FRESHWATER PLACE
2 Southbank Boulevard, Melbourne
CASE STUDY
Location Southbank Boulevarde, Melbourne
Victoria, Australia
Type of Building Commercial Offices
Investors Australand Holdings
GPT Wholesale Office Fund
Building Managers Jones Lang LaSalle
Architect Cox Richardson
Electrical Consultant AHW Consulting Engineers
Electrical Contractors Nilsen Contracting
ABOUT THE BUILDING
Freshwater Place is an award
winning mixed use master
planned development on the
banks of the Yarra River in the
heart of Melbourne’s arts and
entertainment precinct.
Two premium grade commercial
towers and a 60 storey residential
apartment surround an urban
retail village and piazza offering
residents and office staff a vibrant
environment in which to live and
work.
PROJECT DETAILS:
FRESHWATER PLACE
2 SOUTHBANK BOULEVARDE, MELBOURNE
The first office tower to be constructed 2 Freshwater
Place, also known as 2 Southbank Boulevard, was
completed in 2005. At 55,000m2
spread over 38 levels,
2 Freshwater Place was designed for occupancy by
leading edge, high technology organisations with current
tenants including international firms Price Waterhouse
Coopers and Microsoft.
As the second stage of the development Twenty 8
Freshwater Place is a 34,000m2
, 25 level premium grade
building. The design by architect Bates Smart uses a side-
core design to provide expansive open floor plates and
extensive ESD work was undertaken in order to target a
4.5-star NABERS energy rating.
mySmart was the original C-Bus lighting control
integrator during the construction and the majority of
the tenancy fit outs at Twenty 8 Freshwater Place. Based
on our project knowledge and the quality of our service
delivery mySmart has been the exclusive provider of
C-Bus lighting controls and programming to Freshwater
Place managing agents Jones Lang LaSalle since 2009.
With 95% of the building leased
on its completion, 2 Freshwater
Place was occupied in 2005.
Reflecting its premium grade
positioning 2 Freshwater Place
was built to achieve the highest
energy efficiency.
Unfortunately due to operational issues the building
only achieved a 2.5-star NABERS energy rating,
well below its design capability. For Stage One of
the energy efficiency program Engineering Services
Manager, Kok Lim Ng, targeted the building’s C-Bus
lighting control system. This had been completed by
an integrator no longer in business, and Lim believed
that by reprogramming the system significant energy
savings could be made.
As a first step an audit of the building’s lighting was
undertaken. In any commercial office building there
are two main categories of lighting; tenancy office
lighting and base building lighting. Base building
lighting can be further segmented into grey areas;
plant rooms, loading docks etc. and key areas; main
foyers, lifts, lift lobbies, building perimeter and toilets.
2 FRESHWATER PLACE
OVERALL LIGHTING POWER
FOR FRESHWATER 2
Based on the successful delivery of lighting
controls at Twenty 8 Freshwater Place, mySmart
were engaged in July 2009 to act on the findings of
the audit with changes to the base building lighting
control strategy at 2 Freshwater Place.
The reprogramming by mySmart included;
•	 Aligning the building operation and after-hours
schedules
•	 Rescheduling the grey areas to the lowest
possible operational hours
•	 Reprogramming key areas to make use of natural
light
•	 Using sensors to shut down key area lighting
when not required
•	 Ensuring all lighting is shut down when a floor is
unoccupied after hours
By September the optimised lighting control strategy
at 2 Freshwater Place had reduced consumption
by 18,400kWh, a saving of 7.7% over the pre-audit
monthly figures.
Over the period from July 2008 to July 2014 the
optimisation of the lighting control strategy, along
with a lamp replacement program in Stage Three, has
reduced the lighting energy consumption by 37%.
Further since January 2011, 2 Freshwater Place has
consistently gained a 4.5-Star NABERS energy rating.
STAGE ONE
The nature of the strategy for stage one is aggressive.
Wherever possible lighting is turned off to reduce
energy consumption. This is achieved through
programming and lights are either permanently
switched off or the amount of time they are on is
drastically reduced.
STAGE TWO
After 18 months, feedback from the buildings
occupants was used to determine which of the
disabled lighting should be turned back on. An
investment in more sophisticated programming is
required to deliver the lighting levels requested by
occupants whilst still keeping energy consumption
below that recorded at the start of Stage One.
Energy consumption in Stage Two will increase over
that recorded at the end of Stage One however
savings made in Stage One can be used to offset the
increased cost.
STAGE THREE
At the end of Stage Two the majority of savings
possible from programming will have been made.
Other options including upgrading of lamps are now
implemented while programming changes for final
areas including carparks are undertaken.
TWENTY 8 FRESHWATER PLACE
mySmart were instrumental in the delivery of Twenty 8 Freshwater
Place’s lighting system, designing and commissioning the base
building and all bar one tenancy area control systems. Initially
Twenty 8 Freshwater Place was designed as a 4.5-star NABERS
energy rated building. Since completion of the base building,
mySmart has been working with Jones Lang LaSalle to optimise
the entire building to ensure a NABERS energy rating of 5 stars is
achieved.
What is more, is that both 2 and Twenty 8 Freshwater Place have
gained their 4.5 and 5-Star NABERS energy ratings unassisted, i.e.
zero percent Green Power.
mySmart is an Australian company
at the forefront of creating intelligent
environments across a wide range of
sectors from smart buildings to smart
agriculture. Our solutions are customer
centric and incorporate innovative
technologies and the latest sensor
design, control, functionality and analytics.
Our highly trained, industry qualified Consultants and Smart
Building Specialists design, optimise and service environments
to enhance user comfort and productivity, whilst minimising
operational costs and resource consumption.
mySmart, originally established as Complete Technology
Integrations (CTI) in 2001, is a wholly owned Australian company.
With a national footprint and over 60 employees, mySmart
operates across a multitude of markets including commercial
offices, residential, industrial & agriculture, government, retail,
hospitality, health & aged care, education and leisure.
Our solutions include:
•	 Lighting Control and building automation
•	 Asset Performance Analytics
•	 Energy Management
•	 Smart building systems
•	 Guest Technology
•	 System Management Programs
•	 IoT Applications
•	 mySmart Sensors and associated products
•	 Unique custom solutions
mySmart. Building smart cities one mySmart Building at a time.
FROM THE ENGINEERING
SERVICES MANAGER
Kok Lim Ng is the Engineering
Services Manager for Jones Lang
Lasalle at Freshwater Place.
Recognising that there were
some significant issues in the
operation of 2 Freshwater Place,
Lim set to work to try and turn the
building’s performance around.
THE STRATEGY
Lim’s first call was to measure and asses the building’s
energy usage. By conducting an audit Lim was able to
determine exactly how and where energy was being
used. “The first goal must be to establish a baseline
for energy usage”, says Lim. “After that you can work
to isolate seasonal and daily variances that impact on
performance.”
INVEST TO RETURN
Many in our industry find it can be hard to ask owners to
invest in returns they feel may not benefit them directly.
Lim’s initial approach was to look for operational
savings in order to create surplus funds. Once funds
were available they were used where they will give the
quickest returns from the smallest investment.
Optimising lighting automation and control is often the
quickest method to get a quick return. “With mySmart
charging an hourly rate many changes can be made in
a very short period of time for not a lot of money.” says
Lim. “The critical factor is that the integrator is suitably
experienced and able to quickly understand what
changes are required and how best to implement them.”
NOTHING IS IN ISOLATION
Another point to consider is that no change acts in
isolation. A simple change in the programming of the
lighting leads to a reduction of energy used and also
of heat generated. A reduction of heat generated by
lighting also reduces the load on the air-conditioning.
A reduction in the air-conditioning load reduces the
baseline energy and water consumption.”While these
reductions may not be huge, it is a constant loop of
analysis, change, more analysis and more change that
leads to a fully optimised building.”
1300 697 627
mysmart.com.au
info@mysmart.com.au
SERVICE HOTLINE
1300 881 583

More Related Content

What's hot

Intelligent building case study
Intelligent building case studyIntelligent building case study
Intelligent building case study
Hamid Hussain
 
Ambicales Solar Profile
Ambicales Solar ProfileAmbicales Solar Profile
Ambicales Solar Profile
Ambicales
 
Method to identify Building Energy Index BEI
Method to identify Building Energy Index BEIMethod to identify Building Energy Index BEI
Method to identify Building Energy Index BEI
Steve Lojuntin
 
Four practical steps for reducing overall energy costs
Four practical steps for reducing overall energy costsFour practical steps for reducing overall energy costs
Four practical steps for reducing overall energy costsSchneider Electric India
 
WHY CHOOSE US
WHY CHOOSE USWHY CHOOSE US
WHY CHOOSE US
Dario Rosso
 
Naed Industrial Green Electrical Upgrades Brochure Final Files
Naed Industrial Green Electrical Upgrades Brochure Final FilesNaed Industrial Green Electrical Upgrades Brochure Final Files
Naed Industrial Green Electrical Upgrades Brochure Final Files
Carazo Communications
 
Green Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in MalaysiaGreen Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in Malaysia
Steve Lojuntin
 
RENEWABLE ENERGY SOLUTIONS
RENEWABLE ENERGY SOLUTIONSRENEWABLE ENERGY SOLUTIONS
RENEWABLE ENERGY SOLUTIONS
Belacianovic Jotham
 
Design Concepts And Energy Management In Green Building
Design Concepts And Energy Management In Green BuildingDesign Concepts And Energy Management In Green Building
Design Concepts And Energy Management In Green Building
mehtakandy
 
Best Practices & Recommended Architectures Gb
Best Practices & Recommended Architectures GbBest Practices & Recommended Architectures Gb
Best Practices & Recommended Architectures Gb
mehtakandy
 
Yuhua 5-Year Master Plan (2016 -2020)
Yuhua 5-Year Master Plan (2016 -2020)Yuhua 5-Year Master Plan (2016 -2020)
Yuhua 5-Year Master Plan (2016 -2020)
ChowKinFai
 
Building Energy Efficiency Policies and Programs of the United States
Building Energy Efficiency Policies and Programs of the United StatesBuilding Energy Efficiency Policies and Programs of the United States
Building Energy Efficiency Policies and Programs of the United States
International Energy Agency
 
Building byes provision for energy conservation and sustainable development
Building byes provision for energy conservation and sustainable developmentBuilding byes provision for energy conservation and sustainable development
Building byes provision for energy conservation and sustainable development
Shourya Puri
 
Energy efficient street lighting guidelines
Energy efficient street lighting guidelinesEnergy efficient street lighting guidelines
Energy efficient street lighting guidelines
ArTamilVananSiva
 
Zero Energy Building in Malaysia by SEDA Malaysia
Zero Energy Building in Malaysia by SEDA MalaysiaZero Energy Building in Malaysia by SEDA Malaysia
Zero Energy Building in Malaysia by SEDA Malaysia
Steve Lojuntin
 

What's hot (18)

Intelligent building case study
Intelligent building case studyIntelligent building case study
Intelligent building case study
 
Ambicales Solar Profile
Ambicales Solar ProfileAmbicales Solar Profile
Ambicales Solar Profile
 
Power-One
Power-OnePower-One
Power-One
 
Office-building-catalogue-India
Office-building-catalogue-IndiaOffice-building-catalogue-India
Office-building-catalogue-India
 
Method to identify Building Energy Index BEI
Method to identify Building Energy Index BEIMethod to identify Building Energy Index BEI
Method to identify Building Energy Index BEI
 
Four practical steps for reducing overall energy costs
Four practical steps for reducing overall energy costsFour practical steps for reducing overall energy costs
Four practical steps for reducing overall energy costs
 
WHY CHOOSE US
WHY CHOOSE USWHY CHOOSE US
WHY CHOOSE US
 
Finalgeo part1
Finalgeo part1Finalgeo part1
Finalgeo part1
 
Naed Industrial Green Electrical Upgrades Brochure Final Files
Naed Industrial Green Electrical Upgrades Brochure Final FilesNaed Industrial Green Electrical Upgrades Brochure Final Files
Naed Industrial Green Electrical Upgrades Brochure Final Files
 
Green Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in MalaysiaGreen Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in Malaysia
 
RENEWABLE ENERGY SOLUTIONS
RENEWABLE ENERGY SOLUTIONSRENEWABLE ENERGY SOLUTIONS
RENEWABLE ENERGY SOLUTIONS
 
Design Concepts And Energy Management In Green Building
Design Concepts And Energy Management In Green BuildingDesign Concepts And Energy Management In Green Building
Design Concepts And Energy Management In Green Building
 
Best Practices & Recommended Architectures Gb
Best Practices & Recommended Architectures GbBest Practices & Recommended Architectures Gb
Best Practices & Recommended Architectures Gb
 
Yuhua 5-Year Master Plan (2016 -2020)
Yuhua 5-Year Master Plan (2016 -2020)Yuhua 5-Year Master Plan (2016 -2020)
Yuhua 5-Year Master Plan (2016 -2020)
 
Building Energy Efficiency Policies and Programs of the United States
Building Energy Efficiency Policies and Programs of the United StatesBuilding Energy Efficiency Policies and Programs of the United States
Building Energy Efficiency Policies and Programs of the United States
 
Building byes provision for energy conservation and sustainable development
Building byes provision for energy conservation and sustainable developmentBuilding byes provision for energy conservation and sustainable development
Building byes provision for energy conservation and sustainable development
 
Energy efficient street lighting guidelines
Energy efficient street lighting guidelinesEnergy efficient street lighting guidelines
Energy efficient street lighting guidelines
 
Zero Energy Building in Malaysia by SEDA Malaysia
Zero Energy Building in Malaysia by SEDA MalaysiaZero Energy Building in Malaysia by SEDA Malaysia
Zero Energy Building in Malaysia by SEDA Malaysia
 

Similar to Case Study Freshwater Place - mySmart

Case Study Westpac Place - mySmart
Case Study Westpac Place - mySmartCase Study Westpac Place - mySmart
Case Study Westpac Place - mySmart
mySmart
 
How Tenants & Landlords Can Work Together to Reduce Energy Consumption!
How Tenants & Landlords Can Work Together to Reduce Energy Consumption!How Tenants & Landlords Can Work Together to Reduce Energy Consumption!
How Tenants & Landlords Can Work Together to Reduce Energy Consumption!
Memoori
 
SCS_Brochure_Final.2 (1)
SCS_Brochure_Final.2 (1)SCS_Brochure_Final.2 (1)
SCS_Brochure_Final.2 (1)Tom Dearmin
 
The Planet needs Smarter Buildings
The Planet needs Smarter BuildingsThe Planet needs Smarter Buildings
The Planet needs Smarter Buildings
Murray Guy
 
RILA BELK.PDF
RILA BELK.PDFRILA BELK.PDF
RILA BELK.PDFAlan King
 
Fitting Energy Efficiency Into Commercial Tenant Fits Outs
Fitting Energy Efficiency Into Commercial Tenant Fits OutsFitting Energy Efficiency Into Commercial Tenant Fits Outs
Fitting Energy Efficiency Into Commercial Tenant Fits Outs
Zondits
 
MLogan - Career Results
MLogan - Career ResultsMLogan - Career Results
MLogan - Career ResultsMichael Logan
 
PhD Viva LHI
PhD Viva LHIPhD Viva LHI
PhD Viva LHI
Lokman Hakim Ismail
 
ECA Conference Session 3: Kathy MacWilliams
ECA Conference Session 3: Kathy MacWilliams ECA Conference Session 3: Kathy MacWilliams
ECA Conference Session 3: Kathy MacWilliams
Thomas Flaherty
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
Sandro Suzart
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
Sandro Suzart
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
Sandro Suzart
 
Gc going green step by step
Gc going green step by stepGc going green step by step
Gc going green step by step
Green Constitutes Sdn Bhd
 
PRIMEQUEST ENERGY PROFILE (Recovered)
PRIMEQUEST ENERGY PROFILE (Recovered)PRIMEQUEST ENERGY PROFILE (Recovered)
PRIMEQUEST ENERGY PROFILE (Recovered)Dr. Renske Snyman
 
Nugreen FM AprilMay article
Nugreen FM AprilMay articleNugreen FM AprilMay article
Nugreen FM AprilMay articleGeoff Gourley
 
Annual Report, REAP
Annual Report, REAPAnnual Report, REAP
Annual Report, REAP
JC Martel
 
Case study One McNab Avenue - mySmart
Case study One McNab Avenue - mySmartCase study One McNab Avenue - mySmart
Case study One McNab Avenue - mySmart
mySmart
 
Energy solutions in action
Energy solutions in actionEnergy solutions in action
Energy solutions in action
EMEX
 
SELGO COMPANY PROFILE 2015
SELGO COMPANY PROFILE 2015SELGO COMPANY PROFILE 2015
SELGO COMPANY PROFILE 2015Eddie Ngari
 

Similar to Case Study Freshwater Place - mySmart (20)

Case Study Westpac Place - mySmart
Case Study Westpac Place - mySmartCase Study Westpac Place - mySmart
Case Study Westpac Place - mySmart
 
How Tenants & Landlords Can Work Together to Reduce Energy Consumption!
How Tenants & Landlords Can Work Together to Reduce Energy Consumption!How Tenants & Landlords Can Work Together to Reduce Energy Consumption!
How Tenants & Landlords Can Work Together to Reduce Energy Consumption!
 
SCS_Brochure_Final.2 (1)
SCS_Brochure_Final.2 (1)SCS_Brochure_Final.2 (1)
SCS_Brochure_Final.2 (1)
 
The Planet needs Smarter Buildings
The Planet needs Smarter BuildingsThe Planet needs Smarter Buildings
The Planet needs Smarter Buildings
 
RILA BELK.PDF
RILA BELK.PDFRILA BELK.PDF
RILA BELK.PDF
 
Fitting Energy Efficiency Into Commercial Tenant Fits Outs
Fitting Energy Efficiency Into Commercial Tenant Fits OutsFitting Energy Efficiency Into Commercial Tenant Fits Outs
Fitting Energy Efficiency Into Commercial Tenant Fits Outs
 
MLogan - Career Results
MLogan - Career ResultsMLogan - Career Results
MLogan - Career Results
 
PhD Viva LHI
PhD Viva LHIPhD Viva LHI
PhD Viva LHI
 
ECA Conference Session 3: Kathy MacWilliams
ECA Conference Session 3: Kathy MacWilliams ECA Conference Session 3: Kathy MacWilliams
ECA Conference Session 3: Kathy MacWilliams
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
 
Gc going green step by step
Gc going green step by stepGc going green step by step
Gc going green step by step
 
PRIMEQUEST ENERGY PROFILE (Recovered)
PRIMEQUEST ENERGY PROFILE (Recovered)PRIMEQUEST ENERGY PROFILE (Recovered)
PRIMEQUEST ENERGY PROFILE (Recovered)
 
Nugreen FM AprilMay article
Nugreen FM AprilMay articleNugreen FM AprilMay article
Nugreen FM AprilMay article
 
Annual Report, REAP
Annual Report, REAPAnnual Report, REAP
Annual Report, REAP
 
Case study One McNab Avenue - mySmart
Case study One McNab Avenue - mySmartCase study One McNab Avenue - mySmart
Case study One McNab Avenue - mySmart
 
CaseStudy_NAB-Service_
CaseStudy_NAB-Service_CaseStudy_NAB-Service_
CaseStudy_NAB-Service_
 
Energy solutions in action
Energy solutions in actionEnergy solutions in action
Energy solutions in action
 
SELGO COMPANY PROFILE 2015
SELGO COMPANY PROFILE 2015SELGO COMPANY PROFILE 2015
SELGO COMPANY PROFILE 2015
 

Recently uploaded

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 

Recently uploaded (20)

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 

Case Study Freshwater Place - mySmart

  • 1. FRESHWATER PLACE 2 Southbank Boulevard, Melbourne CASE STUDY
  • 2. Location Southbank Boulevarde, Melbourne Victoria, Australia Type of Building Commercial Offices Investors Australand Holdings GPT Wholesale Office Fund Building Managers Jones Lang LaSalle Architect Cox Richardson Electrical Consultant AHW Consulting Engineers Electrical Contractors Nilsen Contracting ABOUT THE BUILDING Freshwater Place is an award winning mixed use master planned development on the banks of the Yarra River in the heart of Melbourne’s arts and entertainment precinct. Two premium grade commercial towers and a 60 storey residential apartment surround an urban retail village and piazza offering residents and office staff a vibrant environment in which to live and work. PROJECT DETAILS: FRESHWATER PLACE 2 SOUTHBANK BOULEVARDE, MELBOURNE The first office tower to be constructed 2 Freshwater Place, also known as 2 Southbank Boulevard, was completed in 2005. At 55,000m2 spread over 38 levels, 2 Freshwater Place was designed for occupancy by leading edge, high technology organisations with current tenants including international firms Price Waterhouse Coopers and Microsoft. As the second stage of the development Twenty 8 Freshwater Place is a 34,000m2 , 25 level premium grade building. The design by architect Bates Smart uses a side- core design to provide expansive open floor plates and extensive ESD work was undertaken in order to target a 4.5-star NABERS energy rating. mySmart was the original C-Bus lighting control integrator during the construction and the majority of the tenancy fit outs at Twenty 8 Freshwater Place. Based on our project knowledge and the quality of our service delivery mySmart has been the exclusive provider of C-Bus lighting controls and programming to Freshwater Place managing agents Jones Lang LaSalle since 2009.
  • 3. With 95% of the building leased on its completion, 2 Freshwater Place was occupied in 2005. Reflecting its premium grade positioning 2 Freshwater Place was built to achieve the highest energy efficiency. Unfortunately due to operational issues the building only achieved a 2.5-star NABERS energy rating, well below its design capability. For Stage One of the energy efficiency program Engineering Services Manager, Kok Lim Ng, targeted the building’s C-Bus lighting control system. This had been completed by an integrator no longer in business, and Lim believed that by reprogramming the system significant energy savings could be made. As a first step an audit of the building’s lighting was undertaken. In any commercial office building there are two main categories of lighting; tenancy office lighting and base building lighting. Base building lighting can be further segmented into grey areas; plant rooms, loading docks etc. and key areas; main foyers, lifts, lift lobbies, building perimeter and toilets. 2 FRESHWATER PLACE OVERALL LIGHTING POWER FOR FRESHWATER 2 Based on the successful delivery of lighting controls at Twenty 8 Freshwater Place, mySmart were engaged in July 2009 to act on the findings of the audit with changes to the base building lighting control strategy at 2 Freshwater Place. The reprogramming by mySmart included; • Aligning the building operation and after-hours schedules • Rescheduling the grey areas to the lowest possible operational hours • Reprogramming key areas to make use of natural light • Using sensors to shut down key area lighting when not required • Ensuring all lighting is shut down when a floor is unoccupied after hours By September the optimised lighting control strategy at 2 Freshwater Place had reduced consumption by 18,400kWh, a saving of 7.7% over the pre-audit monthly figures. Over the period from July 2008 to July 2014 the optimisation of the lighting control strategy, along with a lamp replacement program in Stage Three, has reduced the lighting energy consumption by 37%. Further since January 2011, 2 Freshwater Place has consistently gained a 4.5-Star NABERS energy rating. STAGE ONE The nature of the strategy for stage one is aggressive. Wherever possible lighting is turned off to reduce energy consumption. This is achieved through programming and lights are either permanently switched off or the amount of time they are on is drastically reduced. STAGE TWO After 18 months, feedback from the buildings occupants was used to determine which of the disabled lighting should be turned back on. An investment in more sophisticated programming is required to deliver the lighting levels requested by occupants whilst still keeping energy consumption below that recorded at the start of Stage One. Energy consumption in Stage Two will increase over that recorded at the end of Stage One however savings made in Stage One can be used to offset the increased cost. STAGE THREE At the end of Stage Two the majority of savings possible from programming will have been made. Other options including upgrading of lamps are now implemented while programming changes for final areas including carparks are undertaken. TWENTY 8 FRESHWATER PLACE mySmart were instrumental in the delivery of Twenty 8 Freshwater Place’s lighting system, designing and commissioning the base building and all bar one tenancy area control systems. Initially Twenty 8 Freshwater Place was designed as a 4.5-star NABERS energy rated building. Since completion of the base building, mySmart has been working with Jones Lang LaSalle to optimise the entire building to ensure a NABERS energy rating of 5 stars is achieved. What is more, is that both 2 and Twenty 8 Freshwater Place have gained their 4.5 and 5-Star NABERS energy ratings unassisted, i.e. zero percent Green Power.
  • 4. mySmart is an Australian company at the forefront of creating intelligent environments across a wide range of sectors from smart buildings to smart agriculture. Our solutions are customer centric and incorporate innovative technologies and the latest sensor design, control, functionality and analytics. Our highly trained, industry qualified Consultants and Smart Building Specialists design, optimise and service environments to enhance user comfort and productivity, whilst minimising operational costs and resource consumption. mySmart, originally established as Complete Technology Integrations (CTI) in 2001, is a wholly owned Australian company. With a national footprint and over 60 employees, mySmart operates across a multitude of markets including commercial offices, residential, industrial & agriculture, government, retail, hospitality, health & aged care, education and leisure. Our solutions include: • Lighting Control and building automation • Asset Performance Analytics • Energy Management • Smart building systems • Guest Technology • System Management Programs • IoT Applications • mySmart Sensors and associated products • Unique custom solutions mySmart. Building smart cities one mySmart Building at a time. FROM THE ENGINEERING SERVICES MANAGER Kok Lim Ng is the Engineering Services Manager for Jones Lang Lasalle at Freshwater Place. Recognising that there were some significant issues in the operation of 2 Freshwater Place, Lim set to work to try and turn the building’s performance around. THE STRATEGY Lim’s first call was to measure and asses the building’s energy usage. By conducting an audit Lim was able to determine exactly how and where energy was being used. “The first goal must be to establish a baseline for energy usage”, says Lim. “After that you can work to isolate seasonal and daily variances that impact on performance.” INVEST TO RETURN Many in our industry find it can be hard to ask owners to invest in returns they feel may not benefit them directly. Lim’s initial approach was to look for operational savings in order to create surplus funds. Once funds were available they were used where they will give the quickest returns from the smallest investment. Optimising lighting automation and control is often the quickest method to get a quick return. “With mySmart charging an hourly rate many changes can be made in a very short period of time for not a lot of money.” says Lim. “The critical factor is that the integrator is suitably experienced and able to quickly understand what changes are required and how best to implement them.” NOTHING IS IN ISOLATION Another point to consider is that no change acts in isolation. A simple change in the programming of the lighting leads to a reduction of energy used and also of heat generated. A reduction of heat generated by lighting also reduces the load on the air-conditioning. A reduction in the air-conditioning load reduces the baseline energy and water consumption.”While these reductions may not be huge, it is a constant loop of analysis, change, more analysis and more change that leads to a fully optimised building.”