleanliness is emphasized throughout the process to prevent dirt from entering the transmission.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, plates, discs, retainers, springs and other internal components. Cleanliness is emphasized throughout the process to prevent dirt contamination of parts.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix RBB) Service Repair Manua...9fiisekodkdmd
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents 53 detailed steps for disassembling the various transmission components. These include removing gears, plates, seals, bearings, and clutch groups. Cleanliness is emphasized throughout and components are marked for installation reference.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, springs, and other internal components. Cleanliness is emphasized throughout the process to prevent dirt from entering the transmission.
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents over 60 steps for disassembling components such as gears, plates, seals, bearings, and clutches. Cleanliness is emphasized throughout the process.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions to remove components such as gears, seals, plates, discs, bearings, and clutches. Safety precautions are provided for releasing clutch springs. The disassembly process is described in detail through 50 steps and accompanied by illustrations of each step.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix RBB) Service Repair Manua...9fikslkddmd8u
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents over 60 steps for disassembling components such as clutches, gears, seals, plates, and discs. Cleanliness is emphasized throughout the process to prevent dirt entry.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix RTA) Service Repair Manua...9fikslkddmd8u
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists 50 steps to completely disassemble the transmission, removing components like gears, plates, seals, bearings, and clutch groups. Special tools are required for tasks like compressing clutch springs and removing certain parts. Cleanliness is emphasized throughout to prevent dirt from contaminating internal parts.
This document provides disassembly instructions for a transmission and torque converter for wheel loader models 924G and 924Gz. It lists the required tools and presents a step-by-step process to disassemble the transmission, torque converter, and various clutch groups within the transmission. The disassembly involves removing bolts, seals, gears, plates, discs, bearings, springs, and other internal components. Cleanliness during disassembly is emphasized.
Caterpillar Cat CP-663E Vibratory Compactor (Prefix AEF) Service Repair Manua...ujkfdkkmsmd
This document provides disassembly and assembly instructions for a piston pump used in vibratory compactors. It describes 41 steps to fully disassemble the pump into individual components. This includes removing seals, springs, valves, pistons, plates, blocks, bearings and other parts. Similarly, it lists 41 steps for reassembling all the components in the reverse order. Cleanliness is emphasized throughout the process.
Caterpillar Cat CP-583E Vibratory Compactor (Prefix CNX) Service Repair Manua...ujkfdkkmsmd
This document provides instructions for removing and installing piston cooling jets, pistons, connecting rods, and related components on a Caterpillar 3056E engine. The removal process involves taking out the engine oil pan, removing valve assemblies from the piston cooling jets, and pushing pistons and connecting rods out of the cylinder block. The installation process requires cleaning components, lubricating them with oil, and reinserting pistons and connecting rods into the cylinder block before replacing other parts. Safety notices are provided to keep components clean and contain fluids.
More Related Content
Similar to Caterpillar Cat 924Gz Wheel Loader (Prefix 9SW) Service Repair Manual (9SW00001-02428).pdf
This service repair manual provides instructions for disassembling the power shift transmission on Caterpillar 924G and 924Gz wheel loaders. It outlines 59 steps to fully disassemble the transmission, including removing individual gears, clutches, seals, and other components. Required tools are listed. Detailed illustrations accompany each step to show how to remove specific parts in the correct order. Cleanliness is emphasized during disassembly to prevent dirt from entering internal mechanisms.
This document provides disassembly instructions for the power shift transmission of a 924G and 924Gz wheel loader. It lists 70 steps to fully disassemble the transmission, removing components like gears, clutches, seals, bearings and shafts. Special tools are required for tasks like compressing springs and pulling components. Cleanliness is emphasized throughout to prevent dirt from entering the transmission during disassembly.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix 3DZ) Service Repair Manua...9fikslkddmd8u
This document provides instructions for disassembling the power shift transmission on Caterpillar 924G and 924Gz wheel loaders. The summary is as follows:
1) Place the transmission on a repair stand and remove components like the torque converter, top case, selector valve, and flex plate.
2) Remove gears, bearings, seals, and clutch groups including the forward low and high, reverse second, and first third gear clutches.
3) Clean parts and inspect them for wear during disassembly. Take note of order and numbers of plates and discs for reassembly.
This document provides disassembly instructions for the power shift transmission of Caterpillar 924G and 924Gz wheel loaders. It describes 59 steps to fully disassemble the transmission, including removing the top case, torque converter, gears, bearings, seals, and individual clutch groups like the forward low and high clutches, reverse second gear clutch, and first third gear clutch. Precautions are given to clean components thoroughly and note part orders for reassembly. Required specialty tools are listed.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, plates, discs, retainers, springs and other internal components. Cleanliness is emphasized throughout the process to prevent dirt from entering the mechanisms.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, plates, discs, retainers, springs and other internal components. Cleanliness is emphasized throughout the process to prevent dirt from entering the mechanisms.
This document provides disassembly instructions for the transmission and torque converter of a 924G or 924Gz wheel loader. It lists over 60 detailed steps for disassembling components like gears, plates, seals, bearings, and clutches. Special tools are required and safety precautions mentioned. The transmission must first be removed and cleaned before beginning disassembly.
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents over 60 steps for disassembling components such as gears, plates, seals, bearings, hubs and clutches. Cleanliness is emphasized throughout the process to prevent dirt entry into internal mechanisms.
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents 53 steps for disassembling the various components. These include removing plates, discs, gears, seals, bearings, and other parts of the transmission and torque converter. Cleanliness is emphasized throughout the process.
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents 53 detailed steps for disassembling the various transmission components. These include removing gears, plates, seals, bearings, springs, and other parts. Cleanliness is emphasized throughout the process.
This document provides disassembly instructions for the transmission and torque converter of a 924G or 924Gz wheel loader. It lists over 60 detailed steps for disassembling components like gears, plates, seals, bearings, and clutches. Special tools are required and safety precautions mentioned. The transmission must first be removed and cleaned before beginning disassembly.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, plates, discs, retainers, springs and other internal components. Cleanliness is emphasized throughout the process to prevent dirt from entering the transmission.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, plates, discs, retainers, springs and other internal components. Cleanliness is emphasized throughout the process to prevent dirt contamination of parts.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix RBB) Service Repair Manua...9fiisekodkdmd
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents 53 detailed steps for disassembling the various transmission components. These include removing gears, plates, seals, bearings, and clutch groups. Cleanliness is emphasized throughout and components are marked for installation reference.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions with illustrations. Some key steps include removing the torque converter, valve assemblies, gears, bearing cups, clutch groups, seals, springs, and other internal components. Cleanliness is emphasized throughout the process to prevent dirt from entering the transmission.
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents over 60 steps for disassembling components such as gears, plates, seals, bearings, and clutches. Cleanliness is emphasized throughout the process.
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists the required tools and gives step-by-step instructions to remove components such as gears, seals, plates, discs, bearings, and clutches. Safety precautions are provided for releasing clutch springs. The disassembly process is described in detail through 50 steps and accompanied by illustrations of each step.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix RBB) Service Repair Manua...9fikslkddmd8u
This document provides disassembly instructions for the transmission and torque converter of a 924G/924Gz wheel loader. It lists the required tools and presents over 60 steps for disassembling components such as clutches, gears, seals, plates, and discs. Cleanliness is emphasized throughout the process to prevent dirt entry.
Caterpillar Cat 924G and 924Gz Wheel Loader (Prefix RTA) Service Repair Manua...9fikslkddmd8u
This document provides instructions for disassembling the transmission and torque converter of a 924G or 924Gz wheel loader. It lists 50 steps to completely disassemble the transmission, removing components like gears, plates, seals, bearings, and clutch groups. Special tools are required for tasks like compressing clutch springs and removing certain parts. Cleanliness is emphasized throughout to prevent dirt from contaminating internal parts.
This document provides disassembly instructions for a transmission and torque converter for wheel loader models 924G and 924Gz. It lists the required tools and presents a step-by-step process to disassemble the transmission, torque converter, and various clutch groups within the transmission. The disassembly involves removing bolts, seals, gears, plates, discs, bearings, springs, and other internal components. Cleanliness during disassembly is emphasized.
Similar to Caterpillar Cat 924Gz Wheel Loader (Prefix 9SW) Service Repair Manual (9SW00001-02428).pdf (20)
Caterpillar Cat CP-663E Vibratory Compactor (Prefix AEF) Service Repair Manua...ujkfdkkmsmd
This document provides disassembly and assembly instructions for a piston pump used in vibratory compactors. It describes 41 steps to fully disassemble the pump into individual components. This includes removing seals, springs, valves, pistons, plates, blocks, bearings and other parts. Similarly, it lists 41 steps for reassembling all the components in the reverse order. Cleanliness is emphasized throughout the process.
Caterpillar Cat CP-583E Vibratory Compactor (Prefix CNX) Service Repair Manua...ujkfdkkmsmd
This document provides instructions for removing and installing piston cooling jets, pistons, connecting rods, and related components on a Caterpillar 3056E engine. The removal process involves taking out the engine oil pan, removing valve assemblies from the piston cooling jets, and pushing pistons and connecting rods out of the cylinder block. The installation process requires cleaning components, lubricating them with oil, and reinserting pistons and connecting rods into the cylinder block before replacing other parts. Safety notices are provided to keep components clean and contain fluids.
Caterpillar Cat CP-573E Vibratory Compactor (Prefix CEB) Service Repair Manua...ujkfdkkmsmd
The document provides instructions for removing and installing the final drive planetary and piston motor components on a CS-573E and CP-573E vibratory compactor. It describes using various tools to disassemble components like the housing, hub, gears, seals and installing new components in the reverse order. Precise torques and clear illustrations are provided to correctly assemble the final drive planetary.
Caterpillar Cat CP-563D Vibratory Compactors (Prefix 2RZ) Service Repair Manu...ujkfdkkmsmd
This document provides instructions for removing and installing inlet and exhaust valve seat inserts on CP-563D and CS-563D vibratory compactors powered by a 3116 engine. The removal procedure involves using a valve seat extractor tool to expand below the edge of the valve seat insert in order to remove it from the cylinder head. The installation procedure refers to ensuring parts are clean and checking guidelines for determining if valve seats can be reused.
Caterpillar Cat CP-533E Vibratory Compactor (Prefix ASL) Service Repair Manua...ujkfdkkmsmd
This document provides instructions for disassembling and assembling the piston pump used for drum propulsion on vibratory compactor models CS-533E and CP-533E. The disassembly procedure involves removing 28 components from the pump in 12 steps using various tools. Cleaning and inspecting parts is emphasized before reassembly in the reverse order over 28 steps.
Caterpillar Cat CP-533D Vibratory Compactor (Prefix AET) Service Repair Manua...ujkfdkkmsmd
This document provides instructions for removing and installing inlet and exhaust valve guides on a CS-533D and CP-533D vibratory compactor. It outlines the required tools and gives step-by-step instructions for removing the old guides and pressing new guides into the cylinder head assembly. Proper cleaning and lubrication of parts is emphasized to prevent premature wear. Reusability guidelines for different components are also referenced.
Caterpillar Cat CP-433E Vibratory Compactor (Prefix DAC) Service Repair Manua...ujkfdkkmsmd
The document provides instructions for assembling and disassembling various components of a vibratory compactor model CS-433E or CP-433E, including:
- Assembling the piston motor drum propel system in 24 steps requiring various tools.
- Installing the assembled piston motor drum propel system with 2 illustrations.
- Removing the final drive planetary from the drum propel in 7 steps requiring lifting tools and draining the oil first.
This document provides disassembly instructions for the final drive of a 5110B mining excavator. It lists the required tools and steps to disassemble the various components of the final drive. The major steps include removing the gears, carriers, housings and other components using specialized tools like pullers and presses. Cleanliness is emphasized to prevent contamination of hydraulic components during disassembly and reassembly.
Caterpillar Cat CB534B Roller Service Repair Manual.pdfujkfdkkmsmd
This document provides instructions for replacing the propel speed range switch on models CB534B and CB534C rollers. It describes removing the operator station panel assembly, propel speed range switch, and associated wires and lockwashers. It then describes installing the new propel speed range switch with wires and lockwashers and reinstalling the panel assembly.
Caterpillar Cat CB534C Roller Service Repair Manual.pdfujkfdkkmsmd
This document provides instructions for replacing the propel speed range switch on models CB534B and CB534C rollers. It describes removing the operator station panel assembly, propel speed range switch, and associated wires and lockwashers. It then describes installing the new propel speed range switch with wires and lockwashers and reinstalling the panel assembly.
This document provides disassembly instructions for the final drive of a 5110B mining excavator. It outlines 33 steps to fully disassemble the final drive, including removing gears, carriers, housings, seals, bearings, and other components. Special tools are required and cleanliness is important to prevent contamination of parts. The document emphasizes safety precautions due to heavy component weights and potential for flying debris or released spring forces during disassembly.
Caterpillar Cat 5080 FRONT SHOVEL (Prefix 8SL) Service Repair Manual (8SL0000...ujkfdkkmsmd
This document provides instructions for removing and installing fuel injection nozzles and adapters on a 5080 FRONT SHOVEL excavator with a 3406B engine. It describes using various tools to disconnect fuel lines, remove retainers and nozzles, and clean parts. Detailed steps are given for installing nozzles, adapters, seals and applying lubricants. Similar level of detail is provided for removing and installing the cylinder head assembly, spacer plate, and valves.
This document provides disassembly instructions for a 992K wheel loader torque converter. It lists over 50 individual steps to disassemble the various components of the torque converter housing assembly, including removing pumps, gears, seals, bearings, and other internal parts. Detailed illustrations accompany each step to show how to position the assembly, what tools are needed, and how to separate the individual components. The overall process involves disassembling the entire torque converter and transmission housing to access all internal parts.
This document provides instructions for servicing the power train components of a 992B wheel loader, including removing and installing axles, final drive carriers, ring gears, hubs, wheels, and wheel brakes. The document is divided into several sections covering different components, and each section provides detailed step-by-step instructions and diagrams for disassembly and assembly of the specified components. Safety precautions and notes are included throughout.
This document provides disassembly instructions for a 992K wheel loader torque converter. It describes removing 57 individual components through a step-by-step process involving specialized tools. Key parts that must be removed include the torque converter housing, pump adapter, idler gear, housing assembly, pump drive gear, turbine assembly, impeller clutch, and shaft assembly. Precise instructions are given for each removal to ensure safety and prevent damage to precision components.
This document provides instructions for servicing the power train components of a Caterpillar 992B wheel loader, including removing and installing axles, final drive carriers, ring gears, hubs, wheels, and wheel brakes. The steps describe using hoists and tools to remove heavy components and reassemble them in reverse order. Weights of removed parts are provided to aid technicians performing the work.
This document provides disassembly instructions for the transmission planetary system of a 992G wheel loader. It outlines 52 steps to fully disassemble the transmission, including removing components like the transmission case assembly, end plates, clutches, planetary carrier, and sun gear. Various tools are required to separate, remove, and disassemble the different transmission parts. Detailed illustrations accompany each step to show how to properly disassemble the transmission planetary.
This document provides disassembly instructions for the transmission planetary of a 992G wheel loader. It lists 57 steps to fully disassemble the transmission planetary, including removing components like the transmission case assembly, carrier assembly, clutch housings, and planetary gears. Detailed illustrations accompany each step to show how to remove seals, bolts, springs, and other parts. Special tools are required for tasks like separating transmission components and removing bearings.
This document provides instructions for removing and installing an electronic unit injector on a Caterpillar 3508 engine. It describes:
1. Removing the rocker shaft assembly, pushrods, clamps and bolts to remove the injector.
2. Cleaning the cylinder head bore before installing the new injector.
3. Installing the injector, connecting the harness, and reinstalling removed components.
This document provides instructions for removing and installing the cylinder head on a Caterpillar 3412E engine. It lists the required tools and gives step-by-step details of the removal and installation process. The removal process involves detaching hoses, bolts, and manifolds. Lifting devices are needed due to the heavy weight of parts. The installation process reverses the removal steps and provides tightening specifications for bolts. Precautions are given to keep parts clean and apply lubricants to seals.
Welcome to ASP Cranes, your trusted partner for crane solutions in Raipur, Chhattisgarh! With years of experience and a commitment to excellence, we offer a comprehensive range of crane services tailored to meet your lifting and material handling needs.
At ASP Cranes, we understand the importance of reliable and efficient crane operations in various industries, from construction and manufacturing to logistics and infrastructure development. That's why we strive to deliver top-notch solutions that enhance productivity, safety, and cost-effectiveness for our clients.
Our services include:
Crane Rental: Whether you need a crawler crane for heavy lifting or a hydraulic crane for versatile operations, we have a diverse fleet of well-maintained cranes available for rent. Our rental options are flexible and can be customized to suit your project requirements.
Crane Sales: Looking to invest in a crane for your business? We offer a wide selection of new and used cranes from leading manufacturers, ensuring you find the perfect equipment to match your needs and budget.
Crane Maintenance and Repair: To ensure optimal performance and safety, regular maintenance and timely repairs are essential for cranes. Our team of skilled technicians provides comprehensive maintenance and repair services to keep your equipment running smoothly and minimize downtime.
Crane Operator Training: Proper training is crucial for safe and efficient crane operation. We offer specialized training programs conducted by certified instructors to equip operators with the skills and knowledge they need to handle cranes effectively.
Custom Solutions: We understand that every project is unique, which is why we offer custom crane solutions tailored to your specific requirements. Whether you need modifications, attachments, or specialized equipment, we can design and implement solutions that meet your needs.
At ASP Cranes, customer satisfaction is our top priority. We are dedicated to delivering reliable, cost-effective, and innovative crane solutions that exceed expectations. Contact us today to learn more about our services and how we can support your project in Raipur, Chhattisgarh, and beyond. Let ASP Cranes be your trusted partner for all your crane needs!
Implementing ELDs or Electronic Logging Devices is slowly but surely becoming the norm in fleet management. Why? Well, integrating ELDs and associated connected vehicle solutions like fleet tracking devices lets businesses and their in-house fleet managers reap several benefits. Check out the post below to learn more.
What Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill RoadsSprinter Gurus
Unlock the secrets behind your Mercedes Sprinter's uphill power loss with our comprehensive presentation. From fuel filter blockages to turbocharger troubles, we uncover the culprits and empower you to reclaim your vehicle's peak performance. Conquer every ascent with confidence and ensure a thrilling journey every time.
Understanding Catalytic Converter Theft:
What is a Catalytic Converter?: Learn about the function of catalytic converters in vehicles and why they are targeted by thieves.
Why are They Stolen?: Discover the valuable metals inside catalytic converters (such as platinum, palladium, and rhodium) that make them attractive to criminals.
Steps to Prevent Catalytic Converter Theft:
Parking Strategies: Tips on where and how to park your vehicle to reduce the risk of theft, such as parking in well-lit areas or secure garages.
Protective Devices: Overview of various anti-theft devices available, including catalytic converter locks, shields, and alarms.
Etching and Marking: The benefits of etching your vehicle’s VIN on the catalytic converter or using a catalytic converter marking kit to make it traceable and less appealing to thieves.
Surveillance and Monitoring: Recommendations for using security cameras and motion-sensor lights to deter thieves.
Statistics and Insights:
Theft Rates by Borough: Analysis of data to determine which borough in NYC experiences the highest rate of catalytic converter thefts.
Recent Trends: Current trends and patterns in catalytic converter thefts to help you stay aware of emerging hotspots and tactics used by thieves.
Benefits of This Presentation:
Awareness: Increase your awareness about catalytic converter theft and its impact on vehicle owners.
Practical Tips: Gain actionable insights and tips to effectively prevent catalytic converter theft.
Local Insights: Understand the specific risks in different NYC boroughs, helping you take targeted preventive measures.
This presentation aims to equip you with the knowledge and tools needed to protect your vehicle from catalytic converter theft, ensuring you are prepared and proactive in safeguarding your property.
Expanding Access to Affordable At-Home EV Charging by Vanessa WarheitForth
Vanessa Warheit, Co-Founder of EV Charging for All, gave this presentation at the Forth Addressing The Challenges of Charging at Multi-Family Housing webinar on June 11, 2024.
Ever been troubled by the blinking sign and didn’t know what to do?
Here’s a handy guide to dashboard symbols so that you’ll never be confused again!
Save them for later and save the trouble!
EV Charging at MFH Properties by Whitaker JamiesonForth
Whitaker Jamieson, Senior Specialist at Forth, gave this presentation at the Forth Addressing The Challenges of Charging at Multi-Family Housing webinar on June 11, 2024.
2. Shutdown SIS
Previous Screen
Product: WHEEL LOADER
Model: 924G WHEEL LOADER 9SW
Configuration: 924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056 Engine
Disassembly and Assembly
924G and 924GZ Wheel Loaders Power Train
Media Number -RENR3506-05 Publication Date -01/05/2004 Date Updated -09/10/2017
i01738796
Power Shift Transmission - Disassemble
SMCS - 3030-015
Disassembly Procedure
Table 1
Required Tools
Tool Part Number Part Description Qty
A 1P-2420 Transmission Repair Stand 1
B 1U-9759 Jack Stand 1
C 6V-2156 Link Bracket 2
D 4C-6136 Lifting Bracket 1
E 4C-6399 Spring Compressor 1
F FT-2343 Plexiglass Cover 1
G 1P-2321 Puller 1
H 4C-3652 Spring Compressor 1
Start By:
a. Separate the engine, and the transmission. Refer to Disassembly and Assembly, RENR3503,
"Engine from Torque Converter and Transmission - Separate".
Note: Cleanliness is an important factor. Before the disassembly procedure, the exterior of the
component should be thoroughly cleaned. This will help to prevent dirt from entering the internal
mechanism.
1/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
3. Illustration 1 g00653680
1. Use Tooling (C) and a suitable lifting device in order to place the transmission on Tooling
(A) and (B), as shown. The weight of the transmission is approximately 500 kg (1100 lb).
2. Remove torque converter (1).
3. Remove bolts (2) and the top transmission case. The weight of the top transmission case is
approximately 163 kg (360 lb).
Note: Remove the selector and pressure control valve. Install Tooling (F). Refer to
Disassembly and Assembly, "Selector And Pressure Control Valve (Transmission)- Remove
And Install".
Illustration 2 g00671890
4. Remove bolts (3) and flex plate (4) from torque converter (1).
2/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
4. Illustration 3 g00653775
5. Remove bolts (5) and plate (6).
Illustration 4 g00653801
6. Remove lip type seal (7) and seal (8).
Illustration 5 g00653806
7. Remove bolts (9).
3/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
6. Illustration 9 g00653858
12. Using Tooling (D) to remove the forward low and the forward high clutch group (15). The
weight of the clutch group is approximately 27 kg (60 lb).
Note: When the clutch groups are disassembled, remove the shaft plugs (16) in order to
clean the oil passages. Use a punch to drive the plug into the shaft . Drill the remainder of
the aluminum plug out of the bore. Be careful not to drill any portion of the walls of the
bore. Use shop air or a cleaning solution in order to clean the shafts.
Illustration 10 g00653893
13. Remove ring (17) and washer (18).
5/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
7. Illustration 11 g00653932
14. Remove ring (19).
15. Use a suitable press in order to remove gear (20).
Illustration 12 g00890607
16. Remove ring (22). Remove hub (21). Remove plates and discs (23).
Note: Take note of the number and order of plates and discs for assembly purposes.
Illustration 13 g00653959
17. Remove washer (24).
Note: The retainer may stick to the inside of hub (22) when the hub is removed.
6/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
8. Illustration 14 g00890608
18. Remove ring (26). Press bearing (25) from hub (22).
Illustration 15 g00654018
19. Put the forward low clutch group in a press. Use Tooling (H) in order to compress the
spring. Remove ring (27).
Illustration 16 g00654029
20. Remove retainer (28) and spring (29).
7/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
9. Illustration 17 g00890609
21. Release piston (32) by blowing shop air into lube passage (31). Remove piston (32).
22. Remove seals (30).
Illustration 18 g00654063
23. Remove seals (33).
Illustration 19 g00654078
24. Disassemble the forward high clutch group by removing ring (34). Remove washer (35).
8/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
10. Illustration 20 g00654253
25. Remove ring (36). Remove gear (37).
Illustration 21 g00654261
26. Remove hub (38).
Illustration 22 g00654263
27. Remove ring (39). Use a suitable press in order to remove bearing (40).
9/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
11. Illustration 23 g00654274
28. Remove washer (41). Remove ring (42). Remove the plate and discs (43).
Note: Take note of the number and order of plates and discs for assembly purposes.
Illustration 24 g00654276
29. Put the forward high clutch group in a suitable press. Use Tooling (H) in order to remove
ring (44).
Illustration 25 g00654280
10/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
12. Illustration 26 g00654282
30. Remove retainer (45) and spring (46).
31. Blow shop air into lube passage (48) in order to remove piston (47).
Illustration 27 g00654292
32. Remove seals (49) and (50).
Illustration 28 g00654301
33. Use Tooling (D) in order to remove reverse second gear clutch group (51). The weight of
the clutch group is approximately 32 kg (70 lb).
11/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
13. Illustration 29 g00654339
34. Remove ring (52) and washer (53).
Illustration 30 g00654328
35. Remove ring (54) and gear (55).
Illustration 31 g00654347
36. Remove hub assembly (56).
12/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
14. Illustration 32 g00890610
37. Remove washer (58).
38. Remove ring (57). Remove plates and discs (59).
Note: Take note of the number and order of the plates and discs for assembly purposes.
Illustration 33 g00890611
39. Remove ring (60). Use a suitable press in order to remove bearing (61).
Illustration 34 g00654360
13/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
15. 40. Put the reverse clutch group in a suitable press. Use Tooling (H) in order to remove ring
(62).
Illustration 35 g00654364
41. Remove retainer (63) and spring (64).
Illustration 36 g00654372
Illustration 37 g00654378
42. Release piston (65) by blowing shop air into lube passage (66). Remove piston (65).
43. Remove seals (67).
14/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
16. Illustration 38 g00654403
44. Remove seals (68) and (69).
Illustration 39 g00890612
45. Install a suitable puller under gear (72). Pull gear (72), spacer (70), and bearing (71).
46. Remove spacer (73). Remove washer (74) and (75).
Note: Use Steps 35 through 44 for the remaining disassembly of the second gear clutch
group. In Step 40, use Tooling (E) instead of Tooling (H).
15/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
17. Illustration 40 g00654494
47. Use Tooling (D) in order to remove first third gear clutch group (76). The weight of the
clutch group is approximately 50 kg (110 lb).
Illustration 41 g00654497
48. Remove ring (77) and washer (78).
Illustration 42 g00654507
49. Remove ring (79) and gear (80).
Illustration 43 g00654512
16/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
18. 50. Remove hub assembly (81).
Illustration 44 g00890613
51. Remove ring (82). Use a suitable press in order to remove bearing (83).
Illustration 45 g00654519
52. Remove washer (84).
53. Remove ring (85). Remove plates and discs (86).
Note: Take note of the number and order of the plates and discs for assembly purposes.
17/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
19. Illustration 46 g00654525
54. Put the third gear clutch group in a suitable press. Use Tooling (H) in order to remove ring
(87).
Illustration 47 g00654534
55. Remove retainer (88) and spring (89).
Illustration 48 g00890615
56. Release piston (90) by blowing shop air into lube passage (91). Remove piston (90).
57. Remove seals (92).
18/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
20. Illustration 49 g00654638
58. Remove seals (93) and (94).
Illustration 50 g00890617
59. Disassemble the first gear clutch by installing Tooling (G) through the holes in gear (95).
Pull gear (95), washer (96), and bearing (97) together.
Illustration 51 g00654719
60. Remove washer (98). Remove ring (99) and gear (100).
Illustration 52 g00654724
19/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
21. 61. Remove hub assembly (101).
Illustration 53 g00890619
62. Remove washers (102) and (104). Remove ring (103). Remove plates and discs (105).
Note: Take note of the number and order of the plates and discs for assembly purposes.
Illustration 54 g00654818
63. Remove ring (106).
Illustration 55 g00654824
20/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
22. 64. Remove bearing assembly (107).
Illustration 56 g00654833
65. Put the clutch group in a suitable press. Use Tooling (H) in order to remove ring (108).
Illustration 57 g00654837
66. Remove the retainer and seal assembly (109).
Illustration 58 g00654842
67. Remove spring (110).
21/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
23. Illustration 59 g00654966
68. Remove piston (111). Blow shop air into the lube passage in order to release the piston.
Illustration 60 g00654969
69. Remove seals (112), (113), and (114).
Illustration 61 g00655016
70. Remove input shaft assembly (115).
22/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
24. Illustration 62 g00890621
71. Remove carrier (117) and seal (116). Remove bearing (121) and gear (120).
72. Remove bearing (118) and gear (119).
Illustration 63 g00655110
73. Remove bearing (122) and bearing cups (123).
Illustration 64 g00655120
74. Remove bolt (124), washer (125), and yoke (126).
23/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
25. Illustration 65 g00685060
75. Remove the bolt and washer (127).
Illustration 66 g00890622
76. Remove seal (128). Remove yoke (129) and brake drum (130) together.
Illustration 67 g00890758
77. Remove bolts (131). Remove plate (132).
78. Remove parking brake assembly (133), and lever (134).
24/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
26. Illustration 68 g00655180
79. Remove bolts (135).
Illustration 69 g00655189
80. Install bolts (136). Tighten bolts (136) in order to remove cage (137).
Illustration 70 g00655206
81. Remove shims (138).
25/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
27. Illustration 71 g00890759
82. Remove seal (139). Remove bearing cup (140) and lip seal (141).
Illustration 72 g00890760
83. Remove nuts (142) and cover (143).
Illustration 73 g00655439
84. Remove the output shaft and gear (144).
26/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
28. Illustration 74 g00890761
85. Remove bolts (145) and shield assembly (147).
86. Remove bearing cup (146) and lip seal (148).
Illustration 75 g00655464
87. Remove bearing (149) from the output shaft.
Illustration 76 g00655451
88. Remove bearing (150). Remove ring (151) and gear (152).
27/28
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 30...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
29. Thank you very much for
your reading. Please Click
Here. Then Get COMPLETE
MANUAL. NO WAITING
NOTE:
If there is no response to
click on the link above,
please download the PDF
document first and then
click on it.
GET MORE OTHER MANUALS https://www.aservicemanualpdf.com/
GET MORE OTHER MANUALS https://www.aservicemanualpdf.com/
30. Shutdown SIS
Previous Screen
Product: WHEEL LOADER
Model: 924G WHEEL LOADER 9SW
Configuration: 924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056 Engine
Disassembly and Assembly
924G and 924GZ Wheel Loaders Power Train
Media Number -RENR3506-05 Publication Date -01/05/2004 Date Updated -09/10/2017
i02055589
Power Shift Transmission - Assemble
SMCS - 3030-016
Assembly Procedure
Table 1
Required Tools
Tool Part Number Part Description Qty
A 1P-2420 Transmission Repair Stand 1
B 1U-9759 Jack Stand 1
C 6V-2156 Link Bracket 2
D 4C-6136 Lifting Bracket 1
E 4C-6399 Spring Compressor 1
F FT-2343 Plexiglass Cover 1
G 4C-6143 Clutch Piston Installer 1
H 4C-3652 Spring Compressor 1
J
4C-6137 Bearing Installer 1
4C-6142 Spacer 1
1P-531 Handle 1
K 4C-6402 Plug Installer 1
L 5P-3413 Pipe Sealant 1
M 9S-3263 Thread Lock Compound 1
N 1U-8846 Gasket Sealant 1
1/29
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
31. Note: Cleanliness is an important factor. Before assembly, all parts should be thoroughly cleaned
in cleaning fluid. Allow the parts to air dry. Wiping cloths or rags should not be used to dry parts.
Lint may be deposited on the parts which may cause later trouble. Inspect all parts. If any parts are
worn or damaged, use new parts for replacement.
Illustration 1 g00655451
1. Install gear (152) and ring (151). Heat bearing (150) to a temperature of 135 °C (275 °F).
Install bearing (150).
Illustration 2 g00655464
2. Heat bearing (149) to a temperature of 135 °C (275 °F). Install bearing (149).
2/29
924G and 924Gz Wheel Loader 9SW00001-02428 (MACHINE) POWERED BY 3056...
2021/1/26
https://127.0.0.1/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnurl=/sis...
32. Illustration 3 g00890761
3. ApplyTooling (L) to the seal bore.
4. Install lip seal (148). Lubricate the sealing lip with the lubricant that is being used.
5. Lower the temperature of bearing cup (146). Install bearing cup (146).
6. Use bolts (145) in order to install shield assembly (147). The torque for bolts (145) is
55 ± 10 N·m (40 ± 10 lb ft).
Illustration 4 g00655439
7. Install the output shaft and gear (144).
Illustration 5 g00890760
8. Use nuts (142) in order to install cover (143). The torque for nuts (142) is 9 ± 1 N·m
(6 ± 1 lb ft).